Behavior of Reinforced Embankment on Soft Ground with and without Jet Grouted Soil-Cement Piles

Similar documents
Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

CIV E Geotechnical Engineering I Consolidation

EFFECT OF CEMENT CONTENT ON UNCONFINED COMPRESSIVE STRENGTH OF JAMSHORO SOIL

[Kouravand Bardpareh* et al., 5(6): July, 2016] ISSN: IC Value: 3.00 Impact Factor: 4.116

Jet Grouting to Increase Lateral Resistance of Pile Group in Soft Clay

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

Ground improvement support using Confined aggregate piers in soft soil. Brian Metcalfe, P.E. Director of Engineering Geopier Foundation Company

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong

BEHAVIOR AND SIMULATION OF DEEP CEMENT MIXING (DCM) AND STIFFENED DEEP CEMENT MIXING (SDCM) PILES UNDER FULL SCALE LOADING

Effect of Lime Stabilisation on the Strength and Microstructure of Clay

BEARING CAPACITY IMPROVEMENT USING MICROPILES A CASE STUDY

Suitability of Different Materials for Stone Column Construction

A Study of Loading Time Effect in Oedometer Test

5-20 FOUNDATION REPORT/GEOTECHNICAL DESIGN

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

INDIAN INSTITUTE OF TECHNOLOGY GANDHINAGAR Department of Civil Engineering Soil Mechanics Laboratory

A Case History of Super-Large Scale Bridge Pile Foundation in Soft Soil

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

Downloaded from Downloaded from /1

Lecture Notes. Elasticity, Shrinkage and Creep. Concrete Technology

Bi-Directional Static Load Testing of Driven Piles

Parametric Study on Geogrid-Reinforced Track Substructure

SECTION XXXXX AGGREGATE PIERS PART 1 - GENERAL

REPORT STATUS: DATE: Report n :

USE OF DIPP PILES FOR A NEW SUP BRIDGE IN WEST MELBOURNE

NPTEL Course GROUND IMPROVEMENT USING MICROPILES

PE Exam Review - Geotechnical

Properties of Concrete. Properties of Concrete. Properties of Concrete. Properties of Concrete. Properties of Concrete. Properties of Concrete

Design of Temporary Excavation and Lateral Support System for the DSD Sheung Wan Stormwater Pumping Station

SOIL PRESSURE IN EMBANKMENT STABILIZATIONS

INNOVATIVE SLOPE STABILISATION BY USING ISCHEBECK TITAN SOIL NAILS

Effect of Ground Subsidence on Load Sharing and Settlement of Raft and Piled Raft Foundations

4D grouting pressure model of a bored tunnel in 3D Tunnel

Mechanical behavior of crystalline materials - Stress Types and Tensile Behaviour

Improving Engineering Properties of Soft Soil Using Preloading and Prefabricated Vertical Drains

Study of Various Techniques for Improving Weak and Compressible Clay Soil under a High Earth Embankment

Void structure of Auckland residual soil using X-ray CT scanning

SCG INTERNATIONAL TRINIDAD AND TOBAGO LIMITED COUVA CHILDREN S HOSPITAL

3. CONSOLIDATION TESTS. 3.1 Constant Rate Strain (CRS) Consolidation Tests

THE STUDY OF t-z AND q-z CURVES ON BORED PILE BASED ON THE RESULTS OF INSTRUMENTED PILE LOAD TEST IN MEDIUM AND STIFF CLAYS

Stability of a Mechanically Stabilized Earth Wall

Chapter. Masonry Design

Design Illustrations on the Use of Soil Nails to Upgrade Loose Fill Slopes

Numerical Modeling of Slab-On-Grade Foundations

Static Response of Reinforced Soil Retaining Walls with Modular Block Facing

SITE INVESTIGATION Validation and Interpretation of data

SPECIFICATION FOR REINFORCED SOIL WALL

Application of Vibro Techniques for Infrastructure Projects in India

Geotech Services, X-18, MIDC, Hingna, Nagpur, Maharashtra. Discipline Mechanical Testing Issue Date

