ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION

Similar documents
NEW CASTLE CONSERVATION DISTRICT. through. (Name of Municipality) PLAN REVIEW APPLICATION DRAINAGE, STORMWATER MANAGEMENT, EROSION & SEDIMENT CONTROL

Sediment Basin. Fe= (Depends on soil type)

SECTION UTILITY MANHOLES AND STRUCTURES

SECTION TRENCHING & BACKFILLING

C. Foundation stabilization for pipe and utility structures.

Lyon Creek Cedar Way Stormwater Detention Dam Operation and Maintenance Manual

Installation and Maintenance of Erosion Control BMPs

***************************************************************************************************************

ROLES AND RESPONSIBILITIES Small Pond Approval. SWM MD-378 Pond Checklist Training 10/17/07. Exemptions EMBANKMENT HEIGHT. Height of Dam Weir Wall

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 811 CONDUIT AND DRAINAGE STRUCTURES

Standards for Soil Erosion and Sediment Control in New Jersey May 2012 STANDARD FOR SLOPE PROTECTION STRUCTURES. Definition

TEMPORARY SEDIMENT TRAP CODE

TYPE "A" CATCH BASIN

DESIGN STANDARDS. Division 02 Existing Conditions- Site Work. General

Sediment Basins and Skimmers. Jay Dorsey/John Mathews Ohio Dept. of Natural Resources, Division of Soil and Water Resources

SECTION UNCLASSIFIED EXCAVATION AND GRADING

CATCH BASIN ST-1 ENGINEERING DEPARTMENT PLATE NUMBER 3.33' 3.0' 2.0' 4.33' 3.0' 4.0' 1.00' TO BACK OF CURB LINE

SECTION XXXX POLYMER CONCRETE PUMP STATIONS

City of Charlotte BMP Maintenance and Inspection Check List Grassed Channels / Swales [Note: a separate form must be used for each BMP]

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Richland County Department of Public Works Engineering (Land Development) Division

Construction Specification for Utility Adjustments

SEPTIC TANK CONSTRUCTION GUIDELINES

APPENDIX A EARTHEN EMBANKMENT. VERSION 1.0 March 1, 2011

CITY OF EDMOND STANDARD SPECIFICATIONS FOR CONSTRUCTION

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

PERMEABLE INTERLOCKING PAVERS

A.2.a Random Riprap... Table

LANDSCAPE RETAINING WALLS

PUBLIC WORKS SKAGIT COUNTY SAMISH ISLAND ROAD SAMISH ISLAND ROAD SLIDE REPAIR

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

BMP 6.4.4: Infiltration Trench

4.8. Subsurface Infiltration

Extended Detention Basin Maintenance Plan for [[== Insert Project Name ==]]

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

SOIL EROSION CONTROL PERMIT APPLICATION

Fabrication and Installation Table of Contents

2.1 Backfill - General

MANHOLES, VAULTS AND CATCH BASINS SECTION A. Section Soil and Aggregate Materials. C. Section Storm Drainage Systems

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

CITY UTILITIES DESIGN STANDARDS MANUAL

4.8. Subsurface Infiltration

THIS IS A COURTESY COPY OF THIS RULE. ALL OF THE DEPARTMENT S RULES ARE COMPILED IN TITLE 7 OF THE NEW JERSEY ADMINISTRATIVE CODE.

At least 2 feet above the seasonal high water table Overflow path or structure provided

SLAB ON GRADE Insul-Joint or Expansion Joint Material as Required by A/E Specifications AquaCheck Liquid Coating 400 (Waterproofing Membrane) with Aqu

MODEL Stormwater Local Design Manual. City of Centerville

Forsyth County Procurement

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following:

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

Stormwater Local Design Manual For Houston County, Georgia

ARTICLE V: STORMWATER MANAGEMENT AND DRAINAGE SYSTEMS

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

PASSAIC COUNTY TECHNICAL INSTITUTE CCA 1422 NEW S.T.E.M. BUILDING 2017

STANDARD SPECIFICATION STORMWATER QUALITY MEMBRANE FILTRATION TREATMENT DEVICE

STORMWATER POLLUTION PREVENTION PLAN (SWP3)

Chapter 5 Hydraulic Structures

CHAPTER 8 EROSION AND SEDIMENT CONTROL PLAN REQUIREMENTS

CARROLL COUNTY SUPPLEMENT TO THE 2000 MARYLAND STORMWATER DESIGN MANUAL VOLUMES I & II

Recyclex TRM TURF REINFORCEMENT MAT SPECIFICATION

SECTION RIPRAP, BOULDERS, AND BEDDING

PRECAST CONCRETE ON-SITE WASTEWATER TANKS

DAM INSPECTION CHECKLIST Department of Environmental Protection Bureau of Waterways Engineering Division of Dam Safety

STREAM STABILIZATION PLAN

SECTION 3 DRAINAGE. 3-1 General. 3-2 Drainage Ordinances and Legal Requirements

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

1. Initial Backfill: Backfill placed beside and over pipe in a trench, including haunches to support sides of pipe.

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION A1 EXCAVATION AND BACKFILL GENERAL

Uwall UNIVERSAL CONSTRUCTION MANUAL

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

SECTION MANHOLES AND STRUCTURES. A. Section Includes: 1. Manholes for water, storm drain and sanitary sewer systems.

