Readily Implementable Signal Phasing Schemes for Diverging Diamond Interchanges

Similar documents
Evaluation of Alternative Intersections and Interchanges

Breaking the Diamond: DDIs, CFIs, and SPUIs

Queue Storage Length Design for Metered On-Ramps

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges

COMPARISON OF SPUI & TUDI INTERCHANGE ALTERNATIVES WITH COMPUTER SIMULATION MODELING

EVALUATING THE APPLICATION OF DIVERGING DIAMOND INTERCHANGE IN ATHENS, ALABAMA

Volume to Capacity Estimation of Signalized Road Networks for Metropolitan Transportation Planning. Hiron Fernando, BSCE. A Thesis CIVIL ENGINEERING

DDI s Can Move More Than Cars. Alex Ariniello. Presentation for the ITE Western District Annual Meeting. July, 2016 in Albuquerque, New Mexico

Conclusions & Lessons Learned

A Multi-stage System for Planning Analysis and Signal Design of. Diverging Diamond Interchange

UNION CENTRE BLVD AND I-75 INTERCHANGE WEST CHESTER, OHIO

The Secrets to HCM Consistency Using Simulation Models

Develop Guidelines for Access Management in Las Vegas

MPC-480 June 9, Project Title: A Comprehensive Safety Assessment Methodology for Innovative Geometric Designs. University:

CHAPTER 5 PARALLEL PARKWAY CORRIDOR IMPROVEMENTS

CHAPTER 2: MODELING METHODOLOGY

TecNote Modeling 4-Phase Diamond Interchange Operation With Synchro / SimTraffic

Critical Lane Volume (CLV)-based Capacity and Level of Service Analyses for Diverging Diamond Interchange

Traffic Signal Timing: What s Your Priority? Transportation Education Series May 8, 2012

Calibration and Field Validation of Four Double-Crossover Diamond Interchanges in VISSIM Microsimulation

Michigan Department of Transportation Diverging Diamond Interchange (DDI) Informational Guide. April 2015

The New Highway Capacity Manual 6 th Edition It s Not Your Father s HCM

1. Controlling the number of vehicles that are allowed to enter the freeway,

Diverging Diamond Interchanges in Michigan

DEVELOPMENT, ANALYSIS, AND DESIGN OF A NEW PARKWAY AT GRADE INTERSECTION (PAGI)

Adaptive Signal Control Technology (ASCT) for Rural Applications Lessons Learned from the Bell Rd ASCT Pilot Project

Testing of Light Rail Signal Control Strategies by Combining Transit and Traffic Simulation Models

Project Prioritization for Urban and Rural Projects TEAM CONFERENCE March 7, 2018

Diverging Diamond Interchange Analysis A Planning Tool

Maintenance of Traffic for Innovative Geometric Designs Work Zones

Woodburn Interchange Project Transportation Technical Report

New HCM Chapter(s)/ Alternative Intersections/Interchanges

Surrogate safety assessment for a tight urban diamond interchange using micro-simulation

Operational and Safety Attributes of an Alternative Design, Space-Efficient One-Sided Interchange

An evaluation of SCATS Master Isolated control

Traffic Control Concepts for Urban and Suburban Streets

INTERCHANGE MODIFICATION REPORT

Ramp Metering. Chapter Introduction Metering strategies Benefits Objectives

Exit 73 I-29 Interchange Modification Justification Study

UPDATE OF THE SIGNAL TIMING MANUAL

Interchange Design. Nick Hoernke, Bill Roth and Eric Sorensen

MINNESOTA DEPARTMENT OF TRANSPORTATION Engineering Services Division Technical Memorandum No TS-03 December 5, 2016

INSIGHTS INTO THE FIRST THREE DIVERGING DIAMOND INTERCHANGES IN MISSOURI. A Thesis presented to. the Faculty of the Graduate School

Evaluation of Railroad Preemption Capabilities of Traffic Signal Controllers

DIVERGING DIAMOND INTERCHANGE. Informational Guide

PASSER TM III-98 APPLICATION AND USER S GUIDE

A Sophisticated Transit Signal Priority System How it Works

A Probabilistic Approach to Defining Freeway Capacity and Breakdown

Interchange Improvements at the Queen Elizabeth Way and Glendale Avenue

Appendix B Highway 407 Interchange Review - Cochrane Street Area

INSIDE THIS ISSUE. mctrans.ce.ufl.edu VOLUME 64 \\ OCTOBER Streets Heat Map Freeways Animation HSM Supplement

