Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component

Similar documents
Section 3 Characteristics of Credits Types of units. Economic Noneconomic Generation.

PJM PROMOD Overview. August 1, PJM

2750 Monroe Blvd Audubon, PA

2014 State of the Market

Eastern Wind Integration and

MARKET EFFICIENCY STUDY PROCESS AND PROJECT EVALUATION TRAINING

Gas-Electric Coordination in PJM: Trends, Issues, Interactions, and Looking Ahead

PJM Perspective of the EPA Clean Power Plan: Analysis

Electric Forward Market Report

Day-ahead ahead Scheduling Reserve (DASR) Market

Two Settlement PJM /06/2016

Midwest ISO. Prepared by: Midwest ISO Independent Market Monitor. David B. Patton, Ph.D. Potomac Economics. June Executive Summary: Introduction

Electricity Supply. Monthly Energy Grid Output by Fuel Type (MWh)

IMM Quarterly Report: Fall 2017

LOLE Fundamentals Loss of Load Expectation (LOLE) Fundamentals

Outage Coordination Training MISO Training

Marc de Croisset FBR CAPITAL MARKETS & CO. Coal-to-Gas Switching: Distilling the Issue

MISO SPP Interregional Stakeholder Advisory Committee. April 8 th, 2014 Carmel, IN

Transmission Planning at the Midwest ISO. Mr. Eric Laverty Senior Manager of Transmission Access Planning Midwest ISO June 26 th, 2008

Data Viewer, Member Voting, Account Manager, DR Hub, Power Meter, and Data Miner Roadmaps

Capacity Revenues for Existing, Base Load Generation in the PJM Interconnection

The Polar Vortex and Future Power System Trends National Coal Council Annual Spring Meeting May 14, 2014

2015 Economic Planning Study Assumptions

Committed Offer: Offer on which a resource was scheduled by the Office of the Interconnection for a particular clock hour for the Operating Day.

MISO-PJM Interface Pricing Post Implementation Metrics and Criteria

PJM Interconnection Economic Analysis of the EPA Clean Power Plan Proposal

Generation Capacity Mechanisms and Resource Adequacy Planning

ANNUAL REPORT ON MARKET ISSUES & PERFORMANCE

Reserve Market. PJM State & Member Training Dept. PJM /06/2016

Gas Prices and Offer Price Flexibility in Other ISO/RTO Markets

Capacity Performance Training. June 24, 2015

PJM Manual 21: Rules and Procedures for Determination of Generating Capability Revision: 12 Effective Date: January 1, 2017

PJM Roadmap for edart

APRIL 23, Capacity Value of Wind Assumptions and Planning Reserve Margin

Summary of 2016 MISO State of the Market Report

Demand Response. Overview. Recommendations

Energy Markets - The Basics

Pre-Scheduling Operations

PJM M2M Market Flow Proposal. October 2014

Outlook for Natural Gas Demand for Winter

Dispatch Signal & Locational Marginal Pricing (LMP)

Electricity Markets. Rapid Conference May 17, Mike Rencheck Rencheck Consulting LLC

MISO Energy Storage Study Phase 1 Report

EVALUATION OF MIDWEST ISO INJECTION/WITHDRAWAL TRANSMISSION COST ALLOCATION DESIGN. Prepared by Scott Harvey and Susan Pope

California ISO. Q Report on Market Issues and Performance. July 10, Prepared by: Department of Market Monitoring

MTEP18 Futures. Planning Advisory Committee June 14, 2017

LOAD SERVING ENTITIES PJM REGION

Capacity Performance Training. March 16, 2015

PJM Manual 27: Open Access Transmission Tariff Accounting Revision: 88 Effective Date: November 16, 2017

NYISO/PJM Market-to-Market Coordination

Draft Whitepaper to Platte River Board of Directors

the Real-Time Market will be based on the system marginal costs produced by the Real-Time

Introduction to the PJM Markets

PJM Cold Snap Performance Dec. 28, 2017 to Jan. 7, 2018

Generation Technology Assessment & Production Cost Analysis

Wind Generation s Contribution to the Management of Average Cost and Cost Volatility for Indiana

PJM EIS Generation Attribute Tracking System (GATS)

Further Analyses of the Exercise and Cost Impacts of Market Power In California s Wholesale Energy Market

PJM Manual 10: Pre-Scheduling Operations Revision: 36 Effective Date: December 22, Prepared by Operations Planning Division

20 MW Flywheel Energy Storage Plant

The Virtues of A Virtual RTO

August 22, 2014 FIRE ISLAND WIND

RPM 301 Performance in Reliability Pricing Model

DATA ASSUMPTIONS AND DESCRIPTION OF STUDIES TO BE PERFORMED 2014 EGSL & ELL Integrated Resource Plans

May 4, 2017 PLANNING COMMITTEE. Dear Committee Members:

Manual No. 010 Business Practices Manual Network and Commercial Models

2016 State of the Market Report: Energy & Ancillary Services Market Highlights

Demand Dispatch and Probabilistic Wind Power Forecasting in Unit Commitment and Economic Dispatch: A Case Study of Illinois

MISO s Analysis of EPA s Final Clean Power Plan Study Report

Gas-Electric Infrastructure Challenges. WPUI Gas Program September 17, September 13, 2012 Madison, WI

Technical Bulletin Comparison of Lossy versus Lossless Shift Factors in the ISO Market Optimizations

PJM Reserve Market. PJM State & Member Training Dept. PJM /27/2015

Coal, Carbon, and the Future of the Global Energy Mix

Transmission Reliability Margin Implementation Document TP-PL-002-r10 Effective Date: JUL Purpose. 2 Scope.

Methodology PLG-METH-0002-V1

The Husker Power Plan: A New Energy Plan for Nebraska

Zero Net Carbon Portfolio Analysis

California Independent System Operator Corporation Fifth Replacement Electronic Tariff

Operations Performance Metrics Monthly Report

Market-Based Policy Concepts for Encouraging Fuel Diversity and Retaining Baseload Zero-Carbon Resources. December 4, 2014

Markets Report. Paul M. Sotkiewicz, Ph.D Chief Economist, Markets MC Webinar January 20, 2015 PJM 2015

U.P. Transmission Business Briefing Planning Update. November 29, 2007 Marquette, MI Flora Flygt, Director of Planning

Hedging Coal Price Risk in a Deregulated Power Market

SPP at a Glance. Located in Little Rock. Approximately 600 employees

Energy Market Update. April 8, Kevin Krcil Chris Dubay

2016 ANNUAL VRL ANALYSIS

Modeling the Restructured Illinois Electricity Market as a Complex Adaptive System

Cost Development Guidelines

CSAPR & MATS: What Do They Mean for Electric Power Plants?

