Communal Sewage Inspection Report

Similar documents
Combined Sewer Overflows July 2012-December 2013

This document can be made available in other accessible formats as soon as practicable and upon request. Staff Report. Infrastructure & Public Works

CITY OF LONDON ENVIRONMENTAL & ENGINEERING SERVICES DEPARTMENT WASTEWATER TREATMENT OPERATIONS GREENWAY POLLUTION CONTROL CENTRE 2013 ANNUAL REPORT

ISO Monitoring and Measurement Nonconformance and Corrective and Preventative Action

Solid Non-Hazardous Waste Disposal Site Inspection Report

RE: Year-End Report Woodstock Wastewater Treatment Plant (WWTP), 2012

Solid Non-Hazardous Waste Disposal Site Inspection Report

JEDDAH INDUSTRIAL CITY

I/I Analysis & Water Balance Modelling. Presented by Paul Edwards

Permit To Take Water Inspection Report

Waste Discharge Permit Application. for. Commercial, Industrial and Institutional Discharges

WASTEWATER DEPARTMENT CITY OF MANNHEIM

International Joint Commission Water & Wastewater Treatment Best Management Practices Forum Monday, March 26, 2012 Wayne State University, Detroit MI

Final Report DMR-QA 36. NPDES Permit: IL DMR-QA Study. Open Date: 03/18/16. Close Date: 07/01/16. Report Issued Date: 07/29/16

Water Quality Permitting Program Monitoring Matrix 1,2,3

CANADA BRITISH COLUMBIA WATER QUALITY MONITORING AGREEMENT

Biosolids Monthly Report

Case Study. BiOWiSH Aqua has Positive Long-Term Effects. Biological Help for the Human Race

CANADA BRITISH COLUMBIA WATER QUALITY MONITORING AGREEMENT

Lagoons Operation and Management in New Brunswick

CERTIFICATE OF ANALYSIS REVISED REPORT

Milwaukee Metropolitan Sewerage District Conveyance and Treatment System. MACRO made available by

CITY OF OXFORD WASTEWATER TREATMENT FACILITY ANNUAL PERFORMANCE REPORT FOR THE CALENDAR YEAR OF 2012

CANADA BRITISH COLUMBIA WATER QUALITY MONITORING AGREEMENT

CANADA BRITISH COLUMBIA WATER QUALITY MONITORING AGREEMENT

Water and Waste Water Management in Yangon, Myanmar

Environmental Protection Licence 2688

Environment Protection Licence

Recycling And The New Virginia Stormwater Management Program Regulations VIRGINIA RECYCLING ASSOCIATION 2014 ANNUAL CONFERENCE

The Don River and Central Waterfront are among the most degraded waterways in the City of Toronto.

BASELINE MONITORING REPORT (BMR)

NORTH TORONTO WASTEWATER TREATMENT PLANT 2016 Annual Report

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W

Dealing with Unexpected Wastewater Treatment Plant Disruptions. February 16, 2017

Operations Report. September 10, 2015

SILLIKER, Inc. Southern California Laboratory 6360 Gateway Drive, Cypress, CA Tel. 209/ Fax. 714/

Public Notice. Issuance of Industrial Waste Discharge Permit

AGL UPSTREAM INVESTMENTS PTY LTD GLOUCESTER GAS PROJECT

Inventaire Report Information Report ID: Report Year: 2008 Programs Included:npri. Facility Information.

MUNICIPAL WATER POLLUTION PREVENTION (MWPP) ANNUAL REPORT

Industrial Sewage Inspection Report

Warm Mineral Springs Sampling by Sarasota County

Decentralised Wastewater Management. A sustainable strategy for wastewater management

FORM 26R CHEMICAL ANALYSIS OF RESIDUAL WASTE ANNUAL REPORT BY THE GENERATOR INSTRUCTIONS GENERAL INFORMATION

ENVIRONMENTAL ASSESSMENT

Application for Renewal Industrial Wastewater Discharge Permit

2011 ANNUAL WATER REPORT

INCHEM Tokyo Current Status and Implementation Approach for Industrial Zones Wastewater Management In Yangon Region

