LNG Houston, February 6-7 th, The case for developing a Floating LNG Receiving Terminal on the US East Coast

Similar documents
Trelleborg Marine Systems A Comprehensive Approach to FLNG Docking & Mooring Systems

Lars Odeskaug - TORP CEO

On Board Regasification for LNG Ships. 22 nd World Gas Conference WS 3-2 Tokyo 2003 Wayne Perry

LNG as a marine bunker fuel

SAMSUNG Energy Plant: All-in-One Solution for Floating Power Plants with Gas-fired Combined Cycle Gas Turbines

Development of Efficient, Environmentally Friendly and Flexible Shipboard Regasification Vessel

IMO future plans for regulation

LNG Import Facility Infrastructure Options

HACC/NACC SHIP CONFERENCE NEW YORK CITY - FEB. 5, Overview of the Liquified Natural Gas Market (LNG)

member of the TSAKOS GROUP of companies

RISKS ASSOCIATED WITH THE MARINE ASPECTS OF LNG FPSOs (FLOATING PRODUCTION, STORAGE AND OFFLOAD) UNITS. Braemar Engineering

FOR INDONESIA. P.T GoLNG Indonesia January 2015

MB05. RESPOND TO EMERGENCIES BASIC KNOWLEDGE OF EMERGENCY PROCEDURES, INCLUDING EMERGENCY SHUTDOWN

OLT Offshore LNG Toscana Alessandro Fino CEO

17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17)

MB05. RESPOND TO EMERGENCIES BASIC KNOWLEDGE OF EMERGENCY PROCEDURES, INCLUDING EMERGENCY SHUTDOWN

2017 LPG Loading Master & Certification (3 Days)

Marine Facilities for LNG Carrier Transfer Alternatives

LNG as fuel. OTMW-Module 5 Monday 23 rd of November 2015 University of Piraeus. Working together for a safer world

Developing and Implementing Floating <Title of Presentation>

Höegh LNG - The FSRU provider. Presentation at Marine Money Week 2017 Sveinung J.S. Støhle President & CEO

COMPLETING THE LNG VALUE CHAIN

Design Concept and Features of the Mitsubishi LNG-FPSO (Floating Production, Storage and Offloading Unit)

2019 LPG Loading Master & LPG Terminal Operations - 3 days

MARITIME LNG, REGULATION AND LOCAL DEVELOPMENT FRAMEWORK 25 November 2014 Andrew Morris, Director

6th Annual LNG Transport Handling & Storage 2016 Forum. FSRU as The Pivotal Point for Effective LNG Distribution

A Leader In Maritime Technology

LNG Systems for Marine Application. LNG Reliquefaction & LNG Regasification. Oil & Gas Systems

LNG in the United States

Marine Terminal Information Booklet

Cryogenic Expanders Operating on LNG-FPSO Vessels Hans E. Kimmel

LNG BUNKERING VESSELS AND CNG CARRIERS -Innovative solutions to improve sustainability- LNG/SHORE POWER Workshop TRIESTE 10 th of March 2016

LNG as a Bunker Fuel - LNGF (3 Days)

2019 LNG as a Bunker Fuel - LNGF (3 Days)

TRAINING CATALOGUE. Academy Korea SAFER, SMARTER, GREENER

CFD Based Simulation of LNG Release during Bunkering and Cargo Loading/Unloading Simultaneous Operations of a Containership

Loading Master for Oil, LNG/Gas & Petrochemical Terminals Apr 2019, Dubai 29 Sep - 03 Oct 2019, Dubai

Norwegian LNG Network

Floating offshore gas units

Why LNG? LNG is mainly produced for transportation purposes. More economical to transport gas as LNG compared to pipelines over long distances

B.C. TOWBOAT INDUSTRY CONFERENCE

Ship Transportation of Natural Gas

OTC FLNG Projects Economics Improvement Based on Reliability Assessment

GOLAR LNG: DELIVERING THE WORLD S FIRST FSRUs

ON LIQUEFIED NATURAL GAS (LNG 17) 17 th INTERNATIONAL CONFERENCE & EXHIBITION ON LIQUEFIED NATURAL GAS (LNG 17)