4/26/2013. I-435 and Front Street Diverging Diamond Interchange Missouri Department of Transportation. KCITE 2012 Excellence in Transportation Award

Diverging Diamond Interchanges and their Relation to Sustainable Design

Impacts of Replacing a Tight Diamond Interchange with a SPUI A Wilsonville Interchange Study

/JLIE~P(ARCH. Guidelines for Selecting Traffic Signal Control at Individual Intersections

An Evaluation of Alternative Permissive Periods on Non-Coordinated Phase Performance in Coordinated Traffic Signal Systems

SIMULATION OF TRUCK SAFETY INSPECTION PROCEDURES AT THE TEXAS/MEXICO BORDER

SENSITIVITY ANALYSIS OF OPERATIONAL PERFORMANCE UNDER CONVENTIONAL DIAMOND INTERCHANGE AND DIVERGING DIAMOND INTERCHANGE

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0

PROJECT STUDY REPORT. Cal Poly Pomona Senior Project

M D 355 [FR E D E R IC K R O A D] OVER

I-17 and Happy Valley Road Diverging Diamond Interchange (DDI)

BILLINGS BYPASS UPDATE

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS

Military Highway Interchange

Chapter 7 INTERSECTION DELAY STUDY

MODELLING ADAPTIVE SIGNAL CONTROL REALISTICALLY

Transit Signal Priority Fine-tuning How to get more from your system

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

I-95 Corridor Study Phase II Highway Element

Applications of Microscopic Traffic Simulation Model for Integrated Networks

Goleta Ramp Metering Study

TERRA Engineering creates a competitive traffic data mix with Miovision

Analysis of Queue Estimation Methods Using Wireless Magnetic Sensors

APPENDIX D ACCESS MANAGEMENT GUIDELINES

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies

Comparing Roundabout Capacity Analysis Methods, or How the Selection of Analysis Method Can Affect the Design

Informational Brochure. Proposed Interchange. Interstate Route 295 (I-295) AT Greenville Avenue (State Route 5) Town of Johnston, Rhode Island

Ramp Reversal Research. Roy Parikh, P.E. TxDOT Fort Worth District

VIII. LAND USE ISSUES

A Rule-Based Real-Time Traffic Responsive Signal Control System with Transit Priority: Application to an Isolated Intersection

FINAL REPORT GUIDELINES FOR PRELIMINARY SELECTION OF THE OPTIMUM INTERCHANGE TYPE FOR A SPECIFIC LOCATION

Case Study Evaluation of the Safety and Operational Benefits of Traffic Signal Coordination

ORANGE COUNTY EMPIRICAL ANALYSIS: USING LOOP DETECTOR DATA TO IDENTIFY BOTTLENECK LOCATIONS AND CHARACTERISTICS

GOOD ONYA, AUSTRALIA!

Managing Innovations First of its kind in many ways Innovative design Innovative delivery methods Step through h the project ti in connection to the P

LAS VEGAS STREET RAILROAD CROSSING RR/PUC CONNECTION AND PRELIMINARY DESIGN

Interstate-290 Carbon Monoxide Build vs No-build Analysis For Individual Intersection Locations in Oak Park

Time-In-Queue Delay (TIQD) is the difference between the time a vehicle joins the rear of a queue and the time the vehicle clears the intersection.

OPTIMIZING RAMP METERING STRATEGIES

SERPM 7/DTA Application FSUTMS Users Group Meeting

Active Traffic Management in Michigan. Patrick Johnson, P.E. HNTB Michigan Inc.