The Solution to Pollution is Dilution

Climate Change & Urbanization Have Changed River Flows in Ontario

Pilot Study Report. Z-92 Uranium Treatment Process

NPDES WASTEWATER DISCHARGE PERMIT EVALUATION

Land Application of Biosolids Rules, Regulations and Benefits EPA regulations, under Title 40 Code of Federal Regulations Part 503 (40 CFR 503) -

AUTHORIZATION TO DISCHARGE UNDER THE NATIONAL POLLUTANT DISCHARGE ELIMINATION SYSTEM

CERTIFICATE OF ANALYSIS

Contaminated Extraction Pit treated to allow dewatering for continuation of mining works

INDUSTRIAL USER WASTEWATER DISCHARGE PERMIT APPLICATION FORM

GENERAL PERMIT WMGR098 BENEFICIAL USE OF WASTE FOUNDRY SAND AND SAND SYSTEM DUSTS

STATE ENVIRONMENTAL LABORATORY SERVICES DIVISION

. ARUSHA URBAN WATER SUPPLY AND SANITATION AUTHORITY (AUWSA)

Streamlining I/I Repairs in Berlin Charter Township

ANNUAL WATER QUALITY MONITORING REPORT OLALLA WATER SYSTEM

Wastewater Treatment Plant Facility Plan Update City Project # City of Liberty, Missouri May 6, 2013

Minnesota Pollution Control Agency

Fremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment

Appendix C1: Batch Kinetics Tests

PHASE 1 OF THE CONSENT DECREE/ WET WEATHER IMPROVEMENT PROGRAM ACCOMPLISHMENTS THROUGH 2017

Evaluation of Pollutants in Wastewater Generated by Mobile Car Washing Operations

TOM COOKE MEMORIAL WASTEWATER TREATMENT PLANT

Alexandria Sewage Lagoon Treatment Facility Municipal Class C Environmental Assessment Public Information Centre #2 Welcome!

BLACK STURGEON LAKES WATER QUALITY MONITORING

National Pollutant Discharge Elimination System (NPDES) Permit Program F A C T S H E E T

Kirill Ukhanov, GE Water & Process Technologies, Russia, describes how advanced membrane technology is helping a Russian refinery to meet stringent

Stormwater and LEED. Vancouver LEED User s Group May 27, Craig Kipkie, M.Sc., P.Eng, LEED AP

Facilities Plan. Technical Memorandum No. TM-WW-7 Hydraulic Analysis and Effluent Pump Station

PUBLIC WATER SYSTEM ANNUAL REPORT

CULTUS LAKE SEWER UPGRADE

City of Clinton: Wastewater Systems Annual Performance Report

4.0 SAN GABRIEL RIVER WATERSHED MANAGEMENT AREA

NPDES COMPLIANCE MONITORING STRATEGY AND ANNUAL COMPLIANCE INSPECTION PLAN OCTOBER 1, SEPTEMBER 30, 2018

Lecture 9A: Drainage Basins

2010 Drinking Water Quality Annual Report

Clyde Mine Discharge/Tenmile Creek Water Quality Final Report

The OWASA UNC Reclaimed Water System: A Progress Review

Public Notice. Issuance of Industrial Waste Discharge Permit

Treated Municipal Wastewater Irrigation Guidelines EPB 235

CONSULTING SERVICES : SEWERAGE SYSTEM IMPROVEMENT FOR GREATER TIRANA. 6/8/2012 Address: Rruga Dora D Istria 2/1, Apt 4/13, Tirane, Albania

WASTEWATER TREATMENT. Nelson Environmental Inc. Nelson Environmental Inc.

Final Report. Lisheen Mine Discharge Limit for Phosphorous in Terms of Irish and EU Legislation. November 2007 PROJECT NO.

