HEALTH AND SAFETY MANUAL

Similar documents
Safety Policy and Procedure

Reliant Holdings Ltd Safety Management System

SECTION CAST-IN-PLACE CONCRETE

"CAUGHT-IN/BETWEEN HAZARDS IN CONSTRUCTION ENVIRONMENTS"

Contents. Before you begin. Introduction: Carrying out concreting to simple forms 1. Element 1: Planning and preparing 3

CAL/OSHA ELECTRICAL HIGH VOLTAGE

SECTION RIGID PAVEMENT. 1. Portland Cement Concrete (PCC) pavement. 2. Section Aggregate Base Course.

ACCIDENT PREVENTION PROGRAM HAZARD ANALYSIS SAFETY HEIRARCHY

SCAFFOLDS Revision No: 3

National Craft Assessment and Certification Program S P E C I F I C A T I O N S

SECTION mil thickness COLD FLUID-APPLIED WATERPROOFING

DIVISION 03 CONCRETE SPECIFICATION : FORMS AND FORMWORK

Use of Locally Fabricated or Modified Equipment. DROPS Forum July

September 1, 2003 CONCRETE MANUAL SPECIAL TYPES OF CONCRETE

TECHNICAL SPECIAL PROVISION FOR CONCRETE REPAIRS. Financial Project ID , &

Scaffolding and Raised Platforms

CELCORE CELLULAR INSULATING CONCRETE SPECIFICATION FOR RETROFIT PLACEMENT OVER EXISTING ROOF MEMBRANES

References. EM , Sections 22 OSHA 29CFR (Subpart L ) UFGS [Latest] ANSI A

+/0'-/12!"&21'1/345$1.1/3!6#''-7-! 8#9!:!;<;=!

Introductory Chapter

SCAFFOLDING PROCEDURE

1.02 STANDARD REFERENCES: The following standard specifications shall apply to the Work of this Section as indicated:

MATERIAL HANDLING, STORAGE, AND DISPOSAL

A. Drawings and general provisions of the contract, including General and Supplementary Conditions, apply to this section.

UNIFIED FACILITIES GUIDE SPECIFICATIONS

CF50/100 KW TURBINE ACCESS ROAD, CRANE PLATFORM, CONCRETE, AND LIFTING SPECIFICATIONS C&F GREEN ENERGY REVISION PREPARED BY APPROVED BY DATE

Section Safety Section Cleanup. None Required

STRUCTURAL MASONRY SPECIAL INSPECTOR. Study Guide

WORKING AT HEIGHT PROCEDURE

Excavation Safety Program

EM385 Construction Safety and Health Certification Course Section 14 Material Handling, Storage, and Disposal

***************************************************************************************************************

Date Prepared: Location: Time: Approximate Temperature (degrees F): Weather Conditions: Project Name:

SECTION STAY-IN-PLACE INSULATED CONCRETE FORMING SYSTEM

Section Subparts T. Cleveland State University Work Zone Safety and Efficiency Transportation Center. Demolition

A. Submittal Procedures: See Article 13 of the General Conditions.

SECTION A1 EXCAVATION AND BACKFILL GENERAL

Section Fluid Applied Waterproofing

11. Construction processes and materials Power House Maintenance Building Fuel Treatment Building...

Metal or Woodworking Shop Policy

STANDARD PRACTICE INSTRUCTION

Strong-Seal Sealant Specification, a permanent method of sealing the interior of the chimney and casting in manholes and catch basins.

Surface Repair Using Form-and-Pour Techniques

Preventing Electrocutions:

SECTION EXCAVATING, BACKFILLING, AND COMPACTION FOR UTILITIES

SECTION QUALITY CONTROL - CONSTRUCTION MANAGER EDITION

TYPICAL INSTALLATION INSTRUCTIONS

G. Shop drawing of wall with all dimensions, details, and finishes. Drawings must include post foundations.

CONSULTING OFFICE OF MORRIS S. FARKAS PROFESSIONAL SAFETY ENGINEER

Environmental, Health and Safety Policy for Contractors

SECTION ORNAMENTAL ALUMINUM RAILING. ** NOTE TO SPECIFIER ** Superior Aluminum Products, Inc.; Ornamental aluminum railing products.

SECTION CHAIN-LINK FENCES AND GATES 02821/1

Scissor Lift Safety for Clients and Employees or ARS

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories.

Sawmill Safety & Health. Presented By: John Boysen Safety Consultant OHSA Consultation Program

Construction Specification for Utility Adjustments

Demolition Safety!!!!