Investigations on Some Properties of no-fines Concrete

Experimental investigation of the use of CFRP grid for shear strengthening of RC beams

Properties of anchor grouts in a confined state

GROUND IMPROVEMENT SITE INVESTIGATON

TRAFFIC LOAD INDUCED PERMANENT DEFORMATION OF LOW ROAD EMBANKMENT ON SOFT SUBSOIL

Preloaded Road Embankments: monitoring and analysis of results

Total 30. Chapter 7 HARDENED CONCRETE

Chapter 11 Compressibility of Soil

Proceedings Tailings and Mine Waste 2011 Vancouver, BC, November 6 to 9, 2011

Application of Stress-Wave Theory to Piles

ANALYSIS & DESIGN OF 44 METER M.S.E. (MECHANICALLY STABILIZED EARTH) WALL BY USING PLAXIS 8.2

Module 4:Preloading and vertical drains Lecture 10:Introduction to preloading and vertical drains. The Lecture Contains:

AVOIDING EXCESSIVE DISPLACEMENTS: A NEW DESIGN APPROACH FOR RETAINING WALLS

RETAINING WALL SYSTEM. ViaWall. ViaWall A. ViaWall B. ViaBlock

Lab Exercise #2: Tension Testing (Uniaxial Stress)

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

EFFECT OF THE GRID-SHAPED STABILIZED GROUND IMPROVEMENT TO LIQUEFIABLE GROUND

MSE Walls Problems and Solutions

1. INTRODUCTION. (a) Sand/ Fabric-coated (b) Sand-coated deformed. (c) Helical wrapped/ribbed Fig.1 FRP anchors with different outer surfaces

Spectrum of Axles Approach

In-plane testing of precast concrete wall panels with grouted sleeve

Geotechnical Engineering Software GEO5

Subsurface Investigations PDCA Professor s Driven Pile Institute. Loren R. Anderson Utah State University June 25, 2015

SMU 2113 ENGINEERING SCIENCE. PART 1 Introduction to Mechanics of Materials and Structures

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM

Compressive Strength of Cement Stabilized Soils. A New Statistical Model

Fundamentals of Concrete

Ground Improvement for Increasing Lateral Pile Group Resistance

Mechanical behavior of crystalline materials- Comprehensive Behaviour

PRECAST FIBRE REINFORCED CONCRETE ELEMENT OF RETAINING WALL

Case study of deep excavation in existing underground structure of three-story basement and diaphragm wall

A DSM WALL FOR EXCAVATION SUPPORT

APPENDIX B ABC STRUCTURES DESIGN GUIDE

Ground Improvement Techniques: Dynamic Compaction Martin Larisch & Tim Pervan

4D grouting pressure model PLAXIS

Case Studies on Soil Nailed Retaining Systems for Deep Excavations

Scientific Seminar Design of Steel and Timber Structures SPbU, May 21, 2015

THE OPTIMUM LOCATION OF REINFORCEMENT EMBANKMENT USING 3D PLAXIS SOFTWARE

EVALUATION OF LAMINATED HOLLOW CIRCULAR ELASTOMERIC RUBBER BEARING

A Case Study: Foundation Design in Liquefiable Site

The Mechanical Properties of High Strength Concrete for Box Girder Bridge Deck in Malaysia

Example of the Unified Design procedure for use in the September 8, 2014, short course on in Brazil

Design Methods of Elements from Cross-Laminated Timber Subjected to Flexure

ODOT Design & Construction Requirements for MSE Walls

Performance of Mechanically Stabilized Earth walls over compressible soils

Better ZSOIL, Better Geotechnical Analysis

IMPROVEMENT OF LOAD CARRYING CAPACITY OF BC SOIL USING REINFORCED STONE COLUMN

Solution for the conclusion of the Mackenzie access in Sao Paulo Line 4 Subway.

