A. Testing Laboratory Services: Section B. Excavation, Site Fill and Rough Grading: Section Sub-Base Course Material (If requested).

A. Texas Department of Transportation 2004 Standard Specifications for Construction and Maintenance of Highways, Streets and Bridges (TxDOT).

DIVISION 32 EXTERIOR IMPROVMENTS

SECTION BITUMINOUS CONCRETE PAVEMENT

SECTION ASPHALT PAVING

2014 Capital Project Phase 3 Grand Island Central School District Cannon Design Project No SECTION PAVING PART 1 - GENERAL

SECTION ASPHALT PAVING

PERMEABLE INTERLOCKING PAVERS

CHAPTER 500 STREET PAVEMENTS, CURB, GUTTER AND SIDEWALK CONSTRUCTION SPECIFICATIONS

4.8. Subsurface Infiltration

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS

REQUEST FOR PROPOSAL Asphalt & Concrete Repair

LS 2519 CONCRETE PAVER PAVEMENT RECONSTRUCTION

4.8. Subsurface Infiltration

Asphalt Rubber Chip Sealing DRAFT MAINTENANCE SPECIFICATION. March 22, 2007

PERVIOUS PAVEMENT. Alternative Names: Permeable Pavement, Porous Concrete, Porous Pavers

PAVING SLABS ON A CONCRETE BASE

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

Stanford University Facilities Design Guidelines SECTION SEAL COATS. C. Section : Traffic Striping and Pavement Markings

CITY OF TACOMA RIGHT-OF-WAY RESTORATION POLICY. Guidance on restoration of City Rights-of-Way

Construction Specification for Concrete Unit Pavers

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

SERIES 1100 KERBS, FOOTWAYS AND PAVED AREAS

Summary of the 2011 Changes

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

SECTION 1 BIO-INFILTRATION BUMP OUTS (BIBO)

Municipality of Waterville Public Sidewalk Repair Policy

The Work under this Section consists of performing all operations necessary to complete construction of the leveling course on the prepared subbase.

Extraction and Sieve Analysis ( µm minus) Forming Marshall Specimens, Field Method

CSI SECTION MAINTENANCE OF CONCRETE Repair & Resurfacing with Rapid Hardening, High Strength, Low-Shrink, Non-Metallic Cementitious Materials

SECTION INTERLOCKING CONCRETE PAVERS

City of Brandon Division 2 Standard Construction Specifications Section January 2000 Page 1 of 10 SOIL CEMENT BASE COURSE PART 1 GENERAL

CONCRETE STEPS, HANDRAILS, AND SAFETY RAIL

Section 1 OBC FADS /13 Access to Parking Areas

SECTION 402 PLANT MIX BITUMINOUS SURFACE LEVELING

DRAFT Guidance Specification for Porous or Dense-Graded Asphalt Pavement Structures for Storm Water Management Revised July 28, 2016

SECTION CAST-IN-PLACE CONCRETE

PUBLIC WORKS SKAGIT COUNTY SAMISH ISLAND ROAD SAMISH ISLAND ROAD SLIDE REPAIR

Warm Mix Asphalt (WMA) Guide Specification for Highway Construction

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, EDITION 2007

PART 1 - GENERAL 1.01 General Provisions A. The Conditions of the Contract and all Sections of Division 1 are hereby made a part of this Section.

SECTION CONCRETE PAVING SLABS SET IN MORTAR

for Mortar-Set Concrete Tiling Installations

SECTION SITE CONCRETE

BASE CONSTRUCTION MATERIALS A Aggregate

BIO-AQUIFER STORM SYSTEM

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems

BMP 6.4.4: Infiltration Trench

PERMEABLE PAVERS PHYSICAL AND GEOMETRICAL CHARACTERISTICS - PAVERS DRIVEWAYS, PERMEABLE DRIVEWAYS & PATIOS CHARACTERISTICS CSA A231.