Power Sector Transition: GHG Policy and Other Key Drivers

Ten Years After Gas & Power in Perspective

Potential Electricity and Energy Price Outcomes under EPA s Federal Plan Alternatives for the Clean Power Plan

INDEPENDENT SYSTEM OPERATORS (VI + Access Rules vs. ISO vs. ITSO)

2. Market Operations Overview

GADS and LOLE Considerations in Gas- Electric Coordination. ENGCTF June 13, 2013

NATURAL GAS MARKETS, STRUCTURES, AND MECHANISMS

Federal Energy Regulatory Commission Working Paper on Standardized Transmission Service and Wholesale Electric Market Design

2018 Draft Policy Initiatives Roadmap. Market and Infrastructure Policy December 7, 2017

Table of Contents. 6.2 Socio-Economic Impacts of the Preferred Plan Five-Year Action Plan

1.818J/2.65J/3.564J/10.391J/11.371J/22.811J/ESD166J SUSTAINABLE ENERGY. Prof. Michael W. Golay Nuclear Engineering Dept.

Transcription:

Results and Assumptions For Single Economic Dispatch Production Cost Study PROMOD Component Last Revised: May 25, 26 Disclaimer: "MIDWEST ISO MAKES NO REPRESENTATIONS OR WARRANTIES OF ANY KIND, EXPRESS OR IMPLIED, WITH RESPECT TO THE ACCURACY OR ADEQUACY OF THE INFORMATION CONTAINED HEREIN. MIDWEST ISO SHALL HAVE NO LIABILITY TO RECIPIENTS OF THIS INFORMATION OR THIRD PARTIES FOR THE CONSEQUENCES ARISING FROM ERRORS OR DISCREPANCIES IN THIS INFORMATION, FOR RECIPIENTS' OR THIRD PARTIES' RELIANCE UPON SUCH INFORMATION, OR FOR ANY CLAIM, LOSS OR DAMAGE OF ANY KIND OR NATURE WHATSOEVER ARISING OUT OF OR IN CONNECTION WITH (i) THE DEFICIENCY OR INADEQUACY OF THIS INFORMATION FOR ANY PURPOSE, WHETHER OR NOT KNOWN OR DISCLOSED TO MIDWEST ISO, (ii) ANY ERROR OR DISCREPANCY IN THIS INFORMATION, (iii) THE USE OF THIS INFORMATION, OR (iv) ANY LOSS OF BUSINESS OR OTHER CONSEQUENTIAL LOSS OR DAMAGE WHETHER OR NOT RESULTING FROM ANY OF THE FOREGOING." Midwest Independent Transmission System Operator, Inc. 71 City Center Drive Carmel, IN 4632 1125 Energy Park Drive St. Paul, MN 5518 www.midwestiso.org

Table of Contents 1 INTRODUCTION...5 2 STUDY RESULTS...6 2.1 DIFFERENT OPTIONS FOR ADJUSTED PRODUCTION COST CALCULATION...6 2.2 RESULTS...8 2.3 SENSITIVITY STUDIES...9 APPENDIX...12 1 STUDY ASSUMPTIONS...13 1.1 FUEL FORECAST...13 1.2 LOAD FORECAST AND LOSSES...14 1.2.1 Treatment of Losses in PROMOD...14 1.3 GENERATING UNITS AND PARAMETERS...15 1.3.1 Existing Units...15 1.3.2 Retired Units...16 1.3.3 Variable O & M...16 1.3.4 Penalty Factors...16 1.3.5 Unit Maintenance...16 1.3.6 Forced outage rates...16 1.3.7 Environmental parameters...16 1.4 POWER FLOW CASE...17 1.5 COMMITMENT AND DISPATCH HURDLE RATES...17 1.6 EVENT FILE...18 2 PROMOD BENCHMARK...18 2.1 MISO TO PJM SCHEDULED INTERCHANGE BENCHMARK...19 2.2 HUB LMP BENCHMARK...2 2.3 CAPACITY FACTORS ON GENERATOR CLASSES...25 2.4 ADDITIONAL OPTIONS CONSIDERED FOR BENCHMARK...27 2.4.1 PROMOD switches :...27 2.4.2 Transmission and Generation Outages...27 Page 2

Summary of Tables Table 1: Adjusted Production Cost Savings ($ million)...8 Table 2: Sensitivity Run Results...9 Table A. 1: Summary of Operating Characteristics...15 Table A. 2: Dispatch Hurdle Rates modeled...18 Page 3

Table of Figures Figure 1: Option 1...7 Figure 2: Option 2...7 Figure 3: Option 3...8 Figure 4: Gas Price Sensitivity Results...1 Figure 5: Coal Price Sensitivity Results...11 Figure A. 1: Fuel Forecasts for 26...14 Figure A. 2: MISO/PJM Scheduled Interchange Benchmark...19 Figure A. 3: Cinergy Hub Benchmark...21 Figure A. 4: FirstEnergy Hub Benchmark...21 Figure A. 5: Illinois Hub Benchmark...22 Figure A. 6: Michigan Hub Benchmark...22 Figure A. 7: Minnesota Hub Benchmark...23 Figure A. 8: AEP Gen Hub Benchmark...23 Figure A. 9: Chicago Hub Benchmark...24 Figure A. 1: PJM Western Hub Benchmark...24 Figure A. 11: PJM Western Interface Hub Benchmark...25 Figure A. 12: Capacity Factor comparison...26 Page 4

