Executive Steering Committee Meeting #1: Minutes

Similar documents
ATTACHMENT A. Detailed Study Scope. I-66 (Inside) Multi-modal Study Scope

TransAction Plan October 2017

VRE AT WORK PREPARING VIRGINIA RAILROADING FOR ITS NEXT QUARTER CENTURY

PRTC Strategic Plan Recommendations

Project Overview. A Collaborative Effort

Long Bridge Project. Environmental Impact Statement (EIS) Revised Purpose and Need

NATIONAL CAPITAL REGION TRANSPORTATION PLANNING BOARD

TransAction Plan Draft for Public Comment Spring/Summer 2017

EXECUTIVE SUMMARY...V

I-66 Corridor Improvements Outside the Capital Beltway in Northern Virginia, USA

ARLINGTON COUNTY TRANSIT DEVELOPMENT PLAN

Regional Bus Rapid Transit

Fairfax County Countywide Transit Network Study

Commonwealth Transportation Board Sean T. Connaughton 1401 East Broad Street (804) Chairman Richmond, Virginia Fax: (804)

Corridors of Statewide Significance: Introduction

Transform 66 Multimodal Project: Prioritization Process and Evaluation Criteria Approved March 3, 2016

Environmental Impact Statement (EIS)/ Section 106 Public Meeting Proposed Alternatives. December 14, 2017

PUBLIC TRANSPORTATION PLAN

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement

Pacific Northwest High Speed Rail Corridor Amtrak Cascades Passenger Service Update

3.2. Transportation Management Plan

MOBILITY, ACCESSIBIILTY, AND CONNECTIVITY

Caltrain Fare Study Update

VIRGINIA RAILWAY EXPRESS REQUEST FOR PROPOSALS (RFP) RFP No MAINTENANCE SERVICES FOR COMMUTER RAIL OPERATIONS

Public Hearing for April 2018 Major Service Changes. January 4, 2018

PPTA Project Pipeline

TRANSIT SERVICE GUIDELINES

Option 1: Full Service (Selected for Additional Analysis)

Chapter 4: Developing the Recommendations

METRA UP-W LINE. Locally Preferred Alternative Report

S-09: Auburn Station Access Improvements

CHAPTER 1: INTRODUCTION/ GOALS AND OBJECTIVES

Sustainability. Sustainability Principles. 1. Framework. Spokane Transit s definition of Sustainability is:

Executive Summary October 2017

Update October 15, 2008

CEO REPORT OCTOBER 2017

Loudoun County Chamber of Commerce

KNOXVILLE REGIONAL TRANSIT CORRIDOR STUDY

High-Speed Rail - Chicago to St. Louis Alton Regional Multimodal Transportation Center Project

Operations Concept Technical Report

ITEM 11 - Information January 21, Briefing on Project Submissions for the 2015 CLRP

HB2 Implementation Policy Guide

Chapter 1: The 2035 Virginia Surface Transportation Plan 1. Challenges & Opportunities 2 VTrans2035: The Precursor 2 The VSTP and VTrans2035 2

CEO REPORT FEBRUARY 2018

September Public Meetings. Developing a Blueprint for the Corridor

Current Trends in Traffic Congestion Mitigation

MEMORANDUM EXAMPLES FOR ILLUSTRATIVE PURPOSES NEXT STEPS. Item 3 Long-Range Plan Task Force May 17, 2017

ACKNOWLEDGEMENT/DISCLAIMER

Fairmount Line Feasibility Study

STATEWIDE ANALYSIS MODEL (SAM-V3) June 5, 2014 Janie Temple

EXHIBIT A. TRANSIT AND MULTIMODAL DEVELOPMENT SUPPORT CONTINUING SERVICES SCOPE OF SERVICES FM No

FAIRFAX COUNTY PARK-AND-RIDE DEMAND ESTIMATION STUDY

Service Standards and Policies

Stockton Freight & Passenger Rail Mobility Enhancement

Chapter 10 Goals, Objectives + Policies

TPB Scenario Study Task Force: Proposal for Development and Analysis of Two New Scenarios

1.1 Purpose of the Project

US & USRC Track Capacity Study Train Capacity Analysis Present to Maximum Capacity and Beyond

