Ground Freezing for Tunnel, Shafts, and Adits

Similar documents
Forensics by Freezing

Grouting for Freezing

MONTREAL AT WORK New tunnel construction starts across the city. NORTH AMERICAN EDITION October ~ November 2017

Ground Freezing to Repair Leaks in a Slurry Wall Shaft

A successful case of water cut-off by ground freezing in the excavation of the shaft DST-1

TBM rescue projects using shafts and ground freezing

Geo-Strata. Urban Geotechnical ALSO. Building Careers and Developing Leadership. May/June 2014

SECTION CS-2. TRENCH EXCAVATION CONSTRUCTION STANDARDS

FURTHER TECHNICAL INFORMATION IN RELATION TO THE OPERATIONS OF OUR GROUP

Section WATER LINE IN TUNNELS

Misan University - College of Engineering Civil Engineering Department

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

Kiewit Approach for Tunnel Stabilization and Sewer Pipeline Replacement Project

Pipe Jacking/Microtunnelling. Dr. Mark Knight. Centre for Advancement of Trenchless Technologies (CATT) University of Waterloo.

COMMUNITY BOARD EIGHT

WATER LINE IN TUNNELS

Appendix C. Gallery Place Chinatown Station Structural Assessment

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

No-Dig Technology is the art and science of pipes, ducts and cables using techniques that minimizes / eliminates the need for excavation, i.e.

Freezing techniques made a new tunnel possible

SECTION 39 - MANHOLES TABLE OF CONTENTS

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title

Tunnel. Immersed Tunnels

Advanced Construction Techniques. Ground Freezing

Replacement of the Existing Water Siphons between Brooklyn and Staten Island Siphon Project

F. Provide at least 2 feet of vertical separation between a water line and any utility or stormdrain crossing it.

Large-diameter bored piles and Large-hole drillings Applications

Tunnelling and Underground. Construction Technology

DESIGN AND INSTALLATION OF THE SHORING AND DECKING FOR TTC YONGE STATION

SECTION DRILLED CONCRETE PIERS AND SHAFTS

Earth Retention Systems

Compaction and Jet Grouting

An Introduction to. By Michael L. Schumaker, P.E. An Introduction to Shaner Industries Metal Foundation System

VERTICAL BARRIERS SLURRY TRENCH BARRIERS: excavation equipment. prof. E. Fratalocchi Environmental Geotechnics Waste and polluted sites containment

Slurry MTBM in Alluvial Soils and 25k Rock Chris L. Windley, P.E. McKim & Creed Inc. Stephen D. Leitch, P.E. Hazen and Sawyer, P.C. Joshua P.

Index to Technical Specifications

ITEM 432 TUNNEL CONSTRUCTION

Vest Process Propane Cavern Project, Norway

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

Description of Phase 2 Modified Design

Chapter 3: Permit Procedures and Requirements

SPECIAL CONDITIONS FOR MICROTUNNELING (MT) October, 2006

CONSTRUCTION SPECIFICATION FOR PIPELINE INSTALLATION BY TUNNELLING

Design and Implementation of the South Hartford CSO Tunnel

Preferred Elevated Tank Site

REQUIREMENTS FOR SERVICES UNDER THE RAILWAY CORRIDOR (NON-QR SERVICES)

APPENDIX I. Conceptual Design - Salem Road and McKay Road Trunk Watermain and Sanitary Sewer

SECTION HORIZONTAL DIRECTIONAL DRILLING

SPECIFICATIONS FOR STRUCTURAL EXCAVATION

Progress update (November to March) 03/23/2009 2

TRENCHLESS CONSTRUCTION (BORING, JACKING, AND TUNNELING)

Fleet Elementary School

6 Preliminary Assessment of Construction Method and Constructability Issues

Construction of a Semi-Buried Building A Super-sized Shopping Mall : The Festival Walk

Instrumentation and Data Management for the Zurich Zimmerberg Railway Tunnel Construction Daniel Naterop Solexperts Ltd.

CC1602 Microtunneling

Risk Management of the Restoration of Shanghai Metro Line 4

SHAFT CONSTRUCTION SECANT PILE

REPAIR OF DISPLACED SHIELD TUNNEL OF THE TAIPEI RAPID

Earth Retaining System

Eglinton Crosstown LRT Construction Liaison Committee

DIAPHRAGM WALLS, CUT-OFF WALLS AND SLURRY WALLS

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

TRENCHLESS TECHNOLOGY. Department of Civil Engineering.

