Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood

Similar documents
Factor Potential Effects Mitigation Measures

Welcome. Public Information Event. Dufferin Sanitary Trunk Sewer (STS) System Improvements Municipal Class Environmental Assessment Study

GRAND NIAGARA Proposed Secondary Plan

Welcome. Metro North Transmission Project Burnaby Community Information Open House March 8, About the Metro North Transmission Project

WELCOME! Mill Creek Daylighting Technical Feasibility Study. Thank you! Open House December Please sign in and get a comment form.

Preferred Elevated Tank Site

Metro North Transmission Project Project Update October 2017

Ottawa-Trussler Area Sewage Facility Class Environmental Assessment

407 TRANSITWAY. Planning & Preliminary Design

Welcome to the Boulevard Lake Dam Class Environmental Assessment. Public Information Session #1. June 14, 2016

The Corporation of The City of London

Works, services and infrastructure code

DISTRICT OF NORTH VANCOUVER GUIDELINES FOR THE DEVELOPMENT OF CONSTRUCTION TRAFFIC MANAGEMENT PLANS

The Don River and Central Waterfront are among the most degraded waterways in the City of Toronto.

Sudbury to Hudson Transmission Reliability Project

Canadian Solar Developers Ltd.

18 Cumulative Impacts and Interaction of Effects

Coire Glas Pumped Storage Scheme

Canadian Niagara Power Inc. International Power Line Rebuild Project Fact Sheet

Sudbury to Hudson Transmission Reliability Project Frequently Asked Questions (FAQs)

ENVIRONMENT ACT TERMS OF REFERENCE NOVA SCOTIA DEPARTMENT OF TRANSPORTATION AND PUBLIC WORKS. Beaver Bank Bypass

PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014

Your guide to the. SOUTHERN ALBERTA Transmission Reinforcement

LAND DEVELOPMENT AND PLANNING FORUM 2014 THE 2014 PROVINCIAL POLICY STATEMENT AND ENVIRONMENTAL PROTECTION

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

District of North Vancouver Construction Traffic Management Plan Guidelines

3.6 Riparian Ecosystem Wildlife

Welcome to the Public Information Centre. Red Hill Business Park South Transportation Master Plan Addendum. June 25, :00 p.m. to 8:00 p.m.

KENT BREEZE WIND FARMS

Environment & Conservation Introduction

Airport Road from 1 km North of Mayfield Road to 0.6 km North of King Street Public Information Centre #1

San Francisco Water Power Sewer Operator of the Hetch Hetchy Regional Water System

Chapter 10 Natural Environment

TS 801 ELECTRICAL WORK - GENERAL TABLE OF CONTENTS

ESTIMATE OF QUANTITIES

Information Sheet - Mountain Highway Interchange Noise Assessment and Sound Mitigation

Downtown Estes Loop Project Frequently Asked Questions

Barlow Solar Energy Centre Project Summary Report

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

Managed Forest Tax Incentive Program Encouraging Responsible Forest Stewardship Ministry of Natural Resources and Forestry

Significant Unavoidable Adverse Impacts

WELCOME. Please sign in Representatives are available to answer questions Please complete a comment sheet

Nance County Zoning Regulations for Wind Energy Conversion Systems

Electric Service Handbook

Viridor Waste Management. Proposed Development of an In-Vessel Composting Facility. Land at Exide Batteries, Salford Road, Bolton

Rural Living Environment

SEARs project justification and conclusion

Municipal Class Environmental Assessment for Pottersburg Creek Slope Stability Study South of Hamilton Road, Schedule B

Appendix H Mitigation Monitoring Plan

Goal 2: Recommendations: Timeline Costs Partners. Align policies with the community vision for canopy establishment.