MS-2A LINER SPECIFICATIONS: for STRUCTURAL REPAIR and SEALING of MANHOLES

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 7

STANDARD SPECIFICATION FOR CRIBLOCK CONCRETE CRIBWALL

A. ASTM C 150 Standard Specification for Portland Cement. B. ASTM C 595 Standard Specification for Blended Hydraulic Cements.

Scaffolding Procedures

BP OIL -- TOLEDO REFINERY

Surface Repair Using Form-and- Pour Techniques

SEPTIC TANK CONSTRUCTION GUIDELINES

YOUR LITE-DECK SECTIONS

Residential Building Inspections

The superior self-compacting concrete

(Condensed from National Electric Code)

The Control of Hazardous Energy (Lockout/Tagout)

SUPPLEMENTAL TECHNICAL SPECIFICATION

CONTINUOUS FLIGHT AUGER (CFA) PILES QC/QA PROCEDURES. Preferred QC/QA Procedures

POLYMER CONCRETE 100 EPOXY POLYMER CONCRETE DILUTE ACIDS RESISTANCE

SECTION SITE CONCRETE

SPECIAL SPECIFICATION 4900 Sacrificial Cathodic Protection Pile Jacket

SPECIFICATIONS FOR CAST-IN-PLACE CONCRETE SLAB DUNN COUNTY TRANSFER STATION MENOMONIE, WISCONSIN

!!! Sample Written Program For Your Company!!! Excavation Safety. 29 CFR 1926, Subpart P !!!!! Provided By:

DIVISION 3 HEAVY DUTY CONCRETE FLOOR TOPPING SECTION 03340

BNSF RAILWAY COMPANY

TRENCH SAFETY TRAINING

CUSP Base Exams and T&D Endorsement Exam Sample Questions and Format

SECTION ARCHITECTURAL CAST STONE

DEPAUL UNIVERSITY. Scaffolding Program. Environmental Health & Safety. April 2017

CW 3615 RIPRAP TABLE OF CONTENTS

Walking/Working Surfaces

Uwall UNIVERSAL CONSTRUCTION MANUAL

SECOND REVISED PROPOSED REGULATION OF THE ADMINISTRATOR OF THE DIVISION OF INDUSTRIAL RELATIONS OF THE DEPARTMENT OF BUSINESS AND INDUSTRY

SECTION STRUCTURAL PRECAST HOLLOW CORE SLABS

Walking & Working Surfaces / Back Safety and Ergonomics

Construction OS&H Vertical movement

Attachment A-Flagpole(s) Specifications

CONCRETE FORMWORK CHECKLIST AT SITE

SECTION COLD APPLIED RUBBER MODIFIED ASPHALT WATERPROOFING

Shoring and Reshoring Fundamentals

CONTROL OF HAZARDOUS ENERGY LOCKOUT/TAGOUT PROCEDURES (Revised 8/05)

By CTS Cement Manufacturing Corp.

1. Cast-in-place concrete is specified in Section

ADA APPROVED SURFACE APPLIED DETECTABLE WARNING SYSTEM

Transcription:

HEALTH AND SAFETY MANUAL Title: Concrete and Masonry Construction Approved by: Greg Savoy Rev. 1/1/08 1 Purpose/Scope: This program sets forth safety requirements and hazard controls for concrete or grout mix and pour operations. This program applies to all Company concrete or masonry operations. When work is performed on a non-owned or operated site, the operator s program shall take precedence, however, this document covers Company employees and contractors and shall be used on owned premises, or when an operator s program doesn t exist or is less stringent. 2 Definitions/Responsibilities: 2.1 Definitions 2.1.1 Shoring - a supporting member that resists a compressive force imposed by a load. 2.1.2 Forms - the total system of support for freshly placed or partially cured concrete, including the mold or sheeting that is in contact with the concrete as well as all supporting members including shores, hardware, braces, and all related hardware. 2.2 Responsibilities: 2.2.1 Management: Ensure all equipment is routinely serviced and maintained in a safe condition. Conduct periodic on-site inspection of operations. Provide operation and safety training for affected employees. 2.2.2 Supervisors Ensure access to operation areas are controlled. Provide continuous safety observation and control. Provide immediate corrective training for all unsafe acts. Conduct pre-pour inspections.