StormTech Construction Guide

HARD COURT/RUNNING TRACK CONSTRUCTION. A. Section Includes: Tennis courts, basketball/volleyball courts, and running tracks.

SPECIFICATIONS FOR NEW WORK CHIP SEAL

PARKING LOT AND ROADWAY MAINTENANCE

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

A Design Review of Waterproofing Codes

TRANSPORTATION & PUBLIC WORKS DEPARTMENT TECHNICAL STANDARDS

BIO-AQUIFER STORM SYSTEM

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

550 Surface Treatments

Proudly Made in the U.S.A.

April 1, CITY OF PORTSMOUTH Public Works Department. Bid # Annual Paving Project ADDENDUM NO. 1 NOTICE TO ALL BIDDERS

DATE: December 10, 2012 REPORT NO. PW CHAIR AND MEMBERS COMMITTEE OF THE WHOLE OPERATIONS AND ADMINISTRATION

Narrow Modular Pavers (NMP) for Sand-Set Installations

CONSTRUCTION SPECIFICATION FOR CONCRETE CROSSWALK INDEX TS SCOPE...3

AMENDMENTS Manual of STANDARD SPECIFICATIONS. Adopted by Standard Specifications Committee. Amendment. No. 4. Published by

4-07 Asphalt Treated Permeable Base (ATPB)

*************************************************************************************************************************

D-1 THE CITY OF HARRISBURG 1 1/2" MIN. ID-2 WEARING COARSE EXISTING STREET SURFACE AC-20 SEALER (ALL AROUND) 1 1/2" MIN. ID-2 BINDER COARSE

MATERIAL SPECIFICATION FOR AGGREGATES - GENERAL

INTERLOCKING CONCRETE PAVERS SECTION 02780

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

SPECIFICATION FOR REINFORCED SOIL WALL

Chapter 5 Hydraulic Structures

Division 32. Exterior Improvements

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

BID # REPAIR AREA OF PARKING LOT DAMAGED BY WATER LINE LEAK SECTION C TECHNICAL SPECIFICATIONS OWNER

At least 2 feet above the seasonal high water table Overflow path or structure provided

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

2016 ACHD Supplemental Specifications to the ISPWC. ACHD QC-QA Procedure

SECTION A1 EXCAVATION AND BACKFILL GENERAL

CRUSHED AGGREGATE BLENDED WITH GRANITECRETE ADMIXTURE SURFACING

SECTION TRENCHING & BACKFILLING

MNDOT PAVEMENT DESIGN MANUAL

ACO Specification Information

ITEM 458 WATERPROOFING FOR STRUCTURES

ITEM 340 DENSE-GRADED HOT-MIX ASPHALT (METHOD)

asphalt applications Asphalt surfacings for high stress areas mpa asphalt Asphalt Information Service Mineral Products Association

How to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc.

LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH

What is it? What is Granular Base Stabilization ti (GBS)? Emulsion Full Depth Reclamation Process

Infiltration Guidelines

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Metal Roof Panels

VIRGINIA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR LATEX MODIFIED EMULSION TREATMENT (MICRO-SURFACING)

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

Section 505. CHIP SEALS

Transcription:

University of New Hampshire University of New Hampshire Scholars' Repository Division 32 Exterior Improvements Chapter 5 Technical Construction and Renovation Standards 1-25-2013 321216 - Asphalt Paving Sandra Hickey sandra.hickey@unh.edu Follow this and additional works at: http://scholars.unh.edu/pdch_5_32 Recommended Citation Hickey, Sandra, "321216 - Asphalt Paving" (2013). Division 32 Exterior Improvements. 1. http://scholars.unh.edu/pdch_5_32/1 This Article is brought to you for free and open access by the Chapter 5 Technical Construction and Renovation Standards at University of New Hampshire Scholars' Repository. It has been accepted for inclusion in Division 32 Exterior Improvements by an authorized administrator of University of New Hampshire Scholars' Repository. For more information, please contact nicole.hentz@unh.edu.

