Flood Risk Assessment. Reach Community Solar Farm

Similar documents
Lift irrigation Using man or Animal power Using Mechanical or Electrical Power Flow irrigation a)inundation Irrigation b) Perennial Irrigation Direct

Natural Flood Management. Measures & Multiple Benefits. Steve Rose (JBA)

Recommended Resources: The following resources may be useful in teaching this lesson:

06/01851/MIN CONSTRUCTION OF A NOISE ATTENUATION BUND AT Hermitage Farm, Newport Road, Moulsoe FOR NGW and EF Richards

Trenches combined with living hedges or grass lines Rwanda - Imiringoti

Flood Consequence Assessment. Proposed Commercial Development, Tank Farm Way, Sully

Unit E: Basic Principles of Soil Science. Lesson 7: Understanding Soil Erosion and Management Practices

Section 8: Amended Soil Mounds. 8. Amended Soil Mounds

NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

Page 1. Name:

NORTH WINCHESTER FLOOD WATER MANAGEMENT SCHEME

Streamlines V2, n2 (May 1997) A Newsletter for North Carolina Water Supply Watershed Administrators

BUILDING A WATERSHED MODEL

Very slight to negligible limitations no special land management practices required.

Pahiatua Waste Water Treatment Plant Wetland Erosion and Sediment Control Plan (ESCP)

Attachment 12 Stage 1 Flood Risk Assessment (IE RP-0001)

Surface Water Drainage Pro-forma for major developments

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Understanding Soil Erosion and Management Practices

FACTSHEET INTRODUCTION. help rebalance the water cycle, mitigate the effects of climate change and improve human health and livelihoods.

Radical Terraces Rwanda - Amaterasi y'indinganire

The Islamic University of Gaza- Civil Engineering Department Sanitary Engineering- ECIV 4325 L5. Storm water Management

Hydrology of the West Campus, SUNY Stony Brook

Drainage, Sewerage System, Groundwater and Surface Water drainage

DYASON S KLIP SOLAR ENERGY FACILITY 1 (PTY) LTD. STORMWATER MANAGEMENT PLAN

Design and Installation Guidelines for Retaining Walls. 1 P age. Geo Products, LLC 8615 Golden Spike Lane Houston, TX Phone:

PART 1 GENERAL REQUIREMENTS

Closure Plan Ash Disposal Area PGE Boardman Power Plant

Constructed Wetland Use in Nonpoint Source Control

Saturated Buffer. Subsurface Drainage PURPOSE N REDUCTION LOCATION COST BARRIERS

Soil Permeability Demonstration

Chapter 7. Street Drainage. 7.0 Introduction. 7.1 Function of Streets in the Drainage System. 7.2 Street Classification

Application for resource consent Form B Damming and diversion of water

Of vital importance..

Applying landforming to reclamation: A case study in Central Appalachia

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1

Straw Bale Barrier. - Along the face and at grade breaks of exposed and erodible slopes to shorten slope length and spread runoff as sheet flow

In preparation for constructing buildings on a property, the builder. Site Preparation CHAPTER

Temporary Watercourse Crossing: Culverts

Pasquia Area Drainage and Pumping System

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

Brisbane River Catchment Flood Study overview

Stream Reaches and Hydrologic Units

16.0 Water Quality Management Criteria for Developed Land

THE CARIBBEAN S MOST BEAUTIFUL WASTEWATER TREATMENT SYSTEM: CONSTRUCTED WETLAND AT ANTIGUA, W. I.

Issue paper: Aquifer Water Balance

Green cane trash blanket Australia - Trash blanket

Design criteria, Flooding of sewer systems in flat areas.

Straw Bale Barrier. Parallel to a roadway to keep sediment off paved areas

GEOGRAPHY OF THE FERTILE CRESCENT. Chapter 3 Section 1

Conservation Practices. Conservation Choices. These five icons will show the benefits each practice offers... 6/4/2014

6.0 Runoff. 6.1 Introduction. 6.2 Flood Control Design Runoff

Land Management and Flooding. Where are we now?

