DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA

Similar documents
POTOMAC ELECTRIC POWER COMPANY

East Kentucky Power Cooperative (EKPC) Transmission System Planning Criteria

Rochelle Municipal Utilities TRANSMISSION PLANNING CRITERIA. March 21, 2017

FERC Form No. 715 Part 4 TRANSMISSION PLANNING RELIABILITY CRITERIA

March 3, Submitted to: CAISO

April 26, PJM Mr. Mark J. Kuras Senior Lead Engineer NERC and Regional Coordination 2750 Monroe Blvd. Audubon, PA 19403

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: Service Requested

Summary details for SPC TSR # and MH TSR # are shown in Tables ES.1 and ES.2: IFHS MH MW, firm :00:00 CS

TRANSMISSION PLANNING ASSESSMENT METHODOLOGY AND CRITERIA

SRRTEP Meeting 2019 Annual Assumptions for Pepco

DUQUESNE LIGHT COMPANY. Job Titles and Job Descriptions of Transmission Function Employees

Platte River Power Authority. Ten-Year Transmission Plan ( )

LONG TERM PLANNING, PRINCIPLES & PRACTICAL ANALYSES TURKISH ELECTRICITY TRANSMISSION CORPORATION

Planning Coordinator and/or Transmission Planner TRANSMISSION SYSTEM PLANNING GUIDELINES

AEP Transmission Local Planning Assumptions, Models, and Criteria

Transmission System Security and Planning Standards

PSE&G Assumptions Overview. November 2018

Updated October 2, 2014 TITLE: System Operator Transmission - Senior DEPARTMENT: System Operations

Generation Interconnection Feasibility Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

1.3 Planning Assumptions and Model Development

Standard TPL (i) System Performance Under Normal Conditions

Generation Interconnection System Impact Study Report. For. PJM Generation Interconnection Request Queue Position AA1-038

AEP Guidelines for Transmission Owner Identified Needs

AESO System Operating Limits Methodology for the Planning Horizon (R1 FAC-010-AB-2.1)

NERC PLANNING STANDARDS

PJM White Paper. Transource Independence Energy Connection Market Efficiency Project

Eastside Needs Assessment Report Transmission System King County Executive Summary December 2013

NYSRC RELIABILITY RULE/NERC STANDARD CROSS-REFERENCE

Seasonal Assessments and Modeling of Sub-100 kv Elements (Southwest Outage Recommendations 5, 6, 7 and NERC2) May 7, 2014

LONG-RANGE TRANSMISSION PLAN

2013 SERTP Study Scope Document --DRAFT-- 04/19/2013

DRAFT STUDY PLAN FOR 2018

PID 276 Feasibility Study Report 4.4MW Distribution Inter-Connection Mermentau Substation

Standard TPL-002-0b System Performance Following Loss of a Single BES Element

Transmission Planning Standards for the Baltimore Gas & Electric Company Transmission System

Methodology for Determining and Communicating System Operating Limits for the Planning Horizon (FAC-010 & -014) Revision Log

Scheduled Outages and Service Interruptions in Connecticut. Quat Nguyen Connecticut Public Utilities Regulatory Authority August 31, 2015

Stakeholder Communication. Inputs, Assumptions, and Preliminary Assessment. Base Model. Needs, Solutions, Sensitivity: Yr 5

Glebe to Potomac River Proposed 230kV Line & Substation Project Dominion

Managing Director Transmission Operations

Puget Sound Energy Energize Eastside Narrative and Probable Significant Impacts

Standard TPL System Performance Following Extreme BES Events

Conastone to Raphael Road 230kV New Transmission Line and Reconductoring February 28, 2017

NYSRC RELIABILITY RULES For Planning And Operating the New York State Power System

Table of Contents. To provide a methodology for determining the System Operating Limits (SOL) for the Planning Horizon at the California ISO.

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

TPL 001 AB 0 System Performance Under Normal Conditions

SPP at a Glance. Located in Little Rock. Approximately 600 employees

Transmission Cost Allocation in the Midwest

1.3 Planning Assumptions and Model Development

Feasibility Study for the Q MW Solar Project

B-R1 TRANSMISSION SYSTEM PLANNING PERFORMANCE REQUIREMENTS

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

TABLE OF CONTENTS. UNCONTROLLED WHEN PRINTED 2 USA Operations

Review of Data Change Management Processes for RTCA and Planning Models (Recommendation 16) March, 2017

OHIO VALLEY ELECTRIC CORPORATION. Open Planning Meeting. April 4, 2012

Transmission Function Employees - Job Titles and Descriptions 18 C.F.R 358.7(f)(1)

ReliabilityFirst s Review of Winter Preparedness Following the Polar Vortex

Standard TPL-003-0b System Performance Following Loss of Two or More BES Elements

NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC.