1 Introduction This White Paper serves as the study document for the PROMOD analysis performed for the Single Economic Dispatch Production Cost Study conducted with PJM staff as part of the Joint & Common Market (JCM) analysis. This analysis was performed by the MISO Transmission Asset Management group and the PJM Markets group. The primary analytic tools used in the analysis, for production cost modeling purposes, are the PROMOD IV model from NewEnergy Associates and the GE MAPS software tool from General Electric. This document serves as the assumption document for the PROMOD simulation. The study year is 26, and all results are for the full year. The cases developed for the Single Economic Dispatch Production Cost Study are defined below: Current Market Case: MISO, PJM, SETRANS, SPP, NYISO, IMO and MAPP-Non- MISO are modeled in the case. There are dispatch hurdle rates and commitment hurdle rates between these entities. For the MISO and PJM interface, 1.5$/MWH, 2.5$/MWH, and 5$/MWH dispatch hurdle rates were tested as part of the process to develop the scheduled interchange benchmark. Base on the results of the scheduled interchange benchmark, results at each of the dispatch hurdle rates is provided to obtain a range of benefits. Single Economic Dispatch Case: Same as Current Market Case, except that both the dispatch and commitment hurdle rates between MISO and PJM are $/MWH. PROMOD was benchmarked against the actual January 26 system operation. The benchmark provides a backdrop by which to measure the use of a simulation model as a tool to gauge future performance. A simulation model is needed in order to provide a consistent linkage between past and future expected performance. The intent of the single economic dispatch study is to determine the level of production cost savings exists between the current market case, using an implied hurdle rate to simulate market inefficiencies, and a single economic dispatch case. A metric of adjusted production cost is used to determine the cost savings between the cases. The adjusted production cost captures the actual production cost used to serve the load. The production cost used to serve the purchase/sale to the outside world needs to be adjusted from the total production cost; and, three options to calculate the adjusted production cost are evaluated. The results of the 26 analysis indicated a range of savings from $34 million to $66 million for the PROMOD simulations. The benefits in various scenarios accrue to different market participants. In general benefits tend to be greater in PJM. In some scenarios net benefits in the MISO region are negative. Fuel price sensitivity studies are also performed. The results of the simulation and sensitivity runs are detailed in the following section. Study Assumptions and benchmark results are given in the Appendix. It is important to note that the base case on which the production cost savings are based is benchmarked against the actual market conditions experienced over the last year. Therefore, the production cost savings that result from the analysis are inclusive of the benefits that will be achieved Page 5

via implementation of the various Joint and Common Market (JCM) initiatives already under development or investigation. Specifically, the following JCM initiatives are expected to increase the convergence of the two markets and achieve a significant portion of these savings: PJM implementation of marginal losses; Alignment of PJM Operating Reserve and MISO Revenue Sufficient Guarantee products; Moving Joint-Owned Units between markets; Alternative border pricing point mechanisms. Other potential JCM initiatives are also being considered that could further enhance the convergence of the two markets. In addition, PJM and MISO are and will be continuously analyzing and improving the operation of the Market-to-Market coordination that was implemented as Phase 2 of the Joint Operating Agreement. The initiatives described above are expected to achieve a significant portion of the production cost savings estimated in the simulations, at substantially less cost than a single unit commitment and dispatch. Once the above initiatives have been incorporated into the operations of the two RTOs for a time period significant enough over which to judge their effectiveness, an analysis could be conducted that would indicate more definitively the remaining benefits that might be achieved through a single economic dispatch. 2 Study Results 2.1 Different options for Adjusted Production Cost calculation The benefit of single economic dispatch is measured by the savings in production cost to serve load in the combined region. In reality, each entity has purchases and/or sales with other entities, including entities outside the combined region. If an entity is a net seller its production cost is based on serving its own load plus serving outside load. Therefore, the production cost associated with serving the outside load must be removed from the total production cost for the entity being studied. On the other hand, if an entity is a net purchaser then its outside purchased energy must be added to its production cost. Production cost models such as PROMOD are based on a single economic dispatch of the entire model region, in this case the Eastern Interconnection. All generation in the model is dispatched on an economic basis to serve aggregate load. As such, there is no model derived value of net purchases or sales for a sub region. The value of such transactions must be estimated. In this study the following three options for calculating the Adjusted Production Cost accounting for purchases and sales are investigated: Option 1: CA level calculation - CA s transactions within pool and outside pool are priced separately based on the sign of each transaction. Figure 1 shows the detail of Option 1. Option 2: Pool level calculation - Pool transaction is priced based on the pool-wide load or generation weighted LMP. Figure 2 shows the detail of Option 2. Page 6

Option 3: Pool level calculation - Captures the transaction from each CA to outside pools, and prices this transaction with CA s load or generation weighted LMP. Internal transactions between CAs are not priced. Figure 3 shows the detail of Option 3. CA 2 CA 1 POOL 1 CA1 Net Purchase/Sale with same pool CAs CA1 Net Purchase/Sale with other pools CA1 Adjusted Prod. Cost = CA1 Production Cost + CA1 Net Purchase/Sale with same pool CAs* (CA1 Load Weighted LMP or CA1 Generation Weighted LMP)+ CA 1Net Purchase/Sale with other pools*(ca1 Load Weighted LMP or CA1 Generation Weighted LMP) POOL 1 Adjusted Prod. Cost = Sum(CA1 Adjusted Prod. Cost + CA2 Adjusted Prod. Cost + ) Figure 1: Option 1 POOL 1 POOL 1 Net Purchase/Sale with other pools = POOL 1 Load POOL 1 Generation POOL 1 Adjusted Prod. Cost = POOL 1 Production Cost + (POOL 1 Load POOL 1 Generation)* (POOL 1 Load Weighted LMP or POOL 1 Generation Weighted LMP) Figure 2: Option 2 Page 7

