Magino Project Environmental Impact Statement. Technical Support Document Draft Fish Habitat Compensation Plan

Similar documents
February 15, Mr. Kyle Stanfield Prodigy Gold Incorporated Box 209, 3 Dree Road Dubreuilville, ON P05 1BO

Magino Project Environmental Impact Statement. Technical Support Document Water Management Plan

Fisheries Protection Program: an overview. WaterTech 2016, April 6-8, 2016, Banff

to Nemaska Lithium Inc. c/o Guy Bourassa President and Chief Operating Officer 450 De la Gare-du-Palais Street, 1 st Floor Quebec, Quebec G1K 3X2

Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory

APPENDIX D EA Conditions Review D-1: Federal EA Conditions Review D-2: Provincial EA Conditions Review

Santoy 8 Satellite Mine at the Seabee Gold Mine. Technical Review Comments. on the. Environmental Impact Statement.

NICO COBALT-GOLD-BISMUTH-COPPER PROJECT Community Scoping Session Environmental Overview

DFO Fisheries Protection Program

Labrador Iron Mines Holdings Limited

PROJECT AGREEMENT FOR THE MAGINO GOLD MINE IN ONTARIO

Comprehensive Study Scoping Document. for Lower Mattagami Hydroelectric Complex Redevelopment CEAR Reference Number:

Appendix D. Fisheries and Oceans Canada (DFO) Letter of Advice

DFO - Fisheries Protection Program and Environmental Consultants Workshop. Holiday Inn St. John s NL March 16, 2016

APPENDIX 8. NORTHERN GROUND ELECTRODE LINE WATERCOURSE CROSSING ASSESSMENT BOOKLETS

Detour Lake Gold Mine Project Follow-up Program

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN AND AROUND WATERBODIES AND ON WATERBODY BANKS

APPENDIX O COMPREHENSIVE ALTERNATIVES ASSESSMENT TABLES. RAINY RIVER PROJECT Final Environmental Assessment Report

FISHERIES AND OCEANS CANADA

Côté Gold Project. Where is the Côté Gold Project located? Who owns the Côté Gold Project? Frequently Asked Questions. May 2018.

Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory

Draft Mine Closure Plan. 17 October 2018 Longlac & Geraldton

Review of the Fisheries Act 23 DECEMBER 2016 PREPARED BY: THE CANADIAN ENERGY PIPELINE ASSOCIATION

Frequently Asked Questions Wanapitei River: Allen & Struthers

Pêches et Océans Canada. October 11, 2017 Our file Notre référence 16-HCAA Your file Votre reference EA

Hydrology and Watershed Management

GENERAL SPECIFICATION FOR ENVIRONMENTAL PROTECTION FOR CONSTRUCTION IN WATERBODIES AND ON WATERBODY BANKS

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act:

Fish Habitat Design, Operation and Reclamation Workbook and Worksheets for Placer Mining in the Yukon Territory

Operations Mine Site, Tote Road and Railway

The following potential environmental receptors and impacts form the basis of TRCA s review under Ontario Regulation 166/06 and the Fisheries Act:

Chehalis Basin Strategy Programmatic SEPA Draft EIS

Welcome to the Boulevard Lake Dam Class Environmental Assessment. Public Information Session #1. June 14, 2016

GUIDANCE FOR MAINTAINING AND REPAIRING MUNICIPAL DRAINS IN ONTARIO

Changes / Updates to DFO Regulations. September 16, 2014

Recent Developments in Water Withdrawal Management

Fish Passage Decision Framework for BC Hydro Facilities

MINISTRY OF TRANSPORTATION BEST MANAGEMENT PRACTICES MANUAL FOR FISHERIES DRAFT

Flows and Levels of the Muskoka River System Living in Cottage Country

DFO s Fish Habitat Management Program

Fort McKay Specific Assessment

Fish Habitat Protection Development Permit Area

Preface. MNR # Queen s Printer for Ontario, 2012 ISBN (PRINT) ISBN (PDF)

