EXECUTIVE SUMMARY TABLE - 1

Similar documents
EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION

Hind Energy & Coal Beneficiation (India) Ltd.

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

2 NECESSITY OF THE PROPOSED PROJECT

Hind Energy & Coal Beneficiation (India) Ltd.

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004

M/s. Jindal Electricity Generation (P) Limited was promoted by Sri Omprakash Agrawal & Associates having other business in the area.

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN

Rajasthan State Pollution Control Board

PROPOSED TERM OF REFERENCE

Pre-Feasibility Report For Khargone STPP Stage-I (2X660 MW) District- Khargone, Madhya Pradesh

JAYPEE NIGRIE SUPER THERMAL POWER PROJECT

Environmental Impact Assessment

For PROPOSED IT PARK. By M/s.Balewadi Tech Park Pvt.Ltd. Submitted to State Environment Expert Appraisal Committee III, Maharashtra

N.H. 6 is 50 km away from the proposed plant boundary; in N direction;

TERMS OF REFERENCE. Identification of the sources of pollution and assessing the impacts on the environment due to proposed project if any;

HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS

PART A. M/s Shree Cement Ltd, (Grinding Unit) village - Udepur, Tehsil- Suratgarh, District -Shri Ganganagar, Rajasthan

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

CHECK LIST OF DOCUMENTS / OTHER REQUISITES FOR OBTAINING VARIOUS CLEARANCES FROM THE STATE POLLUTION CONTROL BOARD, ODISHA.

North East Roofing Pvt. Ltd. Expansion of Asbestos Cement Sheets & Accessories Manufacturing Unit (50,000 TPA to 70,000 TPA)

HINGULA OPEN CAST PROJECT HINGULA AREA MAHANADI COALFIELDS LIMITED

ENVIRONMENTAL IMPACT ASSESSMENT FOR PROPOSED CONSTRUCTION OF SEWAGE PUMPING STATION & SEWAGE TREATMENT PLANT

No. 138 /PS-MS/MPPCB/SEAC/TOR (75)/2011 Bhopal, dt. 03 /06/2011. Env. Consultant: Créative Enviro Service, Bhopal. (SN-29)

2 No. Continuous Ambient Air Quality Monitoring System (CAAQMS) installed in downwind & upwind direction and are connected to APPCB server.

Particulate Emission Monitoring HN Pathak Supdtg Engr Madhya Pradesh Power Generation Co. Ltd

Executive summary. EIA STUDY for 1320MW Coal Based Super-critical Thermal Power Plant at Deosar, District Singrauli, Madhya Pradesh 13-13

.in Dated 9th August, Sharma ;

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

PRE-FEASIBILITY REPORT

COAL STOCKPILES IN INDIAN POWER PLANTS. H Ramakrishna TCE Consulting Engineers Limited 73/1, St Marks Road, Bangalore , Karnataka, India

PRE FEASIBILITY REPORT

LANCO ANPARA POWER PVT. LTD

Jaypee Lime Stone Mine Jaypee Bela Plant (A Unit of Jaiprakash Associates Limited)

SINGHAL ENTERPRISES PRIVATE LIMITED

PRE-FEASIBILITY REPORT FOR OM SAIRAM STEEL AND ALLOYS PVT LTD

PROJECT FEASIBILITY REPORT

APPENDIX VIII. Form 1 M APPLICATION FOR MINING OF MINOR MINERALS UNDER CATEGORY B2 FOR LESS THAN AND EQUAL TO FIVE HECTARE

Naubasta Lime Stone Mine ML - I Jaypee Rewa Plant Jaiprakash Associates Limited

OPTIMISATION OF WATER USAGES IN THERMAL POWER PLANTS AND A STUDY ON DRY COOLING SYSTEM

Sr.No Condition Status A. SPECIFIC CONDITIONS:

Max. building height (m)