CA 2 CA 1 POOL 1 CA1 Net Purchase/Sale with other pools POOL 1 Adjusted Prod. Cost = Sum over all CAs (CA1 Prod. Cost + CA1 Net Purchase/Sale with other pools * (CA 1 Load Weighted LMP Or CA 1 Generation Weighted LMP) ) Figure 3: Option 3 Difference between Option 1 vs. (2 and 3) is: Transactions between CAs within the same pool are not included in Options 2 and 3. Options 2 and 3 can only be used for pool level comparison, while Option 1 can be used for both pool and Control Area level comparison. Difference between Option 2 and Option 3 is: Option 2 uses pool level generation or load weighted LMP to price the pool to pool transaction. Option 3 captures CAs transaction from/to outside pool, and uses CAs load or generation weighted LMP to price this transaction. 2.2 Results For current market, we have run 3 cases. The difference between these cases is the dispatch hurdle rate between MISO and PJM. The hurdle rates evaluated are $1.5/MWH, $2.5/MWH and $5/MWH respectively for the three cases. The adjusted production costs of these three cases are calculated and compared to the adjusted production cost from the single economic dispatch case. The results are shown in Table 1. Table 1: Adjusted Production Cost Savings ($ million) Option 1 Option 2 Option 3 MISO PJM Total MISO PJM Total MISO PJM Total $1.5 Hurdle $ (3.12) $46.8 $43.68 $ 8.71 $25.67 $34.38 $(7.63) $22.43 $14.8 $2.5 Hurdle $ 9.83 $55.56 $65.39 $18.42 $34.4 $52.82 $ 2.57 $31.2 $33.59 $5 Hurdle $18.55 $8.12 $98.67 $24.36 $45.72 $7.8 $ 9.33 $42.59 $51.92 Page 8

For Option 1, the total saving is in the range of $44 $99 million. For Option 2, the total saving is in the range of $34 $79 million. For Option 3, the total saving is in the range of $15 $52 million. In benchmark, it is shown that $2.5/MWH hurdle rate case gives the best benchmark of MISO/PJM scheduled interchange. In $2.5/MWH hurdle rate case, three options give the adjusted production cost saving range of $34 million and $65 million. Different options gave out different results, but they are consistent in range of saving, and these savings are very small compared to the total production cost value (less than.2% of the total production cost). 2.3 Sensitivity Studies The following fuel price sensitivity runs were performed on the $2.5/MWh dispatch/$1/mwh commitment hurdle rate case and single market dispatch case: Lower Gas Price (4% lower than original case in all east interconnection) Lower Gas Price (1% lower than original case in all east interconnection) Higher Gas Price (1% higher than original case in all east interconnection) Higher Gas Price (5% higher than original case in all east interconnection) Higher Coal Price in MISO area (1% higher than original case) Higher Coal Price in PJM area (1% higher than original case) The results of these sensitivity runs are shown in Table 2. Table 2: Sensitivity Run Results Adjusted Production Cost Savings ($ million) Option 1 Option 2 Option 3 Gas Sensitivity MISO PJM Total MISO PJM Total MISO PJM Total 4% Lower Gas Price $27.55 $16.78 $44.33 $35.86 $ (2.19) $ 33.67 $24.6 $ (3.82) $2.24 1% Lower Gas Price $.5 $48.2 $48.52 $14.34 $27.25 $ 41.6 $ (1.82) $24.39 $22.57 Base Case $ 9.83 $55.56 $65.39 $18.42 $34.4 $ 52.82 $ 2.57 $31.2 $33.59 1% Higher Gas Price $ 7.95 $51.58 $59.53 $14.69 $3.82 $ 45.51 $ 2.62 $29.28 $31.89 5% Higher Gas Price $25.79 $38.69 $64.48 $32.28 $ 9.5 $ 41.33 $28.37 $ 5.57 $33.94 Coal Sensitivity MISO PJM Total MISO PJM Total MISO PJM Total 1% Higher MISO Coal $13.64 $78.26 $91.9 $25.58 $44.44 $ 7.3 $ 7.92 $36.44 $44.36 Base Case $ 9.83 $55.56 $65.39 $18.42 $34.4 $ 52.82 $ 2.57 $31.2 $33.59 1% Higher PJM Coal $12.96 $4.25 $53.21 $2.41 $2.88 $ 41.3 $ 8.79 $22.93 $31.72 Figure 4 shows the adjusted production cost savings for each of the three options with different gas prices. Between the three options, the gas price change causes the same change pattern of adjusted production cost savings. In the gas sensitivity cases, all gas within the Eastern Interconnection is increased or decreased by the same percentage. The gas sensitivity cases show a small decrease in Page 9

savings attributed to gas price fluctuations. In the coal case sensitivities, only one RTO s coal prices were raised while keeping the coal prices in the other RTO at the original price level. Adjusted Production Cost Saving ($ million) $7. $6. $5. $4. $3. $2. Gas Price Sensitivity 4% Lower Gas Price 1% Lower Gas Price Original Gas Price 1% Higher Gas Price 5% Higher Gas Price $1. $- Option 1 Option 2 Option 3 Figure 4: Gas Price Sensitivity Results Page 1

$1. $9. Coal Price Sensitivity 1% Higher MISO Coal Price Original Coal Price 1% Higher PJM Coal Price Adjusted Production Cost Savings ($ million) $8. $7. $6. $5. $4. $3. $2. $1. $- Option 1 Option 2 Option 3 Figure 5: Coal Price Sensitivity Results Page 11

Appendix Page 12

1 Study Assumptions Various assumptions related to PROMOD studies are discussed in this section. Some of the assumptions are generic for all PROMOD studies undertaken by the MISO; while some are specific to the Single Economic Dispatch study. The underlying source of PROMOD data is contained in Powerbase. Powerbase is a separately licensed tool from New Energy Associates that contains much of the data necessary to create and run PROMOD data files. The data in Powerbase can be replaced in whole or in part with user specified data. For example, MISO adjusts Powerbase data for generators in the interconnection queue and specific generator parameters (e.g. must run status), but does not normally update Powerbase economic data for our members due to confidentiality concerns. The primary assumptions discussed here are: fuel price forecasts, load forecasts, generating units and parameters, power flow case, commitment and dispatch hurdle rates, and case description. Detailed assumptions regarding existing units, retired units, variable operations and maintenance (O & M) values, penalty factors, must run units, unit maintenance and forced outage rates (EFOR) are discussed in the generating units and parameters topic. 1.1 Fuel Forecast 1 The source for the fuel forecasts in the Powerbase database is the Platt s database, Henry Hub forecasts and EIA forecasts. NewEnergy Associates (NEA) contracts with Platts for various fuel price forecasts. NEA starts with Platt s forecasts for natural gas and then uses the basis differential inherent in Platt s forecast for Natural Gas combined with NYMEX Henry Hub futures prices for the first 18 months of the forecast. For the forecast beyond 18 months, the Energy Information Administration (EIA) natural gas forecast for the Henry Hub serves as the base index. The basis differential to each area is then applied against the EIA forecast of the Henry Hub prices. Figure A.1 illustrates the fuel price forecasts. For a detailed listing of the fuel forecasts, please refer to the Appendices. NEA December 25 release data was utilized for this study purposes. The oil price forecasts are based on futures contracts with no basis differential. Heavy Oil forecasts in this PROMOD study are adjusted based on Crude Oil prices and Light Oil price forecasts are adjusted based of Heating Oil prices from NYMEX. The coal price forecasts are from Platts directly. The coal price forecasts include transportation costs. NEA updates the fuel price forecasts every quarter. 1 Platts Fuel Forecasting methodology, found on NEA PowerBase support web site Page 13