Fisheries and Oceans Canada

REASONS FOR DECISION MINISTERIAL APPROVAL PURSUANT TO SECTION 15(1)(a) THE ENVIRONMENTAL ASSESSMENT ACT

PROJECT AGREEMENT FOR THE VICTOR DIAMOND MINE EXTENSION IN ONTARIO

Aquatic Science Unit 1. Introduction to Freshwater Ecology

MINISTERIAL APPROVAL UNDER THE ENVIRONMENTAL ASSESSMENT ACT RABBIT LAKE SOLUTION PROCESSING PROJECT Cameco Corporation and AREVA Resources Canada Inc.

A New Fish Habitat Management Regime for Yukon Placer Mining

Water Level - m Dec 1. Dec/ Jan/ Water Level - m 284.

APPENDIX D 2017 PHOTO ESSAY

Application for Paragraph 35(2)(b) Fisheries Act Authorization for Workforce Accommodation Centre Revision 1, November 2015

Reasons for Ministers Decision

Advice to decision maker on coal mining project

Information Request 37

EVALUATION - SECTION 404 OF THE CLEAN WATER ACT DISCHARGE OF SEDIMENTS FROM OR THROUGH A DAM

ENVIRONMENTAL IMPACT STATEMENT CHAPTER 1: INTRODUCTION, PURPOSE AND NEED

BACKGROUND INFORMATION. for the INITIAL FEDERAL PUBLIC COMMENT PERIOD. on the

CLOCA Rural & Agricultural Guide to Permits

Northern Mine Decommissioning and Reclamation Guidelines

Environmental Review Process. Presented by Environment and Natural Resource Unit, Lands and Economic Development, BC Region

Sabina. Local Study Area and Regional Study Area for Arctic Char. Figure Fishers. Island. Breakwater. Islands. Main Map. Walrus.

Species at Risk Act Permitting Policy

Shell Quest Carbon Capture and Storage Project. Shell Canada Limited

April 10, Ms. Violet Camsell-Blondin Chair Wek èezhìi Land and Water Board #1, th Street Yellowknife, NT, CA, X1A 2P6

CNL(10)51. NASCO Guidelines for the Protection, Restoration and Enhancement of Atlantic salmon Habitat

BlackRock Mining Project

The Project. Federal Regulatory Approvals and Involvement

Beaver Dam Removal in the Omineca Region Ecosystem Standard Operating Procedures

Prosperity Gold-Copper Project MOE (Kym Keogh) Final Comments

Subject: Keewatinoow Construction Camp Waste Water: Screening of Sewage Effluent Discharge. North/South Consultants Inc.

GUIDE TO THE DEVELOPMENT OF A MINING AND RECLAMATION PLAN IN NEW BRUNSWICK

CHAPTER 3 Environmental Guidelines for WATERCOURSE CROSSINGS GOVERNMENT OF NEWFOUNDLAND AND LABRADOR DEPARTMENT OF ENVIRONMENT AND LABOUR

Dirk J.A. van Zyl, Ph.D., P.Eng. P.E. Tailings and Mine Rock Management

Bonsall Creek Watershed Management Plan Gap Analysis

Proposed Approach for Coal Mining Effluent Regulations

Rainy-Namakan Rule Curves Final Letter Report following and considering Public Comments. November 8, 2017

Environmental Regulation & Mine Permitting in Ontario

COTTON CREEK CULVERT REPLACMENT

Information Request 11

Amphibian Protection Strategies. Presented by: Linda Dupuis, M.Sc., R.P.Bio Wildlife Habitat Ecologist

Working Around Water?(Saskatchewan Fact Sheets)

GENERAL SPECIFICATION FOR TEMPORARY FLOW CONTROL FOR CONSTRUCTION IN WATERBODIES

Muskeg River Mine Dedicated Disposal Area (DDA) Plan for In-pit Cell 1

Activities that may Require Permit/Approval. Permit/Approval Required Electrical Safety Authority. Approval (CAA) process.