A Design Review of Waterproofing Codes

SECTION GRAVITY IRRIGATION PIPELINES RUBBER GASKETED REINFORCED CONCRETE PIPE (RGRCP)

D. Removal of existing storm sewerage pipe and drainage structures.

PART 1 GENERAL REQUIREMENTS

CITY STANDARD DETAILS FOR CITY OF JACKSONVILLE FLORIDA DEPARTMENT OF PUBLIC WORKS

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

Electrical Work. NOV Embankments Over Swamps and Compressible Soils

Town of New Tecumseth Engineering Design Criteria and Standards for Subdivisions and Capital Works Projects

File No Supplemental November Geotechnical and Environmental Consulting Engineers

Maryland State Highway Administration PS DRAINAGE PERFORMANCE SPECIFICATION

Ohio Department of Transportation Division of Production Management Office of Geotechnical Engineering. Geotechnical Bulletin

***************************************************************************************************************

BAYFILTER SPECIFICATIONS

10:00 AM, Wednesday, April 8, 2015

New Fulton State Hospital Energy Control Center and Services Building (ECC/SVC) Project Number: M

Section [ ] Storm Water Treatment Device

Curlex II EROSION CONTROL BLANKET SPECIFICATION

SITE SERVICES GUELPH TRANSIT OPERATIONS & MAINTENANCE SECTION WATSON ROAD FACILITY PAGE 1 OF 6 WATER RECLAMATION PROJECT JUNE 2013

Constructed Wetland Use in Nonpoint Source Control

CHAPTER 7 - INFRASTRUCTURE INSPECTION AND ACCEPTANCE... 2

Dam Safety Inspection Checklist

Attachment D-1: Civil/Structural Scope of Work

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Underground Piping for Private Hydrants & Sprinkler Supply Line

Understanding Stormwater Pollution Prevention Plans (SWPPPs) (SWPPPS)

TECHNICAL CONTENT PROPOSED STEEP SLOPE REGULATION

TCC/SHORE TRANSIT BUS MAINTENANCE FACILITY PHASE II

Transcription:

NEW CASTLE COUNTY DEPARTMENT OF LAND USE ENGINEERING CHECKLIST SEDIMENT & STORMWATER MANAGEMENT BASIN CONSTRUCTION For Permanent Structures, pursuant to Delaware Pond Code 378 and Delaware Sediment and Stormwater Regulations Property Name: Application Number: Microfilm Number: Contractor: Inspector/Engineer: Date: Project Information Meets Standards: Not Acceptable: X Not Applicable: N/A Requires Engineer s Certification: * Key I. Materials and Equipment Pipe and appurtenances on-site prior to construction and dimensions checked. 3) 4) 5) 6) 7) 8) Material (including protective coating, if specified) Diameter Dimensions of metal riser or pre-cast concrete outlet structure Required dimensions between water control structures (orifices, weirs, etc.) are in accordance with plans. Barrel stub for prefabricated pipe structures at proper angle for design barrel slope Number and dimensions of prefabricated anti-seep collars Watertight connectors and gaskets Outlet drain valve Appropriate compaction equipment available, including hand or small power tamps. Project benchmark near pond site Equipment for temporary dewatering 87 READS WAY, NEW CASTLE, DE 19720 WWW.NCCDELU.ORG PHONE: 302-395-5400 FAX: 302-395-5587

II. Subgrade Preparation Area beneath embankment stripped of all vegetation, topsoil, and organic matter Cut-off trench excavated a minimum of four (4) feet below subgrade and minimum of four (4) feet below proposed pipe invert, with side slopes no steeper than 1:1 Impervious material used to backfill cut-off trench. (State universal soil classification system soil type) III. Pipe Spillway installation Method of installation detailed on plans A. Bed preparation Installation of trench excavated with 1:1 side slopes. Stable, uniform, dry subgrade of relatively imperviously material (If subgrade is wet, contractor shall have defined steps before proceeding with installation). Invert at proper elevation and grade. B. Pipe placement. Metal/Plastic Pipe 3) 4) Watertight connectors and gaskets properly installed Anti-seep collars properly spaced and having watertight connections to pipe. Backfill placed and tamped by hand under haunches of pipe Remaining backfill placed in max. 8 lifts using small power tamping equipment until 2 cover over pipe is reached. Concrete Pipe 3) 4) 5) Pipe set on blocks or concrete slab for pouring of low cradle. Pipe installed with rubber gasket joints with no spalling in basket interface area. Excavating for lower half of anti-seep collar(s) with reinforcing steel set Entire area where anti-seep collar(s) will come in contact with pipe coated with mastic or other approved waterproof sealant. Low cradle and bottom half of anti-seep collar installed as monolithic pour and of an approved mix. Revised 3/01/05 Page 2 of 6

