Section 704. STEEL SHEET PILING AND COFFERDAMS

Similar documents
Temporary Watercourse Crossing: Culverts

JOB BB0113 SHELL LAKE STR. & APPRS. (S) MARCH 10, 2015 LETTING QUESTIONS PREVIOUSLY ASKED UNDER JOB BB0106.

ODOT Design & Construction Requirements for MSE Walls

Temporary Structures. Cofferdams TOKYO INSTITUTE OF TECHNOLOGY ATCE-II ADVANCED TOPICS IN CIVIL ENGINEERING DEPARTMENT OF CIVIL ENGINEERING

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

C. Foundation stabilization for pipe and utility structures.

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

2.1 Backfill - General

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

Construction Planning, Equipment, and Methods PILES AND PILE-DRIVING EQUIPMENT

***************************************************************************************************************

SECTION TRENCHING & BACKFILLING

LANDSCAPE RETAINING WALLS

PIANC UK Seminar Design Developments and Specification for Steel. Duncan Nicholson Arup Fellow 9/3/17 ICE London

SECTION EXCAVATION AND BACKFILL FOR UTILITIES AND STRUCTURES

Temporary Shoring. Specifications, Applications, & Best Practices. Stephen M. (Matt) Revell, P.E. Assistant Geotechnical Engineer

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Table of Contents for Guide Specifications

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

901 STORMWATER POLLUTION MANAGEMENT SECTION 901 STORMWATER POLLUTION MANAGEMENT

Drill Shaft Contractor and Equipment Arrive On-Site CBT Script

Design and Installation Guidelines for Retaining Walls. 1 P age. Geo Products, LLC 8615 Golden Spike Lane Houston, TX Phone:

SECTION 820 PUMP STATION DEMOLITION AND SITE RESTORATION

Bridge Manual - Part I - June CHAPTER 5 SPECIAL PROVISIONS AND ESTIMATE

Bonner Bridge Replacement Update:

901 - TEMPORARY EROSION AND POLLUTION CONTROL SECTION 901 TEMPORARY EROSION AND POLLUTION CONTROL

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers

October 1, Re: Contract ID A Plans, Proposal, EBS, Questions & Answers October 8, 2013 Letting

Storm Drain Inlet Protection for Construction Sites (1060)

CHANGES IN 2006 SPECIFICATIONS SECTION 804 DRIVEN PILES SECTION 814 DRILLED SHAFTS

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Wall Modular Block Mechanically Stabilized Earth, Item S.

CONSTRUCTION SPECIFICATION FOR TRENCHING, BACKFILLING, AND COMPACTING

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

RESIDENTIAL CONSTRUCTION New Dwellings and Additions

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong

ENGINEERING DIRECTIVE

SPECIFICATION FOR PIPE CULVERT CONSTRUCTION

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0

CONSTRUCTION METHOD FOR CCSP AND REVETMENT

Item Name Description Unit of Measure Mobilization Per WSDOT Lump Sum

Town of Essex, Vermont January, 2017 Standard Specifications For Construction CHAPTER 3 EROSION AND SEDIMENT CONTROL

Selection of Proprietary Shoring Equipment

Section 906. STRUCTURAL STEEL

CM 420. Lesson 4: Cofferdams. describe cofferdams and when they are used on construction projects;

Design of Rigid Pavements

INDEX FOR SPECIFICATIONS FOR JACKING CULVERTS THROUGH EMBANKMENTS SCOPE... 2

Table of Contents. Section 11,010 - Construction Survey Section Includes Description of Work Submittals 1. 1.

SPECIFICATIONS FOR BRIDGE CONSTRUCTION SECTION 2 BACKFILL. 2.1 General...2-1

CITY OF FARGO SPECIFICATIONS CONCRETE SIDEWALKS AND DRIVEWAYS

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

1.364 ADVANCED GEOTECHNICAL ENGINEERING HOMEWORK No. 5

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

GEOSYTHETIC SLOPE SPEC-V0704rev.doc STANDARD SPECIAL PROVISION FOR GEOSYNTHETIC REINFORCED SLOPE CONSTRUCTION

STATE OF OHIO DEPARTMENT OF TRANSPORTATION SUPPLEMENTAL SPECIFICATION 863 REINFORCED SOIL SLOPES. October 19, 2012

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

10:00 AM, Wednesday, April 8, 2015

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

Modular Sediment Barriers (Instream)

OKLAHOMA DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION FOR DRILLED SHAFT FOUNDATIONS

CONTRACTOR AND EQUIPMENT ARRIVE ON-SITE

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

TEMPORARY SEDIMENT TRAP CODE

Storm Drain Inlet Protection

Open Trench Construction Plan Review The open trench construction plan review involves the following general investigative elements:

KIEWIT FOUNDATIONS GROUP

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

Ironton Russell Bridge Project

CIVIL BREADTH Exam Specifications

Table of Contents. July

ENGINEERED SOLUTIONS. Metric Sheeting. Tomorrow s Environments Engineered

A. This Section includes subdrainage systems for foundations and underslab areas. A. Product Data: For each type of drainage panel indicated.