CAPITAL AREA TRANSIT PLANNING SERVICE STANDARDS AND PROCESS. Planning Department

PERSPECTIVES ON FRONT RANGE PASSENGER RAIL

ITEM 9 Action October 18, 2017

TRANSIT ALTERNATIVES ANALYSIS OF THE ROUTE 7 CORRIDOR. Background Information Report Appendix

Long-Range Plan Task Force: Draft Analysis Results

Caltrain Business Plan Draft Business Strategy and Scope. Board of Directors December 7, 2017 Agenda Item 9

DC Circulator Fare Adjustment Plan. April 2018

Tier 1 Recommendations October 30, 2017

NEW JERSEY STATE RAIL PLAN NJ TRANSIT New Jersey Department of Transportation

HB2 Implementation Policy Guide

Peoria Programs Rail. John McCarthy. Jacobs. St. Louis, MO. Jim Prost, AICP. Vantage Point Development Advisors. Annapolis, MD

Comprehensive Operations Analysis (COA)

Sunrise Project South I-205 Corridor Improvement Project

MONITORING IMPLEMENTATION AND PERFORMANCE

KING COUNTY FERRY DISTRICT 2014 STRATEGIC PLAN

METRO VANCOUVER MOBILITY PRICING INDEPENDENT COMMISSION FINAL TERMS OF REFERENCE. Revised - June 30, 2017

NJ State Rail Plan. New Jersey Short Line Railroad Association Briefing September 12, 2012

National Capital Region Congestion Report

Team Introduction. Stakeholder and Public Engagement. Importance of the US 280 Corridor. Project Overview, Schedule, and Deliverables.

California State Rail Plan. Santa Cruz County Regional Transportation Commission November 2, 2017

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION

NEW OPPORTUNITY FOR MIDDLESEX COUNTY

PUBLIC HEARING April 24, 2017

Transit, Intercity Bus, Taxi 8-1

PROTECTING Our Quality of Life... Why the Capital Region Needs to Invest in Mass Transit NOW

Transportation Concurrency

I-95 Corridor Coalition

Transit Service Guidelines

AMPO Annual Conference Session: Performance (Part 1) October 18, 2017 Savannah, GA

November 8, RE: Harrah s Station Square Casino Transportation Analysis Detailed Traffic Impact Study Review. Dear Mr. Rowe:

June 18, Re: I-66 Outside the Beltway Tier 2 Draft EA and 4(f) Evaluation

TRANSPORTATION FACTS. OUR CUSTOMERS: Travel Patterns

Washington Metropolitan Area Transit Authority INVITES YOUR INTEREST IN THE POSITION OF CHIEF ENGINEER

COMPREHENSIVE TRANSPORTATION REVIEW THE WHARF PHASE 2 PUD

Bonnie Doon Grade Separation

Everett Transit Action Plan Open House and Community Meeting

Welcome and thank you for your interest in the proposed Baltimore-Washington Superconducting Maglev Project.

Downtown Estes Loop Project Frequently Asked Questions

DRAFT NATIONAL CAPITAL REGION FREIGHT PLAN. July 2016

Future System Planning (ST4)

DART s Role in Transit - Oriented Development. Jack Wierzenski,, Director Economic Development & Planning Dallas Area Rapid Transit

APPENDIX H: TRAVEL DEMAND MODEL VALIDATION AND ANALYSIS

Transcription:

Executive Steering Committee Meeting #1: Minutes DATE/TIME: November 10, 2015 9:00-11:00 AM PLACE: VDOT Northern Virginia District Office, 4975 Alliance Drive, Fairfax, VA 22030 SUBJECT: Executive Steering Committee (ESC) Meeting #1 ATTENDEES: ESC Members Rick Canizales, Prince William County (Alt for Tom Blaser) Helen Cuervo, VDOT Bryan Foster, Deputy City Manager, City of Manassas Brian Henshaw, Town Manager, Town of Haymarket Monica Backmon, Director, NVTA Todd Horsley, DRPT (Alt for Jennifer Mitchell) Helen Cuervo, Administrator, VDOT Kelley Coyner, Director, NVTC Betsy Massie, Director of Grant and Project Development, PRTC VRE GHX Study Team Doug Allen, VRE Christine Hoeffner, VRE Sonali Soneji, VRE Tom Hickey, VRE Jason Mumford, AECOM Lauryn Douglas, AECOM Meredith Judy, Rhodeside & Harwell Jeff Schlossberg, Rhodeside & Harwell 1