Trans Mountain Expansion Project Overview

Case study The construction of the West Rail Tsing Kwai Tunnel from Mei Foo to Tsuen Wan

D7: TUNNEL CONSTRUCTION AND METHODOLOGY

Civil Engineering Construction I (CBE5031)

Construction Technology B (CON4313)

DIFFICULT GROUND SOLUTIONS:

CONSTRUCTION STANDARDS SECTION CS 3 TRENCH FOUNDATION, BEDDING AND BACKFILL

A. Section includes temporary excavation support and protection systems.

CONSTRUCTION SPECIFICATION FOR THE INSTALLATION OF ELECTRICAL CHAMBER

Martha Lake Gateway Sewer. An Introduction to Trenchless Methods and Evaluation for the Installation of New Pipelines

CIVIL BREADTH Exam Specifications

H. Underground Transmission System Design

Contents. Glossary 9. Foreword 10

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

Method for Installation of PEHD Manholes - a technical report with 29 self-explanatory Figures -

UNDERGROUND UTILITY CONTRACTORS GENERAL TRADE KNOWLEDGE EXAMINATION CONTENT INFORMATION

Pipe Jacking. Japan Sewage Works Association

B. Base Course: Aggregate layer placed between the subbase course and hot-mix asphalt paving.

COMMUNITY BOARD EIGHT

MOA Project # Golden View Drive Intersection & Safety Upgrades

Introduction to Utilidors, Power Distribution and Communication Systems in Cold Regions

Minimum Guidelines for the Design and Use of Underpins When Performing Foundation Stabilization and/or Supplementation UP-08

Anacostia River Tunnel Design/Build Project Washington, DC

COPYRIGHTED MATERIAL. Contents PART ONE: THEORY...1. Preface to the Third Edition xiii. About the Authors xv. Acknowledgements xvii

4.0 CONSTRUCTION METHODS AND ACTIVITIES

White Paper. Geothermal Heating and Cooling

The Technical and Contractual Matters of Bored Piling Works. By Wallace Yeung Vibro (H.K.) Ltd.

This specification supplements the requirements of the Occupational Health and Safety Act, and its Regulations.

Subject: Geotechnical consultation Permafrost foundation Plate Boundary Observatory (PBO), Alaska DMA Job No , UNAVCO P.O. No.

SECTION TRENCHING

MALCOLM. support of excavation. Provides Excavation Support for Miami Tunnel. Introduction

CONSTRUCTION SPECIFICATION FOR TUNNELLING

Trenchless Pipeline Crossings

Transcription:

Ground Freezing for Tunnel, Shafts, and Adits Joseph A. Sopko, Adam Curry Moretrench American Corporation Bianca Messina Skanska USA Civil Stephen Njoloma McMillen Jacobs Associates ABSTRACT Construction of a 0.81km long, 6.1m diameter sewer tunnel, a component of D.C. Water s Clean River Project required construction of three drop shafts and connecting adits. The location of these three shafts and adits was complicated by their locations in a populated suburban neighborhood. Ground freezing from the surface was selected as the method to provide temporary earth support and groundwater control during construction. The ground freezing option was not only the most technically appropriate method, it provided significant advantages to accommodating the citizens in the neighborhood. Not only did the drilling and installation process provide a minimal equipment footprint at each site and reduce cuttings and spoils, but the refrigeration plants were located at a remote location reducing noise levels during the freezing process and construction. This paper discusses the design and implementation process of this complex freezing system that included drilling refrigeration pipes at complex angles in order to minimize traffic interruption and avoid utilities. Additionally, horizontal freeze pipes were drilled under 3 bars of pressure from the EPB tunnel in order to ensure that the adit connections were sufficiently frozen. The intricate cooling system extended over half a mile on both the surface and underground tunnel with instrumentation and monitoring along all points. INTRODUCTION The relatively short (0.81km) First Street Tunnel had three individual drop shafts designed to transport combined sewage from higher elevation sewers to the tunnel via small diameter (2.4-5m) adits. The three shafts and adits are shown in section in Figure 1. 1

Figure 1. First Street Tunnel shafts and adits Construction of these shafts and adits was complicated by their locations within a residential neighborhood. In selecting the support of excavation for the shafts and the required ground improvement for the adits, consideration was given to minimizing the impact on the residents as well as minimizing noise. Secant piles and slurry diaphragm walls were considered for the shafts while jet grouting was a technical feasible method of ground improvement for the Sequential Excavation Method (SEM) for the adits. While both methods were technically and economically feasible, there were some significant disadvantages related to their compatibility with working in a residential neighborhood. Specifically there was concern that space was limited for slurry diaphragm wall construction due to the reinforcing steel on-site storage and placement. Jet grouting would result in a significant amount of cuttings and spoils that would not only create a less than pristine site, but would also result in significant traffic for disposal. Furthermore, jet grouting would require significant utility relocations to avoid angled drill holes. Ground freezing was originally considered, however immediately ruled out due to the constant operations of the refrigeration plants at each of the three shaft and adit sites. Ground freezing, however, had several technical advantages to the methods. Specifically: Ground freezing could be used for groundwater control and temporary earth support for the shafts and adits requiring one equipment mobilization. Cuttings and spoils would be minimized. Freezing could be used to ensure a water-tight connection from the adits to First Street Tunnel. Vehicle traffic near the residential structures would be minimized. Construction noise and vibration would be minimized 2