321216 - Asphalt Paving This article is available at University of New Hampshire Scholars' Repository: http://scholars.unh.edu/pdch_5_32/1

SECTION 32 1216 - ASPHALT PAVING 1.1 SUMMARY A. Section Includes: 1. Cold milling of existing hot-mix asphalt pavement. 2. Hot-mix asphalt patching. 3. Hot-mix asphalt paving. 4. Hot-mix asphalt paving overlay. 5. Porous Asphalt: Shall be considered on a case by case basis. Please visit for specifications: a. http://www.unh.edu/erg/cstev/pubs_specs_info/unhsc_pa_spec_10_09.pdf 6. Pavement markings and paint. 7. Bicycle lanes. 8. Bus Stop Pull-Outs. 9. Crossings and Sidewalks. 10. ADA Tactile Warning Strips. B. General: All sitework performed in the preparation and installation of asphalt pavement including sidewalks, fire lanes, streets, and parking lots shall be in accordance with most current version of The Asphalt Institute. This standard shall be used for all subgrade preparation, surface type, composition of mix, compaction, pavement structure and drainage work. In all case existing Asphalt should be reclaimed ground and re-used wherever and whenever possible. Every effort shall be made to use porous parking surfaces as an alternative to standard asphalt for new parking areas. 1. The use of islands shall be limited to areas where it is necessary to control safe flow of vehicle traffic. 2. Locate islands so as not to hinder snow removal operations. 3. Islands shall not be placed in areas such as parking lots for the sole purpose of aesthetics. 1.2 QUALITY ASSURANCE A. Manufacturer Qualifications: A paving-mix manufacturer registered with and approved by authorities having jurisdiction or the New Hampshire DOT. B. Regulatory Requirements: Comply with materials, workmanship, and other applicable requirements of The Asphalt Institute and Department of Transportation of New Hampshire for asphalt paving work. ASPHALT PAVING 32 1216-1

1.3 PROJECT CONDITIONS A. Environmental Limitations: Do not apply asphalt materials if subgrade is wet or excessively damp, if rain is imminent or expected before time required for adequate cure, or if the following conditions are not met: 1. Tack Coat: Minimum surface temperature of 60 deg F (15.6 deg C). 2. Asphalt Base Course: Minimum surface temperature of 40 deg F (4.4 deg C) and rising at time of placement. 3. Asphalt Surface Course: Minimum surface temperature of 60 deg F (15.6 deg C) at time of placement. B. Pavement-Marking Paint: Proceed with pavement marking only on clean, dry surfaces and at a minimum ambient or surface temperature of 40 deg F (4.4 deg C) for oil-based materials and 55 deg F (12.8 deg C) for water-based materials, and not exceeding 95 deg F (35 deg C). 1.4 AGGREGATES A. Coarse Aggregate: ASTM D 692, sound; angular crushed stone, crushed gravel, or cured, crushed blast-furnace slag. B. Fine Aggregate: ASTM D 1073 or AASHTO M 29, sharp-edged natural sand or sand prepared from stone, gravel, cured blast-furnace slag, or combinations thereof. C. Mineral Filler: ASTM D 242 or AASHTO M 17, rock or slag dust, hydraulic cement, or other inert material. 1.5 ASPHALT MATERIALS A. Asphalt Binder: AASHTO M 320 or AASHTO MP 1a, PG 64-22, PG 58-28, or PG 70-22. B. Tack Coat: ASTM D 977 or AASHTO M 140 emulsified asphalt, or ASTM D 2397 or AASHTO M 208 cationic emulsified asphalt, slow setting, diluted in water, of suitable grade and consistency for application. 1.6 AUXILIARY MATERIALS A. Herbicide: Commercial chemical for weed control, registered by the EPA. Provide in granular, liquid, or wettable powder form. Product should be Green approved. 1. Color: White, Yellow B. Pavement-Marking Paint: MPI #97 Latex Traffic Marking Paint. Product should be Green approved. 1. Color: White, Yellow ASPHALT PAVING 32 1216-2