FORM V ENVIRONMENTAL STATEMENT REPORT FOR THE FINANCIAL YEAR M/s Halki Lime Stone Mine (Unit: J. K. Cement Limited) PART A

Infrastructure Development and Environment

Welcome to. Kendal Power Station

PRE FEASIBILITY REPORT

Environmental impact assessment of a 1600 MW thermal power plant project in Karimnagar district of Telangana

THE RAMCO CEMENTS LIMITED

ENVIRONMENTAL MONITORING PROGRAMME

Telefax : 011: Dated 1 st March, 2013

ENVIRONMENTAL IMPACT ASSESSMENT AND YOU

4.0 ENVIRONMENTAL IMPACTS AND MITIGATION MEASURES. Negative or adverse impacts during the construction phase are:

HINAUTI LIMESTONE MINE Mine Lease area ha. (A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.P)

Sub: Submission of compliance report. Ref: Letter 1.No.21-4(67)/NCR/CGWA/ dated 16 Mar No.4-6/NCR/TS-637 dated

Monitoring the Implementation of Environmental Safeguards

Environmental Guideline on Stone crushing plant set up temporarily for the purpose of a project by a public department

Existing vegetation with each tree detail like species, girth, canopy etc. Contours with levels Natural features like water body, stream etc.

CMPDI. 4.6 Mine Closure Plan

RAPID ENVIRONMENTAL IMPACT ASSESSMENT

PROJECT BRIEF. Noise environment: No Entrant noise generation sources exist in and around project area.

ZZH/CLAB-KSPCB/04/ Environmental Officer,

Dilipbhai D. Patel. BLOCK NO. 43, F.P. NO. 45,O.P NO. 40 T.P.S. No- 17 (PUNA), Ta: SURAT CITY, DIST: SURAT

Environmental Impact Assessment of Hydroelectric Power Plant LEEZA MALIK (2013CEP2080) TUSHAR SINGLA (2011MT50623)

No.IA-J-11011/363/2017-IA-II(I) Goverment of India Minister of Enviroment,Forest and Climate Change Impact Assessment Division ***

Scania Steels and Powers Ltd.

at Sarora Village, Tilda Tehsil, Raipur District, Chhattisgarh in 64 acres of land. Now

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS

COAL WATER SLURRY FUEL Alternate Fuel for Thailand

PRESENTATION ON DEVELOPMENT OF NEW POWER PROJECTS APPROACH & WAY FORWARD

Babcock Borsig Steinmüller GmbH. Bełchatów - Retrofitting the EU s Largest Power Plant Site

Lünen State-of-the-Art 813MW Coal-Fired USC Boiler with High Efficiency and Flexibility

Biomass Boiler Emission Abatement Technologies. Simon Wakefield

RED CATEGORY CONSENT & AUTHORIZATION ORDER BY REGISTERED POST WITH ACKNOWLEDGEMENT DUE

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN

MIDC, Nagpur Expansion of Existing Butibori Industrial Area (BIA Phase II) - Form-1

No. J-l1015/313/2010-IA.II (M) Government of India Ministry of Environment & Forests

Portbury Dock Renewable Energy Plant. Cumulative Impact Assessment Non-Technical Summary September 2009

Excerpt of Thermal Power Guidelines for New Plants

APPENDIX H AIR DISPERSION MODELLING REPORT BY PROJECT MANAGEMENT LTD. (REF. CHAPTER 11 AIR QUALITY AND CLIMATIC FACTORS)

M/s. SAL STEEL LTD Survey no.245/p, Village:-Bharapar, Taluka:- Gandhidham, District:-Kutch, Gujarat.