Ashbridges Bay Erosion and Sediment Control Class EA: ABTP NLC Presentation June 17, 2013

Fish Passage Culvert Inspection (FPCI)

In re: Town of Norwich Pool Dam Reconstruction, Stream Alteration Permit Application

December 6, 2017 NSTIR and NSDA 1 of 6

LNG Canada Development Inc.

SCIENCE EVALUATION OF INSTREAM FLOW NEEDS (IFN) FOR THE LOWER ATHABASCA RIVER

EXECUTIVE SUMMARY. Consultative Committee Report Jordan River Water Use Plan

WELCOME! Mill Creek Daylighting Technical Feasibility Study. Thank you! Open House December Please sign in and get a comment form.

Environmental Trail Screening Tool. Legislation & Guidelines. Legislation/Guidelines. Implications for Trail Development

FORM B: DAMMING AND DIVERSION OF WATER

Department of Environment and Conservation. NEIA newleef 2013 October 10, 2013

Appendix N. NWPA Permit Application ALDERON IRON ORE CORP.

Star Orion South Diamond Project ENVIRONMENTAL IMPACT STATEMENT SUMMARY

CITY OF NEW WESTMINSTER. Bylaw No. 7033, 2005 RIPARIAN AREAS PROTECTION BYLAW

Transcription:

Magino Project Environmental Impact Statement Technical Support Document 20-14 Rev. No. Revision Date Approved 0 Document issued for EIS

Table of Contents SECTION 1.0 INTRODUCTION... 1 SECTION 2.0 BACKGROUND... 2 SECTION 3.0 OFFSET GUIDANCE... 2 Fisheries Act... 2 MMER Schedule 2... 3 SECTION 4.0 AFFECTED FISH HABITAT... 3 SECTION 5.0 REFERENCES... 13 Page ii

Tables Table 1: Summary of total fish habitat (m2) lost to the Magino Mine... 6 Table 2: Breakdown of stream fish habitat (m2) by waterbody and watershed lost to the development of the Magino Mine... 6 Table 3: Breakdown of waterbody fish habitat (m2) by waterbody and watershed lost to the development of the Magino Mine... 7 Page iii

Figures Figure 1: Magino Site Layout... 4 Figure 2: Federal Authorizations... 5 Figure 3: Potential Offset Opportunities...11 Page iv