10.1 INTRODUCTION 10.1 DRAINAGE

DIVISION SEVENTEEN FLOODPLAIN MANAGEMENT WATER BODY PROVISIONS. For the purposes of this Section, the following definitions shall apply:

Understanding flood risk

Baynards Park, Cranleigh, Surrey

STORM WATER MANAGEMENT REPORT

KDOT TEMPORARY EROSION - CONTROL MANUAL

Agricultural/Rural Riparian Buffer Analysis

E. STORMWATER MANAGEMENT

Construction of Dariali HEPP. Reinstatement Plan

The Flood Risk Implications of Strategic Development at Barnham / Eastergate / Westergate

Created by Simpo PDF Creator Pro (unregistered version) Asst.Prof.Dr. Jaafar S. Maatooq

iv) Alberta fish weirs

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR GRASSED WATERWAYS. Definition. Purpose

RMB Chivenor Flood Defence Scheme. Non-Technical Summary FINAL. Version 3.0

Topic: Site Formation

3.8 Effluent distribution and irrigation systems. Managing effluent for irrigation. Systems for land application. Recycling irrigation tailwater

TORO ENERGY LAKE MAITLAND DEWATERING AND WATER BALANCE REVIEW

Performance Floors for Warehouses and Distribution Centres. Kevin Dare, Managing Director, Face Consultants Ltd.

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Sustainable Catchment Area Management Planning (SCAMP NI)

LAYING IBSTOCK CLAY PAVERS FOR PERMEABLE PAVEMENTS

Installation and Maintenance of Erosion Control BMPs

Nancy L. Young, Forester USAID/USDA Natural Resources Conservation Service

PART I: ASSESSMENT OF WETLAND HYDROLOGY AT RESTORATION SITES PART II: CLIMATE CHANGE IMPACTS ON WETLAND HYDROLOGY BOUNDARIES. Mike Vepraskas NC State

PROJECT NO A. ISSUED: February 29, 2016

Regulatory Guidance Letter 96-02

Flood Protection Provided By Our Lagoon Drainage System

TES Industrial Development SW ¼ SEC Lacombe County Outline Plan

Chapter 6. Hydrology. 6.0 Introduction. 6.1 Design Rainfall

BENELUX: WATER CONSERVATION AND FARMER PARTICIPATION CASE # 29

SABI Code of Practice for On-farm Irrigation Design

6.0 SITE EROSION POTENTIAL AND EVALUATION. 6.1 General

KENT BREEZE WIND FARMS

Adaptation planning at different spatial scales

Departments of Agronomy C709 Conservation Farming and Biological and Agricultural Engineering. Permanent grass cover

Division 8 Intensive Animal Husbandry Code

Placement and Interpretation of Soil Moisture Sensors for Irrigated Cotton Production in Humid Regions SITE SELECTION IN A FIELD OBJECTIVE

Flood Risk Assessment

Soil Resources Analysis Hurricane Ivan-RCW Expansion Project Conecuh National Forest

Vision The resilience of water supply and sanitation in the face of climate change. Technology fact sheets

At least 2 feet above the seasonal high water table Overflow path or structure provided

Geoenvironmental impact assessment of a landfill for solid chemical wastes

Adaptation planning at different spatial scales

The Effect of Surface Texture on Evaporation, Infiltration and Storage Properties of Paved Surfaces

Transcription:

Flood Risk Assessment Reach Community Solar Farm Andy Rankin 4 th February 2014

Introduction 1.1 Reach is a village of approximately 100 households on the edge of the Fens. We intend to construct a small solar farm that should generate sufficient electricity each year to match the consumption in the village. The solar farm will be owned and operated by a non-for-profit co-operative. 1.2 We have identified a site on the outskirts of the village that is suitable for our purposes, and have a provisional agreement with the owner to lease the land. An 11kV line crosses the land, and UK Power Networks have confirmed that it will be possible to connect into this line. 1.3 The site is approximately 1 hectare. Around 1/3 of area will be covered with solar panels mounted on steel frames. The remainder will be kept as grassland, and we intend to mount the panels sufficiently high off the ground that grazing of sheep can continue on the site. 1.3 The land is very gently undulating. Some of the land lies within flood zone 1, but towards the eastern side of the site it falls away slightly, and falls within flood zones 2 and 3. 1.4 The site benefits from flood defences built along the banks of the River Cam, Reach Lode and Swaffham Bulbeck Lode. 1.5 We consider here the risk of increased run-off from the solar panels. We also consider whether the site might be at risk if the flood defences along the Cam or Lodes were to be breached. Figure 1: Proposed site for community-owned solar farm. Picture taken from the junction of Little Fen Drove with Blackberry Droveway, looking North.

2 Site Description 2.1 The site lies at the edge of the fens. To the south-east the land rises gently towards the villages of Reach and Swaffham Prior. To the north, the land gradually falls to below Ordnance Datum. A network of drains managed by Swaffham Internal Drainage Board divert water within this area to the pumping station at Upware, which pumps it into the River Cam. 2.2 The lowest point in the site is approximately 2m above the water level in the drain which runs along the north-western and north-eastern borders of the field. Figure 2: Location plan. The site (marked in red) lies just below the 5m contour and is drained by ditches maintained by Swaffham Internal Drainage Board on the north-eastern and north-western boundaries. To the north the land drops to below sea level.

Figure 3: Site plan with flood map overlay. The boundary of the region covered by solar panels is shown in red. Light blue is flood zone two, dark blue is flood zone three. The hatching indicates that the area is protected by flood defences.

3 Risk of inundation and over-topping of flood defences 3.1 Although the site lies partially within zones with a theoretical risk of flooding, in practice the flood defences along the Cam and along Swaffham Bulbeck Lode and Reach Lode, along with the extensive network of maintained drainage ditches and the pumping station at Upware, maintain safe levels within the area managed by the Swaffham Internal Drainage Board. As long as the flood defences remain intact and operational practices stay in place to maintain the levels there is a very low likelihood of flooding at the site. 3.2 It is difficult to assess the risk of over-topping or failure of the flood defences. At present the defences are well maintained, and it is considered extremely unlikely that a major failure will occur. In the event that a failure did take place however, levels could in theory eventually rise to an extent that flooding could occur over parts of the solar farm site. 3.3 It should be noted that there is considerably lower land to the north of the site; much of Adventurer's Fen and Swaffham Prior Fen lie below Ordnance Datum. In the event of a failure, an area of many square miles of this lower-lying land would have to flood to a depth of several meters before the solar farm was threatened. The risk of this happening is extremely low. 3.4 Panels will in any case be mounted such that junction boxes and isolators are at least 1m above ground level. Armoured cable, which can withstand flooding, is the only electrical component that will be used below this level. Even in the very unlikely event of breach of the river defences severe enough to cause flooding at the site, water levels are not likely to reach the height of any electrical component that would be affected by the flood waters. Figure 4: Mounting frames. The only components sensitive to water ingress are the junction boxes and isolators shown in red. Water levels would have to reach at least 1m before these were affected by flood waters.

4 Run off 4.1 As solar panels are impermeable, they will shed water to the lower (southern) edge of each row of panels. There will therefore be a small strip beneath the lower edge of each row of panels that will receive a slightly higher amount of rainfall, while the strip of earth directly below each row of panels will be drier. If the ground under the front of each row of panels is not able to absorb the water, run-off could occur. Figure 5: Run-off due to concentration of rainfall to the front edge of each row of panels. 4.2 We understand that there has been at least one case where solar panels, installed on a steep slope on compacted clay, have caused increased run-off owing to the infiltration rate of the land not being sufficient to absorb the increased water falling upon it. 4.3 The principal factors affecting infiltration rate are soil characteristics, vegetation cover, and slope angle. 4.4 Grass cover helps reduce runoff and erosion by slowing movement of water in the affected areas. 4.5 Clay soils are less permeable and at more risk of flooding than sandy or peaty soils, and permeability can be further reduced by compaction of soils for example by vehicle movements during development.