Fuel Price Forecasts (26) 14. 13. 12. 11. 1. 9. Price in $/MMBtu 8. 7. 6. 5. 4. 3. 2. 1.. PB_Distillate PB_Residual PB_NatGas PB_Coal Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Figure A. 1: Fuel Forecasts for 26 Coal starts at $ 2. per MMBtu in Jan 26 as seen in figure 2. Natural gas starts at $11.7 per MMBtu, oil distillate at $12 per MMBtu and residual at $1 per MMBtu. 1.2 Load Forecast and Losses The load forecasts in the Powerbase database come from FERC 714 filings. NEA scales these values to match the sub regional totals to the NERC Electricity and Supply Demand (ES &D) database. These values are verified by MISO against load flow data for a specific year for some studies. MISO members submit load forecasts to MISO as a part of Module E process, but this data is only for the near-term and less than 18 months. For the purposes of this single economic dispatch study, hourly load data for Jan 26 was requested from the Data Management Team (DMT) department of MISO. These values were given by control area and did contain transmission losses. (Note to the reader: PROMOD requires losses in its load data) 1.2.1 Treatment of Losses in PROMOD There are 3 options to treat losses in PROMOD. They are: Option 1: Load in PROMOD load file is equal to actual load plus the loss. Losses and LMP loss component are not calculated by PROMOD. Page 14

Option 2: Load in PROMOD load file is equal to actual load plus the loss. Losses are not calculated by PROMOD. LMP loss component is calculated by PROMOD in an approximation method. (this option is used in PROMOD analysis by MISO staff) Option 3: Load in PROMOD load file is equal to actual load. PROMOD calculates losses and the LMP loss component, this is sometimes called marginal loss calculation method 1.3 Generating Units and parameters Detailed assumptions regarding existing units, retired units, variable operations and maintenance (O & M) values, penalty factors, must run units, unit maintenance and forced outage rates (EFOR) are discussed in this section. 1.3.1 Existing Units The Appendices contains specific generating unit information of the type used in this study. Typically as part of the PROMOD model development process, MISO verifies generators in the default Powerbase database against the MISO load flow models. Stakeholders are involved in this process. The Expansion Planning Working Group (reporting to Planning Sub-Committee) is sent a list of generators mapped to load flow models and member comments are solicited. A list of the existing units in the database is given in Appendix A of this document. Table A.1 below shows a summary of several operating characteristics, by class, for existing units in the Eastern Interconnect. These are average values for that class/type of existing units from the Powerbase database. Only heat rates, forced outage rates, start up costs, ramp up date and ramp down rates are shown. Table A. 1: Summary of Operating Characteristics Average FuelType Heat Rate (MMBtu/MWh) Forced Outage Rate (%) Startup Cost Adder ($) Ramp Up Rate (MW/hr) Ramp Down Rate (MW/hr) Combined Cycle 7.2 4.1 9.3 122.4 147.8 Combustion Turbine <= 1 12.4 7.8 3.1 59.5 51. Combustion Turbine > 1 12.3 5.1 4.8 159. 186.7 ST Coal <=1 12.1 6.1 5.8 26.4 28.9 ST Coal >1, <=2 1.4 6.6 9.4 55.9 59.5 ST Coal >2 9.8 7.5 22.1 154.5 167.3 ST Gas <=1 12.8 6.3 3.5 27.3 28.9 ST Gas >1, <=2 11. 7.6 7.2 61.3 62.8 ST Gas >2 1.2 1. 19.3 173.3 174.4 ST Oil <=1 12.9 3.6 3.7 27.7 31.8 ST Oil >1, <=2 1.5 6.8 7.6 62.9 68.4 ST Oil >2 1.1 9.1 19.7 186.9 199.3 Page 15

1.3.2 Retired Units Units are retired in the database based on public announcements, various ISO web sites and from Platt s database, by NEA. In addition to the retirements found in the default database, MISO also makes sure that the units retired in the load flow model are retired in the PROMOD model. This is done as a part of the PROMOD model development process. 1.3.3 Variable O & M Variable Operations and Maintenance (O&M) values are included in the Powerbase database. The source for these values is the FERC Form 1 data and EIA Form 412. Generator data in the Appendices also shows the variable O & M costs modeled for each unit in the PROMOD database. 1.3.4 Penalty Factors Penalty factors are factors assigned to generators in the PROMOD to mimic certain sensitivities. In this particular PROMOD run we did not assign any penalty factors. 1.3.5 Unit Maintenance In PROMOD, maintenance is automatically scheduled for all units except for nuclear. Nuclear unit maintenance is well known from the NRC (Nuclear Regulatory Commission) web site. Hence these units maintenance schedules are input in the Powerbase database by NEA. The remaining units are scheduled in PROMOD using the automatic maintenance scheduler; whereby, PROMOD schedules maintenance according to the overall system reliability as a target. 1.3.6 Forced outage rates NEA updates Forced Outage rate (FOR) information from NERC GADS (Generator Availability Data System) data in the default database. These are based of historical 5-year average values by class of generators. These values are not changed by MISO in this particular PROMOD study. 1.3.7 Environmental parameters The Powerbase database has emissions cost associated with some of the units in the Eastern Interconnect. This data comes from the Continuous Emission Monitoring System (CEMS) data source of the Environmental Protection Agency (EPA) web site. The effluents modeled in the database include: Carbon dioxide (CO 2 ), Nitrous oxide (NO x ), Ontario Nitrous oxide (ONTARIO NO x ), State Implementation Plan Nitrous oxide (SIP NO x ) and Sulfur oxides (SO x ). The allowance costs for each pollutant are as follows: ONTARIO NO x - $ 2,687.5 per ton (May to September), SIP NO x - $ 2,687.5 per ton (May to September), and Page 16