Environmental Information Worksheet

OPERATION PHASE: ENVIRONMENTAL MANAGEMENT PROGRAMME

Chapter 13: Wildlife and Vegetation

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

SOUTHWEST CONNECTICUT RELIABILITY PROJECT

CMPDI. 4.6 Mine Closure Plan

Gainesville Technical Center 5399 Wellington Branch Drive Gainesville VA Phone (703)

Introduction. They can help ensure that all key issues and elements have been considered; They help ensure that the review process is systematic; and

E.L. Smith Solar Farm Project Open House. Lower Level

Natural Resource Management of Pipeline Infrastructure

CONSTRUCTION SPECIFICATION FOR INSTALLATION OF CABLE

NTW.1 Network Utilities

CHAPTER 4. IMPACT ASSESSMENT AND ESTIMATED LEVEL OF TAKE

Toronto and Region Conservation 2017 Progress & 2018 Budget Peel Council

ESIA for the proposed Baynes Hydropower Project:

CIRCUIT C7BM (W6CS STR 1 JCT X BARRETT CHUTE SS) CLASS ENVIRONMENTAL ASSESSMENT. Draft Environmental Study Report

Welcome to our Open House!

Theme Comment Response. All neighbours should be entitled to revenue sharing, not just those who have signed an option agreement with Suncor.

Inveraray to Crossaig Overhead Line Reinforcement

Environmental Assessment Matrix

(Condensed from National Electric Code)

EPCOR Distribution & Transmission Inc.

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number:

FINDINGS OF FACT AND STATEMENT OF OVERRIDING CONSIDERATIONS

Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11

EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE

C&B Alberta Solar Development ULC

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

PROPOSED PIPELINES TO SERVE THE COMMUNITY OF FENELON FALLS: ENVIRONMENTAL REPORT

WATERSHED. Maitland Valley. Report Card 201

TORONTO GREEN STANDARD VERSION 2.0

RE: Initiating Near Term Transmission Components of the Central Toronto Integrated Regional Resource Plan

Wetlands Project Guidance

introduction 1 On behalf of db symmetry we are pleased to welcome you to view our emerging plans for a new logistics park at Rugby.

Construction of Dariali HEPP. Reinstatement Plan

State Route 8 Bridge Replacement Project

CHAPTER 9 DISCUSSIONS, CONCLUSIONS, AND RECOMMENDATIONS

Toronto Hydro s Climate Adaptation Actions

Standard Performance Attributes for Transportation Projects

Draft Environmental Impact Statement (DEIS) Public Hearing

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:

The Narragansett Electric Company d/b/a National Grid. and Clear River Energy LLC. (Burrillville Interconnection Project) RIPUC Dkt. No.

U.S. DEPARTMENT OF THE INTERIOR FISH AND WILDLIFE SERVICE OKLAHOMA ECOLOGICAL SERVICES FIELD OFFICE

1. Urban Design. Current Land Uses

Dust generation/ Air pollution. Noise and vibration. Water pollution. Drainage and sedimentation

General Plan Update Workshop 6 Agriculture, Conservation, & Open Space February 23, 2005

NEEDS ASSESSMENT REPORT

USDA Forest Service Lake Tahoe Basin Management Unit Forest Plan Revision Topics Need for Change

TABLE OF CONTENTS. LIST OF FIGURES Figure 4-1: Alternative 1 System Overview Figure 4-2: Alternative 3 System Overview...

Nestlé Waters North America Inc. Special Use Permit San Bernardino National Forest Project Proposal

Transcription:

Leaside to Main Infrastructure Refurbishment Project Strengthening the transmission system in your neighbourhood

Purpose of this Public Information Centre Provide you with an update on Hydro One s infrastructure project in your community Review Class EA consultation activities and field studies completed to date Present the preferred underground cable route selected between Leaside Transformer Station (TS) and Todmorden Junction (JCT) Provide information on construction methods and techniques Outline next steps in the planning and approvals process and additional opportunities for your participation Solicit your input and address comments or concerns you may have

Proposed Project To ensure a continued, reliable supply of electricity to the area, Hydro One will: 1. Replace two sections of existing underground 115 kilovolt (kv) cable located between: Leaside Transformer Station (TS) and Todmorden Junction (JCT) and; Lumsden JCT and Main TS 2. Replace existing overhead shield wire, used to protect the line from lightning, located between: Todmorden JCT and Lumsden JCT

Need for Leaside to Main Project Hydro One must refurbish aging transmission infrastructure to ensure a continued safe and reliable supply of power to Toronto Hydro customers in the area and minimize the risk of future power interruptions The existing underground cables were installed in the1950s and are approaching their end of life Replacing the existing overhead shield wire with new fibre optic wire will enhance Hydro One s ability to monitor and control the transmission network This project will strengthen and modernize the electricity grid that powers your city every day