4.6 Slope angle is a very important factor in determining the behaviour of water reaching the ground. Water will run very rapidly from a steep slope, but will pool on flatter areas, allowing it to permeate into neighbouring drier areas. 4.7 At the proposed site for the community-owned solar farm at Reach, the following factors will reduce the likelihood of increased run-off: We intend to retain vegetation beneath and around the solar panels. The ground is fairly level, so even if the infiltration rate of the soil is exceeded the velocity of any standing water that does begin to form will be slow, giving a greater likelihood that it will be absorbed by the drier land under the panels. The ground at Reach is well drained. Recent archaeology studies showed between 300 and 500mm of free-draining soil above the clay subsoil throughout the site. As the site is small total vehicle movements over the ground during the build will be limited, so the ground will not be compacted to the extent that it would be in larger developments. Figure 6: Soil characteristics. The clay subsoil is covered with well-drained topsoil throughout the site.

4.8 Owing to the low ground slope, retention of vegetation, and well drained soils we do not expect measurably increased run-off as a result of the installation of the panels. 4.9 Swaffham Internal Drainage Board had no objections to the proposal when contacted in our initial Screening Opinion request to the Council. They will however be consulted again when the planning application is lodged. 5 Drainage Checks 5.1 As solar farms are relatively new and the effect of increased run-off is uncertain, the Environment Agency have recommended for similar sites that monitoring be undertaken at six monthly intervals for increased flooding or erosion [1]. If problems are encountered at the site, remedial action can then be taken. 5.2 We propose the following simple monitoring scheme for problems due to increased run-off. The checks will be undertaken by staff visiting the site for maintenance visits at 6 monthly intervals, and the results of the checks recorded. Check Check for the presence of standing water at the site Check for presence of water channels forming, or soil erosion Check that ditches bounding the site are not blocked or overgrown Action required If standing water is present on the land a drainage engineer should be consulted. If water channels are developing or there is any evidence of soil erosion a drainage engineer should be consulted. Ditches should be cleared if necessary. The local Drainage Board should be informed if there are any blockages in the drains that they maintain. 5.3 If the regular monitoring demonstrates that erosion or flooding is occurring, professional advice will be sought on a course of action to improve the drainage. [1] http://docs.huntsdc.gov.uk/anitepublicdocs/00332751.pdf

6 Summary 6.1 Parts of the site lie within flood zones 2 and 3, and if undefended would be at high risk of flooding during a 100-year flood event. 6.2 There are however extensive flood defences along the River Cam and the Lodes, together with a network of drainage ditches to drain the area to the pumping station at Upware. The flood defences and drainage system should prevent flooding in normal circumstances. 6.3 There remains a small possibility of breaching of flood defences or over-topping. However, as the site is several meters higher than the land to the north, a very considerable volume of water would have to flow into the area before the site itself was threatened by floodwater. 6.4 Solar panels are impermeable, and will shed water to the lower (southern) side of each row. There will therefore be a slight increase in water reaching the ground at these points. However, the ground at the site is well-drained, and vegetation will be retained at ground level. As the ground is flat water that falls from the panels is likely to permeate into the drier ground behind rather than run off as surface water. 6.5 A perimeter track allows access to nearby drains for maintenance. This is carried out regularly by the local Drainage Board. 6.6 Checks will be undertaken at six-monthly intervals for the presence of increased standing water or erosion at the site. If problems are encountered, professional advice will be sought and action taken to improve the drainage. 6.7 There are precedents for planning permission being granted in similar locations. For example, the nearby solar farm at Chittering is largely in flood zone three, but is also protected by the flood defences of the River Cam catchment. The Chittering development is more than an order of magnitude larger than the scheme that we propose, and is at a lower elevation.