Environmental Protection (NJDEP) The Louis Berger Group, Inc.

Similar documents
ABC S OF FRESHWATER WETLAND DESIGN: CONCEPT TO CONSTRUCTION

Freight Street Development Strategy

Geneva Dam. Design of a Steep, Temporary, Riprap Ramp

DES MOINES RIVER RESERVOIRS WATER CONTROL PLAN UPDATES IOWA ASCE WATER RESOURCES DESIGN CONFERENCE

IAFSM 2010 Annual Conference. City of Rockford Keith Creek Greenway Flood Mitigation Project

South St. Vrain / Hall Meadows Restoration Planning August 20, 2015

Fargo-Moorhead Metropolitan Area Flood Risk Management Project

Appendix VI: Illustrative example

PRENTISS CREEK (SUB-E) KENSINGTON PLACE CONCEPT PLAN VILLAGE OF DOWNERS GROVE, ILLINOIS AUGUST, 2011

Hydrologic Calibration:

Stormwater Management Studies PDS Engineering Services Division ES Policy # 3-01

December 7, Dr. Christine Pomeroy University of Utah Civil and Environmental Engineering MCE Salt Lake City, UT. Dear Dr.

Outlet Structure Modeling

DRAFT. Jacob Torres, P.E.; Nick Fang, Ph.D., P.E.

Using Dredging Lessons Learned in a Large Contaminated Sediment Feasibility Study. Presented by John Laplante, Carl Stivers, and Clay Patmont

ENVIRONMENTAL RESOURCE PERMIT APPLICATION

Climate Change Impacts on Joint Riverine and Coastal Flooding on Calleguas Creek in Ventura County, CA

GEOMORPHIC EFECTIVENESS OF FLOODS ON LOWER TAPI RIVER BASIN USING 1-D HYDRODYNAMIC MODEL,HEC-RAS

Municipal Class Environmental Assessment for Pottersburg Creek Slope Stability Study South of Hamilton Road, Schedule B

Note that the Server provides ArcGIS9 applications with Spatial Analyst and 3D Analyst extensions and ArcHydro tools.

Lower Columbia River Pile Dike Assessment

Department of the Army Permit Application

Are You Ready for Risk and Uncertainty Analysis?

PUBLIC NOTICE US Army Corps of Engineers, Honolulu District

Appendix B HYDROLOGIC AND HYDRAULIC MODELING

OVERVIEW OF RESERVOIR OPERATIONS AND FLOOD RISK MANAGEMENT

PUBLIC NOTICE. REPLY TO: Denver Regulatory Office 9307 South Wadsworth Blvd 30 DAY NOTICE Littleton, CO FAX (303)

U.S. Army Corps of Engineers Mobile District

SEATTLE DISTRICT CIVIL WORKS PROGRAM

NJDEP Regulations that impact or soon will impact agricultural operations. April 1, 2007 Horses 2007

HYDRO EUROPE ISIS Report. Team

Municipal Stormwater Management Planning

Mississippi Coastal Improvements Program (MsCIP) Comprehensive Barrier Island Restoration Plan

Fort Leonard Wood, Missouri. September 2013

LOCATION AND DESIGN DIVISION

Alternative Approaches to Water Resource System Simulation

San Jacinto River Waste Pits Superfund Site

Suspended Sediment Discharges in Streams

Camp Creek: Tackling Erosion and Improving Water Quality in a Recreational Playground Mitchellville, Iowa

Ponds. Pond A water impoundment made by excavating a pit, or constructing a dam or an embankment.

Technology News from the Ecosystem Management and Restoration Research Program October 1999

Coal Combustion Facility Assessment Report. October 20, 2010

LEGAL AUTHORITY AND JURISDICTIONS

Appendix I Cost Engineering Pigs Eye Lake Ramsey County, MN Section 204 DRAFT. Draft Feasibility Study Report with Integrated Environmental Assessment

FREQUENTLY ASKED QUESTIONS: URBAN STREAM RESTORATION BMP. David Wood Chesapeake Stormwater Network. Lisa Fraley-McNeal Center for Watershed Protection

CORTE MADERA CREEK FLOOD CONTROL PROJECT UNIT 4 DESIGN ALTERNATIVES

Introduction to Sediment Remediation. Presented to: Lower Passaic River Community Advisory Group July 14, 2011

PRELIMINARY HYDROLOGY/HYDRAULICS ANALYSES RESULTS

Phase II Report on Hydrology, Hydraulics, and Low Water Dams

POOL 11 ISLANDS SUNFISH LAKE AND MUD LAKE OPERATION AND MAINTENANCE MANUAL

Coastal and Hydraulics Laboratory. US Army Engineer R&D Center

Good morning, Chairman Yaw, Chairman Yudichak, Chairman Vulakovich, Chairman Costa,

Project Goals and Scoping

FINDINGS: Olsson used a three-step analysis strategy to develop a benefit cost ratio that would indicate the relative feasibility of this project.