Sanitary Sewer Systems. Sewage Collection System. Types of Sewage 10/12/2016. General Overview

Development of a Stormwater Management Plan for Phase II Small MS4s Insight and Innovation

Proposed Wastewater Treatment Facility Equipment Repair and Replacement Project

Copies: Mark Hildebrand (NCA) ARCADIS Project No.: April 10, Task A 3100

314 CMR: DIVISION OF WATER POLLUTION CONTROL

Tunnel Works. How we got here - Fort Wayne s Consent Decree. Tunnel Works Program Frequently Asked Questions

CHEMICAL FREE PHOSPHOROUS ELIMINSTION P-UPTAKE PROCESS

INSTRUCTIONS TO FILL OUT WASTEWATER DISCHARGE PERMIT APPLICATION BASELINE MONITORING REPORT

CITY OF POWELL RIVER LIQUID WASTE MANAGEMENT PLAN - STAGE 3

The Metropolitan District. Stormwater & I/I Reduction Presentation March 16, 2017

The Myakka River. Presented to the Myakka River Management Coordinating Council January 9, 2009

Transcription:

Ministry of the Environment Ministère de l Environnement Communal Sewage Inspection Report Client: Inspection Site Address: City of Ottawa, Business/Facility Name: Robert O. Pickard Environmental Centre Mailing Address: 800 Green Creek Dr, Gloucester, Ontario, Canada, K1J 1A6 Physical Address: 800 Green Creek Dr, Ottawa, City, Ontario, Canada, K1J 1A6 Telephone: (613)580-2424, Extension: 22814, FAX: (613)745-9197, email: lawrence.gangur@ottawa.ca Client #: 5391-5TESF7, Client Type: Municipal Government, NAICS: 221320, 541380 Robert O. Pickard Environmental Centre Address: 800 Green Creek Dr, Ottawa, City, K1J 1A6 District Office: Ottawa GeoReference: Map Datum: Unknown, Zone: 18, Accuracy Estimate: 10-30 metres eg. Medium Quality GPS, Method: Map, UTM Easting: 453580, UTM Northing: 5034554,, LIO GeoReference: Zone: 18, UTM Easting: 453673.62, UTM Northing: 5033573.0, Latitude: 45.454147, Longitude: -75.59248 Sewage Works Number: 120000729 Contact Name: Gary Robidoux Title: Process Superintendent Contact Telephone: (613)580-2424 ext23303 Contact Fax: Last Inspection Date: 2011/03/09 Inspection Start Date: 2012/03/15 Inspection Finish Date: 2012/03/15 Region: Eastern 1.0 INTRODUCTION For Clarity within this report it should be noted that the Ministry of the Environment has restructured their approvals process. As of October 31st, 2011, all Certificates of Approval will be referred to as Environmental Compliance Approvals (ECA). An inspection of the Robert O. Pickard Environmental Centre was conducted to assess compliance with applicable Ministry of the Environment legislative requirements, as well as conformance with current Ministry guidelines and policies for operations during 2011. The inspection also assessed the collection of wastewater and conveyance to the sewage treatment plant. The inspection included a review of historical information contained in the Ministry files; a review of available operating data for 2011; a detailed assessment of compliance with the terms and conditions of the ECA and conformance with MOE policies and procedures; a tour of the treatment system; and a review of the audit sample results of the plant's final effluent collected on July 26th, 2011. The inspection focused on the operation and performance of the treatment plant. It was noted at the time of inspection that clarifier #8 is out of commission. Digester #4 got emptied in 2010 and is still out of commission. The intent is to get it back on line and then commence clean-out of digester #3. 1.1 AUTHORIZING AND CONTROL DOCUMENT INFORMATION Page 1