Floating storage and regasification barges

Swivel and Marine Systems. Swivel stack and fluid transfer systems for multiple applications

Innovative Financing Solutions for Emissions Compliance :

Environmental and Social Impact Assessment [ESIA] for Proposed Liquefied Natural Gas (LNG) Project at Tema in the Greater Accra Region of Ghana

Equipment and Solutions LNG / NG STARVAP TM REGASIFICATION APPLICATIONS

TRAINING CATALOGUE. Academy Korea SAFER, SMARTER, GREENER

SMALL LNG SOLUTIONS FOR INDONESIA

Liquefied Natural Gas Terminals Services and solutions

LNG Carriers Ship Life Extension. Ed Waryas. Lloyd s Register North America, Inc.

Classification of the Largest Ever Floating Storage Regasification Unit

PERP Program LNG Receiving Terminals New Report Alert

OMV VESSEL SELECTING CRITERIA (update 07/2017)

ABI6010 International Technical Certificate in Jetty and Terminal Operational Safety UNIT 1 TERMINAL MANAGEMENT, SAFETY AND SECURITY


Classification of FSRUs

Supply of natural gas to island economies

3 rd LNG SUPPLY, STORAGE AND TRANSPORTATION PHILLIPINES FORUM 2016 SMX AURA, MANILA

LNG market developments. 12 th of February 2015 Jonathan Raes development EXMAR LNG Infrastructure

This document is a preview generated by EVS

Avoiding the Disconnect

Chapter 23. Liquefied Natural Gas

UPDATE OF THE AUTHORISATION OF A LNG CARRIER TO UNLOAD AT THE LNG TERMINAL IN PANIGAGLIA PANIGAGLIA LNG TERMINAL

THE TRANSFER OF LNG IN OFFSHORE CONDITIONS. SAME SONG NEW SOUND

Developing efficient and reliable LNG infrastructure to support Indonesia s fast-growing energy demand

CHAPTER 3: GENERAL DESCRIPTION OF THE PROPOSED COEGA INTEGRATED POWER PROJECT

small to mid-scale LNG solutions LNG-TO-POWER

LNG R E F E R E N C E P R O J E C T S. Phone: +49(0) GOC Engineering GmbH Bachovenstr. 8; Sinzig, Germany

Petronet LNG Ltd., India. LNG Terminal Design- Major Design Considerations

Mapping of ISO standards on LNG

Risk Assessment of Operation of LNG Tankers. LNG Conference Copenhagen

Processing LNG Offshore: Maximizing Reliability, Performance & Safety. By Inga Bettina Waldmann at KANFA Aragon FLNG World Congress 28 th June 2016

LNG BUNKER CHECKLIST PORT OF ENERGY IN GOTHENBURG SHIP TO SHIP

Liquefied Natural Gas (LNG) Production and Markets. By: Jay Drexler, Dino Kasparis, and Curt Knight

OVER VIEW OF LNG SHIPPING SAFETY CONCERNS. Presentation by Capt. B.B. Sinha. The Shipping Corporation of India Ltd New Delhi.

LNG Bunkering and the risks involved in operations using LNG as fuels

North American LNG 2006

La tutela ambientale sui mari internazionali (Environmental Regulations of the Shipping Industry)

Loading Master for Oil, LNG/Gas and Petrochemical Terminals

HOUSTON OFFICE 2401 Fountain View, Suite 510 Houston, Texas Tel:

A New Contender Shuttle Tankers, Contractor Owner, Service as Needed

Fundamentals of LNG ISO Quality Standards

Fundamentals of LNG Nov 2018, Dubai. This course is Designed, Developed, and will be Delivered under ISO Quality Standards

TEMA LIQUEFIED NATURAL GAS PROJECT ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT

Pareto conference. 31 August 2011

LNG INFRASTRUCTURE AND INSTALLATIONS. George Pratikakis General Director Naval Architecture Progress (NAP)

Micro Motion Developments in HFO & LNG metering Per Stenhammar. Business Development Manager

Executive Summary. Engineering Report of the: Adaptation of jetties and LNG transfer facilities for loading of bunker vessels in Fos Tonkin

American Institute of Marine Underwriters

The Technical & Practical challenges of FLNG

Early Production in Deep Waters. Mats Rosengren, Frontier Drilling do Brasil Vitoria, Brazil

Freeport LNG Liquefaction Project

Positions Job Description Requirement

Woodfibre LNG Limited Response to SIGTTO LNG Ports and Risk Reduction Options

LNG Business In India

Port infrastructure for alternative fuels and maritime transport: the Livorno case

Transcription:

LNG 2002 Houston, February 6-7 th, 2002 The case for developing a Floating LNG Receiving Terminal on the US East Coast By Sveinung J. Stohle, Executive Vice President, Golar LNG Ltd.

Golar LNG s Strategy Be a shipowner that charters out LNG tonnage for various periods to the market in general. Be an LNG trader that buys LNG FOB from various sources either alone or with a partner, and sells gas to LNG customers all over the world. As part of the trading activity, Golar will consider investing in other parts of the LNG chain, like liquefaction or regasification capacity. Be an LNG development / construction company that invests in or develops new concepts like floating regas or liquefaction units.

Why a floating LNG regasification terminal for the US East Coast? A) Defined market need for additional regasification capacity B) Safety concerns regarding land based facilities, i.e. issues raised regarding operations at Everett and Cove Point after the September 11 th incident. C) Golar as experienced shipowner is comfortable with floating installations, and have direct experience of similar installations through the Frontline Group of companies. Golar press release Nov. 2001: Given the growth in the US gas market, and the difficulties that some companies have encountered in siting new landbased regas facilities in the US, which have only been aggravated by the recent tragic events in the US, we believe that floating regas units addresses all such concerns, since they are movable, and thus can be placed away from other installations and densely populated areas.

Agenda: 1. Project overview 2. Technical concept 3. Regulatory process 4. Market and economics 5. Project schedule and milestones

Project Overview Golar LNG Ltd., have conducted a feasibility study for the conversion of an existing Moss design LNG carrier into an offshore LNG receiving terminal. The ship used as basis for the study is one of Golar LNG s existing ships, the Golar Freeze, but it is important to underline that the scope of the evaluation is to develop a floating regas terminal concept, that can be applied to both exisitng and new build ships. The study not only examined the feasibility of converting the ship itself, but also site selection, the regulatory & permitting process, the time needed for implementation, as well as estimated project returns. Main results of the study: Although further work is required through detailed design and engineering, the conclusion of the study is that the project is both technically and economically attractive, and should therefore be carried further into the next Phase.

Project Concept To develop an offshore regasification terminal using an existing Moss design LNG carrier as the basis for the study The offshore regasification terminal would perform the following functions Receipt of LNG Storage of LNG Vaporisation Send out of gas into Gas Transmission System Construction Timeline c. 20 months from commencement of conversion design stage until start-up This naturally means that as compared to any land based facility, this project will have a very short development period

Project Concept The conversion of the LNG carrier involves: Prepare cargo and hull systems for c.20 years service Install LNG transfer system from LNG Carriers to Floating Terminal Install mooring systems for Terminal and for mooring LNG Carriers to Floating Terminal Construct vaporisation equipment and necessary utility systems for regasification and send-out Design and construct a gas evacuation system from the terminal to the Gas Transmission system. Estimated CAPEX for the vessel itself, conversion of vessel, related infrastructure costs, hook-up and commissioning c. US $195M

Agenda: 1. Project overview 2. Technical concept 1. Terminal Design 2. Site Evaluation 3. Regulatory process 4. Market and economics 5. Project schedule and milestones