ARC. CEO, Ulla Röttger

Post Combustion CO 2 Capture Scale Up Study

Chemplast Sanmar Limited Marine Terminal Facility, Chitrapettai Village Cuddalore District, Tamil Nadu

Gold Standard Passport CONTENTS

Kazushige KUROSAWA*, Zhibao ZHANG**, and Zhengbing WANG** [Delivered Products & Systems] 1. Introduction. 2. Overview of Nanjing

CCR COMPLIANCE FUGITIVE DUST CONTROL PLAN. Prepared for: Tucson Electric Power Company Springerville Generating Station Springerville, Arizona

Appendix VIII: Determination of chimney heights

KADALADI TALUK, RAMANATHAPURAM DISTRICT, TAMIL NADU

PRE FEASIBILITY REPORT. For PROPOSED BULK DRUG PRODUCTS MANUFACTURING UNITS. M/s. M.K. DRUGS. F-10, Industrial Area, Focal Point, Tehsil: Derabassi

Dr. NARLA TATA RAO THERMAL POWER STATION (Dr. NTTPS) STAGE V (1X800 MW)

Total No. of Questions : 5] [Total No. of Printed Pages : 2 [3683]-1. P. G. D. E. M. (Semester - I) Examination

Jhajjar Project Management An Insight. March 4, 2013

Torpa Small Hydro Power Project

F.P.No.52, S.No.53/B, 54/2/B, D.T.P.S.No.80, Village: Bhat, Dist: Gandhinagar.

Checklist in respect of selection of Design Consultancy for EER&M of Parli TPS (U-3)

Compliance of Environmental Clearance SEIAA/GUJ/EC/8(a)/251/2012 Dated (Period April 2016 to September 2016)

A proposed new gas-fired power station on the Wilton International site

Worldwide Pollution Control Association. August 3-4, 2010

Preparatory study for Steam Boilers Ecodesign

MAJHIGAWAN LIMESTONE MINE Mine Lease area ha. ( A UNIT OF JAIPRAKASH ASSOCIATES LIMITED) JAYPEE VIHAR, SIDHI (M.

Transcription:

EXECUTIVE SUMMARY 1.0 PROJECT DESCRIPTION 1.1 INTRODUCTION Dwarkesh Energy Limited (DEL) proposes to set up a 1320 MW (2 x 660 MW) Super Critical Coal Based Thermal Power Plant at Villages Torniya, Chhippipura & Rampuri, Tehsil Harsud, District Khandwa, Madhya Pradesh. As per EIA Notification dated 14th September & as amended on 1st December, 2009, this project falls under Category A (> 500MW, Coal based), S. No. 1(d) (Thermal Power Plants), & hence requires Environment Clearance. The project was considered before the Expert Appraisal Committee (T) for technical presentation (ToR Reconsideration) on 6 th June, 2011. The EAC has suggested Terms of References (ToR) Letter vide its MoEF Letter No. J-13012/17/2011 - IA. II (T)& letter dated July 26, 2011 for preparation of Draft EIA/EMP Report. 1.2 DETAILS OF THE PROJECT TABLE - 1 SALIENT FEATURES OF THE PROJECT S.No Particulars Details 1 Location Torniya, Chhippipura & Rampuri, Tehsil Harsud, Distt. Khandwa (Madhya Pradesh) 2 Geographical Positions Latitude 21 59'46.61" to 22 1'0.36" N M/s Dwarkesh Energy Limited (DEL) 1 Longitude 3 Elevation above MSL 280 m 4 Land Required for the Activity 935 Acre 76 45'38.38" to 76 47'5.66" E 5 Present Land Use Max Single Crop Agricultural Use 6 Nature of Soil Medium Black 7 Nature of Terrain Moderately Undulating 8 Predominant Wind Direction Towards South West 9 Nearest Highway NH 59A at a distance of 50 km from the proposed project site in NW direction. State Highway SH-15 at a distance of 500m from the proposed project site.

