Geotechnical Specification and Construction Update

Similar documents
SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

ODOT Design & Construction Requirements for MSE Walls

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENT 1120 MIXTURE DESIGN FOR CHEMICALLY STABILIZED SOILS. June 13, 2011

DOT-FHWA QA/QC Plan Sample Selected pages (not a complete plan)

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following:

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

LANDSCAPE RETAINING WALLS

SECTION AGGREGATES

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

ENGINEERING DIRECTIVE

A.2.a Random Riprap... Table

A. Texas Department Transportation 2004 Standard Specifications for Construction of Highways, Streets and Bridges (TxDOT):

Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # PROJECT SPECIFICATIONS TABLE OF CONTENTS

2.1 Backfill - General

Designer Supplement: AS-2-15 Approach Slab Installation January 16, 2015

Bureau of Materials Materials Approval Procedures

SECTION FOUNDATION DRAINAGE

INTERLOCK BETWEEN PARTICLES AT EACH PERFORATION

LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH

Wall Modular Block Mechanically Stabilized Earth, Item S.

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

C. Foundation stabilization for pipe and utility structures.

SECTION RIPRAP, BOULDERS, AND BEDDING

BASE CONSTRUCTION MATERIALS A Aggregate

MSE WALLS CASE STUDIES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

SECTION TRENCHING & BACKFILLING

This supplemental technical specification replaces Section 713 of the 2007 Standard Specifications for Highway Construction.

SECTION BITUMINOUS CONCRETE PAVEMENT

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 863 REINFORCED SOIL SLOPES. October 19, 2012

UNHSC Bioretention Soil Specification February, SOIL PREPARATION (PERFORMANCE SPECIFICATION) for Bioretention Systems

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

MODULAR CONCRETE RETAINING WALL

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

Redi Rock Specification and Installation Manual

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects

Construction Best Management Practices Handbook BEST MANAGEMENT PRACTICES

VERTI-BLOCK - DESIGN MANUAL

R-TANK SPECIFICATIONS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

SECTION WATER TREATMENT RESIDUAL REMOVAL, DISPOSAL, AND LAGOON CLEANING

MECHANICALLY STABILIZED EARTH (MSE) WALL SYSTEMS

3 rd PARTY MATERIALS TESTING MANUAL

The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase.

PERMEABLE INTERLOCKING PAVERS

GUIDE SCHEDULE OF SAMPLING & TESTING FOR DESIGN-BID-BUILD (DBB) PROJECTS MAY 2016

Design Manual: Gravity Wall. Section 1

BAYFILTER SPECIFICATIONS

Full Depth Reclamation

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007

2016 ACHD Supplemental Specifications to the ISPWC. ACHD QC-QA Procedure

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

Uwall UNIVERSAL CONSTRUCTION MANUAL

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General

SECTION PREFABRICATED PIPE BRIDGE(s)

BASED ON DFD MASTER SPECIFICATION DATED 2/24/2014

SECTION EROSION AND SEDIMENTATION CONTROLS

2. A preconstruction meeting with the TWA s staff is required prior to initiating construction.

B. Backfill and compact utility bedding and fill placed in the utility trenches between the top of the utility bedding and the subgrade elevation.

SECTION BASIC ELECTRICAL MATERIALS AND METHODS

Table of Contents for Guide Specifications

TION GUIDE ALLA T INS

Minimum Sample and Test Requirements (MSTR)

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems.

3/28/2016 APWA-WA CONSTRUCTION MATERIALS COMMITTEE. SPEAKERS: Cody R. Hart, P.E. Jessica Knickerbocker, P.E.

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

Full-Depth Reclamation with Cement

SECTION Section Excavation and Backfill For Structures Section Embedment and Base Course Aggregate

SECTION CAST-IN-PLACE CONCRETE

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

SECTION GRADING AND SITE PREPARATION CITY OF LEE S SUMMIT, MISSOURI STANDARD SPECIFICATIONS

MOA Project # Golden View Drive Intersection & Safety Upgrades

Characterizing Engineering Properties of Foundry Sands

PRODUCT SPECIFICATIONS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION SITE CONCRETE

SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket

PROPOSED STOCK PILE YARD PHASE 1 SITE: MYRA FALLS MINE

SPECIFICATION FOR REINFORCED SOIL WALL

A. Product Data: Submit manufacturer s product data, with complete general and specific installation instructions, recommendations, and limitations.

PART 1 - GENERAL 1.01 General Provisions A. The Conditions of the Contract and all Sections of Division 1 are hereby made a part of this Section.

02632 Segmental Concrete Retaining Wall System Page - 1

SECTION 20 INDEX PAVING FABRIC 1. SCOPE OF WORK MATERIAL REQUIREMENTS CONSTRUCTION AND INSTALLATION REQUIREMENTS...