STATE OF ILLINOIS ILLINOIS COMMERCE COMMISSION

Standards de planification du NERC

Transmission Planning Procedures and Planning Criteria TDOG108

PJM Transmission Replacement Processes Senior Task Force COST ALLOCATION & COST RECOVERY Educational Session. June 3, 2016

East Kentucky Power Cooperative (EKPC) Baseline RTEP Integration Report

11. TRANSMISSION AND INTERCONNECTION FACILITIES

A. Introduction 1. Title: Automatic Underfrequency Load Shedding Requirements

Lower Mornington Peninsula Supply Area

Black Hills Power, Inc Basin Electric Power Cooperative Powder River Energy Corporation

RCP2 Project Overview Document

EIPC Interconnection-wide Webinar and Stakeholder Discussion. November 17, 2015

MIDWEST ISO UPDATE. Sherman Elliott Manager State Regulatory Affairs

South Fork RFP LIPA Board of Trustees REV Committee Briefing. September 21, 2016

Generator Interconnection Affected System Impact Study. Plains & Eastern Clean Line Final Report

AESO TRANSMISSION PLANNING CRITERIA BASIS AND ASSUMPTIONS

PID275 Feasibility Study Report 9.33 MW Distribution Inter-Connection Valentine Substation

Wide-Area Trans-Regional Northeast Reliability Assessment

Reliability Analysis Update

Last revised: March 1, 2018 TRANSMISSION FUNCTION TITLES AND JOB DESCRIPTIONS

Interconnection Feasibility Study

NERC TPL Transmission System Planning Performance Requirements

Standard TPL-003-0a1a System Performance Following Loss of Two or More BES Elements

NORTHERN MAINE INDEPENDENT SYSTEM ADMINISTRATOR, INC.

New York Independent System Operator System Reliability Impact Study Criteria and Procedures

System Impact Study and Facilities Study Process Manual For Cleco Power LLC

Mapping Document for FAC-010-3

Appendix 1 PRELIMINARY DELIVERABILITY BASELINE ANALYSIS STUDY REPORT

ENTERGY FACILITY CONNECTION REQUIREMENTS March 2007

System Impact Study E001 Moon Lake 230 kv 200 MW Plant

Addressing System Restoration Issues for the ISO New England System. Michael I. Henderson ISO New England Inc. PES General Meeting July 2015

EMERGENCY PREPAREDNESS & RESILIENCY IN THE ENERGY INDUSTRY

Standard Development Timeline

Ergon Energy Corporation Limited

October 6, Submitted to: CAISO

Standard TPL Transmission System Planning Performance Requirements

Reliability Analysis Update

ASSOCIATED NERC STANDARD(S): TPL (referred to as TPL-001 in this document) IMPLEMENTATION: In effect when approved.

PRINCIPAL CONCLUSIONS

BEFORE THE NEW JERSEY BOARD OF PUBLIC UTILITIES

Transcription:

DUQUESNE LIGHT COMPANY TRANSMISSION PLANNING CRITERIA Transmission Planning Criteria Updated: March Compiled: September 2007 Compiled from: s Comprehensive Transmission Reliability Plan, July 2005 s Strategic Transmission Plan, December 2005 s FERC Form 715 Annual Transmission Planning and Evaluation Report, March 2007 1

SECTION 1: GENERAL OVERVIEW The reliability guidelines used to plan the transmission system of (DLC) are the criteria by which the ability of the transmission system to serve the future load is determined. In addition to load growth, any significant changes to the generation capacity on DLC s or neighboring utility systems must also be included in any evaluation. (DLC) defines its bulk electric transmission system as facilities with voltages of 69 kv and above this includes transformers with low side voltages of 69 kv and 138 kv and lines with voltages of 69 kv, 138 kv, and 345 kv. The transmission system consists of over 670 circuit-miles of overhead and underground transmission lines. The DLC service territory is governed by the reliability standards established by the North American Electric Reliability Corporation (NERC), ReliabilityFirst Corporation (RF), and PJM Interconnections, LLC (PJM) organizations. DLC became a member of the PJM Interconnection on January 1, 2005. The exact planning requirements of these regulated institutions can be found on their websites and external publications. DLC will adhere to any requirements directed by these agencies in order to meet their established reliability planning criteria. In addition to these external organizations, DLC also has its own internal planning criteria which will meet or exceed the planning standards above. The following assessments and criteria will be used for all DLC transmission facilities. SECTION 2: TRANSMISSION PLANNING YEARLY ASSESSMENTS DLC performs seasonal engineering assessments in order to test for the adequacy of its transmission system for known, short-term conditions. DLC prepares an individual company assessment of the DLC zone bulk electric system for the up-coming peak summer and peak winter load period. This assessment includes the effect of known, planned, and forced outages on overall system performance. DLC also performs an annual 5-year and 10-year transmission (future) assessment of its local facilities to ensure ongoing adequate delivery service to retail customers in DLC s service territory in accordance with DLC s local reliability standards and distribution service restoration policies. The future year assessment ensures that the appropriate equipment loading is determined by using historical and projected circuit loads. In order to allow adequate construction time for new projects or system upgrades, load forecasting is essential in anticipating future overloads on existing facilities. This way, relief projects are scheduled prior to the actual occurrence of such overloads. This also helps to minimize loss of 2