RECOMMENDED RAMP DESIGN PROCEDURES FOR FACILITIES WITHOUT FRONTAGE ROADS

Ramp Metering 2010 evaluation report

Chapter 4 Chapter 4 INTERSECTION TURNING MOVEMENT COUNTSSUMMARY OF VEHICLE MOVEMENTS PURPOSE TYPES OF COUNTS

INTELLIGENT TRANSPORTATION SYSTEMS APPENDIX

NW La Center Road/I-5 Interchange Improvement Project (MP 16.80)

INTERCHANGE SAFETY. Steve Allen. Houston Daugherty. Director, Strategic Transportation Investments Division (TDOT)

MITSIMLab: Enhancements and Applications for Urban Networks

Project History Interchange Innovation Existing Conditions Proposed Design Approval Process Final Details PRESENTATION FOCUS

Transcription:

Tian, Xu, de-camp, Kyte, and Wang Readily Implementable Signal Phasing Schemes for Diverging Diamond Interchanges Zong Tian*, Ph.D., P.E. Hao Xu, Ph.D Center for dvanced Transportation Education and Research University of Nevada, Reno Reno, NV Email: zongt@unr.edu Gerry de Camp, P.E. Free-Lance Signal Operations Consultant Email: gerry.de.camp@gdecamp.com Michael Kyte Department of Civil and Environmental Engineering University of Idaho Moscow, ID Email: mdkyte@gmail.com Yinhai Wang, Ph.D., P.E. Pacific Northwest Transportation Consortium (PacTrans) University of Washington, Seattle, W -00 Email: yinhai@uw.edu Submitted for the th nnual Meeting of the Transportation Research oard Word Count:,0; Figures: ; Total:,0+*0=,

Tian, Xu, de-camp, Kyte, and Wang 0 bstract Diverging Diamond Interchanges (DDI) are emerging as an efficient alternative to conventional diamond interchanges with proven safety and operational efficiency. The number of DDIs is expected to increase significantly in the U.S. over the next decade. While geometric design of DDIs is getting mature based on experiences from existing sites, traffic operations, particularly the various signal phasing schemes, are not yet well defined and recognized. This paper provides five feasible signal phasing schemes which can be easily implemented using standard NEM - phase signal controllers. Discussions are provided regarding the advantages and disadvantages of each phasing scheme. These phasing schemes should be implemented according to the specific traffic pattern and geometric layout of DDI sites in order to achieve the best operational performance. Other relevant issues included in the paper are pedestrian handling, yellow change and red clearance intervals at DDIs. Keywords: Diverging diamond interchange, signal control, operations, signal phasing

0 0 0 Introduction The first diverging diamond interchange (DDI) in the U.S. was put into operation in Springfield, Missouri in 00, six years after Gilbert Chlewicki () first introduced this innovative design concept. Due to the great success of its operations, the number of DDIs has grown significantly in the past few years with over 0 now in operation and more than 0 under planning and design. DDI has proven to be a cost effective interchange type, providing both efficient and safe traffic operations. Considering DDI still a relatively new concept, there is an urgent need to gather the knowledge and lessons learned from existing research and practices in order to better guide future design and operations. review of the current state of the practice has shown that most DDIs implemented so far are not operating using the most efficient signal phasing schemes, neither in free mode nor coordination mode. There is also a lack of understanding of how a phasing scheme can be designed and implemented to fit certain traffic and geometric conditions. The purpose of this paper is to provide a comprehensive documentation of the various signal phasing schemes that can be easily implemented into standard signal controllers following the NEM phase/ring/barrier convention. Other relevant signal control aspects covered in this paper include pedestrian phasing and special consideration of signal change intervals. In order for readers to easily understand the phasing principles, links to YouTube are provided for viewing the animations of the presented phasing schemes. It is the desire of the authors that the paper serves as a practitioners guide on implementing safe and efficient signal phasing schemes for DDIs under different traffic and geometric conditions. Phasing Scheme Categorization t a DDI, the off-ramp control type influences the phasing options. The left-turn and right-turn movements at a DDI s off-ramp can be signalized or unsignalized (e.g., yield or stop control). When controlled by traffic signals, they can be on the same phase or separate phases. Off-ramp right turns rarely become critical movements because of the possible use of overlaps or through channelized design (). Therefore, the DDI phasing schemes described next only include the signalized off-ramp left turn phases. ased on our best knowledge, we categorize DDI phasing schemes into five types as summarized in Figure. Each is described below, ranging from the simplest to the most sophisticated schemes. Controller overlap phases are used in three of the schemes. Using overlaps is common at signalized interchanges where a movement can be controlled by more than one phase. ll phasing schemes are based on the operation of a single controller, which is a common and effective practice at DDIs. For convenience, we follow a convention, whenever possible, that designates phases,,, for the north-south off-ramps and phases,,, for the east-west arterial approaches. We also try to comply with the default NEM -phase, dual ring,