Underground Piping for Private Hydrants & Sprinkler Supply Line

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

CETCO-VOLCLAY CG-50 SPECIFICATION GUIDELINES MIX IN PLACE

TensarTech TW1 Wall System Earth Retaining Structures

GUIDE SCHEDULE OF SAMPLING & TESTING FOR DESIGN-BUILD PROJECTS BY THE INDEPENDENT QUALITY FIRM (IQF) August 29, 2017

Austin Technical Manuals - Standard Specifications Preservation of Trees and Other Vegetation (610S) 03/27/2000

PERMEABLE ARTICULATING CONCRETE BLOCK (P-ACB) SPECIFICATION FOR PARKING LOTS, DRIVEWAYS, ALLEYS AND ROADWAYS

CHAPTER 11 CONDUITS AND FITTINGS

PRODUCT SPECIFICATION CSI FORMAT Slope and Channel Grid Systems April 2009

Transcription:

Geotechnical Specification and Construction Update Steve Slomski, P.E. Office of Construction Administration

Topics 2016 C&MS Revisions Supplemental Specifications & Supplements Revisions & Additions Construction Manual Of Procedures Update Schedule & Plans Consultant Inspection Prequalification

2016 C&MS Revisions General Changes Emphasize when ODOT is responsible for compaction testing: Unless otherwise specified in the Contract Documents, the Engineer will perform all compaction tests according to Supplement 1015. Items 203, 204, 205, 206, 304, 411, and 503 Items 611 and SGB - Contractor is always responsible RAP (Reclaimed Asphalt Pavement) replaces RACP

Item 201 Clearing And Grubbing Removed the listing of the restrictions for material movement from quarantined areas associated with destructive insects (e.g., emerald ash borer, Asian longhorned beetle), due to it becoming outdated Added Ohio Department of Agriculture web address for the listing of current restrictions

Item 202 Removal of Structures And Obstructions Excess removed or excavated materials to be disposed according to 105.16 and 105.17 Recycle Use in a legitimate fill operation Dispose in appropriate waste area Dispose in licensed C&D debris facility Renumbered sections 202.10 through 202.13

Items 205 & 206 Chemically Stabilized Embankment & Subgrade Removed Lime Kiln Dust (LKD) as an approved material for chemical stabilization LKD was not a successful economical alternative to cement LKD may still be used as a drying agent for moisture control of wet embankment material (203.07.A)

Item 206 Chemically Stabilized Subgrade Submit the construction procedure, for phased work, to ensure full depth and continuity of subgrade stabilization across phase interfaces Clarified that air temperatures must be above 40 F for the curing period Discontinued allowing concrete curing compound (705.07 Type 2) to be used for the curing coat

Chemically Stabilized Subgrade Cobbles & boulders caused damage and excessive wear to reclaimer teeth FRA-270-17.28 & FRA-71-5.29. Also on FRA-70-3.41 Occurred in both cut and fill sections Indicated in original soil profiles (FRA-71 project) Soil Survey - Crosby & Kokomo Series

Chemically Stabilized Subgrade RPCC from adjacent bridge demolition used in fill Although allowed, RPCC was place to subgrade elevation Do not placed material at least 1-foot below the flow line of underdrains (203.03.E)

Item 208 Rock Blasting Deleted use of the term trim blasting as a synonym for cushion blasting Trim blasting, still used in SS 862 Rockfall Protection, refers to low energy removal of large rock blocks or overhangs Changed a water quality test parameter to sulfate Removed a reference to a specific lightning detector model.

Supplemental Specifications Revised and Supplements 4 Supplemental Specifications 2 Supplements Added 1 Supplemental Specification 2 Supplements Deleted S-1016 Loss On Ignition of Topsoil replaced by AASHTO T 267 in Items 653 and 659

Supplemental Specification 840 Mechanically Stabilized Earth Walls Added two new systems Tabbed (punched) steel strips (Sanders MSE) Modular block w/ geogrids (Redi-Rock Positive Connection) Revised design submittal requirements: Competent individuals to prepare and check the design calculations and drawings Preparers and checkers to initial each sheet, and shall be different individuals One Ohio P.E. to sign, seal, and date design calculations and drawings submittal

Supplemental Specification 840 Mechanically Stabilized Earth Walls Added emphasis to design requirements, which were sometimes not followed by the suppliers Use only one soil reinforcement system for the entire length of the retaining wall. mixing steel strips and steel ladders Aesthetic treatment limits extend from the top of the leveling pad to the top of the uppermost facing panel. plain finish panels below groundline, behind barriers, and behind coping

Supplemental Specification 861 Geogrids for Subgrade Stabilization Required that geogrids are to be punched and drawn polypropylene Modified geogrid material properties to include available products and qualify more suppliers Added Designer Guidance to include an Alternate design to be able to use a proprietary geogrid

Supplemental Specification 862 Rockfall Protection Added an excavation pay item for removal and disposal of material from the rock slope, which include both previously fallen and scaled material Method of measurement determined during plan preparation by plan note, either: By a three-dimensional volume method By the measured in vehicle method

Supplemental Specification 863 Reinforced Soil Slopes Added guidance to the Designer Note to address: Roadway geometrics may concentrate storm water runoff and cause severe erosion on the slope Enhanced erosion protection measures, beyond simply establishing vegetation, may be needed Potential measures: runoff diversion or armoring with dumped rock, geosynthetics, or tied concrete blocks