SECTION 1.0 INTRODUCTION Prodigy Gold Incorporated (Prodigy) proposes to develop the Magino Gold Project (the Project), which is situated at a past-producing mine site. The Project is located in Northern Ontario, approximately 40 kilometres (km) northeast of Wawa. The Project will involve the mining of up to approximately 150 million tonnes (Mt) of ore and approximately 430 Mt of mine rock from an open pit in the same location as the past-producing underground mine. The proposed development of the Magino Project site will include project components such as an open pit, a tailings management facility, a mine rock management facility, ore processing plant, mine rock and overburden stockpiles, and ancillary infrastructure required to support construction and operation activities throughout the life of the mine. Within the proposed mine site area, a number of lakes, streams and wetlands are located. The development of mine infrastructure for the Project will require the infilling and diversion of waterbodies frequented by fish, resulting in the loss of fish and fish habitat. Under the Fisheries Act and MMER Schedule 2, the removal of any commercial, recreational or Aboriginal (CRA) fisheries, or the proposed deposition of mine waste material into fish frequented waterbodies requires authorization from the Department of Fisheries and Oceans, and Environment and Climate Change Canada. The Fisheries Act contains two key provisions on conservation and protection of fish habitat essential to sustaining freshwater and marine fish species. The Department of Fisheries and Oceans (DFO) administers Section 35, the primary habitat protection provision, prohibiting any work or undertaking that would cause the harmful alteration, disruption or destruction of fish habitat. This generally involves physical works that will affect fish and fish habitat (i.e., loss of part of a stream to build a road). As of 2014, Environment and Climate Change Canada administers Section 36, the main pollution prevention provision, which prohibits the deposit of deleterious substances into waters frequented by fish, unless authorized by regulations under the Fisheries Act or other federal legislation [i.e., the Metal Mining Effluent Regulations (MMER) which allows the discharge of deleterious substances at specified concentrations]. It is important to note that the definition of fish is not consistent between Section 35 and Section 36. Section 35 applies to habitats supporting commercial, recreational and aboriginal fisheries, whereas Section 36 applies to habitat frequented by fish, in which fish are defined as fin fish. Thus, habitats affected by the project development have been considered in light of the project activity (i.e., mine waste deposition vs. loss to infrastructure) and the fish community to identified habitat loss to be approved under Section 35 or Section 36 (MMER Schedule 2) of the Fisheries Act. Since 2011, Prodigy has been completing baseline studies to characterize and understand potential environmental, human and socio-economic effects associated with proposed development activities. Local Aboriginal groups have provided Traditional Knowledge and Traditional Land Use Studies to provide a better understanding of how land within the project site has been, and is being utilized. Through baseline studies and engagement with the public and Aboriginals groups, Prodigy has identified that the primary potential use of affected waterbodies is for recreational purposes. No commercial or Aboriginal fisheries will be affected by the proposed development activities. The Fisheries Act, under Section 35(2), requires that the proponent prepare an offsetting plan following prescribed guidelines and regulations, in order to receive authorization from the Minister. This includes consulting with the government, public and Aboriginal communities to Page 1

ensure feedback is considered and incorporated into any proposed offset plans. Similarly, MMER Schedule 2 requires the proponent to prepare a fish habitat compensation plan, on which stakeholders are to be consulted prior to the submission of that plan for approval. The objective of both processes is an overall result of no net loss, while potentially providing improved fishing and fish habitat opportunities. This draft compensation plan presents a summary of the proposed offset strategies which are required for the Magino Project. Waterbodies requiring Fisheries Act Section 35(2) approval and MMER Schedule 2 amendments will be distinguished. Prodigy will continue to engage with the government, public and Aboriginal communities throughout the associated approvals processes to ensure the offset plans are developed in a way that results in no net loss. SECTION 2.0 BACKGROUND Within the Project Study Area (PSA), there are three watersheds (Herman-Otto Lake, McVeigh Creek and Webb-Goudreau) with a total of 20 lotic and lentic waterbodies providing a variety of different habitat opportunities. Dependent on the water body in question, the size and depth vary. Generally, lentic waterbodies within the PSA are shallow warm water habitats, with limited fish over wintering potential. These waterbodies tend to support small-bodied forage fish such as dace species, darters and brook stickleback. Water courses within the PSA tend to be low gradient, shallow, meandering streams with significant beaver activity influencing habitat conditions. The large bodied fish species found within the PSA are Northern Pike, Yellow Perch, White Sucker, Walleye, Burbot and Lake Whitefish. Both Burbot and Lake Whitefish are found only within the Herman-Otto watershed in the PSA. Neither Walleye or Northern Pike are found within the McVeigh Creek watershed within the PSA. Chapter 4, Section 4.3.4 and TSD 15 describe fish and fish habitat conditions within waterbodies assessed in the RSA, LSA and PSA. To reduce potential impacts on the waterbodies associated with the site, Prodigy has continually refined its mine site design since the submission of its initial project description. This has included improved engineering design and engagement with the public and Aboriginal communities. Aboriginal groups such as the Métis Nation of Ontario (MNO) and Missanabie Cree First Nation (MCFN) have suggested that the mine foot print be kept as small as possible. As such, the ore stockpiles will be consolidated and relocated in order to affect fewer watersheds and waterbodies. In addition, the overburden piles will be moved closer to the tailings and mine rock management area. As a result, the predicted area of disturbance has been decreased as has the number of waterbodies that could be potentially affected. All waterbodies affected by mine site infrastructure are located within the PSA. Although impacts to some waterbodies cannot be avoided, in order to proceed the Project will require the removal of fish habitat for the development of infrastructure. SECTION 3.0 OFFSET GUIDANCE Fisheries Act Subsection 35(1) of the Fisheries Act (administered by Fisheries and Oceans Canada) prohibits the carrying on of a work, undertaking or activity that results in serious harm to fish that are part of a commercial, recreational or Aboriginal fishery or to fish that support such a fishery (DFO, 2013). However, under Paragraph 35(2)(b) of the Fisheries Act, the Minister of Fisheries and Oceans Page 2

