Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update November 1, 2016 Tom Peyton Second Avenue Subway Program Director - Construction
Phase 1 Overview The Re-routed Q train will travel from the new 96 th Street Station south through Manhattan and into Brooklyn, terminating at Coney Island
Current Progress The Second Avenue Subway Project is on budget and scheduled for revenue service in December 2016 Overall Construction is 98% complete as of October 1, 2016 NYC Transit revenue service training is underway
5 Active Contracts 96 th St. Station Finishes, Systems, Ancillary Buildings and Entrances 86 th St. Station Finishes, Systems, Ancillary Buildings and Entrances 72 nd St. Station Finishes, Systems, Ancillary Buildings and Entrances 63 rd St. Station Upgrade All Stations Track, Power, Signals & Communications Systems
Testing Track Geometry Car September 2016
Testing Track Geometry Car September 2016
Testing Pre Revenue Service Train October 2016
Station Areas
63rd Street Station Rehabilitation Station Upgrade Contract Contract Value incl. AWOs: $190.8 M Award Date: January 13, 2011 Forecast Completion: December 2016
Construction Progress Architectural finishes are near completion and station systems testing is underway Sidewalk reconstruction is complete Work zone on the NE corner of 64 th Street and Third Avenue has been removed Plaza on the NW corner of 63 rd Street and Third Avenue has been opened to the public
Current Progress The Plaza at 63 rd Street and Third Avenue is open to the public.
Current Progress Ancillary 2 (NW corner of 63 rd Street & Third Avenue)
Current Progress Entrance 1 (SE corner of 63 rd Street & Third Avenue)
Project Completion Look Ahead STATION Completion of ceilings and wall tiles, lighting, and column enclosures Testing of mechanical, electrical, and plumbing systems in new station area ENTRANCE 1 Installation of finishes and tiles Testing of elevators and escalators STREETSCAPE Trees in the station area will be planted this fall season
72 nd Street Station Finishes, MEP Systems, Ancillary Buildings and Entrances Contract Contract Value incl. AWOs: $286.1 M Award Date: February 14, 2013 Forecast Completion: December 2016
Construction Progress The station and track has been energized Ancillary 1 (NW corner of 69th Street and Second Avenue) and Ancillary 2 (NW corner of 72nd Street and Second Avenue) façade work is nearing completion Entrance 1 and Entrance 2 escalator installation nearing completion Entrance 3 (SE corner of 72nd Street and Second Avenue) façade work and elevator installation nearing completion Tunnel Smoke Systems Management (TSSM), HVAC, Fire Protection System (FPS), elevator and escalator testing in progress
Current Progress Ancillary 1 (NW corner of 69 th Street & Second Avenue)
Current Progress Ancillary 2 (NW corner of 72 nd Street & Second Avenue)
Current Progress Entrance 3 (SE corner of 72 nd Street & Second Avenue)
Current Progress Sidewalk Restoration (east side of 70 th -71 st Street & Second Avenue)
Current Progress Sidewalk Restoration (east side of Second Avenue between 72 nd and 73 rd Streets)
Current Progress Sidewalk Restoration (NE corner of 73 rd Street and Second Avenue)
Project Completion Look Ahead MAIN STATION CAVERN Installation of: Floor tiles, ceiling panels, conduits, mechanical, electrical and plumbing systems at the mezzanine level Tunnel Smoke Systems Management (TSSM), HVAC, Fire Protection System (FPS), elevator and escalator testing in progress Installation of fare array gates and turnstiles ENTRANCE 1 Architectural finishes and lighting work to continue at escalator incline portion of Entrance 1 Installation of street and mezzanine-level escalators Installation of wall tiles, duct work, conduit work and finishes
Project Completion Look Ahead ANCILLARY 1, ANCILLARY 2, ENTRANCE 3 Construction of façades Electrical and mechanical equipment installation and testing for revenue service Installation of escalators and elevators at Ancillary 2
86 th Street Station Finishes, Entrances, Ancillaries, and MEP Systems Contract Contract Value: $223,000,000 Award Date: June 12, 2013 Forecast Completion: December 2016
86 th Street Station Progress Façade installation has begun on Ancillary structures Test trains are running in the station The structural frame for the elevator at E. 86 th Street has been installed East side sidewalk restoration is nearing completion Installation of artwork by MTA Arts & Design is underway Fan testing at Ancillary structures is underway
Construction Progress Installation of façade at Ancillary 1 (NE corner of 83 rd Street) 27
Construction Progress Sidewalk restoration at 83 rd Street (SW side)
Construction Progress Sidewalk restoration on the east side of Second Avenue (82 nd 83 rd Streets)
Construction Progress Sidewalk restoration on the east side of Second Avenue (87 th 88 th Streets)
Project Completion Look Ahead 82 nd Street to 88 th Street Completion of east side sidewalk restoration between 82 nd and 88 th Streets Installation of Ancillary 1 and 2 façade tile West side sidewalk restoration will begin on Second Avenue between 84 th and 88 th Streets
Project Completion Look Ahead 83 rd Street between 2 nd and 3 rd Avenues Above ground work will continue including installation of building finishes on Ancillary 1 Sidewalk reconstruction work 86 th Street between 1 st and 2 nd Avenues Sidewalk and elevator finishing work 86 th Street between 2 nd and 3 rd Avenues Above ground work including installation of building finishes on Ancillary 2
Project Completion Look Ahead Underground Construction Installation of architectural finishes; wall panels, tiles, floor tile, acoustical panels and service carriers on the platform and mezzanine levels Installation of station signage and customer information screens (CIS) Installation of art work
96 th Street Station Finishes, MEP Systems, Ancillary Buildings and Entrances Contract Contract Value: $324,600,000 Award Date: June 22, 2012 Forecast Completion: December 2016
96 th Street Station Progress Sidewalks restored along east and west side of Second Avenue, side streets nearly complete Tree planting scheduled for November Roadway restoration on side streets in process Final testing of station safety, HVAC, elevators, and escalators Station finishes, wayfinding signs, art and floor tile nearly complete Installation of street level elevator cab at Entrance 3 during testing
96 th Street Station Progress Façade of Ancillary 2 west side of Second Avenue and 97 th Street
96 th Street Station Progress Façade of Ancillary 1 east side of Second Avenue and 93 rd Street
96 th Street Station Progress Bike lane striping on the east side of Second Avenue 104 th 105 th Streets 93 rd 94 th Streets
96 th Street Station Progress Bus lane striping west side of Second Avenue between 98 th 99 th Streets
96 th Street Station Progress Sidewalk restoration south side of 97 th Street between First & Second Avenues
96 th Street Station Progress Sidewalk restoration matching tint and pattern west side of Second Avenue and 92 nd Street
96 th Street Station Progress Installation of entrance canopy east side of Second Avenue at 94 th Street
96 th Street Station Progress Installation of entrance glass west side of Second Avenue between 95 th 96 th Streets
Project Completion Look Ahead Completion of street level restoration Tree planting in the fall planting season Completion of station finishes Advanced testing of all systems before handover to NYCT Completion of Entrance 2 & Entrance 3 glass canopy and plaza pavers
Systems Installation Track, Power, Signals and Communications Systems Contract Contract Value incl. AWOs: $292.8 M Award Date: January 18, 2012 Forecast Completion: December 2016 45
Systems Installation Signal system has been installed Con Edison feeders at 86th and 96th Street stations are energized Geometry trains were run and interferences with systems were resolved Signal train and stress train ran in October as scheduled In service testing is complete Inspection is ongoing Installation of wayside traction power cables to 3rd Rail