Supplement 1015 Compaction Testing of Unbound Materials Documentation requirements for technicians Use separate forms for each material/pay item Fill out forms completely Provide phase number, test location (station, offset, wall number) Provide gauge readings and backup calculations for trench or moisture corrections Require minimum weight of 30 lbs for the concrete block used for Proctor mold compaction

S 1015 - Compaction Testing Sample soil from area directly under the gauge Proctor mold on a concrete block or surface when compacting sample Block weight not in Supplement 4 thick block or 8 cube Technician was using this concrete cylinder, 12 lbs

S 1015 - Compaction Testing Added minimum weight of 30 pounds to Supplement Adequate size shown Bottom of mold completely supported on block MOP lists minimums Concrete block 4 x 12 Cinder block 6 x 12

Supplement 1015 Compaction Testing of Unbound Materials Guidance on performing Test Sections Use production equipment and materials Construct a new test section when the material changes or supporting material changes For Method A, use only the OMC from the laboratory moisture-density curve For Method B, use new material on a new adjacent area for each moisture content section Maximum dry density from the test section is used for compaction control

Supplement 1120 Mixture Design For Chemically Stabilized Soils Sulfate content now determined by new Supplement 1122, which is similar to TEX-145-E method For phased construction, collect in-place soil samples from locations distributed across the treated area of each phase Additional reporting requirements Geographic coordinates of sample locations Station limits and construction phase of treatment recommendations

Supplemental Specification 867 Temporary Wire Faced Mechanically Stabilized Earth Wall Issued April 15, 2016 Replaces designer written plan notes Similar to SS 840

SS 867 TWFMSE Wall Preconstruction meeting with supplier representative Bulging wire facing panels were not overlapped

SS 867 TWFMSE Wall Temporary crossing permanent reinforcements Potential for damaging permanent system Shop drawings submitted separately and only showed one wall system Temporary wall designer responsible for correcting conflict

New Supplement 1122 Determining Sulfate Content in Soil Issued July 17, 2015 Replaces TEX-145-E method in S 1120 and GB-1 Essentially same procedure, clarifies ambiguous steps Make 3 filtrate samples from 3 soil sample splits 16 to 24 hour soaking time Gravimetric or vacuum filtration procedures Specifies filter paper porosity Zeroing of colorimeter to filtrate Stop testing when sulfate content > 8000 ppm

New Supplement 1123 Geotextile Fabrics Prequalification Procedure Issued April 17, 2015 All approved companies required to participate in the NTPEP audit program for geotextiles. Private Label companies allowed to be listed as long as they follow the NTPEP program. Allowed geotextiles listed on the Department s Approved List, rather than the Qualified Products List. Primarily, affects how project personnel accept the materials in the field.

Construction Manual Of Procedures New 2016 Edition to be published 12/23/2016 Revised to include changes made to 2016 C&MS Minor updates and edits for most Items SS 840 MSE Walls cleaned up, brought up-to date, edited for content; no policy changes. S 1015 Compaction Testing of Unbound Material reorganized, correct references, cleaned up.

Revised Figure 204.G Subgrade Treatment Chart old geotextile

MOP Documentation Revision Documentation Requirements sections being revised to point to a construction web SharePoint site that will house work inspection forms. Eventually, these will be Quality Conformance Checklists and the Quality Inspection Frequency Procedure when e-construction is implemented. Daily diaries stored in SiteManager cannot be electronically searched.

Consultant Inspection Prequalification Started in October 2013 Supplement 1121 Certification of Nuclear Density Gauges & Operators Currently administered through Office of Consultant Services

Written Testing Verify that Soil & Aggregate Inspectors know ODOT s procedures for compaction testing of unbound materials Supplement 1015 Written test 30 multiple choice questions 90 percent to Pass Test taken 463 times to 309 individuals

Compaction Prequalification Testing Results Number of NDG Operators Tested = 309 Through 6/17/16

Compaction Prequalification Testing Results Testing through 6/17/16

MSE Wall Inspection Reject panels with connectors bent > 15 Bending may crack galvanization

MSE Wall Inspection Repair of coating not acceptable Replacement connector has been used, but should not become acceptable.

MSE Wall Inspection Power driver scratched galvanization on connector Washer will protect coating Install bolts from bottom with washer & nut on top

MSE Wall Inspection Backfill not placed to bottom of soil reinforcement at back of panel

S 1015 - Test Sections Test Section Method A used for granular materials: Items 304, 611 & 840 Lab Moisture-Density Curve used only for the Optimum Moisture Content For compaction acceptance, use Maximum Dry Density from the test section

S 1015 - Test Sections Actual production equipment Test Area: 400 to 10 SY Witnessed by ODOT Provide test section results to compaction inspector New test section needed when materials or supporting material changes Test Section Method B: Use new material on new area for each moisture content

QUESTIONS Stephen.Slomski@dot.ohio.gov 614 466 4318 or Lunch