LNG Terminal Design Philosophy Well Proven Technology in all Respects Inherently Safe High Reliability & Redundancy Simple Minimal Equipment Count Modular Easy to Maintain Applicable to existing or New Build vessels

LNG Terminal - Safety Standards Relevant Safety Standards DNV Rules for Classification of Ships (Liquefied Gas Carriers) IMO Gas Code (IGC 1993) Industry Standards (API, ASME, ISO, etc.) OCIMF - Standardization of Manifolds for LNG SIGGTO - Society of International Gas Tankers & Terminal Operators SOLAS - International Convention for Safety of Life at Sea ICLL - International Convention of Load Lines The safety standards for the LNG Terminal are derived from relevant industry, shipping, offshore and onshore standards.

LNG Terminal - Main Particulars Length Overall (excluding external turret) : 287.5 m Length Between Perpendiculars : 274.0 m Breadth Moulded : 42.4 m Depth to Main Deck Moulded : 25.0 m Draught, Design : 11.5 m Freeboard abt. : 12.5 m Number of LNG Tanks : 5 Total LNG Storage Volume : 125,000 m 3 Maximum Gas Sendout Capacity : 600 t/h ( 5.2 MMTPA ) Normal Gas Sendout Capacity : 350 t/h ( 3.0 MMTPA ) Installed Power Generation Capacity : c. 11 MW

LNG Terminal Overview & Design Specifications Design Basis Storage Capacity : 125,000 m 3 Nominal Regasification Capacity : 3.0 MMTPA Maximum Gas Sendout : 5.2 MMTPA Availability Per Year : 350 Days Water Depth : >20 m Design Life : 20 Years Pipeline Pressure : 80 Barg The LNG Terminal is a steel monohull with 5 Moss type LNG tanks with regasification plant in the forward end. The Terminal is moored with an external turret arrangement for free weather-vaning. The gas send-out line is arranged through the mooring system down to the seabed then directly to the shore manifold. The LNG tankers will be moored in a side by side configuration for efficient loading. Process and utility systems have been designed for simplicity and for ease of operation and maintenance, with simple subsystems and control loops.

LNG Terminal Overview & Design Specifications Mooring System

LNG Terminal Overview & Design Specifications Cargo Containment System

LNG Terminal Overview & Design Specifications Loading Arms

LNG Terminal Overview & Design Specifications Process Equipment

LNG Terminal Overview & Design Specifications Power Generation

LNG Terminal Overview & Design Specifications Side by Side Operations

LNG Terminal Overview & Design Specifications Motion Characteristics The roll motion may be minimized through the use of bilge keels and active heading control. Precise motion characteristics to be determined in the detailed engineering phase, at which time modification of existing bilge keels is to be addressed for motion dampening. A motion analysis of the terminal in operating wave conditions is to be performed during detailed design. Purpose - to define global motions of the terminal, displacements and accelerations of special points of interest.

LNG Terminal Overview & Design Specifications Safety Systems Equipment and pipework throughout the process and storage areas shall be designed with the following in mind: Leakage & Spillage Prevention Leakage Detection Cryogenic Temperature Protection Gas Leakage & Pipe Rupture Protection Fire Detection Fire & Explosion Protection Emergency Shut-Down System (ESD) - pneumatically operated and located at strategic positions (tank domes, loading arm area, process area). Release can also be activated from the control room on either ship or LNG Terminal. Two Levels of ESD are provided: Entire system shutdown. Triggers the loading arm release valves and mooring line hooks and initiates departure of the LNG carrier.