Analysis of Floodplain Fish Habitat on the San Joaquin for the San Joaquin River Restoration Project (SJRRP)

SECTION 3 NATURAL RESOURCES

HYDROLOGIC MODELING CONSISTENCY AND SENSITIVITY TO WATERSHED SIZE

Hydrologic and Ecologic Impacts from the CERP Indian River Lagoon South Project

Council of Governments

COON CREEK WATERSHED DISTRICT PERMIT REVIEW. Spring Lake Park Schools Westwood Middle School st Avenue NE, Spring Lake Park, MN 55432

Urban Hydrology Characteristics and their Influence on Urban Stream Restoration Technology. Presented by:

Local Flood Hazard Mitigation Program. A framework for hazard mitigation in the NYC West of Hudson Water Supply Watersheds

Habitat Grant Projects Clinton River Watershed

CHESAPEAKE BAY COMPREHENSIVE WATER RESOURCES AND RESTORATION PLAN. Habitat GIT Meeting 9 May 2017

Living Shorelines & Coastal Resiliency: A Consultants Perspective. Presented by: Bethany Bearmore, P.E. Louis Berger

FEMA s Mitigation Support for Resiliency: Innovative Drought and Flood Mitigation Projects

Flow-ecology relationships. Flow-ecology relationships Susitna case study

2017 Central Valley Flood Protection Plan Update: Overview

Working in Arid and Semi-Arid Climates with Hydromodification Concerns

Dredge and Fill Standards on the Highland Lakes

Mark Twain Lake Water Control Manual Update

City of Katy Flood Protection Study (Meeting 3 of 3) October 23, 2017

HEC-RAS 2D Modeling in Support of Ascension Parish Levee Certification

Functional Uplift Based Stream Assessment & Restoration Design

Riverine Hydraulics TABLE OF CONTENTS

Adjusted Flood Prone Acres

iswm TM Criteria Manual City of Azle Section 14 City of Azle Subdivision Ordinance DRAFT-June Chapter 1

Chapter 11 Culverts and Bridges

Instream Flow Study for the Proposed Lower Bois d Arc Creek Reservoir, Texas

Prepared for Urban Drainage and Flood Control District

Appendix H: Construction Impacts H-5 Dredged Materials Management Alternatives Analysis

Design of CAD Pits in San José Lagoon, San Juan, Puerto Rico

SECTION 11: REGULATORY FLOODWAYS

THE CORPS REGULATORY AUTHORITY

Duwamish Waterway Self Guided Tour: Turning Basin Number Three and Terminal 105 Aquatic Habitat Restoration Sites

US Army Corps of Engineers and Stream Restoration Permitting

G.B. Sonny Hall, PhD. Veronika Thiebach

CESAM-RD-C April 24, 2013 PUBLIC NOTICE NO. SAM AFM JOINT PUBLIC NOTICE SAM AFM U.S. ARMY CORPS OF ENGINEERS

Will be modified map from GIS 6/16 EOD

CE Hydraulics. Andrew Kennedy 168 Fitzpatrick

Clean Water Act Regulatory Program

STORMWATER RUNOFF AND WATER QUALITY IMPACT REVIEW

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows:

APPENDIX F. SECTION 404(B)(1) EVALUATION SHORT VERSION. Herbert Hoover Dike Dam Safety Modification Study

ND Detention Project Development Update

What Are Environmental (Instream) Flows?

Sediment management of hydropower cascade: example of CNR run-of-river developments, French Rhone River, France

Transcription:

Hydraulic Modeling for Preliminary Evaluation of Potential Flooding Impacts for Various Dredging, Capping and Armoring Scenarios of The Lower Passaic River Restoration Abdulai Fofanah, PE, D.WRE, CFM Murat Utku, PE, PhD Michael Burlingame, PE Steve Rock Stephen Trainor, PE Ellis Byeon, EIT The Louis Berger Group, Inc. The Louis Berger Group, Inc. New Jersey Department of Environmental Protection (NJDEP) The Louis Berger Group, Inc. The Louis Berger Group, Inc. The Louis Berger Group, Inc.