Authorizing/ Control Document Number Issue Date Effluent Limits (yes/no) Effluent Monitoring Requirements (yes/no) Effluent Reporting Requirements (yes/no) ECA (sewage) 3-0935-83-887 1988/11/01 Yes Yes Yes ECA (sewage) 2659-64TPYC 2004/12/04 Yes Yes Yes ECA (notice #1) 2659-64TPYC 2007/09/08 No No No ECA (notice #2 2659-64TPYC 2009/11/10 No No No ECA (air) 2572-4JSSQ6 2000/05/10 No No No ECA (air) 0105-6FJRV2 2005/10/19 No No No ECA (sewage) 0595-8D2SAQ 2011/02/10 Yes Yes Yes ECA (sewage) 7359-8HLNDP 2011/06/30 Yes Yes Yes The plant is currently operating under ECA #7359-8HLNDP. 2.0 INSPECTION OBSERVATIONS Sewage Treatment Plant Sewage Works Number: 120000729 Certificate of Approval Number(s) Yes No C of A Number(s): 7359-8HLNDP Plant Ownership: Munc. OCWA Other Operating Authority: Munc. OCWA Other Service Population: 720,000 Wastewater Collection System Certificate of Approval Number(s): Yes No C of A Number(s): Various Collection System Ownership: Munc. OCWA Other Operating Authority: Munc. OCWA Other 2.1 SYSTEM DESCRIPTION Type Of Plant Primary: Yes No Secondary: Yes No Advanced: Yes No Biological Treatment: Yes No Conventional AS Contact Stablization Extended Air Rotating Biological Contactor Lagoon(s): Yes No Other: Yes No Describe: Communal Septic Constructed Wetland Effluent Discharge Frequency: Seasonal: Continuous: Does the Plant Practice Phosphorous Removal? Yes No Effluent Disposal Method: Surface Water Surface Land Disposal If disposal is to surface water, name of immediate receiving stream: Ottawa River 2.2 EFFLUENT QUALITY ASSESSMENT Snowfluent Other Annual: No Direct Discharge: Subsurface Page 2

Parameter Year 1 Year 2 Year 3 Limits 2009 2010 2011 BOD5 (mg/l) 7.79 8.48 8.5 25 Suspended Solids (mg/l) 12.33 11.03 11.61 25 Total Phosphorus (mg/l) 0.84 0.76 0.49 1.0 Limits are based on: Certificate of Approval PO Order Does the facility comply with its limits: Yes Director's Order Guidelines Effluent Objectives are listed under condition 6 of the ECA and effluent limits are listed under condition 7. No exceedences were reported in 2011. 300 R.O.P.E.C BOD 5-2011 250 200 mg/l 150 100 50 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec BOD In BOD Out BOD Limit Page 3

R.O.P.E.C. Suspended Solids - 2011 400 350 300 250 mg/l 200 150 100 50 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec SS In SS Out SS Limit R.O.P.E.C. Total Phosphorus - 2011 7 6 5 mg/l 4 3 2 1 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec TP In TP Out TP Objective & Limit Page 4

Raw BOD and Suspended Solids Trends 400 350 300 1000 m3/day 250 200 150 100 50 0 Jan-05 Apr-05 Jul-05 Oct-05 Jan-06 Apr-06 Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08 Oct-08 Jan-09 Apr-09 Jul-09 Oct-09 Jan-10 Apr-10 Jul-10 Oct-10 Jan-11 Apr-11 Jul-11 Oct-11 Raw BOD Raw S.S. Linear (Raw S.S.) Linear (Raw BOD) 2.3 CAPACITY ASSESSMENT Flows shown below are for the last three calendar years. Identify the year, eg., 1999 Item Year 1 2009 Year 2 2010 Year 3 2011 Average daily flow (m 3 /day) 430040.00 412940.00 388890.00 Maximum daily flow (m 3 /day) 1001000.00 905000.00 1055000.00 Capacity Design (m 3 /day) 545000.00 545000.00 545000.00 % of capacity, based on average daily flow 78.91 75.77 71.36 Flow Trends 1400 1200 1000 1000 m3/day 800 600 400 200 0 Jan-05 Apr-05 Jul-05 Oct-05 Jan-06 Apr-06 Jul-06 Oct-06 Jan-07 Apr-07 Jul-07 Oct-07 Jan-08 Apr-08 Jul-08 Oct-08 Jan-09 Apr-09 Jul-09 Oct-09 Jan-10 Apr-10 Jul-10 Oct-10 Jan-11 Apr-11 Jul-11 Oct-11 Average Daily Flow Maximum Daily Flow Linear (Average Daily Flow) Linear (Maximum Daily Flow) Page 5