Agenda: 1. Project overview 2. Technical concept 1. Terminal Design 2. Site Evaluation 3. Regulatory process 4. Market and economics 5. Project schedule and milestones

Site Selection Process Site Comparison Assessment Methodology A comparison was conducted for a number of sites using consistent criteria as the comparison basis. This exercise was carried out in order to confirm that no site selection criteria would come within the Unacceptable Risk category. The main comparison criteria were as follows: 1. Proximity to Gas Consuming Region 2. Proximity to Existing Gas Transmission Systems 3. Site Safety 4. Site Security 5. Carrier Ingress / Egress

Section D East Coast U.S.A. Sites Considered Existing Land Based Facilities. Elba Elba Island Is.. Cove Cove Point. Everett Everett A number of sites along the entire East Coast have been considered, Conclusions The most attractive location for an offshore LNG terminal has been determined and chosen in light of the following. Access to Gas Transmission System and Markets No threat to public Large planned Power Generation capacity additions High Cost Gas region

Agenda: 1. Project overview 2. Technical concept 1. Terminal Design 2. Site Evaluation 3. Regulatory process 4. Market and economics 5. Project schedule and milestones

Critical Permitting Phases Process flow applicable to: Federal level State level Local level

Agenda: 1. Project overview 2. Technical concept 1. Terminal Design 2. Site Evaluation 3. Regulatory process 4. Market and economics 5. Project schedule and milestones

US Natural Gas Consumption (Historical and Forecast) LNG + Pipeline imports? 35000 30000 LNG Imports Pipeline Imports US Domestic Gas Forecasts Consumption (Bcf) 25000 20000 15000 10000 5000 0 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2005 2010 2015 2020 Sources: History: Energy Information Administration (EIA), International Energy Annual 1999, DOE/EIA-0219(99)

LNG + Pipeline Imports (Historical and Forecast) 7000 6000 5000 US Pipeline Imports US LNG Imports Forecasts Impor ts (Bcf) 4000 3000 2000 1000 0 1990 1991 1992 1993 1994 1995 1996 1997 1998 1999 2000 2005 2010 2015 2020 Sources: History: Energy Information Administration (EIA), International Energy Annual 1999, DOE/EIA-0219(99)

Project Economics Yr 1 (Q4) 2 3 4 5 6 No. of Cargoes 6 45 60 62 64 64 EBITDA 5.25 34.0 49.0 51.0 53.0 53.0 Cash flow after OPEX Deduction (US $M) 90 80 70 60 50 40 30 20 10 Revenue (after OPEX) v time 0 1 2 3 4 5 6 YEAR

Agenda: 1. Project overview 2. Technical concept 1. Terminal Design 2. Site Evaluation 3. Regulatory process 4. Market and economics 5. Project schedule and milestones

Strategic Milestones Phase 1: January 2002, completed Feasibility study, which shows that the project is attractive and should be carried to the next phase Phase 2: Q1 2002: Identify Project partners and negotiate JVA to set up separate terminal NewCo Identify potential Customers Negotiate Capacity Rights with customers on long-term basis Initiate Regulatory Process with relevant Agencies Prepare all relevant EIA s and commence permit application activities Initiate detailed Engineering and procurement Initiate project financing activities Negotiate cost of procuring vessel Prepare and issue tender for conversion with yards Phase 3: Q1 2003 Vessel conversion and equipment installation Phase 4: Q1 2004 Project start-up

Project Master Schedule TASK NAME Month 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 1. Regulatory Agency Co-ordination 1 Identi fy Rel evant Agencies 2 Conduct Appraisal meetings 3 Devel op Permitti ng Matrix 2. Permit Application Activitites 1 Prepare/Submit Initial Appl ication 2 Prepare/Submit Draft EIS 3 EIS Review 4 Prepare/Submit Final EIS 5 Fi nal EIS Approval 6 Fi nal Permits Received 3. Detailed Engineering Activities and Procurement 1 Conversion Desi gn 2 Pi peline W ork 3 Risk Assessment 4 Tenders/Bid Review 5 Issue Purchase Orders 6 M aterial Deli very 4. Facility Construction Activities 1 Vessel Conversion 2 Pi peline/connection 3 Regas Plant Construction 4 Hook-up/Testing/Commissioning 5 Start-up 5. Commercial Activities

Golar LNG Ltd.