0 0 0 and -barrier structure. We use the term stage to differentiate it from the NEM phase. stage indicates a duration during which multiple signal phases can occur simultaneously. For a better visualization of how each phasing scheme works without taking too much space, we provide the stage diagrams for three of the phasing schemes. In the stage diagrams, the phase(s)/movement(s) in each stage are shown for both signals to better illustrate progression between the two signals. Links to the YouTube videos for most of the phasing schemes are also provided for easier visualization of the operations. Phasing Scheme - (P-): -stage split with off-ramp overlap This phasing scheme is found to be the most commonly used scheme at existing DDI sites. This scheme was first documented in a report by the FHW (). The Missouri DOT () included a slightly modified barrier structure which that ensures no stopping between the signals for the arterial movements. The advantages of this phasing scheme include: (a) no stops between the signals for the arterial traffic; (b) only two critical phases, thus with less lost time, higher capacity, and shorter cycle length; and (c) easy to implement and efficient when off-ramp traffic is light. The major disadvantage of this phasing scheme is that off-ramp traffic generally stops between the signals and internal queue spillback can occur if the spacing is short and off-ramp left-turn volume is high. Figure illustrates the stage diagram to depict the traffic progression between the two signals. Phasing Scheme - (P-): or -stage split with off-ramp overlap This is a variation of P- with each side having two phases (, ) and (ф, ф). Therefore, the arterial phases in the same direction (e.g., and ф for the E direction) do not have to end together, potentially reducing individual movement delay. The trade-off is possible stops for the arterial traffic. The off-ramp phases still overlap with the arterial phases. The two overlaps (D, E) for the off-ramps are needed if separate phases are given to the off-ramps (e.g., ф and ф in this case). This phasing scheme shares the same fundamental issues with P-, where internal queue spillback could result if spacing is short and off-ramp left-turn volume is high. Following this same operation, there could be other forms of phase numbering and overlap usage. Phasing Scheme (P-): -stage concurrent with off-ramp overlap This phasing scheme allows the two signals to turn green at the same time for both directions. Therefore, the two arterial directions move concurrently. When the phase splits are shorter than the travel time between the two signals, arterial movements do not stop, resembling in some way a simultaneous two-way progression. Under low volume conditions, the two sides can operate barrier free to minimize local intersection delays. The major disadvantage of this scheme is that the arterial traffic most likely stops between the signals when spacing is short and volume is high. potential internal queue spillback can result in higher lost time for the off-ramp phases. YouTube animation of this scheme can be found at: http://www.youtube.com/watch?v=dxcrbholiq.

E ф ф D P-: -stage split with off-ramp overlap P-: or -stage split with off-ramp overlap D=ф+ф; E=ф+ ф ф ф ф ф P: -stage concurrent with off-ramp overlap P: -stage split without off-ramp overlap =ф+; =+ф E D C C ф D *P: -stage split with overlap =ф+; =ф+ф; C=ф+ф; D=+ф; ф and ф are dummy phases; ф=ф=travel time (T.T.) *P: -stage split with overlap =ф++ф; =+ф; C=+ф; D=ф+; E=ф+ф; ф and ф are dummy phases,ф=ф=travel time (T.T.) *Note: P and P were invented by UNR team members. Figure. Classification of DDI phasing schemes

Tim Tian, Xu, de Camp, Kyte, and Wang Stage : W and SL move simultaneously. SL will most likely stop inside. Stage : W and S stop, E and NL move simultaneously. NL will most likely stop inside. 0 See YouTube animation: http://www.youtube.com/watch?v=gyxu-uqwsuqws Figure. Stage and progression diagram using phasing scheme P- Phasing Scheme (P-): -stage split without off-ramp overlap This is essentially a split phasing operation, and is currently being used at the I-0/Moana Lane DDI site in Reno, Nevada. Two overlaps (,) are used for the internal approaches. The major advantage of this scheme is excellent progression for all movements. The internal links are mostly free of vehicle queues, a highly desirable objective for DDIs where signal spacing is short. However, due to the nature of split phasing with three critical phases, this results in higher lost time and lower capacity. Longer queues on the external approaches can also be problematic to interfere with the adjacent signals and freeway. YouTube video demo can be found at: http://youtu.be/pjonscxjy. 0 Phasing Scheme (P-): -stage split with arterial-ramp overlap This is a phasing scheme invented by the authors, which resembles the TTI- phasing scheme at conventional diamond interchanges (,). Four overlaps (,, C, D) are used. The stage diagram of this phasing scheme is illustrated in Figure. Phases are numbered so that the default NEM phasing structure remains unchanged. The only caution is to set both ф and ф equal to the internal travel time (T.T.) and to be operating under max recall. ll vehicle stops are essentially eliminated between the two signals. ecause of the use of overlaps to allow off-ramp phases and arterial phases to move at the same time, some efficiency is gained compared to phasing scheme. lthough it is a -stage scheme, there are only three phases that incur lost times.