BASE CONSTRUCTION MATERIALS A Aggregate

SECTION CAST-IN-PLACE CONCRETE

MARINE SPECIALTY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION FOR COMPUTER BASED TESTING Revised March 2012

SPECIFICATION FOR THE ERECTION AND MAINTENANCE OF TRAFFIC SIGNS, CHEVRONS, MARKERS AND SIGHT RAILS

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA

Features. A Wide Selection of Shapes and Types. Superb Drivability and Water tightness

EXCAVATION AND TRENCHING SAFETY REQUIREMENTS

SECTION PILING

MOA Project # Golden View Drive Intersection & Safety Upgrades

UNDERPINNING A CRANE FOUNDATION

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

4.8. Subsurface Infiltration

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation

Project Address: Name of Person Completing Form:

SECTION A1 EXCAVATION AND BACKFILL GENERAL

Scott Neubauer. Bridge Maintenance and Inspection Engineer Office of Bridges and Structures Iowa DOT

SPECIAL SPECIFICATION 4385 Railroad Bridge Construction

TGO3 - Buttress, Shoring, Buttress - Issued for Bid

BIDS WILL BE CONSIDERED NON-RESPONSIVE WITHOUT THE REQUIRED SIGNATURE ACKNOWLEDGING THE FOLLOWING:

LADOTD Construction Specifications: Parts II, III & IV MARK MORVANT, P.E. ASSOCIATE DIRECTOR, RESEARCH

DUKE UNIVERSITY DESIGN GUIDELINES

SHOTCRETE APPLICATION MANUAL

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following:

Transcription:

Section 704. STEEL SHEET PILING AND COFFERDAMS 704.03 704.01. Description. This work consists of the following: A. Providing and driving permanent steel sheet piling, B. Designing, providing, installing, maintaining, and removing temporary steel sheet piling, or cutting off temporary steel sheet piling left in place, including bracing, tie backs, walers, and related material, and C. Designing, installing, maintaining, and removing cofferdams or cutting off cofferdams left in place, including sheet piling, bracing, tie backs, walers, and related material. 704.02. Materials. Provide material in accordance with the following: Geosynthetics... 910 Steel sheet piling... 906 Provide new or used continuous interlock-type steel sheet piling including connections and corner pieces. Used steel sheet piling must be in good condition and its use must be approved by the Provide steel sheet piling with a nominal section modulus of at least 18.1 cubic inches per foot of wall, for both temporary steel sheet piling and cofferdams, when installed adjacent to traffic or when supporting traffic loads. Provide the permanent steel sheet piling section modulus shown on the plans. The Contractor may provide cold-rolled sheeting for applications specified in this section. 704.03. Construction. A. Design and Installation. Design steel sheet piling and cofferdams in accordance with the AASHTO Standard Specifications for Highway Bridges, 17th edition, and the contract. Include the following information, as applicable, on the design documents: 1. Sheet piling section modulus and, embedment depth; 2. Design criteria for bracing and bracing sections, connection and tieback details, and deadman sections; 3. Assumptions and references for the design calculations; 4. Any temporary loads for construction equipment, construction materials, traffic loading and any unbalanced hydrostatic pressure loading; and 5. Profile views and plan views with cross sections. 361

704.03 Document each stage of the construction on the working drawings. Submit an electronic file copy and one paper copy of the proposed design, supporting calculations and working drawings for steel sheet piling and/or cofferdams to the Engineer for review not less than 10 working days before beginning work, in accordance with subsection 104.02. If required by subsection 104.02, have working drawings sealed by Contractor s designer. Begin work only after the Engineer approves the sheet pile design. The Engineer will not make allowance for increases in cost or lost time associated with resubmittals of the design due to comments or questions from the Department. Construct steel sheet piling and cofferdams to the cutoff elevations and coordinate with the construction staging required by the contract. Provide a copy of any steel sheet piling or cofferdam design and working drawings at the job site as required by MIOSHA Construction Safety Standard. B. Driving Steel Sheet Piling. Drive, brace, and cut off steel sheet piling in accordance with the Contractor s design for temporary steel sheet piling and cofferdams and the contract. The Contractor may use drop hammers. Unless otherwise shown on the plans, the Contractor may use vibratory hammers. Cut off temporary steel sheet piling, left in place, to the elevation shown on the plans. Do not pull up or redrive temporary steel sheet piling, left in place, to match the cut off elevation required, unless otherwise shown on the plans or approved by the After casting adjoining concrete, do not drive steel sheet pilings to a greater depth. To lower the top of permanent sheet piling after placing adjoining concrete, remove by cutting. C. Cofferdams. Construct partial or total enclosure cofferdams to allow construction of substructures, above the seal or subfooting, in the dry without damaging the work. The Engineer may approve alternate methods, in lieu of cofferdams. The Engineer will consider approval after receiving applicable MDNRE permits for the alternate method. Construct cofferdams with interior clearance for constructing forms, and inspecting form exteriors, and to allow pumping outside the forms. Construct cofferdams to protect the work from damage from high water and prevent damage to the foundation by erosion. Align or enlarge cofferdams or cribs that tilt or move laterally during the process of sinking, to provide required clearance. 362