C. Pavement Line and Markings: For durability, maximum visibility and enhanced public safety, unless waived, the University uses NHDOT and Town of Durham reflectorized paint and thermoplastic pavement markings and lines. Ideally, dual centerlines and single fog line/lane mark lines are installed. On core campus low volume streets, single center line and fog line omission may be considered if approved by the Traffic Safety Committee. Resurfaced pavement suggests the preferred use of thermoplastic pavement markings. Ongoing maintenance or over-painting of existing paint or thermoplastic markings requires the use of reflectorized paints to DOT standard. If required, obliteration of existing markings shall be by grinding or abrasion and not overpainting with paint, asphalt or any other material. In general, all pavement lines excluding crosswalks and stop lines should be 4 in width, applied in one pass and in single width. Stop lines shall be 18 in width. Crosswalks shall be standard continental bar style. See Attachment E. On thermoplastic pavement line and marking installations special care should be taken to ensure application on well cured pavement, above minimum ambient temperature application and conforming material mix. Thermoplastic pavement marking standards can be found in detail in 2006 NHDOT Standard Specifications Section 632 - construction requirements. On reflectorized paint pavement markings or over markings, the street should be swept clean and install lines be continuous, straight and pre-marked. The University mandates the use of ASTM approved standard 100% acrylic type, low VOC, fast drying white or yellow suitable for bituminous or concrete surfaces. Reflective beads should be added for street applications. Pavement marking paint standards can be found in detail in 2006 NHDOT Standard Specifications Section 708 traffic paint identification. 1. All roads shall be striped with a double yellow line in the center. 2. All roads with or without curbing shall be striped on each outside edge with a white line. 3. All parking lots shall be striped with white traffic paint. 4. All paint used for striping shall meet requirements of State of New Hampshire specifications. Paint shall comply with Green Standards for application. D. Miscellaneous Pavement Markings 1. Bike lane symbols and text see Chapter 5, Division 32, Section 321216 Attachments B and C. 2. Given the low speed nature of our streets, the University does not typically install other lane designation, advance stop, yield or similar in-lane surface pavement markings on UNH maintained streets. In the few cases where such markings exist or are proposed and approved by the UNH Traffic Safety Committee, markings should comply with standard MUTCD dimensions and styles and be compatible with Town of Durham use standards. E. Glass Beads: AASHTO M 247, Type 1. F. Wheel Stops: Precast, air-entrained concrete, 2500-psi (17.2-MPa) minimum compressive strength, 4-1/2 inches (115 mm) high by 9 inches (225 mm) wide by 72 ASPHALT PAVING 32 1216-3