6) 7) 8) Upper half of anti-seep collar(s) formed with reinforcing steel set. Concrete for collar of an approved mix and vibrated into place. (Protected from freezing while curing, if necessary). Forms stripped and collar inspected for honeycomb prior to backfilling parge if necessary. C. Backfilling Fill placed in maximum 8 lifts. Backfill taken minimum 2 above top of antiseep collar elevation before transversing with heavy equipment. IV. Riser/Outlet structure installation A. Metal Riser Riser base excavated or formed on stable subgrade to design dimensions. Embedded section of aluminum or aluminized pipe to be painted with zinc chromate or equivalent on inside and outside surfaces. Set on blocks to design elevations and plumbed. Reinforcing bars placed at right angles and projecting into sides of riser. Concrete poured so as to fill inside of riser to invert of barrel. B. Pre-cast concrete structure Dry and stable subgrade. Riser base set to design elevation. If more than one section, no spalling in gasket interface area, gasket or approved caulking material placed securely. Watertight and structurally sound collar or gasket joint where structure connects to pipe spillway. C. Pour Concrete Structure Footing excavated or formed on stable subgrade, to design dimensions with reinforcible steel set. Structure formed to design dimensions, with reinforcing steel set as per plan. Concrete of an approved mix and vibrated into place (Protected from freezing while curing, if necessary) Revised 3/01/05 Page 3 of 6

Forms stripped and structure inspected for honeycomb prior to backfilling. Parge if necessary. V. Embankment Construction A. Fill Material Soil engineer s test Visual test by inspector B. Compaction Soil engineer s test Visual test by inspector C. Embankment Fill placed in max. 8 lifts and compacted with appropriate equipment Constructed to design cross-section, side slopes and top width Constructed to design elevation plus allowance for settlement VI. Impounded area construction Excavated/graded to design contours and side slopes Inlet pipes have adequate outfall protection Forebay Wet pond requirements 10 ft. reverse slope bench one foot above normal pool elevation 10 ft. wide level bench one foot below normal pool elevation VII. Earth Emergency spillway construction. Spillway located in cut or structurally stabilized with rip-rap, gabions, concrete, etc Excavated to proper cross-section, side slopes and bottom width Entrance channel, crest, and exit channel constructed to design grades and elevations VIII. Outlet protection A. End Section Securely place and properly backfilled Revised 3/01/05 Page 4 of 6

B. Endwall Footing excavated or formed on stable subgrade, to design dimensions and reinforcing steel set, if specified Endwall formed to design dimensions with reinforcing steel sets as per plan Concrete of an approved mix and vibrated into place (Protected from freezing, if necessary). Forms stripped and structure inspected for honeycomb prior to backfilling. Parge, if necessary C. Riprap apron/channel Apron/channel excavated to design cross section with proper transition to existing ground Filter fabric in place Stone sized as per plan and uniformly placed at the thickness specified IX. Vegetative Stabilization Approved seed mixture or sod Proper surface preparation and required soil amendments Excelsior mat or other stabilization materials, as per plan X. Miscellaneous Toe drain Temporary dewatering device installed as per plan w/appropriate fabric, stone size and perforations if included Drain for ponds having a permanent pool Trash rack/anti-vortex device secured to outlet structure Trash protection for low flow pipes, orifices, etc Fencing (when required) Access Road Set aside area for clean-out and maintenance CERTIFICATION PAGE FOLLOWS Revised 3/01/05 Page 5 of 6

CERTIFICATION OF PROFESSIONAL ENGINEER / LAND SURVEYOR: I, the undersigned, hereby certify that I am a Professional Engineer / Land Surveyor registered in the State of Delaware and that, to the best of my knowledge and belief, each element of this checklist was considered and the construction/ installation is in general accordance with the approved plan. Signature and Seal of Applicant Date CERTIFICATION OF CERTIFIED CONSTRUCTION REVIEWER: I, as the Certified Construction Reviewer, possess a current valid certification card, #. I have personally reviewed and accurately reported on each element of this checklist and hereby certify that each element of this checklist was considered and constructed/ installed in general accordance with the approved plan. Signature of Certified Construction Reviewer Date Revised 3/01/05 Page 6 of 6