10 Nearest Major Railway Station Khandwa Junction (45km), Barud R.S (2 km NE) 11 Nearest Airport Indore approx 180 km 12 Nearest Village Torniya 0.5 Km 13 Nearest Port Surat WSW approx 450 km 14 Topography Area of plant site is generally flat 15 Monuments Nil 16 Archaeologically Important Places None 17 National Parks None within in 10 Km Radius 18 Forests Pratapura Reserve forest at 5km South East-South West Direction 19 Seismicity Zone-III 20 Streams/River Ghorapachar Nadi (1.5 km, SW) M/s Dwarkesh Energy Limited (DEL) 2 Patal Nadi (6.8km,NE) Agni river (11km, SW) Chota tawa river(12.5km, NW) 21 Nearest Town/City Khandwa approx 45 km Technical Details of the Proposed 1360 MW (2x660 MW) Super Critical Coal based Thermal Power Plant 22 Plant Capacity 1320 MW (2 660MW) Fuel Source and Consumption 23 Quantity & Source of Fuel 6.9 MTPA (Source: Imported Coal from Overseas) 24 Fuel Gross Calorific value 3300 Kcal/Kg to 4200 Kcal /Kg 25 Fuel Consumption at 85% PLF 6.9 MTPA 26 Support Fuel & Source Heavy Fuel From Nearest Refinery 27 Support Fuel & Requirement Approx 10000kl Ash Generation 28 Total Ash Generation 2.76 MTPA Water-Requirement, Source 29 Water Source and Quantity Total Water requirement: 39.60 MCM (4520m 3 /hr) Source: Indira Sagar reservoir [Application submitted vide Letter No. JKLCL/P. Plant/2010-2011/3 dated 08.11.10 to Narmada Valley Development Authority, Bhopal for allocation of 50 MCM water from Indra Sagar Reservoir for the project (Annexure 2A). Narmada Valley Corporation in its 18 th meeting recommended water

30 Raw Water Requirement 4520 Cu.M / hr 31 Treatment Scheme Land 32 Total land Required 935 Acre Plant & Equipment 33 Boiler & Auxiliaries allocation to project vide letter no. S. No. 290.187/ Secretary/ River valley/ Work/ 11/ 187.03/ 1252 dated 28.12.11 (Annexure 2B)] Separate ETP will be provided 34 Boiler Pulverized Coal Firing Boiler The Steam Generator shall be of once through type with Supercritical Parameters, Constant as well as Sliding Pressure operation, Two Pass, Single reheat, balanced draft, outdoor arrangement, all steel structure, complete hanging construction and dry bottom pulverized coal fired. Supercritical boiler is designed for firing range of specified pulverized coal as fuel, employing direct and opposed wall firing system or Tangential firing system. 35 Auxiliary Boiler One (1) no. water tube type, natural circulation, pressurized furnace, LDO fired, outdoor type auxiliary steam generator with its auxiliaries, having adequate steaming capacity with steam parameters of 20 kg/sq.cm (g) pressure and 3500C steam 36 Steam parameter per Boiler Temperature (a) At Superheater outlet- 570 0 c (b) At Reaheater Outlet - 596 0 c Presssure - 257kg / Sq.cm 37 Boiler Efficiency 85% Turbine & Auxiliaries 38 Turbine Heat Rate 1850Kcal/Kwh 39 Plant Heat Rate 2300Kcal/Kwh 40 Ash Generation and Handling System Dry and Wet Ash Handling System 41 Total Ash 2.76 MTPA 42 Bottom Ash 0.55MTPA Cooling Tower M/s Dwarkesh Energy Limited (DEL) 3

43 Cooling System Natural Draft Cooling System 44 No. of Cooling Tower 2 (one for each unit) 45 Capacity 74200 CuM Chimney 46 No. of chimney 1 47 Height of Chimney 275m High Twin flue gas path for 2x 660 MW Project Schedule 48 Unit-1 42 Months 49 Unit-2 48 Months Manpower Requirement 50 During Construction Phase Approx 1000 51 During o & M Approx 250 Source: Prefeasibility Report & Site Visit Report 2.0 PROCESS DESCRIPTION 2.1 Thermal Power Generation Process In thermal power generation, chemical energy of coal is first converted into thermal energy (during combustion), which is then converted into mechanical energy (through a turbine) and finally into electrical energy (through a generator). The flow chart below shows the process for coal fired Thermal Power Plant. M/s Dwarkesh Energy Limited (DEL) 4