NON-LINEAR FEM ANALYSIS FOR CES SHEAR WALLS

VOL. 11, NO. 16, AUGUST 2016 ISSN ARPN Journal of Engineering and Applied Sciences

Influence of unloading soil modulus on horizontal deformation of diaphragm wall

Transcription:

Behavior of Reinforced Embankment on Soft Ground with and without Jet Grouted Soil-Cement Piles by 1 Dennes T. Bergado and 2 Glen A. Lorenzo 1 Professor and 2 Doctoral Candidate, respectively Geotechnical Engineering Program Asian Institute of Technology, Bangkok, THAILAND 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 1

2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 2

Soil Profile along Bangkok-Chonburi SOFT CLAY MEDIUM CLAY STIFF CLAY 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 3

Failure of Embankment on Soft Ground 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 4

Problem of Bridge Approach on Subsiding Ground 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 5

Basal Reinforced Piled Embankments Transition between non-piled and piled foundations 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 6

Some Applications of Soil-Cement Piles (DJM Research Group, 1984) Prevent slope failures and settlement of embankment and structure Increase stability of slopes Increase horizontal resistance of structures Reduce settlement and prevent slope failures of bridge s abutments 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 7

Advantages of Soil-Cement Stabilization It can significantly increase the strength and reduce the compressibility of soil. Soil improvement can be attained at optimum period of only 1 month. Cement is abundant and cheaper in Asia. Cement is effective than lime. 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 8

Full-Scale Embankment on DMM Piles (Jet grouting) THE SITE 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 9

Soil Profile at the Site (Jet grouted piles) 0 Unit weight (kn/m 3 ) 12 14 16 18 20 1 2 Clay backfill Weathered clay 3 Depth (m) 4 5 6 7 Soft clay 8 9 10 Medium stiff clay Unit weight G s PL w N LL P' o P' max 11 2.6 2.65 2.7 2.75 2.8 G s 20 40 60 80 100120 PL, w N, LL 0 20 40 60 80 Corrected S u (kpa) from Vane Sheat Test 0 50 100 150 200 P' o and P' max (kpa) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 10

Jet Grouting Machine Jet pressure = 20 MPa 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 11

Sequence of Soil-Cement Piles Installation (1) Positioning (2) Penetration (Remolding) (3) Completion of (4) Feeding of penetration cementing agent (withdrawal) (5) Completion 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 12

Plan View and Layout of DMM Piles 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 13

Front Elevation and DMM Pile Penetration 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 14

Section thru Center Line 17m 6 m 6 m 6m 14.5m 2m 1.5m 4 m 3m PIEZOMETERS REFERENCE 6m HEXAGONAL WIRE MESH REINFORCEMENT VERTICAL PRE-CAST CONCRETE FACING 9 m 6 m PIEZOMETER BOARD 3 m 3 m P1-P5 P1-P5 S5/S1 S6/S2 S7/S3 S8/S4 P6 P7 P8 DS1 DS2 DS3 P6 P7 P8 DS6 DS7 DS8 DUMMY REINFORCEMENT FOR FIELD PULL-OUT TEST EXTENSOMETER WIRES WELL COMPACTED AYUTHAYA SAND BACKFILL EXTENSOMETER SUPPORT 1.5m CLAY BACKFILL 1m WEATHERED CRUST SOFT CLAY SETTLEMENT REFERENCE 8m P1-P5 P6 P7 P8 NOTE: PLEASE SEE THE PLAN VIEW FOR DETAILS OF THE LOCATION OF OTHER INTRUMENTATION POINTS 15 m depth 6 @ 1.5m = 9m 2m 1m 0.6 m DIAMETER SOIL- CEMENT PILES AT 1.5 m SPACING IN SQUARE PATTERN MEDIUM STIFF CLAY 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 15