SO x - $1,565.5 per ton. NewEnergy Associates updates these costs every quarter based on the CEMS web site. 1.4 Power flow case Generators in this PROMOD model were mapped to the 25 series MISO 26 power flow case. The transmission topology reflects transmission projects verified with Appendix A from the MISO MTEP (not to be confused with the listing of Appendices in this report) and SPP Transmission planning projects listing. Inserts from SPP load flow models were added on top of the MISO topology. 1.5 Commitment and Dispatch hurdle rates PROMOD performs the transmission constrained unit commitment and economic dispatch, therefore its solution includes two steps. The first step is unit commitment, and the second step is economic dispatch. For each step, the user can define its own hurdle rate. The hurdle rate defined for the unit commitment step is called the commitment hurdle rate, and the hurdle rate defined for the economic dispatch step is called the dispatch hurdle rate. The hurdle rate will influence the capability of a pool to obtain support or sell energy to other pools. A pool is defined in PROMOD as a set of companies that have no hurdle rates between them and their generators will be committed and dispatched together to meet their total load. Separate pools will exchange energy when the difference between dispatch cost in the buying and selling pools is greater than the hurdle rate between them. Normally, users will set the commitment hurdle rate to be more expensive than the dispatch hurdle rate such that the pool units will be dispatched against its own pool load first in order to get the commitment order right and then allow pool interchange during the final dispatch via the dispatch hurdle rate. In this study, for current market cases, the commitment hurdle rates are set as $1/MWH between all pools. Exception was MISO to MH, where we set the commitment hurdle rate as $/MWH. The dispatch hurdle rates between pools are set as shown in Table A.2. The MISO/PJM dispatch hurdle rates are set as $1.5/MWH, $2.5/MWH and $5/MWH for three market cases. For the single economic dispatch case, the dispatch and commitment hurdle rates are set the same as in current market case, except that the dispatch and commitment hurdle rates between MISO and PJM are set to $/MWH. Page 17

Table A. 2: Dispatch Hurdle Rates modeled DISPATCH HURDLE RATES TO /FROM -> on-peak/off-peak FROM /TO MISO PJM SPP SETRANS IMO MH NYISO TVA NONMISO MISO * 2.5/2.5 7.5/5.3 7.5/5.3 7.5/5.3 / N/a 7.5/5.3 7.5/5.3 PJM 2.5/2.5 * n/a 4.8/4.8 N/A n/a 7./7. N/a 4.8/4.8 SPP 5./5. n/a * 5./5. N/A n/a N/a N/a 5./5. SETRANS 8.3/8.3 6.5/4.5 8.3/8.3 * N/A n/a N/a N/a 8.3/8.3 IMO 1.5/8.5 n/a n/a n/a * 1.5/8.5 6.5/4.5 N/a n/a MH n/a n/a n/a n/a 7./5. * N/a N/a 11.6/7.3 NYISO n/a 5./5. n/a n/a 7./5. n/a * N/a n/a TVA N/a * n/a NONMISO 4.2/3.7 4.2/3.7 6.8/6.8 4.2/3.7 N/A 6.5/4.5 N/a N/a * 1.6 Event File The event file in PROMOD contains the list of contingencies and monitored elements. For this analysis there were 492 contingencies and 137 monitored elements. The actual event file is confidential; however, an excel spreadsheet that contains the event file information is included in the Appendices. Monitored flowgates in PROMOD constitute an event file. The source for this event file is the MISO Book of flowgates and NERC Book of flowgates. Certain flowgates may have operating guides associated with them in real time operations. Hence the event file is scrubbed to remove any flowgates that might have an operating guide associated with them. For a detailed listing of flowgates modeled in the Single Economic Dispatch study, please refer to the spreadsheet in the Appendices. 2 PROMOD Benchmark An integral part of the single economic dispatch study effort is the benchmarking of PROMOD results to actual MISO and PJM Day-ahead market data in Jan 26. The followings are the variables that we used to perform the benchmark: Scheduled interchange between MISO and PJM LMPs at Hubs Capacity Factor of generating units For the benchmark purpose, we collected the following information: Hub LMP in MISO and PJM day-ahead market (January 26) Hourly generations of all units in MISO market (January 26) The hourly scheduled interchange between MISO and PJM in year 25 Page 18

We also collected the MISO companies hourly load data from MISO market of January 26, and used them to replace the original January 26 load data from PowerBase. Following sections discuss in detail the PROMOD benchmark with market data. 2.1 MISO to PJM Scheduled Interchange Benchmark The scheduled interchange benchmark served as the primary metric to determine the hurdle rate to be applied for the case used for LMP and capacity factor benchmark. We have run the following hurdle rate cases: 1) $1.5/MWH dispatch hurdle, $1/MWH commitment hurdle between MISO and PJM. 2) $2.5/MWH dispatch hurdle, $1/MWH commitment hurdle between MISO and PJM. 3) $5/MWH dispatch hurdle, $1/MWH commitment hurdle between MISO and PJM. From each case run, we get the hourly interchange between MISO and PJM. The duration curves of these hourly interchanges are shown in Figure A.3. The duration curve of Year 25 MISO/PJM scheduled interchange data from market is also shown in the same figure. Net MISO/PJM TIES Scheduled Interchange Duration Curve 8, 6, Note: Negative Values are out of PJM PROMOD 5$ Hurdle Rate 25 Historical Data PROMOD 2.5$ Hurdle Rate PROMOD 1.5$ Hurdle Rate 4, 2, MW 1 24 479 718 957 1196 1435 1674 1913 2152 2391 263 2869 318 3347 3586 3825 464 433 4542 4781 52 5259 5498 5737 5976 6215 6454 6693 6932 7171 741 7649 7888 8127 8366 865-2, -4, -6, -8, 3/9/26 % of Time Figure A. 2: MISO/PJM Scheduled Interchange Benchmark Page 19