(the Minister) may issue an authorization with terms and conditions in relation to a proposed work, undertaking or activity that may result in serious harm to fish (DFO, 2013). The proponent of a project proposing work that may result in serious harm to fish is required to prepare an offsetting plan, which follows prescribed guidelines and regulations, in order to receive authorization from the Minister. For the Magino Project, an application under normal circumstances will be submitted for Section 35(2) authorization. This application will require Prodigy to provide information identified in Schedule 1 of the Fisheries Act Application Regulations and an irrevocable letter of credit to guarantee the implementation of the offsetting plan (DFO, 2013). Described below is list of information requirements that will accompany the application letter, once submitted to regulatory authorities: Contact Information; Description of the Proposed Undertaking; Timeline; Location; Description of Fish and Fish Habitat; Description of Effects on Fish and Fish Habitat; Measures and Standards to Avoid or Mitigate Serious Harm to Fish; Residual Serious Harm to Fish after Implementation of Avoidance and Mitigation Measures and Standards; and Offsetting Plan. MMER Schedule 2 Under Section 36 of the Fisheries Act (administered by Environment and Climate Change Canada), any mining project that proposes to use a natural water body frequented by fish to deposit mine waste (a deleterious substance) is required to obtain a Schedule 2 amendment of the Metal Mining Effluent Regulations. To support a Schedule 2 amendment, the project proponent must successfully complete a federal Environmental Assessment as well as: prepare an assessment of alternatives for mine waste disposal for consideration; prepare a fish habitat compensation plan for consideration as part of the EA; and participate in public and aboriginal consultations on the EA, including on possible amendments to the MMER (ECCC, 2013). After completing the steps described above, an amendment package will be prepared by Prodigy. This amendment package will be completed justifying the proposed Schedule 2 amendment and then be submitted for approval by the Minister of Environment and Climate Change Canada and the Minister of Fisheries and Oceans. SECTION 4.0 AFFECTED FISH HABITAT Construction and operation of the Project will require the infilling, diversion and removal of waterbodies frequented by fish. The proposed Project site layout is presented in Figure 1. Figure 2 identifies waterbodies requiring Fisheries Act and MMER Schedule 2 approval. Page 3

Figure 1: Magino Site Layout Page 4

Figure 2: Federal Authorizations Page 5

Page 6 MAGINO PROJECT A summary and break down of impacts to fish habitat by watershed are presented in the tables below (Tables 1-3). The infrastructure components affecting waterbodies are also identified. Table 1: Summary of total fish habitat (m2) lost to the Magino Mine Habitat Schedule 2 (m 2 ) Fisheries Act Authorization (m 2 ) Total Fish Habitat Lost (m 2 ) Stream 22,024 84,705 106,729 Waterbody 313,835 202,363 516,198 Total 335,859 287,068 622,927 Table 2: Breakdown of stream fish habitat (m2) by waterbody and watershed lost to the development of the Magino Mine Mine Infrastructure Affecting Waterbody Stream Study Area FAA/Schedule 2 Distance (m) McVeigh Creek Watershed Inlet to Waterbody 2 PSA Schedule 2 TMF/MRMF 85.1 43 Waterbody 2 to confluence with McVeigh Creek Tributary Waterbody 1 to confluence with Unnamed Tributary McVeigh Creek Tributary to Confluence with McVeigh Creek Clarification/Polishing Pond to Lovell Lake Lovell Lake to Spring Lake Waterbody 3 to Spring Lake Area (m 2 ) PSA Schedule 2 TMF/MRMF 1010.2 6,572 PSA Schedule 2 TMF/MRMF 962.3 8,270 PSA Schedule 2 TMF/MRMF 1160.7 3,609 PSA Schedule 2 Stockpile/Fill Area 493.1 981 PSA Schedule 2 TMF/MRMF 511.4 2,313 PSA Schedule 2 TMF/MRMF 197.2 223