Instrumentations and Laying of Reinforcements 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 16

Reinforcement Connection 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 17

Hexagonal Wire Mesh Width Length Basic hexagonal wire mesh reinforcement geometry Steel core wire Zinc Coating Steel core wire PVC Coating Zinc Coating Cross section of different types of hexagonal wire mesh reinforcement 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 18

Deformation and Necking Phenomenon of Hexagonal Wire Mesh Reinforcement during Pullout (Conventional pullout test) Hexagonal cell in the centerline of the reinforcement Hexagonal cell at the edge of the reinforcement 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 19

Modified Pullout Test Set Up (In-soil Pullout Test) Boundary of Large Scale Pullout Box Apparatus Pullout Direction Outer Clamps Steel Rods In-soil Clamps 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 20

Pullout Test Apparatus (Maccaferri, 1997) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 21

70 Maximum Pullout Resistance in Various Pullout Test Programs Maximum pullout load (kn/m) 60 50 40 30 20 10 0 Tult = 44.8 kn/m (in-air tensile test) Maccaferri (1997) Kongkitkul (2001), L = 0.70 m Kabiling (1997), L = 1.10 m Kabiling (1997), L = 0.90 m Kabiling (1997), L = 0.70 m 0 20 40 60 80 100 120 140 160 Applied normal pressure (kpa) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 22

The Finished 6m High Reinforced Embankment 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 23

Surface Settlement (hollow symbol= on clay ; solid = on pile ) Fill height (m) Settlement (mm) 8 6 4 2 0 0 50 100 150 200 250 300 350 400 0 60 120 180 240 300 360 420 Time (Days) 0 60 120 180 240 300 360 420 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 24 S1 S5 S10 S14 S2 S6 S11 S15 S p (ave.) =325mm (improved ground) S p =1200mm (Untreated ground)

Differential Settlement between Soil and Pile (hollow symbol= on clay ; solid = on pile ) Settlement (mm) 0 50 100 150 200 250 300 350 400 Time (Days) 0 60 120 180 240 300 360 420 S1 S5 S10 S14 S2 S6 S11 S15 click 25mm 60mm 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 25

Horizontal Inclinometer H1 (on pile) Distance (m) 0 2 4 6 8 10 12 14 16 18 20 22 0 50 100 150 Settlement (mm) 200 250 300 350 400 Started on Jan 28 Ended on Feb 12 29.Jan 05.Feb 09.Feb 12.Feb 13.Feb 15.Feb 23.Feb 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 26

Horizontal Inclinometer H2 (on clay) Distance (m) 0 2 4 6 8 10 12 14 16 18 20 22 0 50 100 150 Settlement (mm) 200 250 300 350 400 29.Jan 05.Feb 09.Feb 12.Feb 13.Feb 15.Feb 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 27

Predicted vs. Measured Settlement Fill ht. (m) Settlement (mm) 8 6 4 2 0 0 50 100 150 200 250 300 350 400 450 Time (days) 0 50 100 150 200 250 300 350 400 450 500 Field monitoring, [S2 at the Center], on pile Field monitoring, [S6 at the Center], on ground Untreated ground (1D method) Lorenzo and Bergado (2003), on pile Lorenzo and Bergado (2003), on clay Asaoka's method on clay 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 28

Steel-Grid Reinforced Embankment on Unimproved Ground Soil Profile at the Site 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 29

Steel-Grid MSE Embankment on Unimproved Soft Foundation 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 30

Front Elevation (unimproved foundation) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 31

Section View (unimproved foundation) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 32

Pullout Friction Resistance of Steel Grid 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 33

Pullout Bearing Resistance of Steel Grid 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 34

Comparison of Lateral Displacement Profiles (with and without jet grouted piles) Wall face Depth (m) 6 5 4 3 2 1 0-1 -2-3 -4-5 -6-7 -8-9 -10-11 -12-13 -14 Lateral movement (mm) 0 100 200 300 400 500 Backfill/ Weathered clay Soft clay Medium to Stiff Clay With jet grouted piles (TE2), after construction With jet grouted piles (TE2), 7 months after const'n No improvement (TE1), after construction No improvement (TE1), 7 months after const'n 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 35