life of equipment as a result of any anticipated overloads. As part of the continuing data collection, records of current and historical loads on individual circuits are maintained. As part of DLC s assessment, a load flow program (e.g., the Siemens PSS/E Load Flow program) is used to perform both a thermal/voltage analysis and a transient stability analysis of the transmission system. A short-circuit program (e.g., the Electrocon CAPE program) is used to perform the short-circuit analyses. DLC reviews the system using a base case scenario with all facilities in service to simulate normal operating conditions. DLC engineers seek operator input to identify operational issues or outage coordination scenarios that may not appear in the planning studies. DLC engineers perform the short-circuit analysis to determine whether circuit breakers have interrupting capability for faults that they will be expected to interrupt as well. Lastly, the use of transmission to replace antiquated system designs where substations rely solely on subtransmission support is considered. Opportunities to reduce inventory, maintenance, and problems created by load growth in areas of marginal capacity are analyzed when applicable. These criteria form the basis for the planning of DLC transmission facilities. These practices are not associated with NERC Reliability Standards; however, they demonstrate that transmission planning takes additional factors into account in order to ensure the reliability of the transmission system. Solutions to identify transmission system problems and concerns are determined only after applying the various planning criteria, evaluating all practical alternatives, and selecting the most cost effective solutions. Opportunities to simplify and/or standardize the transmission system are explored as well as opportunities to evaluate the intelligence and protection of the electric grid. DLC evaluates all solutions through its Capital Planning process. The resulting plan is treated as a dynamic document and subsequently reviewed, revised, expanded, and amended as additional issues and/or changes in existing issues arise. SECTION 3: TRANSMISSION CRITERIA In planning the transmission system, DLC believes more stringent reliability guidelines are appropriate to address the needs of a major city. The City of Pittsburgh and its major load centers supporting its urban population and its critical services and infrastructure utilized by the surrounding tri-state area, including a concentration of hospitals and universities, require reliability standards for transmission service more stringent than NERC criteria alone provides. The DLC transmission system relies on underground cables to supply the City of Pittsburgh. Some of these cables may share a common trench or a common oil return pipe. Outages of these common facilities are simulated and transmission solutions are developed so that no loss of load results. Underground cable outages could be long in duration and therefore, the remainder of the system should continue to operate 3

reliably and within its normal rating limits following such events. As a result, DLC will advocate transmission solutions so that no loss of load occurs following an N-2 contingency supporting the City of Pittsburgh. Additionally, DLC endeavors to diversify sources of supply, wherever possible, so that no one substation is the sole source of supply to DLC s load centers. DLC also takes into consideration existing major facilities that are obsolete and/or known to require high and expensive maintenance, options are evaluated to reduce or eliminate those costs. DLC s transmission system is also required to be reviewed and modified in order to reliably support and supply its distribution load. Transmission projects can arise from efforts to accommodate load growth, back-up capacity needs of the underlying electrical system, or to expand the intelligence of the electric grid. Where feasible and cost effective, and in order to ensure reliable service to transmission substations, the Transmission Planning department has also developed guidelines which stipulate that once a bulk power substation exceeds or is projected to exceed 100 MVA (approximately 22,000 customers), the station will require three (3) transmission sources. This practice ensures continuous reliable service during routine maintenance scenarios as well as single contingency events. 4

Document Control Issued By: Distribution: Senior Manager, Transmission Planning Senior Manager, Document Approval Prepared By Approved By Approval Signature E. Cook J. Harchick /signature on file/ Date 12/30/2016 Document Change/Revision History Version Prepared By Summary of Changes Date 0.0 E. Cook Initial creation 12/14/2016 5