Figure 1: Process flow Diagram for Thermal Power Plant M/s Dwarkesh Energy Limited (DEL) 5

3.0 DESCRIPTION OF ENVIRONMENT Baseline study of the study area (i.e. 10 km radius from the project boundary) was conducted during Post Monsoon season, 2011. Baseline study included for ambient air quality, ambient noise level, water quality, soil quality, land use pattern, demography, flora & fauna found separately in the core & buffer zone etc. The concentration of SPM, PM 10 and PM 2.5 for all the 8 AAQM stations ranges between 143.93 µg/m 3 to 221.88 µg/m 3, 46.64 to 73.65 µg/m 3 and 21.95 µg/m 3 to 32.76 µg/m 3 respectively. As far as the gaseous pollutants SO2 and NO2 are concerned, the SO2 concentrations are in the range of 6.47 µg/m 3 to 9.23 µg/m 3 and the NOx concentration in the range of 14.06 µg/m 3 to 21.39 µg/m 3 for all the 8 AAQM stations. Hence, the concentration of SPM, PM10, PM2.5, SO2& NO2 at all 8 AAQM stations are found to be well within the prescribe standards. Values for Ozone & Hg were found within the prescribed norms. Analysis of four surface water samples reveals that the ph were in the range of 8.04 to 8.19, Total Hardness varies from 136.00 to 209.60 mg/l, Total Dissolved Solid varies from 213.00 to 329.00 mg/l and Nine ground water samples showed ph in the range of 7.46 & 8.17, Total Dissolved Solids from 302.00 to 661.00 mg/l and total hardness ranges between 148.00 & 592.00 mg/l. The analysis results show that soil is almost neutral with ph value ranging from 7.06 to 7.18 with Organic Matter from 0.54% to 0.87 %. The phosphorous varies from 8.80 to 11.38 kg/ha in the moderate amount, Potassium ranges from 119.01 to 380.76 kg/ha and Nitrogen from 208.01 to 272.70 kg/ha. 3.1 SOCIO-ECONOMIC ENVIRONMENT As of 2001 India census, population of the study area is 35470. The Schedule caste is 12.08%and scheduled tribe is 33.08% of the total population. Average literacy rate is 57.34%. The total number of households is 6416. 4.0 ANTICIPATED ENVIRONMENTAL IMPACTS During construction phase, dust will be the main pollutant, which will be generated from the site development activities and vehicular movement on the road. During operation phase, SO 2, NO 2, PM & CO will be generated from the power generation process. M/s Dwarkesh Energy Limited (DEL) 6

Industrial Waste water will be generated from Cooling tower blow down, DM plant, Filter backwash water, Boiler blow down and sanitary wash. The same will be treated properly & will be recycled back to the process. The sanitary waste water generated from plant & colony will be treated in STP and will be reused for plantation purpose. The unit will be Zero Discharge Unit. Rainwater harvesting measures will be adopted within the Plant/ colony area. Fly Ash will be collected in dry form and will be supplied to down stream users for value added product. Bottom ash and unused fly ash will be collected in ash pond of suitable design. During construction phase impact of noise in the area will be temporary in nature. Ear muffs and Plugs will be provided to workers, which shall further reduce impact of noise. During operation phase the source of noise will be various components of Turbine unit, D. G. Sets, Air compressors, Transformer and Boilers. The construction activities will result in loss of topsoil to some extent within the plant area & waste disposal area. The topsoil requires proper handling like separate stacking so that it can be used for green belt development. No significant adverse impact on soil in the surrounding area is anticipated, only temporary impact will be observed due to the construction activities. No Eco sensitive Zone viz. National Park, Wildlife Sanctuary, Biosphere reserve wildlife corridors falling with the 10 km radius of the project site. 5.0 ENVIRONMENTAL MONITORING PROGRAM Table: 2 Environmental Monitoring Program S. No. DESCRIPTION FREQUENCY OF MONITORING 1. Meteorological Data Daily 2. Ambient Air Quality at Plant site Quarterly/ Half Yearly 3. Stack monitoring Quarterly/ Half Yearly 4. Water Quality Quarterly/ Half Yearly 5. Noise Level Monitoring Quarterly/ Half Yearly 6. Soil Quality Half Yearly/yearly Ambient air quality monitoring, stack monitoring, water quality (ground water and surface water monitoring) will be conducted at site as per guideline presented by M/s Dwarkesh Energy Limited (DEL) 7