Comparison of Surface Settlements (with and without jet grouted piles) Surface settlement (mm) 0 100 200 300 400 500 600 700 800 900 1000 1100 1200 1300 1400 1500 FACE EMBANKMENT TOE With jet grouted piles (TE2), after construction With jet grouted piles (TE2), 1 year after const'n No improvement (TE1), after construction No improvement (TE1), 1 year after const'n 0 5 10 15 20 Horizontal distance (m) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 36

Settlement Reduction and Rate of Settlement 0.00 0 300 600 900 1200-0.20 Settlement (m) -0.40-0.60-0.80-1.00-1.20 Finite element Finite element SS6 Untreated, 1-D conventional Sp =1200mm (Untreated ground) Time (Days) Click to location of SS6 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 37

Excess pore pressure (kpa) Faster Rate of Consolidation of Improved Ground 40 35 30 25 20 15 10 5 0-5 Outside the improved ground (35% dissipated) p1/6 p2/6 p3/6 p4/6 p5/6 p6/6 p7/6 p8/6 0 10 20 30 40 50 60 Time (days) OARD click 3 m 3 m P1-P5 P1-P5 P1-P5 S5/S1 S6/S2 S7/S3 S8/S4 P6 P7 P8 DS1 DS2 DS3 P6 P7 P8 DS6 DS7 DS8 P6 P7 P8 Within the improved ground (55% dissipated) Excess Pore Pressure in Clay at 6m Depth 8 7 6 5 4 3 2 1 0 Height (m) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 38

One-Dimensional and Unconfined Compression of Cement-Admixed Clay of Higher Water Content 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 39

Properties of the Base Clay Bangkok Clay 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 40

Definition of higher water content clay: A clay that has a natural water content equal to or greater than its liquid limit (LL), or a clay that has been remolded to water content equal to or greater than its LL. 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 41

Conceptual Diagram of Cement Stabilized Clay at Higher Water Content Prolong curing Better dispersion of cementing agents/ions within the pores. It is expected to yield higher strength. Higher permeability and good drainage ability. 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 42

Laboratory Test Remolding the base clay at clay water contents from liquid limit (LL) to 2LL. Water/cement ratio of slurry of 0.6. Curing the specimens directly in the oedometer rings for oedometer tests, and in the PVC mold for UC tests. Curing the specimen in the humid room within 7, 14 and 28 days; only 28 days for oedometer tests. 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 43

Void ratio, e 5.5 5.0 4.5 4.0 3.5 3.0 2.5 2.0 1.5 Remolding Symbol water content (%) 250 200 160 130 100 Undisturbed Intrinsic Generated post yield compression line Void ratio, e 5.5 5.0 4.5 4.0 3.5 3.0 2.5 2.0 1.5 1.0 1.0 10 100 1000 10000 Effective stress, σ v ' (kpa) a) 5% Cement content; 130% to 200% remolding water content 10 100 1000 10000 Effective stress, σ v ' (kpa) b) 10% Cement content; 100% to 250% remolding water content Post-Yield Compression Lines (5% and 10% cement) (measured values vs. predicted values) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 44

Void ratio, e 5.5 5.0 4.5 4.0 3.5 3.0 2.5 2.0 1.5 1.0 Remolding ymbol water content (%) 250 200 160 130 100 Undisturbed Intrinsic Generated post yield compression line 10 100 1000 10000 Effective stress, σ v ' (kpa) c) 15% Cement content; 100% to 200% remolding water content Post-Yield Compression Lines (15% cement) (measured values vs. predicted values) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 45