McVeigh Creek (downstream of Spring Lake) McVeigh Creek (downstream of Spring Lake) to Summit Lake PSA LSA RSA FAA FAA TMF/MRMF/ Stockpile/Fill Area and Decrease in Water Flow Decrease in Water Flow Decrease in Water Flow MAGINO PROJECT 1,743.4 40,007 2,283.0 29,354 731.9 5,107 Total 9,178.3 96,477 Webb-Goudreau Lake Watershed Waterbody 10 to Web PSA FAA Open Pit 428.9 4,997 Lake and upstream Inlets to Webb LSA FAA Open Pit 120.8 4,778 Webb to Goudreau Lake PSA FAA Open Pit 128.5 462 Total 678.3 10,237 Herman Otto Lake Watershed Outlet of Waterbody 7 PSA Schedule 2 Stockpile/Fill Area 84.1 19 Total 84.1 19 Table 3: Breakdown of waterbody fish habitat (m2) by waterbody and watershed lost to the development of the Magino Mine Waterbody Study Area FAA/Schedule 2 Mine Infrastructure Affecting Waterbody McVeigh Creek Watershed Waterbody 2 PSA Schedule 2 TMF/MRMF 23,236 PSA Schedule 2 TMF/MRMF 36,189 Area (m 2 ) Page 7

Waterbody 1 Lovell Lake Clarification / Polishing Pond FAA PSA Schedule 2 PSA FAA TMF/MRMF (outside the footprint) TMF/MRMF/ Stockpile/Fill Area Plant-Crusher Pad Area MAGINO PROJECT 5,656 131,977 18,601 Waterbody 3 PSA Schedule 2 TMF/MRMF 28,871 Schedule 2 TMF/MRMF 5,319 Waterbody south of PSA TMF/MRMF FAA Lovell Lake (outside the footprint) 1,028 Total 250,876 Webb-Goudreau Lake Watershed Webb Lake PSA FAA Open Pit 114,408 Waterbody 10 PSA 14,176 FAA Open Pit (drawdown) LSA 48,494 Total 177,078 Herman Otto Lake Watershed Water Quality Control PSA Schedule 2 Pond/Stockpile/Fill 88,243 Waterbody 7 Area Total 88,243 Page 8