the State Pollution Control Board. Quality of soil of the surrounding area and noise in the plant premises will also be measured as per SPCB Guidelines. 6.0 ADDITIONAL STUDIES The Additional Studies conducted as per the additional Terms of References vide MoEF Letter No. J-13012/17/2011 - IA. II (T)& letter dated July 26, 2011 are Risk Assessment, Disaster Management Plan; Hydro-geological Study & Rain water Harvesting Plan. 6.1 RISK ASSESSMENT AND DISASTER MANAGEMENT STUDIES The risks associated with the proposed project like spontaneous ignition of coal and Hazard analysis involves the identification and quantification of the various hazards (unsafe conditions) that exist in the proposed plant. On the other hand, risk analysis deals with the recognition and computation of risks, the equipment in the plant and personnel are prone to, due to accidents resulting from the hazards present in the plant. This requires a thorough knowledge of failure probability, credible accident scenario, vulnerability of population etc. Much of this information is difficult to get or generate. Consequently, the risk analysis is often confined to maximum credible accident studies and these details discussed in details in EIA report. 6.2 GEOLOGICAL & HYDROGEOLOGICAL STUDIES Geo morphologically the area consists of structural hills of Vindhyan, Denudation hills of Deccan traps. Apart from these above units features like flood plains, alluvial plains, valley fills etc are also seen in the district. The investigated area falls in the Khandwa district, the area of Khandwa district is subdivided in various geological formations, forming different type of the aquifer in the area. It is underlain by granite gneiss of Archean age, Bijawars sandstone & shale, Vindhyan Sandstone and shales, Bagh sandstone & shales, Deccan traps basalt. Major of the district is occupied by Deccan traps. Two types of aquifers are found. Weathered aquifer and fractured aquifers. Water level in the area ranges from 8 mts. to 12 mts. Hydro geologically the area is composed of alluvial and for artificial ground water recharge, Recharge wells will be most feasible recharge techniques. This will help in M/s Dwarkesh Energy Limited (DEL) 8

augmenting the groundwater storage around the tube wells so that they can sustain in long term. 6.3 SOCIO-ECONOMIC STUDIES The Socio-economic profile of the study area has been studied extensively by J.M. Enviro Net Pvt. Ltd. A survey was conducted by a team of four field Assistants, One Supervisor and two Senior Advisors. There are only three villages namely Torniya and Rampuri and some part (Only Government land) of Chhipipura village, which are directly affected due to land acquisition. Land use pattern and demographic data as obtained from primary data and census 2001 have been presented in Chapter III of the Draft EIA/EMP Report for the said project. 6.4 SOLAR POWER HARVESTATION Feasibility studies for harnessing solar power within premises are under process by State Ministry of Renewable Energy Resources and TC Energy Infratech (Engineering Consultant). Details of the same shall be furnished in the Final EIA/ EMP Report. 7.0 PROJECT BENEFITS The company s management will recruit the eligible semi skilled & unskilled workers from the nearby villages based on need, hence rapidly increasing the socio-economic status of the villagers. Excise revenue the project will provide an excise and tax revenue for the state and hence developmental works in the districts will be enhanced. Overall development of rural areas, new shops, upliftment of locals through small business opportunities. M/s Dwarkesh Energy Limited (DEL) 9