Modified void index, I vnc 3.0 2.5 2.0 1.5 1.0 0.5 0.0-0.5-1.0 Symbol Cement content 15% 10% 8% 5% 3% Intrinsic Fitting curve 10 100 1000 10000 Effective stress, σ v ' (kpa) Normalized Post-Yield Compression Curves Normalizing parameter I vnc = (e t -e t,1600 )/C * ct where: e t = void ratio of treated sample at certain effective stress, σ v ; e t1600 = void ratio of treated sample at effective stress of 1600 kpa for certain cement content; C * ct = mean slope of the postyield compression line for certain cement content. Fitted curve I vnc = -0.06(logσ' v ) 3 +0.59(logσ' v ) 2 2.76(logσ v ) + 4.74; in similar form of ICL of Burland (1990). 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 46

Schematic Diagram for Predicting Compression Line of Cement Treated Clay (curing time: at least one month) Void ratio, e 5.5 5.0 4.5 4.0 3.5 3.0 2.5 2.0 1.5 1.0 e ot,1 e ot,2 σ vy,1 σ vy,2 Post-yield compression line for particular cement content 10 100 1000 10000 Effective stress, σ v ' (kpa) Void ratio after curing, e ot e ot = initial void ratio after curing; σ vy = predicted vertical yield stress. Swelling index 5.5 5.0 4.5 4.0 3.5 3.0 2.5 2.0 1.5 1.0 0.5 Increasing A w 20% 15% 10% 5% Cement content, A w 10 100 1000 10000 Vertical yield stress, σ vy (kpa) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 47

Coefficient of Permeability from Oedometer Test of Untreated and Cement-Treated Soft Bangkok Clay Void ratio, e 6.0 5.5 5.0 4.5 4.0 3.5 3.0 2.5 2.0 1.5 1.0 0.5 Symbol Cement content 15% 10% 8% 5% Intrinsic Undisturbed C=2.5 e = 1.2Log(k) + 2.0 e = 1.2Log(k) + C Note: k x 10-10 m/s C=1.5 0.01 0.1 1 10 100 1000 Permeability, k v (x10-10 m/s) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 48

Unconfined Compression Tests UC strength, q u (kpa) 1200 1100 1000 900 800 700 600 500 400 300 200 100 0 28 days curing Note: * = remolding water content + = cement content 100-20 100-15 100-10 100-5 130-20 130-15 130-10 130-5 160-20 160-15 160-10 160-5 Base clay 0.0 0.5 1.0 1.5 2.0 2.5 UC strength, q u (kpa) 1200 1100 1000 900 800 700 600 500 400 300 200 100 0 14 days curing 0 0.5 1 1.5 2 2.5 Axial strain (%) Axial strain (%) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 49

Unconfined Compression Tests (cont d) UC strength, q u (kpa) 1000 900 800 700 600 500 400 300 200 100 0 Curing 28 days 14 days 7 days UC strength, q u (kpa) 1000 100 10 q = u B A wc/ A w Curing 28 days 14 days 7 days 2 6 10 14 18 22 26 30 34 2 6 10 14 18 22 26 30 34 Clay water/cement content ratio, wc/a w Clay water/cement content ratio, wc/a w q = u B A wc/ A w A = f (time, clay type, etc.) = intercept B = f (clay type, etc.) = slope 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 50

Modulus of Elasticity versus UC Strength (Laboratory mix cement-treated Bangkok clay) 200 180 Initial tangent modulus, E i Secant modulus, E 50 E i = 175q u R 2 = 0.985 Modulus of deformation E i, E 50 (MPa) 160 140 120 100 80 60 40 20 E 50 = 147q u R 2 = 0.986 E i = 115q u Horpibulsok (2001) E i = 121q u Win (1997) E 50 = 114q u Win (1997) 0 150 300 450 600 750 900 1050 Unconfined compressive strength, q u (kpa) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 51