The total loss of fish habitat resulting from the development of the Magino mine is estimated at 622,927 m 2. Under the Fisheries Act, 287,068 m 2 will require offsetting and 335,859 m 2 under MMER Schedule 2 will require compensation. As offset plans are developed, the total areas lost will be converted into habitat units to ensure no net loss is achieved. At the time of the EIS submission, the offsetting plans are not yet finalized; however design concepts have been developed. The objective of habitat compensation measures associated with the Prodigy Gold project will be to create habitat which achieves the biotic and abiotic habitat requirements of the resident fish species (Yellow Perch, Northern Pike, Walleye, Burbot and Whitefish) and minimize the risk of adverse effects to the environment (i.e., flooding and erosion). The overarching goal will be to compensate lost habitat productive capacity on a like for like basis to maintain the fish communities within, and the functionality of, the existing habitat. Therefore, the general approach will be to design habitat to meet the current life history requirements of the resident fish. Consideration with respect to habitat for spawning, juveniles, and adult foraging as well as over wintering habitat will be incorporated into the offsetting plan as appropriate. The offsetting plan will consider not only the physical habitat requirements (i.e., flow, depth, fish passage, cover, and substrate) but also the biological requirements (e.g., food). Key design considerations will include: Maintenance of existing watersheds to the extent possible; Maintenance of the existing hydrologic flow regime to the extent possible; Minimization of temporal disruptions to the extent possible; Promotion of connectivity within watersheds and habitats; Incorporation of natural channel design concepts; Incorporation of opportunities to increase productivity of the system (e.g. increased littoral zones); Enhancement of habitat complexity; and Incorporation of any limiting habitat types for resident fish populations to the extent possible (i.e., overwintering habitat). As far as practical, natural channel design techniques will be applied to mimic natural flow and flooding patterns, and incorporate shoreline and riparian vegetation. In addition, features will be incorporated for habitat and physical diversity, and to provide refuge areas (i.e., usable area for fish under either low flow or winter conditions). Prodigy has identified five potential opportunities within the Project area that could provide sufficient fish and fish habitat compensation. 1) Construct an outlet diversion channel from Water Body 6 to either Herman Lake or Otto Lake. Conversely, Water Body 6 s elevation could be increased to enhance fish habitat; in addition shoreline habitat improvements, such as spawning shoals, could be created near the confluence point; 2) There is an opportunity to create habitat during the re-alignment of McVeigh Creek to Spring Lake; 3) During the construction of the channel from Water Body 10 to Goudreau Lake fish habitat could be created. There is also potential for creating a water body upstream of West Goudreau Lake; 4) Create a new water body by increasing the pond elevation of a low area south of Spring Lake and create a channel leading into Spring Lake; and Page 9

5) Increase the size of Water Body 9 through damming prior to its discharge into Water Body 8. Page 10

Figure 3: Potential Offset Opportunities Page 11

Prodigy has discussed fish habitat offset proposals with the Aboriginal communities. BFN has suggested that Prodigy participate in an offset project in the St. Mary River sponsored by the Federal government. Due to the geographic distance and potential cost, the opportunity was determined to be a low priority. In Prodigy s engagement with Aboriginal communities, MFN and MNO identified that they are considering other fisheries offset opportunities and will look to provide Prodigy such information prior to the Company s application to DFO. Prodigy has also engaged local community members during open houses (e.g. in Dubreuilville) to identify any other potential offset opportunities. As engagement continues, Prodigy will continue to discuss potential offset opportunities that could benefit both the public and Aboriginal communities. It is expected that the offsetting plan to be implemented during construction of the Project will provide sufficient habitat to ensure no net loss of habitat due to the development of the Project. However, if additional habitat is required, Prodigy will seek opportunities within the region to develop additional compensation measures. Such measures will be undertaken in concert with the Ontario Ministry of Natural Resources and the Department of Fisheries and Oceans. As conceptual plans are developed, Prodigy will continue to engage with government agencies, the public and Aboriginal groups to ensure feedback is incorporated into final designs. Once feedback from stakeholders has been collected and offset plans refined, Prodigy will submit final plans for authorization to the Department of Fisheries and Oceans, and Environment and Climate Change Canada. Page 12

SECTION 5.0 REFERENCES Environment and Climate Change Canada. (2013). Guidelines for the Assessment of Alternatives for Mine Waste Disposal. Retrieved from the Environment and Climate Change website: https://ec.gc.ca/pollution/default.asp?lang=en&n=125349f7-1&offset=1&toc=hide Department of Fisheries and Oceans Canada. (2013). An Applicant s Guide to Submitting an Application for Authorization under Paragraph 35(2)(b) of the Fisheries Act. Retrieved from the Department of Fisheries and Oceans website: http://www.dfo-mpo.gc.ca/pnw-ppe/reviews-revues/application-eng.html Page 13