inches (1800 mm) long. Provide chamfered corners, drainage slots on underside, and holes for anchoring to substrate. 1. Dowels: Galvanized steel, 3/4-inch (19-mm) diameter, 10-inch (254-mm) minimum length. G. Wheel Stops: Solid, integrally colored, 96 percent recycled HDPE or commingled postconsumer and postindustrial recycled plastic; UV stabilized; 4 inches (100 mm) high by 6 inches (150 mm) wide by 72 inches (1800 mm) long. Provide chamfered corners, drainage slots on underside, and holes for anchoring to substrate. 1. Dowels: Galvanized steel, 3/4-inch (19-mm) diameter, 10-inch (254-mm) minimum length. 2. Adhesive: As recommended by wheel-stop manufacturer for application to asphalt pavement. 1.7 MIXES A. Hot-Mix Asphalt: Dense, hot-laid, hot-mix asphalt plant mixes approved by authorities having jurisdiction; designed according to procedures in AI MS-2, "Mix Design Methods for Asphalt Concrete and Other Hot-Mix Types. B. Porous Asphalt mixes shall be considered for all new parking areas on a case by case basis. All new parking areas will need to demonstrate the need for why porous pavements are not feasible prior to selection of standard hot-mix asphalt. In general, porous asphalt projects can be cost effective for new parking areas and are not limited by soil type. Porous asphalt pavement type will be selected based on durability needs. For parking lot reconstruction, the use of porous pavements may be limited due to cost associated with base preparation. Attachment A includes specifications for porous asphalt. Please visit the UNH Stormwater Center website to check for updates on application and specification details. 1. http://www.unh.edu/erg/cstev/pubs_specs_info/unhsc_pa_spec_10_09.pdf 1.8 UNIVERSITY GUIDELINES A. Sidewalks: All sidewalks around and leading to a facility shall be a minimum of 6 feet wide and a minimum of 3 inches thick, applied in two (2) lifts. Pavers may be considered for sidewalls and installed only with University signed approval. ADA indicator pads shall be installed at all sloped transitions. B. Fire Lanes and Driveways: Provide a minimum of 12 feet wide, 4 inches thick, applied in two (2) lifts. C. Streets: Provide a minimum of 32-foot curb to curb wide, thickness determined by proposed usage of road as indicated in The Asphalt Institute s specifications. Streets shall include a marked bike lane. ASPHALT PAVING 32 1216-4

D. Parking Lots: Provide in a square or rectangular pattern, with minimum 4 inch thick asphalt, applied in two (2) lifts. E. Curbing: All curbing shall be granite with a 4-inch reveal where vehicle climbing occurs, all other reveals 6-inches. Curbing shall be vertical or sloping with application approved by University of New Hampshire Plant Maintenance. F. Gravel: 1. All gravel utilized in the preparation of sidewalks, fire lanes and driveways shall be minimum 6 inch of 3/4-inch bank run crushed gravel. 2. All gravel utilized for parking lots and roads shall be minimum 12 inch of 1-1/2 inch bank run crushed gravel. G. Islands: 1. Provide islands with vertical granite curbing no more than 5 inches high. 2. Interior of islands shall be paved or filled with crushed stone no smaller than 1- inch in size. 3. Islands located by roadways shall contain no plant material, such as grass or shrubs. 4. Islands located away from roads and parking lots, and used to direct foot traffic, or are used for aesthetic purposes, shall be landscaped with trees, shrubs, and mulch or stone BUT MAY NOT CONTAIN GRASS. Ornamental grass shall be considered. 5. Islands utilized to separate parking lots from roadways shall not contain guardrails, fences, or any other like material which would hinder snow removal. 6. Islands located in parking lots shall be considered for use as bioretention systems or bioswales by use of curb cuts or drop inlets. 7. Bioretention and bioswales shall pond a maximum of 6 of water, and will be designed to promote detention time and infiltration. Soils must be designed for infiltration and evaluated for need of amendments. Overflow bypass shall be provided and plumbed to adjacent drainage network if necessary. 8. All areas that receive rainfall must be designed to drain within a maximum of 72 hours for vector control. H. Bicycle Lanes: 1. See Attachment B and C for Bicycle Lane Markings. I. Bus Stop Pull-Outs: 1. See Attachment D for Bus Stop options. J. Mobility Impaired: Comply with ADA Requirements for handicap access where applicable. ASPHALT PAVING 32 1216-5

1.9 DISPOSAL A. Except for materials indicated to be recycled, remove excavated materials from project site and legally dispose of them in an EPA-approved landfill. 1. Do not allow milled materials to accumulate on-site. ATTACHMENT: Attachment A: UNHSC Design Specifications for Porous Asphalt Pavement & Infiltration Beds Attachment B: Standard Bicycle Lane Marking Attachment C: Shared Bicycle Lane Marking Attachment D: Bus Stop Options Attachment E: Crosswalk Striping END OF SECTION 32 1216 ASPHALT PAVING 32 1216-6