Vertical Yield Stress σ vy versus UC Strength q u of Cement-Treated Bangkok Clay and Ariake Clay Vertical yield stress, σ vy ' (kpa) 2200 2000 1800 1600 1400 1200 1000 800 600 400 200 0 σ vy = 1.4q u (kpa) Bangkok clay, 28 days curing Bergado and Lorenzo (2002) σ vy = 1.55q u (kpa) Bangkok clay 14 and 28 days curing This study σ vy = 1.27q u (kpa) Kamon and Bergado (1991) Ariake clay Test data, 28 days Test data, 14 days 0 200 400 600 800 10001200 Unconfined compressive strength, q u (kpa) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 52

Optimum Mixing Clay Water Content Optimum mixing clay water content (w opt ) is hereinafter defined as the total clay water content (or mixing clay water content) of the clay-cement paste that would give the highest possible improvement in strength of cured cement-admixed clay. 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 53

Effect of Mixing Clay Water Content on Unconfined Compression (10% Cement Content) Unconfined compressive strength, q u (kpa) 1200 1100 1000 900 800 700 600 500 400 300 200 100 0 28 days curing Total clay water content 105% 135% 165% 80% 0 1 2 3 4 5 Axial strain (%) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 54

Effect of Mixing Clay Water Content on 1-Dimensional Compression (10% Cement) Void ratio, e 4.0 3.5 3.0 2.5 2.0 1.5 Totalclay water content 165% 135% 105% 80% 1.0 10 100 1000 10000 Effective stress, σ v ' (kpa) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 55

Typical Strength Curve of Cement-Admixed Clay (to get the optimum mixing clay water content) Unconfined compression strength, q u (kpa) 800 700 600 500 400 300 200 100 cw=ll cw=1.15ll 60 80 100 120 140 160 180 Total clay water content, cw (%) 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 56

CONCLUSIONS 1) Two full-scale reinforced embankments were constructed on soft ground. The first embankment (TE1), 5.7m high and reinforced with steel-grids, was constructed on unimproved ground. The second embankment (TE2), 6.0m high reinforced with hexagonal wire reinforcement, was constructed on jet grouted soil-cement piles improved ground. 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 57

CONCLUSIONS (cont d) 2) After embankment construction, the maximum lateral movements in the unimproved soft foundation soil was 130mm, while that of improved foundation soil was only 5mm. Therefore, the installation of soil-cement piles has effected significant increase in the lateral resistance and the bearing capacity of the foundation soil. 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 58

CONCLUSIONS (cont d) 3) One year after embankment construction, the maximum surface settlement of TE1 was 1.0m while that of TE2 was only 0.325m. Therefore, the soil-cement pile installation in the soft foundation has also effectively reduced the settlement by at least 70%. 4) Also, one year after construction the unimproved foundation was far from its 90% consolidation, but the soil-cement piles improved ground was already close to its 90% consolidation. 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 59

CONCLUSIONS (cont d) 5) The maximum lateral movement of the reinforced embankment on soil-cement piles improved ground was lower than that of reinforced embankment on unimproved foundation. 6) The existence of optimum mixing clay water content (w opt ) has been proven from the results of UC tests and oedometer tests of cement-admixed clay. 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 60

CONCLUSIONS (cont d) 7) w opt was found to fall within liquid limit (LL) up to 1.15LL of the base clay. 8) At optimum mixing clay water content, only 10% cement content by weight is needed instead of 17% in the conventional method to obtain a UC strength of 650 kpa, with consequent 40% cost reduction. 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 61

Layout of Settlement Plates 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 62

Location of Piezometers EZOMETER OARD S5/S1 S6/S2 S7/S3 S8/S4 3 m 3 m P6 P7 P8 P1-P5 DS1 DS2 DS3 P6 P7 P8 P1-P5 DS6 DS7 DS8 P1-P5 THE AILS P6 P7 P8 6 @ 1.5m = 9m 2m 1m 2004/1/24 Behavior of Reinforced Embankment on Soft Ground... 63