The figure shows that the $ 2.5/MWH hurdle rate case is closer to the historical data. So in LMP and capacity factor benchmark, we will use the $ 2.5/MWH hurdle rate case results. 2.2 Hub LMP Benchmark Hub LMPs from PROMOD case with $ 2.5/MWh PJM/MISO dispatch hurdle rate and $1/MWh commitment hurdle rate is used to benchmark the Day Ahead ( DA ) market data (Jan 26). The following hub LMPs were collected from the MISO and PJM DA market: 1) Cinergy 2) FirstEnergy 3) Illinois 4) Michigan 5) Minnesota 6) AEP Gen 7) Chicago 8) PJM Western 9) PJM Western Interface. To evaluate the PROMOD LMPs against the actual DA market results, the following statistic indices are used: Correlation The single number that describes the degree of relationship between two variables. For benchmark purpose, the two variables are PROMOD LMP and DA market LMP. The closer the number to 1, the closer the relationship of these two variables has. Significance of correlation: Determines if the probability of correlation is a real one and not a chance occurrence. If we assume correlation of a chance occurrence is not greater than 1%, then the critical value of correlation is.188. Therefore if the correlation of the hub LMPs is larger than.188, we conclude the correlation is "statistically significant. Average Error This is an index widely used to check the quality of forecasted values compared to the true values. For a certain hub, the PROMOD hub LMPs are: P1, P2,, P744, the DA market hub LMPs are: M1, M2,, M744, then the Average Error for these LMPs is: AvergeError 744 abs( P M 744 ) / M i i i = 1 = i The hub LMP benchmarks for these hubs are shown in Figure A.4 Figure A.12. Page 2

CINERGY Hub LMP Benchmark (Jan 26) 14 12 CINERGY Hub LMP (PROMOD) CINERGY Hub LMP (Market Data) Correlation =.84 >.188 Average Error = 13.3% 1 Hub LMP ($/MWH) 8 6 The points fall in this area are hours with PROMOD LMP and DA Market LMP difference smaller than 1% Correlation of Cinergy Hub LMP from PROMOD and Market 4 12 2 1 1 35 69 13 137 171 25 239 273 37 341 375 49 443 477 511 545 579 613 647 681 715 Hours Cinergy Hub LMP from Market 8 6 4 2 Correlation of Cinergy Hub LMP from PROMOD and Market 2 4 6 8 1 12 Cingergy Hub LMP from PROMOD Figure A. 3: Cinergy Hub Benchmark FE Hub LMP Benchmark (Jan 26) 12 1 Correlation =.74 >.188 Average Error = 17.3% Hub LMP ($/MWH) 8 6 4 The points fall in this area are hours with PROMOD LMP and DA Market LMP difference smaller than 1% Correlation of FirstEnergy Hub LMP from PROMOD and Market 12 2 FE Hub LMP (PROMOD) FE Hub LMP (Market Data) 1 33 65 97 129 161 193 225 257 289 321 353 385 417 449 481 513 545 577 69 641 673 75 737 Hours FirstEnergy Hub LMP from Market 1 8 6 4 2 Correlation of FirstEnergy Hub LMP from PROMOD and Market 2 4 6 8 1 12 FirstEnergy Hub LMP from PROMOD Figure A. 4: FirstEnergy Hub Benchmark Page 21

ILLINOIS Hub LMP Benchmark (Jan 26) 12 1 Correlation =.88 >.188 Average Error = 18.2% Hub LMP ($/MWH) 8 6 4 1 The points fall in this area are hours with PROMOD LMP and DA Market LMP difference smaller than 1% Correlation of Illinois Hub LMP from PROMOD and Market 2 IL Hub LMP (PROMOD) IL Hub LMP (Market Data) 1 32 63 94 125 156 187 218 249 28 311 342 373 44 435 466 497 528 559 59 621 652 683 714 Hours Illinois Hub LMP from Market 9 8 7 6 5 4 3 2 1 Correlation of Illinois Hub LMP from PROMOD and Market 1 2 3 4 5 6 7 8 9 1 Illinois Hub LMP from PROMOD Figure A. 5: Illinois Hub Benchmark MICHIGAN Hub LMP Benchmark (Jan 26) 14 12 Correlation =.78 >.188 Average Error = 14.8% Hub LMP ($/MWH) 1 8 6 12 The points fall in this area are hours with PROMOD LMP and DA Market LMP difference smaller than 1% Correlation of Michigan Hub LMP from PROMOD and Market 4 1 2 1 35 69 13 137 171 25 239 273 37 341 375 49 443 477 511 545 579 613 647 681 715 Hours MICHIGAN Hub LMP (PROMOD) MICHIGAN Hub LMP (Market Data) Michigan Hub LMP from Market 8 6 4 2 Correlation of Michigan Hub LMP from PROMOD and Market 2 4 6 8 1 12 Michigan Hub LMP from PROMOD Figure A. 6: Michigan Hub Benchmark Page 22

MINNESOTA Hub LMP Benchmark (Jan 26) 14 12 Correlation =.639 >.188 Average Error = 31.5% 1 Hub LMP ($/MWH) 8 6 The points fall in this area are hours with PROMOD LMP and DA Market LMP difference smaller than 1% 4 Correlation of Minnesota Hub LMP from PROMOD and Market 14 2 MINNESOTA Hub LMP (PROMOD) MINNESOTA Hub LMP (Market Data) 1 36 71 16 141 176 211 246 281 316 351 386 421 456 491 526 561 596 631 666 71 736 Hours Minnesota Hub LMP from Market 12 1 8 6 4 2 Correlation of Minnesota Hub LMP from PROMOD and Market 2 4 6 8 1 12 14 Minnesota Hub LMP from PROMOD Figure A. 7: Minnesota Hub Benchmark AEP GEN HUB Benchmark (Jan 26) 12 1 Correlation =.88 >.188 Average Error = 1.4% Hub LMP ($/MWH) 8 6 4 The points fall in this area are hours with PROMOD LMP and DA Market LMP difference smaller than 1% Correlation of AEP GEN Hub LMP from PROMOD and Market 12 2 AEP GEN HUB LMP (PROMOD) AEP GEN HUB LMP (Market Data) 1 35 69 13 137 171 25 239 273 37 341 375 49 443 477 511 545 579 613 647 681 715 Hours AEP Gen Hub LMP from Market 1 8 6 4 2 Correlation of AEP GEN Hub LMP from PROMOD and Market 2 4 6 8 1 12 AEP Gen Hub LMP from PROMOD Figure A. 8: AEP Gen Hub Benchmark Page 23