I. Project background and objectives a. The meeting began with introductions by all participants. Doug Allen (VRE) welcomed everyone to the meeting and thanked them for attending. b. Christine Hoeffner (VRE) gave an overview of VRE and the project and its current service, and Jason Mumford (AECOM) presented an overview of the current alternatives and constraints. Meeting attendees were encouraged to ask questions throughout the presentation. II. Public and stakeholder engagement and coordination a. The GHX Study team is coordinating with the I-66 Outside the Beltway study teams. GHX is one of the ten multimodal improvement strategies recommended by the Commonwealth Transportation Board for the I-66 corridor. The teams are also discussing potential shared park-and-ride facilities, if feasible and desirable for both initiatives. b. The study is also coordinating with Dominion Power regarding the alignment of the proposed Haymarket High Voltage Transmission Line. Dominion has been responsive and collaborative in determining an alignment for their service. Dominion submitted plans to the State Corporation Commission (SCC) at the end of October. The preferred alignment is above ground along I-66. VRE will submit a letter to the SCC in support of this alignment. c. VRE will be reaching out to Haymarket, Manassas, PWC, PRTC, NVTC, NVTA to offer presentations to their boards and commissions. VRE will continue to keep these boards and commissions informed throughout the study process. d. Agency and stakeholder coordination is very important. Elected officials need to know about this initiative, and understand the economic development opportunities and value it will offer the County, Town, and Commonwealth. e. The GHX Study will include a study of infrastructure needs and ROW impacts. Long Bridge is the primary bottleneck in the larger railroad network between Haymarket and Washington, DC. A Federal TIGER grant was awarded to the District Department of Transportation (DDOT) to initiate NEPA for the Long Bridge expansion. That study is expected to start after January 1, 2016. An American Recovery & Reinvestment Act (ARRA) grant is currently funding pre-nepa work. VRE is participating in the study oversight committee. 2

III. Discussion: Alternatives and Constraints Alternatives a. The GHX Study is considering alternative alignments to serve future development, including a proposed town center, in Innovation Park. The study team will develop order of magnitude cost estimates and estimate demand for a station and alignment off of the B-Line. b. Within the existing NS B-Line right-of-way, there is room for a second track. A third track would likely require additional right-of-way. A third track may be necessary in order to accommodate future passenger rail and freight demands, however, this will be determined as part of the current study. c. The VRE GHX Study will consider future ridership potential at Broad Run and the potential new stations if the Manassas line is extended. There are many current riders that already live within the corridor extension area. The study will consider alignments that include two branches and alignments that remove Broad Run station to avoid a two-line configuration of the Manassas Line. The study will consider the ridership, scheduling, and storage/maintenance implications of both scenarios. d. There is concern from current riders about trains filling up before they arrive at Manassas. This will be studied as part of the service planning exercise. e. VRE is studying the addition of mid-day and weekend on the Manassas Line. This should be easier to maintain on the Manassas Line than on the Fredericksburg Line because most of that corridor is not critical to NS operations (except the B-Line segment). CSX operations will also have to be considered for trains going all the way to DC, however. Operating costs and railroad operating agreements are the biggest challenges for providing this additional service. I-66 traffic is getting worse on weekends, so additional VRE service could provide value. f. VRE has some reverse commute revenue trains that make limited stops along the Manassas Line because potential conflicts with peak direction trains make it difficult to maintain a dependable schedule. VRE also operates several reverse commute nonrevenue trains; the inability to maintain a dependable schedule precludes operating them in revenue service. Maintaining a dependable schedule is the biggest challenge to successful reverse commute service. g. The study is considering Prince William County s plans and projections to understand the future demand for jobs and development patterns along the corridor. For example, at Innovation Park at GMU, the distance between the B Line and the planned Innovation 3