Robert O. Picard Environmental Centre Flows - 2011 1600 1400 1200 1000 m 3 /day 1000 800 600 400 200 0 Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Maximum Daily Flow Design Capacity (ADF) Average Daily Flow Peak Flow Rate 2.4 EFFLUENT SAMPLING REQUIREMENTS Sampling requirements are based on : Certificate of Approval Does the plant meet the sampling requirements? Yes 2.5 EFFLUENT REPORTING REQUIREMENTS Reporting Requirements are based on :Certificate of Approval Does the plant meet the effluent reporting requirement? Yes 2.6 MINISTRY SAMPLING AT TIME OF INSPECTION Were Ministry samples collected at the time of inspection Yes Grab sample- Effluent - Phys/Chem, Grab sample - Effluent - Metals, Sample Locations and Analyses: Grab sample - Effluent - Bacteriological Ministry staff collected audit sample of the final effluent on August 8th, 2011 (see results below). Additional Ministry audit samples were not collected at the time of the inspection. Parameter Name Value Units Qual Mercury 0.02 ug/l <=W Aluminium 0.045 mg/l <T Barium 0.020 mg/l Beryllium 0.001 mg/l <=W Cadmium 0.001 mg/l <=W Calcium 39.5 mg/l Cobalt 0.001 mg/l <=W Chromium 0.002 mg/l <=W Page 6

Copper 0.003 mg/l <=T Iron 0.179 mg/l Lead 0.005 mg/l <=W Magnesium 10.6 mg/l Manganese 0.059 mg/l Molybdenum 0.005 mg/l <=W Nickel 0.01 mg/l <=W Potassium 13.6 mg/l Silver 0.005 mg/l <=W Sodium 106 mg/l Strontium 0.631 mg/l Titanium 0.001 mg/l <=W Vanadium 0.001 mg/l <=W Zinc 0.022 mg/l Hardness 142 mg/l Oxygen demand; CBOD 2.6 mg/l Solids; suspended 5.0 mg/l Arsenic 0.0005 mg/l <=W Selenium 0.0005 mg/l <=W Nitrogen; nitrite 0.829 mg/l Nitrogen; nitrate+nitrite 0.87 mg/l Nitrogen; ammonia+ammonium 26.3 mg/l Phosphorus; phosphate 0.07 mg/l <T Nitrogen; total Kjeldahl 28.7 mg/l Phosphorus; total 0.20 mg/l Escherichia coli 36 c/100ml <=T A measurable trace amount: interpret with caution <=W No measurable response (zero) Sample results did not indicate any exceedences with effluent limits in the ECA. 2.7 DISINFECTION a) Method of disinfection: Chlorination b) Disinfection Period: Seasonal c) Comment on the seasonal disinfection period for Disinfection required from May 16th to November 15 each year: d) Disinfection Required By: Certificate of Approval e) Residual monitoring technique: Autoanalyser f) Was there a measurable chlorine residual in the final effluent after contact: Not obtained The plant is currently disinfecting seasonally. They have approval, under the current ECA, for a dechlorination system. The City is currently adapting the chlorination contact channels to accommodate the dechlorination system. It is expected that the dechlorination system will be on line some time in June 2012. Once the system in on line, the plant will be chlorinating on a continuous basis. 2.8 PLANT CLASSIFICATION & OPERATOR CERTIFICATION a) Plant classification: i) Facility Level: Level IV ii) Certificate Number: 128 iii) Date of Issue: 1990/02/22 b) Plant operators have the appropriate level of certification for this plant: Yes No Page 7