These advantages were too significant to totally discard the freezing concept. After reviewing the site plan in detail, an alternative approach was considered. The Channing Street Shaft site where the Tunnel Boring Machine (TBM) would be launched was not only relatively far from the residences, but had ample laydown room to place the refrigeration plants, pumping skid, and instrumentation trailer. This unprecedented approach was to use the Channing Street site as the lay-down area and transfer the refrigerated coolant to each of the three sites using a subsurface distribution manifold. Using this concept, the ground could be freezing at each of the sites literally unnoticeable to the residents of the community. COOLANT DISTRIBUTION MANIFOLD The initial design computations concluded that three electrically powered mobile refrigeration units would be required to provide sufficient cooling capacity to the shafts and adits at the required times as proposed by the original schedules. As shown in Figure 2, the plants and pumping system would be located near the Channing Street Shaft. The refrigerated calcium chloride brine would be pumped to each of the sites through a subsurface manifold system as shown in Figure 3. The Pumping Station Site was located 670 m from the plants. In addition to the hydraulic requirements as related to the pumping capacity and pipe size, heat loss through the system was also evaluated. Figure 2. Freeze plant and pumping system Source: Rob Chamberland. MTAC 3

Figure 3. Subsurface manifold system The manifold was buried and essentially undetected during the process. The heat loss was mitigated by backfilling the trench with polyurethane insulation. This insulation resulted in a heat gain of less than 2 o C at the Pumping Station, consistent with the thermal design requirements of providing - 25 o C brine or colder through each subsurface refrigeration pipe. It should be noted that in addition to maintaining the cold brine temperature within the manifold pipes, the insulation also served to reduce or eliminate any frost effects to the sidewalks and pavements due to the freezing temperatures. While the design of the frozen earth structures stipulated a brine temperature of -25 o C or colder, sufficient flow through each individual freeze pipe or circuit of freeze pipes is just as important to the timely and successful formation. To ensure both temperature and flow requirements, an instrumentation system specifically designed for this project was designed and fabricated. Figure 3 shows the placement of conduits, one to be used to transmit information for the shaft sites back to a centralized computer and SCADA system. The performance of the distribution system was monitored with flow meters and also the supply and return temperatures of the circulating brine. Flow meters were used to evaluate the overall mass flow in and out of the pumping system. The brine supply and return temperature was measured at each pipe or circuits of pipes. By evaluating the difference between the supply and return temperatures it was possible to not only confirm sufficient flow, but also to balance the system across each individual structure. FROZEN EARTH SHAFTS The frozen earth for the shafts provided both temporary earth support and groundwater control. The three frozen shafts are described in Table 1. Table 1. Frozen shaft dimensions (m) Shaft Shaft Inside Diameter Excavated Depth Depth to Rock Adams Street 6.0 29.9 42.8 V Street 7.0 27.3 44.0 Pumping Station 7.0 26.8 40.0 4

Figure 4. Typical shaft freeze system Figure 4 shows the typical system for this project. To provide bottom stability of the excavation, the frozen wall was terminated in competent rock below the excavation invert. A structural evaluation of the frozen shafts prior to design was completed following a frozen soil test program completed on samples retrieved following the contract award. The analyses concluded that at 2.5 to 3.0m thick freeze wall would provide the required resistance to lateral earth and hydrostatic pressures and the time and temperature dependent creep properties of the frozen earth. A thermal analysis estimated a freezing time of approximately eight weeks, using refrigeration pipes at 1.0m spacing. The freeze pipes were drilled with mud rotary methods and verified for verticality with an orientable inclinometer. Once the freezing process was initiated, the ground temperature data indicated freezing times compatible with the thermal model. As the frozen wall was formed, pore water within the shaft was forced to the center as a result of the expansion created as the water was converted to ice. This 5