Project Infrastructure Junction: The point where a transmission line switches from overhead infrastructure to underground cables Lumsden Junction Leaside Transformer Station Transformer Station: A station with power transformers and other electrical equipment arranged to transfer power from one voltage level to another

Hydro One s Role in Delivering Electricity to Your Community Ontario Power Generation and Private Generation Companies Hydro One Network Transformer Station Generation Step-up Transformer Station Transmission Lines 230,000 volts - 500,000 volts Transmission Lines 115,000 volts Junction 115,000 volt Underground Cable Home Wiring 120/240 volts Pole-Mounted Transformer Distribution Lines 27,600 and 13,800 volts Toronto Hydro Step-down Transformer Station Shared

Class EA Study Area

Leaside TS to Todmorden JCT Underground Cable Routes Evaluated Two feasible options were identified and evaluated for replacing the underground cable between Leaside TS and Todmorden JCT Option 1: Follow existing route - Directional drilling and micro-tunneling were construction methods explored where surface trenching was not possible (steep slope, east of Leaside Bridge) Option 2: Cross Millwood Road, follow existing overhead Right-of-Way (ROW), run along existing access road east to Todmorden JCT

Leaside TS to Todmorden JCT Route Selection Criteria Each route was evaluated and scored on the following criteria: Natural Environment Area of natural vegetation, particularly woodland, that requires clearing Number of trees requiring removal Crossings of environmentally significant and sensitive areas Proximity to, and crossings of, watercourses Presence of Species at Risk Natural hazards (eg. erosion concerns, slope stability) Technical & Cost Duration of construction Number of significant obstacles Complexity of construction method Adequacy of construction workspace Socio-economic Environment Proximity to residences, schools, hospitals, businesses and other facilities Length of road closures required during construction Disruption to street infrastructure Disruption to traffic and transit First Nations Cultural/traditional/historical land or resources identified Conservation interests identified Potential effects on fish, wildlife and botanical species of interest

Route Evaluation Results Options 1 and 2 scored similarly on many of the criteria evaluated with the exception of the following: Option 1 Option 2 This route is favorable with respect to: Potential to maintain slope stability Lesser effects on Species at Risk This route is favorable with respect to: Less complex construction methods required Less disruption to transit Less disruption to pedestrians Lesser effects to recreational resources Lesser effects to residential/ commercial properties Based on the evaluation and input received through consultation, Option 2 has been selected as the preferred route.

Leaside TS to Todmorden JCT Preferred Route Option 2

Lumsden JCT to Main TS Underground Cable Route It is proposed that the new cables be installed in the same location as the existing cables: Makes best use of existing underground ROW Alternative routes would increase construction complexity; at least one additional 90º turn would be required Area is heavily congested with other underground utility infrastructure

Environmental Mitigation Measures Measures to reduce, prevent or mitigate potentially adverse environmental effects during design, construction and operation could include: Controlling noise, mud, dust, traffic disturbances and other nuisance effects during construction Protecting cultural heritage resources Minimizing soil erosion and compaction Minimizing effects on terrestrial and aquatic resources Environmental management during construction and operation Please share your comments and feedback with us!

Underground Cable Replacement Construction Methods Examples of surface trenching Cross linked polyethylene (XLPE) cable The new underground cables will be encased within a duct bank rather than directly buried in the ground. This will allow for ease of future maintenance, as required. The construction process for replacing these cables will involve: Surface trenching (approximately 2 m x 2 m) and constructing a concrete duct bank Installing modernized XLPE cables, which do not contain insulating oil

What Can Local Residents and Businesses Expect? Leaside TS Todmorden JCT One or two lanes on Millwood Road will be restricted for short durations. Hydro One is working with Toronto Hydro to coordinate planned work and avoid multiple disruptions. Traffic control measures will be in place as required. Hydro One will install a double gate system to allow access to the existing trails that cross the ROW when construction vehicles are not present. Signage will be in place on other trails that require temporary closure. As consultation planning progresses, additional details will be determined. These will be presented at the pre-construction PIC.