2.9 FLOW MEASUREMENT a) Flows are being metered at: Raw Sewage, Final effluent, Bypass b) Date of last calibration of effluent flow meter: 2011/09/01 Calibration is done in-house on an annual basis. Occurs between September and November. 2.10 BYPASSES, AND/OR OVERFLOWS Plant Collection System Are bypasses and overflows routinely reported? Yes No Yes No Are bypasses and overflows routinely monitored? Yes No Yes No Are bypasses and overflows routinely sampled? Yes No Yes No PLANT INFORMATION: Plant Bypass Plant Overflow Item Year 1 Year 2 Year 3 Year 1 Year 2 Year 3 2009 2010 2011 2009 2010 2011 Total number of events? 0 0 0 0 0 0 Total duration of event(s)? (Hour(s)) Of the total number of events, how many are dry-weather events? Total quantity with no treatment? (1000 m 3 ) Total quantity with only disinfection? (1000 m 3 ) Total quantity with primary treatment? (1000 m 3 ) Total quantity with primary treatment and disinfection? (1000 m 3 ) Total quantity with other treatment? (1000 m 3 ) Total quantity with other treatment and disinfection? (1000 m 3 ) What is the most common reason for event(s)? What is the name of the receiving water? Ottawa River Ottawa River Ottawa River Ottawa River Name the most important type of sensitive receptor? beach beach beach beach What is the approximate distance to the sensitive receptor? (km) 8 8 8 8 COLLECTION SYSTEM INFORMATION: (Satellite(s), Lift Station(s) and Regulator(s)) Lift Station Overflow Other Location Overflow Item Year 1 Year 2 Year 3 Year 1 Year 2 Year 3 2009 2010 2011 2009 2010 2011 Total number of events? 3 0 4 381 61 30 Total duration of event(s)? (Hour(s)) 14 35 1123 1000 0 Of the total number of events, how many are dry-weather 0 0 0 0 0 events? Total quantity with no treatment? (1000 m 3 ) 24.300 16.795 647.195 891.250 387.288 Total quantity with only disinfection? (1000 m 3 ) 0.000 0.000 0.000 0.000 0.000 Page 8

Total quantity with other treatment? (1000 m 3 ) Are any overflow(s) at combined sewer locations? (Yes/No) What is the most common reason for event(s)? What is the name of the receiving water? Name the most important type of sensitive receptor? What is the approximate distance to the sensitive receptor? (km) 0.000 0.000 0.000 0.000 0.000 No No Yes Yes Yes weather weather weather weather weather Ottawa River Ottawa River Ottawa River Ottawa River Ottawa River Ottawa River beach beach beach beach beach beach 8 8 8 8 8 8 Comments: There were no overflows reported at the plant. There were three reported overflows at pumping stations noted in the above table under lift station overflow. April 10th - overflow at the Valley pumping station June 24th - overflow at the Park pumping Station June 24th - overflow at the Valley Drive pumping station All three overflows were attributed to wet weather flows. The City has 5 combined sewer regulators that can overflow into the Ottawa River, these combined sewer overflows are noted in the above table under Other Location Overflow. The 2011 Combined Sewage Report has not been released yet, the quantities listed in the above table are obtained by reports given at the time of the events to the Ministry's Spills Action Centre (SAC). City staff have not been reporting duration of by-pass events, only flow amounts making it impossible to estimate the total duration of the events from the SAC reports. It is recommended that when City staff report CSO's to SAC they also indicate the duration of the event. Since October 2011, real time flow monitoring equipment and automatic samplers have been installed and operational in the 5 regulators. This will enable the City to more accurately determine CSO volumes and effluent quality. The 2010 Combined Sewage Report has the following statements: - Total combined sewer overflow volume for the 2010 Control Period is estimated to be 443,000m3. - The August 15-16 event caused approximately 28% of the total CSO volume for the Control Period. Just under 44 mm rain was recorded by Environment Canada at their Experimental Farm gauge on August 15; however, this followed a non-trivial 16 mm of rain on the previous day, therefore the antecedent conditions to the large August 15 event would have been considered "wet", which leads to higher runoff and infiltration and hence more overflow. - In decreasing order of CSO volumes, the 6 largest overflow sites were; Rideau Canal Interceptor Overflow Booth Street Sewer Overflow (to Tailrace) Rideau River Collector Overflow (Keefer Regulator) at John Street Manor Park Overflow (Sandridge Sewer) Bolton Street Overflow (Cathcart) Cave Creek Collector Overflow (to Tailrace) - Taken together, the above 6 sites generated approximately 94% of the system's total CSO. - The City has programs and projects underway that will significantly reduce overflows from these sites. - Major regulator upgrades have been implemented at five of the six sites listed above, namely the Booth Street Sewer Regulator, Rideau Canal Interceptor Regulator, Keefer Regulator, Cave Creek Collector Regulator and Cathcart Regulator. Real Time Control capability is a feature at the first three of these Page 9