expansion was observed through pressure measurements in a piezometer drilled and installed in the interior of each shaft. Following the indication of the closure of the frozen wall, an additional two to three weeks of freezing was required to achieve the required 2.5 to 3.0m thickness. Once this thickness was achieved excavation commenced. Prior to achieving the 3.0m thickness excavation was able to begin within the upper fill area, which contained no pore water. Standard soldier piles and lagging were used in this non-frozen area to ensure ground stability. Once the 3.0m thickness of frozen wall was achieved, excavation through the frozen soil began using a Brokk hammer along with mini excavator. As excavation progressed a 10cm thick layer of foam insulation was sprayed onto the exposed earth. Due to site noise and work hour restrictions, excavation, form, and concrete works had to be performed during weekdays and daytime hours only. Excavation of each of the three frozen shafts took approximately 2.5 months each. Immediately after bottoming out the shaft excavation, the base slab was poured followed by the formwork for the walls of the shaft. The formwork was installed in 4.9m lifts followed by pouring of the concrete liner. Once poured the formwork was stripped and raised for the next lift. Cycle time per lift averaged approximately 1 week. Wooden block-outs within the liner were also installed at the adit connection locations. After the entire height of shaft line was poured and cured, the freeze pipes for the shaft were shut off. FROZEN ADITS AND TUNNEL CONNECTIONS The frozen soil for the adit connections provided both a temporary earth support system as well as a ground water cutoff. The adits were designed as solid frozen soil masses. The dimensions of the frozen masses are outlined in the table below: Table 2. Frozen soil mass dimensions (m) Adit Location Length Width Height Adams Street Adit 26.5 8.2 8.2 Adams Channing 8.5 7.9 8.2 Tunnel Connection V Street Adit 24.7 9.7 11 Pump Station Adit 25.9 9.1 10 At a minimum, 1.8 m. of frozen soil was required by design around the designed excavated area. Unlike the shafts, the adits were considered sufficiently frozen when temperature monitors combined with thermal modeling indicated a complete frozen mass. As a precaution, probe drilling was performed ahead of the excavation to verify anticipated frozen soil conditions. Excavation of the adits was performed utilizing Sequential Excavation Methods (SEM). A Brokk utilizing a roadheader type mining attachment was used to excavate the adits. Upon completion 1.2m of excavation, a lattice and girder support system was installed and 28 cm of shotcrete, installed in 2 passes, were used as additional excavation support. This was necessary due to the fact that freeze pipes were removed during excavation and thawing would occur prior to the installation of the final lining. Schedule required the passing of the TBM through the adit connection areas prior to completion of the adits. As such, a latter connection between the frozen adit and the newly mined tunnel was necessary. Freeze pipes that were installed prior to the TBM mining had to be decommissioned once 6

the main tunnel passed. To facilitate such connection, with the concerns of thawing, additional freeze pipes were installed from within the tunnel through the invert to ensure a sufficient frozen mass beneath the connection. Figure 5. Tunnel Connection Drawing Trumpets were mounted on the tunnel liner and core holes were drilled though a series of valves and wiper seals to prevent excess soil loss in the event that unfrozen soil was encountered. Once the freeze pipes were installed, urethane grout was used to seal the protrusion through the tunnel liner. Additionally, cooling loops were secured to the tunnel lining along the excavation line to ensure that a sufficient seal was maintained between the concrete lining and the frozen soil. 7

Figure 6. Trumpet and freeze pipe detail HEAVE AND MITIGATION Because of the difficulty in accurately estimating the freeze related heave and/or settlement, the approach for the First Street Tunnel was to go beyond evaluation of freeze related heave through modeling and to incorporate freeze heave mitigation as part of the project-wide protection of structures process. The protection of structures process required performing analyses to determine allowable and maximum movements or deformation limits and, if required, mitigations for any impacts during construction. During construction, information from instrumentation and monitoring of the existing utilities and structures was used in the selection and timely deployment of mitigation measures for excessive heaving. Typical mitigations that were used included installation of heat trace pipes to cut off or slow down freeze growth and modifications to the brine flow in the freeze system. Other mitigation measures included systematic isolation or shut-down of portions of the freeze system to control freeze related ground deformations and protect existing utilities and structures. CONCLUSION In order to accommodate the specific needs of this project all methods of work had to be evaluated. Due to the rigorous constraints relating to available area, noise, structural stability, and environmental concerns, ground freezing was proven to be the necessary method of support of excavation. With the unique structure and layout of the First Street Tunnel project, alternate ideas and concepts of supply and install of brine were critical to the success of the project. Implementation of innovative concepts within the ground freeze technology allowed for lessened impact to the surrounding community. Accurate monitoring and survey throughout the entire process proved critical to ensuring real-time data updates for schedule progression along with mitigation of any issues within the system. 8