Do not brace cofferdams to substructure forms. Bracing which extends into or remains in the finished concrete is not permitted. If dewatering, pump from a sump located outside the forms. Do not dewater until the tremie seal obtains the minimum strength in accordance with subsection 706.03.H.3. If the plans do not call for a tremie seal, discharge water pumped from a cofferdam into a geotextile filter bag. If the plans call for a tremie seal, maintain the water level inside the cofferdam equal to the water level outside the cofferdam, until the tremie seal is placed, unless otherwise approved by the After placing tremie seal and initially dewatering into a geotextile filter bag, the Contractor may pump silt-free and sediment-free water directly into the watercourse, if approved by the Remove cofferdams without disturbing or marring finished concrete. Cut off the cofferdams, left in place, at the elevation shown on the plans. Do not pull up or redrive cofferdam sheeting to match the cut off elevation, unless otherwise shown on the plans or approved by the 704.04. Measurement and Payment. Pay Item Pay Unit Steel Sheet Piling, Permanent... Square Foot Steel Sheet Piling, Temp... Square Foot Steel Sheet Piling, Temp, Left in Place... Square Foot Cofferdams (Structure No.)... Lump Sum Cofferdams, Left in Place (Structure No.)... Lump Sum A. Steel Sheet Piling. 1. Steel Sheet Piling Permanent. The Engineer will calculate quantities of Steel Sheet Piling, Permanent based on the lines and lengths below cutoff, shown on the plans or authorized by the 2. Steel Sheet Piling, Temp and Steel Sheet Piling, Temp, Left in Place. The Engineer will calculate quantities of Steel Sheet Piling, Temp and Steel Sheet Piling, Temp, Left in Place based on the area of earth retention. The Engineer will calculate the vertical dimension of the area, based on the difference in ground elevations at the sheeting line, or the planned foundation excavation limits at the sheeting line, whichever is less. Unless otherwise shown on the plans, the Engineer will calculate the lateral limits based on the design specified in subsection 704.03.A. 363

If retaining earth on both sides of the same steel sheet piling during different construction stages, the Engineer will calculate the quantity based on the stage requiring the largest area of earth retention; not the sum of the areas of earth retention for each stage. The Engineer will take horizontal measurements along the sheet piling alignment without allowance for the structural shapes of the separate sections. a. Steel Sheet Piling, Temp. The unit price for Steel Sheet Piling, Temp includes designing, providing, installing, maintaining, and removing the sheet piling, bracing, tie backs, walers, deadman, related material, and equipment required to maintain support of the sheeting and adjacent embankment. b. Steel Sheet Piling, Temp, Left in Place. The unit price for Steel Sheet Piling, Temp, Left in Place includes designing, providing, installing, maintaining, and cutting off the sheet piling, bracing, tie backs, deadman, walers, related material, and equipment required to maintain support of the sheeting and adjacent embankment. B. Cofferdams. The Engineer will measure, and the Department will pay for filter bags as specified in subsection 208.04. 1. Cofferdams. If the contract includes a separate pay item for Cofferdams, the Engineer will group and measure cofferdams for the structure as a unit. The unit price for Cofferdams, of the type required, includes designing, providing, installing, maintaining, and removing sheet piling, bracing, tie backs, walers, deadman and related material. 2. Cofferdams, Left in Place. If the contract includes a separate pay item for Cofferdams, Left in Place, the Engineer will group and measure cofferdams specified as left in place for the structure as a unit. The unit price for Cofferdams, Left in Place includes designing, providing, installing, maintaining, and cutting off of sheet piling, bracing, tie backs, walers, deadman, and related material. If the contract does not include a pay item for Cofferdams or Cofferdams, Left in Place, the cost of constructing a cofferdam for structures not crossing streams is included in the unit prices for other items of work; for structures crossing streams or encroaching on water courses, the cost of constructing a cofferdam will be paid for as extra work. 364

If the Engineer authorizes an alternate method to a sheet pile cofferdam, the Department will pay for the alternate method at the unit price for Cofferdams or Cofferdams, Left in Place. 365