In-Line storage in the West Nepean Collector has also been implement as part of the overall upgrade program. Together, these upgrades are expected to allow the City to reduce CSO volumes for an average year by roughly two thirds. Permanent, real time flow monitoring equipment is now in place these five upgraded regulators, although instrumentation challenges are still being resolved. - For the Manor Park Overflow site (i.e. the 4th largest site), construction of a new storage facility was recently completed, and separation in the area continues. It is expected that these improvements will virtually eliminate CSOs from this site, for all but very large rain events. - Based on simulations and monitoring, overflows per site ranges from 0 to 53, with an average of 17. - For the 2010 Control Period, the total duration of overflow per site ranged from 0 hours to 219 hours, with an average of 42 hours. - For the 2010 Control Period; The total number of individual CSO event, as defined by MOE Polity F-5-5, was 69. Wet Weather Flow Capture rate, per F-5-5 definition, was 95%; this is significantly better then F-5-5's target of 90%. Total flow capture rate for the entire system was 99.5% 2.11 SLUDGE (BIOSOLIDS) MANAGEMENT Sludge Stabilization: Sludge Storage: Total available storage: Volume Retention Time Certified waste hauler Certificate numbers of haulers are: Method of Disposal/Utilization: Certified waste disposal facility Certificate number(s) of facilities are: Anaerobic Holding Tank 800 m3/day 3 days Yes Third High Farms, H480300 Agricultural Yes various Most of the bioslids are land applied, other uses include compost, landfill and daily land cover. 2.12 WASTEWATER COLLECTION SYSTEMS 1. Does this plant receive sewage from a Combined Sewer Collection System (sanitary sewage, roof leaders, foundation drains, catch basins and/or storm water conveyed within a single pipe)? If yes, approximately, what percentage of the sewer collection system is combined? 2. How are bypasses, overflows and/or combined sewers being minimized or eliminated? Yes > 25% 6-10 % No 11-25 % 0-5 % a) Pollution Prevention and Control Plan (As described in Procedure F-5-5) Yes No Developing i. Other Plan Yes No Developing b) Characterization Study? Yes No Developing c) Implementation Plan? Yes No Developing Comments: Page 10

All 5 regulators are now on Real Time control and linked to the SCADA system. There are two groups of operators at the plant, one group looks after the plant while the other looks after the collection system. A pollution Prevention and Control Plan was presented to the Ministry in November 2008. A floatables study was presented in June 2009. City council has approved a five-year, $251.64 million plan to fund an underground storage system that's meant to nearly eliminate discharges of raw sewage into the Ottawa River. The following key projects are ongoing: - CSO Storage tunnel - Pollution Prevention and Control Plan - Sewer Separation - Wet Weather Infrastructure Management Plan - Outfall Renewal EA 3.0 REVIEW OF PREVIOUS NON-COMPLIANCE ISSUES No previous non compliance issues 4.0 SUMMARY OF INSPECTION FINDINGS (HEALTH/ENVIRONMENTAL IMPACT) Was there any indication of a known or anticipated human health impact during the inspection and/or review of relevant material, related to this Ministry s mandate? No Specifics: Was there any indication of a known or anticipated environmental impact during the inspection and/or review of relevant material? No Specifics: Was there any indication of a known or suspected violation of a legal requirement during the inspection and/or review of relevant material which could cause a human health impact or environmental impairment? No Specifics: Was there any indication of a potential for environmental impairment during the inspection and/or the review of relevant material? No Specifics: Was there any indication of non-conformance or minor administrative non-compliance? No Specifics: Page 11

5.0 ACTION(S) REQUIRED 6.0 OTHER INSPECTION FINDINGS 7.0 INCIDENT REPORT Not Applicable 8.0 ATTACHMENTS PREPARED BY: Environmental Officer: Name: Tracy Hart Ottawa District Office District Office: Date: 2012/03/28 Signature REVIEWED BY: District Supervisor: Name: Tara MacDonald District Office: Ottawa District Office Date: 2012/03/29 Signature: File Storage Number: SI OC GL GR 430 Note: "This inspection report does not in any way suggest that there is or has been compliance with applicable legislation and regulations as they may apply to this facility. It is, and remains, the responsibility of the owner and/or the operating authority to ensure compliance with all applicable legislative and regulatory requirements" Page 12