T.T. Time T.T. Tian, Xu, de Camp, Kyte, and Wang ф ф Stage : E and NL move simultaneously for a duration of travel time, T.T. ф Stage : NL arrives at the left side signal exactly after E stops, so NL does not stop. ф Stage : W starts and progresses through the left side without stopping. ф Stage : W and SL move simultaneously for a duration of travel time, T.T. Stage : SL arrives at the right side signal exactly after W stops, so SL does not stop. Stage : E starts and progresses through the right side without stopping. =ф+; =ф+ф C=ф+ф; D=+ф ф and ф are dummy phases ф=ф=travel time (T.T.) See YouTube: http://youtu.be/cvmtlrvoi 0 Figure. -Stage split with arterial-ramp overlap Phasing Scheme (P-): -stage split with arterial-ramp overlap This is a slightly modified phasing scheme from what was invented by researchers at the University of Nevada, Reno and was presented at the rd TR nnual Meeting (). It was fully tested using hardware-in-the-loop simulation. Details of this phasing scheme are illustrated in Figure, including the progression diagram and the NEM phase/ring/barrier structure. This scheme also has three phases that incur lost times due to the use of overlaps. For example, there is no lost time between ф and for overlap C. This phasing scheme also adopts a strategy similar to operating conventional diamond interchanges where the arterial and off-ramp phases are allowed to move simultaneously while still maintaining no stops between the signals. In this example, the southbound left-turn and the westbound arterial have an overlap stage for the duration of the travel time (T.T.) by using two dummy phases: ф and ф. This is an additional efficiency gained by the southbound off-ramp traffic. The length of ф and ф can also be

Time T.T. Tian, Xu, de Camp, Kyte, and Wang increased to exceed the travel time by trading off some internal stops with an increased capacity. This treatment proves to be very efficient when the interchange operates near capacity (). The slight delay in the middle is generally not a concern as vehicles are cleared out rather quickly. ф ф Stage : SL and W move simultaneously for a duration of T.T. ф ф D Stage : SL arrives at the right side signal without stopping exactly after E stops. The NL progresses through the left side signal. Stage : The later arrivals from NL do not stop at the off-ramp, but stop inside DDI. Stage : W starts and progresses through without stopping. (a) Stage and progression diagram =ф++ф; =+ф C=+ф; D=ф+ E=ф+ф; ф and ф are dummy phases; ф=ф=travel time (T.T.) 0 (b) Phase/ring/barrier diagram YouTube video can be found for this phasing at http://youtu.be/qwaqeuts Figure. -stage split with arterial-ramp overlap s for the northbound off-ramp, it allows overlap with, thus significantly increasing the phase time and capacity. ecause the first part of ф runs concurrently with ф, those vehicles stopped at the off-ramp signal in a queue can mostly progress through the left signal. Vehicles arriving after the queue discharge will go through the off-ramp signal without stopping, and then stop at the left signal. This operation does not increase the total number of stops for the northbound off-ramp. potential internal queue spillback is unlikely unless the off-ramp traffic volume is very high. For example, for a 00-ft and -lane internal storage spacing, it can store approximately (00 ft/ ft per car) * lanes = cars. For an off-ramp left-turn volume of,000 vph, It would require about /(000/00) = seconds to fill the storage space, which is unlikely with a typical cycle length and phase split setting. The sequence for and can be switched to achieve the desired operational objectives for the two off-ramps.