Chicago Hub LMP Benchmark (Jan 26) 12 1 Correlation =.838 >.188 Average Error = 2.3% Hub LMP ($/MWH) 8 6 The points fall in this area are hours with PROMOD LMP and DA Market LMP difference smaller than 1% Correlation of Chicago Hub LMP from PROMOD and Market 4 12 2 1 1 34 67 1 133 166 199 232 265 298 331 364 397 43 463 496 529 562 595 628 661 694 727 Hours Chicago Hub LMP (PROMOD) Chicago Hub LMP (Market Data) Chicago Hub LMP from Market 8 6 4 2 Correlation of Chicago Hub LMP from PROMOD and Market 2 4 6 8 1 12 Chicago Hub LMP from PROMOD Figure A. 9: Chicago Hub Benchmark PJM Western Hub LMP Benchmark (Jan 26) 14 12 Correlation =.725 >.188 Average Error = 16.7% Hub LMP ($/MWH) 1 8 6 12 The points fall in this area are hours with PROMOD LMP and DA Market LMP difference smaller than 1% Correlation of PJM Western Hub LMP from PROMOD and Market 4 1 2 1 36 71 16 141 176 211 246 281 316 351 386 421 456 491 526 561 596 631 666 71 736 Hours PJM Western Hub LMP (PROMOD) PJM Western Hub LMP (Market Data) PJM Western Hub LMP from Market 8 6 4 2 Correlation of PJM Western Hub LMP from PROMOD and Market 2 4 6 8 1 12 PJM Western Hub LMP from PROMOD Figure A. 1: PJM Western Hub Benchmark Page 24

PJM WestInterface Hub LMP Benchmark (Jan 26) Hub LMP ($/MWH) 12 1 8 6 4 12 Correlation =.795 >.188 Average Error = 12.7% The points fall in this area are hours with PROMOD LMP and DA Market LMP difference smaller than 1% Correlation of PJM WesterInt Hub LMP from PROMOD and Market 1 2 PJM WestInterface Hub LMP (PROMOD) PJM WestInterface Hub LMP (Market Data) 1 38 75 112 149 186 223 26 297 334 371 48 445 482 519 556 593 63 667 74 741 Hours PJM WesternInt Hub LMP from Market 8 6 4 2 Correlation of PJM WesterInt Hub LMP from PROMOD and Market 2 4 6 8 1 12 PJM WesterInt Hub LMP from PROMOD Figure A. 11: PJM Western Interface Hub Benchmark From these figures and the statistic indices, we can see PROMOD hub LMPs benchmarked well to DA Market LMPs. 2.3 Capacity factors on generator classes Nuclear units: Comparing market data with initial PROMOD runs, PROMOD benchmarks well with market data. However, we did not change the outage schedule for nuclear units in PROMOD so that nuclear units were dispatched in more or less the same manner in both market data and PROMOD data, as in quarterly Cost Benefit studies. Combined cycle (CC s) units: We found that PROMOD dispatched combined cycle units less when compared to the market data. Combustion Turbines (CT s): Consistent with the quarterly Cost Benefit studies, we found that PROMOD did not dispatch CT s to the level found in the market. Hydro units: Consistent with the quarterly Cost Benefit studies, we found that hydro units were dispatched more in PROMOD than in the MISO market data. Pumped storage, run-ofthe-river and hydro storage constitute the hydro units in PROMOD data. Steam turbine Coal units (ST Coal): Steam turbine coal units were split into 2 classes based on their ratings, less than 3 MW class and greater than or equal to 3 MW class. We found that PROMOD over dispatched in at least one class. Page 25

Some of the possible reasons include: 1. Units may be assigned to different categories in PROMOD than in the market data. For example, if a unit with 4MW maximum capacity is split into 2 units (2MW, 2MW) in market data, it will be counted in category (<3MW) in DMT data, but be counted in category (>3MW) in PROMOD. Consequently, it is more appropriate to compare the total coal generation rather than by size category. 2. From the designation of jointly owned units (JOU s) in our market data, it was quite difficult to point out in which class of ST Coal units we should assign the market data. Hence we added 85% of JOU energy to ST Coal greater than or equal to 3 MW category, and 15% of them to ST Coal less than 3 MW category. Hence PROMOD and market data dispatches were consistent in that category. Capacity Factors Bench Marked by Resource Type - MISO Market versus PROMOD Run 1/1/6 through 1/31/6 ST Oil ST Gas.%.5%.6% 2.5% PROMOD (Jan-26) MISO Winter Market (Jan-26) Hydro 7.5% 4.6% CT Oil.3%.6% Combined Cycle 8.3% 6.6% CT Gas.1% 5.2% Nuclear 93.1% 96.7% ST Coal(<3) 63.5% 6.6% ST Coal(>=3) 82.% 79.8% % 1% 2% 3% 4% 5% 6% 7% 8% 9% 1% Figure A. 12: Capacity Factor comparison Based on our quarterly Cost Benefit studies observations, ST Coal units and nuclear units constitute approximately 95% of the total energy in the fall 25 MISO market. Hence achieving a good benchmark on these units is very important. Page 26

2.4 Additional options considered for benchmark 2.4.1 PROMOD switches : Couple of adjustments made to the PROMOD switches helped us to arrive at a better LMP benchmark. They are: Making sure the bid logic switch is ON: Bid Logic switch enables us to include start up and no load costs in the unit costs Designating that coal and nuclear units would provide spinning reserves, the default was: CT s can also provide spinning reserves (also see the section on benchmark on units contributing to spinning reserves ) 2.4.2 Transmission and Generation Outages For benchmarking purposes a listing of transmission and generation outages for the period of January 26 was obtained. There were 35 transmission outages for January 26 with voltage levels above 138 kv. Incorporating these outages in PROMOD did not change the LMP benchmark and there was a significant increase in PROMOD run times. Hence this option was not used in our benchmark. Additionally, there was 7, MW of coal unit capacity out of service in the January 26 period. The coal units were either out on maintenance or being forced out. Incorporating these outages in PROMOD did not change the LMP benchmark. Page 27