What Can Local Residents and Businesses Expect? Main TS Lumsden JCT Entrances to businesses will remain accessible during construction. Small sections of Main Street and Lumsden Avenue will be restricted to one lane as construction progresses along each street. Traffic control measures will be implemented as necessary. Bus routes along Main Street may require re-routing. Hydro One is working with the TTC to minimize disruption. Driveway entrances to homes along Main Street may be restricted during work hours for a short duration. Driveway access will be restored after working hours using metal plates. As consultation planning progresses, additional details will be determined. These will be presented at the pre-construction PIC.

Tree Protection and Preservation Construction of this project will require the selective removal and/or trimming of some vegetation in various locations Hydro One is working closely with City of Toronto Urban Forestry Services and Toronto Region Conservation Authority to identify vegetation that requires removal and develop appropriate restoration and mitigation plans

Biodiversity Initiative Hydro One will be inviting interested parties to participate in biodiversity workshops to collectively identify and select initiatives to compensate for potential project effects to the natural environment Biodiversity initiatives will be selected based on a set of evaluation criteria (eg. initiatives in closer proximity to the project area will be considered more favourable) Examples of biodiversity initiatives that may be considered include: - Planting of native species - Habitat creation for pollinator species (eg. bees) - Removal/control of invasive species We anticipate the first workshop will be held in 2017, with implementation planned for 2018 Join our project contact list to receive future updates on this initiative

Natural Environment Data Collected Hydro One retained Golder Associates Ltd. to conduct natural environment surveys within the study area (i.e. within 120 m of the proposed project) as part of the Class EA. Surveys included: Ecological Land Classification - 27 vegetation communities identified Botanical inventory - 83 plant species/species groups observed, including one Species at Risk (butternut) Wildlife inventory - 72 wildlife species observed, including six Species at Risk (eg. barn swallow) Butternut observed during field surveys

Natural Environment Data Collected Breeding bird surveys - 50 bird species observed Frog and toad call count surveys - American toads, green frogs and gray tree frogs observed Bat acoustic monitoring - Big brown bats and hoary bats recorded using acoustic monitors Golder staff conducting evening amphibian and turtle nesting field surveys, May 2016 Survey station for basking turtles and evening amphibians

Todmorden JCT to Lumsden JCT Shield Wire Replacement Don River Taylor Creek TODMORDEN JCT " ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( ( Massey Creek ( ( ( ( (" LUMSDEN JCT " ( Station or Junction Existing Overhead Skywire Water 1:10,000 [ 0 200 400 m Existing shield wire will be replaced with fibre optic wire, capable of monitoring and controlling high voltage equipment Shield wire replacement is not subject to the Environmental Assessment Act, but is included in the scope of this project

Replacing the Shield Wire Shield Wire Transmission Lines 115 kilovolts Shield wire, also referred to as skywire, is used to protect our equipment from lightning and does not carry electricity To replace this wire, crews will manually climb towers to pull new shield wire between existing equipment Temporary roads may be required for small vehicle access to tower structures Access to trails along Taylor Creek Park may be restricted for short durations

Timeline PUBLIC AND STAKEHOLDER CONSULTATION Briefing for City of Toronto elected officials Class Environmental Assessment initiated Public Information Centre #1 Introduction to project Community Walks in the project areas Field Studies completed Public Information Centre #2 Notice of Completion & Draft Environmental Study Report available for a 45-day review period Final Environmental Study Report filed with the Ministry of the Environment and Climate Change Anticipated Start of Construction. Prior to this, a Pre-Construction PIC will be held. Hydro One will also obtain other non-ea permits & approvals required. December 2015 January 2016 February 8 & 10, 2016 Spring 2016 Spring 2016 August 9, 10 & 17, 2016 Current Stage September 2016 Fall 2016 Early 2017, contingent on the outcome of the Class EA process

Your input is important to us Thank you for joining us at this Public Information Centre. Please join our project mailing list and complete a comment form before you go. To share concerns or request information call or email us at: Telephone: 416-345-6799 Email: Community.Relations@HydroOne.com www.hydroone.com/projects/leasidetomain