Pedestrian Crossings and Handling Pedestrian crossings and timing are directly related to the type of pedestrian path designs. There are generally two types of designs related to pedestrian path: external and internal (). The external design places all the crosswalks and pedestrian path outside of the interchange, while the internal design takes the pedestrians to the inside median (see Figure ). From a signal control point of view, the internal design has many advantages compared to the external design. One of the most significant benefits is to eliminate signalized crosswalks crossing the left-turn movements onto the freeway, which are supposed to be free flow movements. X X X X Figure. Pedestrian crossings and phasing 0 with the internal design and DDI P scheme 0 The four signalized crosswalks can be easily accommodated by the non-conflicting vehicle phases. For example, the four crosswalks can be controlled by the following corresponding vehicle phases with the DDI P scheme: X by ф; X by ; X by ф; and X by. The use of overlap to control pedestrian crosswalks could potentially improve pedestrian services by reducing delay times (). For the case shown, X can be controlled by an overlap phase of ф and while X can be controlled by an overlap phase of ф and. Yellow and Red Clearance Intervals The calculation of yellow change interval is no different from typical signalized intersections where the ITE recommended guidelines could be applied. However, due to the special geometric layout, the calculation of red clearance interval deserves some attention. In particular, the clearance distances as well as the red clearance intervals for the arterial phases are longer than that at normal intersections. For example (refer to the DDI layout in Figure from a Utah site), the red clearance of ф (NT facing to the left) needs to ensure that the vehicle passes the conflicting point before starting (EL). On the other hand, the red clearance interval for

may be shorter than the ITE recommendation due to the longer move-up distance for ф. Utah DOT (0) has exercised a unique phasing and detector setup where downstream detectors are placed between the crossover and the off-ramps (see detectors calling and ф in Figure ). Instead of using a long red clearance interval for ф, the downstream detector (calling ), once triggered will delay the start of, similar to a dynamic red clearance extension. This innovative design deserves further evaluation as part of this research. () () 0 Figure. Utah DOT detector design to reduce all-red clearance (courtesy of Matt Luker at Utah DOT) Summary Various signal phasing schemes are documented in this paper for operating DDIs. The advantages, disadvantages, and their applicable conditions are also discussed. This paper fills some of the knowledge gaps in the signal control aspect of DDI operations. While no detailed analyses were conducted to provide quantitative assessments on the various phasing schemes, the descriptions are intuitive enough for easily visualizing how each phasing scheme works and whether it is suitable for certain traffic flow and geometric conditions. It is the desire of the authors that this paper serves as a valuable guide for practicing signal engineers to identify and implement safe and efficient signal phasing schemes at DDIs.

0 0 References. Chlewicki, G. (00). New Interchange and Intersection Designs : The Synchronized Split-Phasing Intersection and the Diverging Diamond Interchange, nd Urban Street Symposium, naheim, C.. Chlewicki, G. (0). Should the Diverging Diamond Interchange lways e Considered a Diamond Interchange Form? Transportation Research Record, pp. -.. ared, J. (00). Double Crossover Diamond Interchange, McLean, V, pp. -.. Dayem,. and Tian, Z. (00). Modified TTI- Phasing Scheme to Control Diamond Interchange Locations with Heavy Off-Ramp Right-Turn Demand. TR th nnual Meeting Compendium.. Missouri Department of Transportation (00). Missouri s Experience with a Diverging Diamond Interchange. Report No.: OR 0-0, Jefferson, MO, pp... Tian, Z., Messer, C., and alke, K. (00). Modeling the Impact of Ramp Metering Queues on Diamond Interchange Operations, Transportation Research Record, pp. -. Hu, P., Tian, Z., and Xu, H. (0). n dvanced Signal Control Method for Diverging Diamond Interchanges, to be presented at the 0 TR nnual Meeting.. Tian, Z., Urbanik, T., and Gibby, R. (00). pplication of Diamond Interchange Control Strategies at Closely Spaced Intersections. Transportation Research Record, 0, pp. -.. Wang, X. and Tian, Z. (00). Pedestrian Delay at Signalized Intersections with a Two- Stage Crossing Design. Transportation Research Record, pp. -. 0. Rasband, E., Forbush, T., and sh K. (0). UDOT Diverging Diamond Interchange (DDI) Observations and Experience, Report No. UT-.0, Salt Lake City, Utah. 0