Town Center will impact the ability of riders to walk to destinations in that area. A bus shuttle service may be a viable alternative for the last mile. h. Prince William County has noted the potential value of Transit Oriented Development (TOD), mixed use development, co-located parking and structured parking at future stations. This type of development could significantly increase the economic value of VRE stations in Prince William and Haymarket. i. Many people buy homes in Manassas because they can walk to the station. This has led to a tremendous amount of economic development for the City. This can serve as a model for the Town of Haymarket. Ideally, VRE will become an all-day system, which will impact development patterns even more. j. The future Haymarket station sites should consider mixed-use development to give people a reason to stay and shop when you get off the train. IV. Discussion: Implementation a. VRE does not plan to phase implementation of the extension project, as it likely would not save time or costs in the long-term. There is a perceived cost savings to phasing, however in reality it would likely be more costly to phase the project. End of line stations have specific needs and phasing the extension would create a temporary end of line station, which would be difficult to plan in the context of a future VRE extension farther west. There are concerns from some about impacts to community and cultural resources in the study area, which is why a phased implementation strategy has been suggested. The potential impacts include existing residential communities in Haymarket, and historic resources identified during the I-66 Study. These will all need to be addressed. b. VRE is responsible for extending the track, if needed. There would be an evaluation of the public benefit, but the tracks would still likely be owned and maintained by the private railroad. NS would provide access to the existing right-of-way, under an access agreement, and VRE would pay for the track construction. c. There are seven or eight at-grade crossings along the length of the extension corridor. VRE does not know if NS will request grade separation or whether the future rail and vehicular traffic conditions will warrant it. This will need to be negotiated, but NS typically does not require it. There are some planned grade separations, e.g., at Route 15, which is an opportunity for potential station access. Traffic patterns and circulation will be important to discuss as part of this study. 4

Funding a. VRE has submitted the project for HB2 evaluation. A future request to NVTA and HB 599 evaluation is anticipated. b. NVTA and DRPT are very interested in next steps, as funding partners. NVTA will issue the FY2018 Program Call for Projects next fall (2016). c. The GHX Study will develop both capital and operating cost estimates. VRE needs to make sure that it can continue to operate existing service before it commits to expanded operations. VRE is committed to maintaining high-quality service for existing customers while it also expands the system. d. DRPT s Rail Enhancement Fund is one possible source of funds for joint infrastructure projects. DRPT Rail Enhancement Fund requires performing a cost/benefit analysis to weigh the costs to the state and benefits to both passengers and freight. e. Marshall, Leesburg and Front Royal are watching this study. VRE riders from these jurisdictions would use the Haymarket station. The VRE rider origin dots will move further out if the extension is built. It will be important to demonstrate that the benefits of the project are accruing to the same people who are paying the cost of the project. f. VRE will re-examine the zone structure for fares with the extension. VRE a 55-65 percent fare recovery rate, which is very good for the industry. g. VRE is preparing a system-wide financial plan, which will be coordinated with the GHX project funding plan. VRE is developing a financial model to look at various operating scenarios, and different levels of funding required for various service options. Freight-Passenger Rail Coordination and Interoperability a. The B-Line is strategically important for NS s Crescent Corridor Initiative in the nationwide freight network, and VRE expects increased NS traffic on the segment. VRE is carefully coordinating with NS during this study process. b. If VRE wanted to implement the extension without using NS tracks, the cost would be very high. NS owns the right-of-way, maintains the tracks, manages dispatching, pays taxes, etc. When positive train control needed to be added to the railroad lines, VRE s cost was much lower than it would have been if they had owned the tracks. This is one indicator of the benefit that VRE enjoys by not owning the tracks. As a result, VRE needs a good relationship with NS and CSX (and Amtrak). c. Currently VRE renegotiates with NS every five years for use of their tracks. This is a typical arrangement for similar services across the country. To date, it has not interfered with VRE s ability to expand system investment. There is an access agreement with NS (and 5

CSX and Amtrak) and VRE pays on a per train mile basis, which is less expensive than VRE owning and maintaining the track for itself. d. NS will want two tracks, at minimum, and will likely require three tracks in the future, if the VRE service is extended. NS will own, control, use, and maintain the tracks. This is the typical approach used throughout US. The potential exists for NS to say no to a VRE extension if they need the capacity themselves, although VRE believes an agreement can be reached with NS for joint operations. VRE can inquire about an agreement longer than five years, if these improvements are made. The study team will research case studies to show that this negotiation process is typical. e. The number of train slots available to VRE is governed by its access agreement with CSX. VRE has a maximum of 20 trains per day on the Manassas Line (10 in each direction) under the current agreement, with another 18 trains per day on the Fredericksburg Line Four of those trains are currently on loan to the Commonwealth for their Amtrak Virginia service, although there are provisions for those trains to be returned for VRE use. Even with the additional tracks in the NS right-of-way, there will still be a bottleneck on CSX tracks at the Long Bridge as the trains travel toward DC until additional capacity is provided there. Action Items: Set up project briefings with NVTA, NVTC, PRTC, and City of Manassas. 6