Definition of Terms Overview Remedial Scenarios Modeling Methodology Preliminary Results Preliminary Conclusions

Dredging (Environmental): The removal of contaminated sediments from the waterway Capping (In-situ): Leaving contaminated sediments in place and placing a layer of sand and/or other material over it Armoring: Placing a layer of material (gravel, riprap, etc.) over a cap to prevent erosion Armored surface substrate

Dredging (Navigational): Removal of sediments from the channel to allow boats to pass FFS: Focused Feasibility Study which presents the remedial alternatives in detail Alternatives from June 2007 DRAFT FFS were grouped and evaluated in 3 remedial scenarios All alternatives have been substantially changed since then, in response to stakeholder comments and additional technical work

General purpose of the modeling was to provide a preliminary assessment of potential flooding impacts resulting from various draft 2007 FFS remedial alternatives Seven remedial alternatives for the lower 8 miles of the Passaic River study area were modeled

Draft 2007 FFS remedial technologies included various combinations of: Dredging Capping Armoring Each technology could result in activity subject to the NJDEP Flood Hazard Area Control Act Rules (N.J.A.C 7:13) (the Rules) Modeling was performed to determine compliance with substantive requirements of the Rules

Evaluating alternatives for compliance with the NJDEP Rules Evaluate potential flooding impacts Flood storage Obstructions to flow Protect public safety Construct new structures above flood hazard area elevation Provide healthy riparian corridors Preserve vegetation Protect habitat

All seven alternatives were modeled by NJDEP/Berger using tools that NJDEP typically relies upon (i.e. HEC-RAS, flooding modeling) EPA also performed flood modeling using a hydrodynamic model developed under the CARP program Presentation focuses on three scenarios that are representative of all seven alternatives modeled

Dredging to navigational depths

Capping and armoring

Capping and armoring with dredging less than for navigation

Hydrologic Engineering Center River Analysis System (HEC-RAS) model used Model developed by US Army Corps of Engineers The HEC-RAS system contains four onedimensional river analysis components for: Steady flow water surface profile computations Unsteady flow simulation Movable boundary sediment transport computations Water quality analysis Study based on steady flow component to assess potential changes in water surface profiles due to channel modifications associated with each remedial alternative

HEC-RAS model input data River and floodplain cross sections

HEC-RAS model input data Structures River and floodplain roughness

HEC-RAS model input data Upstream boundary conditions Upstream Boundary Fluvial Peak Flows Q 10-YR Q 50-YR Q 100-YR Q 500-YR (cfs) (cfs) (cfs) (cfs) 15,300 25,300 31,800 46,200 Downstream boundary conditions Tidal Elevations Coincident Storm Surge Mean High Water T 10-YR T 50-YR T 100-YR T 500-YR MHW (ft. NGVD29) (ft. NGVD29) (ft. NGVD29) (ft. NGVD29) (ft. NGVD29) 7.5 9.3 10.2 12.8 3.6

Modeling performed for all four upstream boundary conditions with their associated storm surge downstream boundary conditions Modeling also performed for all four upstream boundary conditions with a mean high water downstream boundary condition Modeling was performed assuming a sub-critical flow regime

Preliminary results assessment focused on coincident storm surge downstream and upstream peak flow boundary condition

Dredging to navigational depths scenario could result in water surface elevation decrease of between 0.0 ft - 0.7 ft Effects of water levels above 8 miles need further study

Capping and armoring scenario could result in water surface elevation increases of between 0.0 ft to 1.4 ft

Capping and armoring scenario with dredging less than for navigation could result in zero to only minor (i.e. within error band of the model) water surface elevation increases of between 0.0 ft to 0.1 ft

Dredging to navigational depths could result in water surface elevation decrease by an estimated 0.7 ft during peak flooding, but further study would be needed to confirm this. Capping and armoring [without dredging] could potentially result in increased water surface elevations during flood events Modeling indicates zero to negligible water surface elevation increases for the capping and armoring with dredging less than for navigation

As remedial alternatives for the Lower Passaic River are further developed, additional flood modeling by NJDEP and EPA would appear to be appropriate Although comparison to and reconciliation with more sophisticated modeling efforts may be required, the HEC-RAS modeling conducted for this study was seen as an acceptable means of identifying preliminary order-of-magnitude flooding impacts

QUESTIONS?