8.0 ENVIRONMENTAL MANAGEMENT PLAN 8.1 WATER POLLUTION MANAGEMENT Waste water will be generated from Cooling tower blow down, DM plant, Filter backwash water, Boiler blow down and sanitary wash. Waste water generated from the plant process will be treated & reused. The composite liquid effluent treatment plant has been designed to treat all liquid effluents which originate within the power station e.g. Water Treatment Plant (WTP), floor washings, service water drains etc. Oily wastes will be processed through oil separators to trap oil from the effluents emanating from the Oil Handling Area. Rain water harvesting shall be practiced. Ground water quality shall be monitored regularly. 8.2 AIR POLLUTION MANAGEMENT The following measures will be adopted: A High efficiency Electrostatic precipitator (ESP) having efficiency not less than 99.98% would be installed to control and limit the particulate emission to 50 mg/nm3. To facilitate wider dispersion of pollutants one stack (twin flue) of 275 m height above plant grade level is envisaged. Emission of NOx will be controlled using advanced coal burner. All the internal roads shall be concreted / asphalted to reduce the fugitive dust due to vehicular movement. Fugitive dust emission at all requisite points in coal handling plant and coal stockyard will be controlled by providing water sprinklers. The emissions from the stacks shall be continuously monitored. CREP guidelines will be followed. 8.3 NOISE POLLUTION MANAGEMENT The noise generating sources in the proposed plant will be from turbines, generators, compressors, pumps, fans, coal handling plant etc. M/s Dwarkesh Energy Limited (DEL) 10

All equipments shall be designed for noise levels not exceeding 85 dba. Machines shall be housed in building & provided with acoustic enclosures as required to maintain noise levels within limits. The operator s cabins (control rooms) shall be properly (acoustically) insulated with special doors and observation windows. All applicable Personal Protective Equipments (PPEs) shall be provided. The wide greenbelt around the plant will attenuate the noise level. 8.4 SOLID WASTE MANAGEMENT The fly ash is collected in silos and would be encouraged to be utilized locally /marketed in dry form. Fly ash generated from the proposed power plant would be commercially utilized (both domestically and exporting) to the extent possible in one or more of the following industries: Cement Industry. Brick industry. Fly ash aggregate making industry. Road making/ paving. As per MOEF guidelines 100% fly ash utilization will be ensured within Four (4) years of commissioning of the plant. Bottom Ash will be disposed to ash pond in semi dry form. Unutilized fly ash will be disposed to ash pond. A blanket of water will be maintained over the ash pond area to control fugitive dust emission. After the ash pond is abandoned, it would be reclaimed by providing earth cover and thereafter tree plantation. 8.5 OCCUPATIONAL HEALTH & SAFETY MEASURES In order to ensure good health of workers, periodic health check-up camps for workers would be organized. Occupational health surveillance programme would be taken as a regular exercise for all the employees. M/s Dwarkesh Energy Limited (DEL) 11

All required safety items would be provided to workers and employees while on duty. Regular checking and maintenance of various equipments will be done to ensure their proper service. An elaborate fire hydrant system covering all the building including the coal stockyard would be provided. 8.6 GREEN BELT DEVELOPMENT Plantation will be done in and around the plant premises. Tree plantation would be undertaken in about 33% of the total plant area in all available spaces in the plant and township. Plantation will be done as per the guidelines. 80% survival rate will be maintained with all possible effort. The trees will be planted at suitable grid spacing to encourage proper growth. 9.0 CONCLUSION As discussed, it is safe to say that the project is not likely to cause any significant impact on the ecology of the area, as adequate preventive measures will be adopted to contain the various pollutants within permissible limits. Green belt development around the area would also be taken up as an effective pollution mitigative technique, as well as to control the pollutants released from the premises of DEL. M/s Dwarkesh Energy Limited (DEL) 12