3 Requirements: 2.2.3 Employees Follow all safety and operational procedures. Immediately notify supervisor of all unsafe conditions. 3.1 Shoring 3.1.1 All Shoring equipment shall be inspected prior to erection to determine that the equipment meets the requirements specified in the formwork drawings. 3.1.2 Shoring equipment found to be damaged shall not be used for shoring. 3.1.3 Erected shoring equipment shall be inspected immediately prior to, during, and immediately after concrete/grout placement. 3.1.4 Shoring equipment that is found to be damaged or weakened after erection shall be immediately reinforced or replaced. 3.1.5 The material used for shoring shall be sound, rigid, and capable of carrying the maximum intended load. 3.2 Formwork: 3.2.1 Formwork shall be designed, fabricated, erected, supported, braced and maintained so that it will be capable of supporting without failure all vertical and lateral loads that may reasonably be anticipated to be applied to the formwork. 3.3 Reinforcing Steel: 3.3.1 Reinforcing steel for structures shall be adequately supported to prevent overturning and to prevent collapse. 3.3.2 Measures shall be taken to prevent unrolled wire mesh from recoiling. Such measures may include, but are not limited to, securing each end of the roll or turning over the roll. 3.3.3 All protruding reinforcing steel, onto and into which employees could fall, shall be guarded to eliminate the hazard of impalement. 3.4 Removal of Formwork: 3.4.1 Forms and shores shall not be removed until it has been determined that the concrete/grout has gained sufficient strength to support its weight and superimposed loads. Such determination shall be based on compliance with one of the following: The plans and specifications stipulate conditions for removal of forms and shores, and such conditions have been followed. The concrete/grout has been properly tested with an appropriate ASTM standard test method designed to indicate the concrete

compressive strength, and the test results indicate that the concrete has gained sufficient strength to support its weight and superimposed loads. Shoring shall not be removed until the concrete/grout being supported has attained adequate strength to support its weight and all loads in placed upon it. 3.5 Cement Pumping Operations: 3.5.1 When the initial plans are made to pump cement to the forms the supervisor should contact the company contracted to perform the cement pour and set up a meeting at the site. Explain and show the representative what is planned and what our expectations of their part of the job entail (i.e. set-up of equipment, location of the pour, and piping/hose requirements). 3.5.2 The pump discharge line shall be steel pipe with the exception of a hose whip at the end of the piping. The hose whip must remain as short as possible. 3.5.3 Protective material shall be placed on the client s floor/decking in order to protect from spillage. 3.5.4 A pump discharge line composed of pipe with a hose whip shall be used to lesson the effects of pressure changes in the piping due to clogs forming and releasing. 3.5.5 Visually inspect the inside of the hose whip for damages or frayed hoses. The condition of the hose is important to ensure good flow. 3.5.6 Use 45-degree fittings instead of 90-degree fittings. Locate the pump so the least amount of turns is created in the piping and hose run. This will help the flow of cement through the hose and help prevent clogs. 3.5.7 Workers shall be briefed on the hazards of pumping cement and necessary precautions. The supervisor shall monitor the hose and piping closely to stop as much hose movement as possible. 3.6 General: 3.6.1 Conduct a Job Safety Analysis (JSA) meeting with the workers at the beginning of each shift to review the hazards that each person may encounter and give instructions for hazard elimination and/or protection. 3.6.2 Inspect all tools and equipment at least daily before use. 3.6.3 Workers, mixing dry contents, saw cuts or other dust raising actions with concrete/grout, may be exposed to dust inhalation. Workers shall use approved respiratory protection when exposed to silica dust above the threshold limits.

Implement dust control measures during sawing, grinding, chipping and mixing operations. 3.6.4 Ensure backup alarms work on all equipment and/or require all equipment to be escorted into position. Keep workers out of the path of mixing trucks. 3.6.5 Be aware of the swing radius of the concrete chutes, pinch points and the handling of chutes. Fingers caught in chute pinch points may be amputated. 3.6.6 Permit one (1) person trained with standard crane hand signals to signal the crane operator swinging the cement bucket. Ensure the swing path of the cement bucket is not over any personnel. 3.6.7 Check for overhead power lines and avoid contact with float handles, pump booms and other tools and equipment. 3.6.8 If electrical lines are too close for safe float and finish work, the concrete pour shall be reconfigured to avoid potential contact hazards. 3.6.9 Protect all moving parts of batch plants, mixers, portable mixers and other equipment with the appropriate safety guards or barriers. Keep fingers, hands, loose clothing and hair away from pinch and catch points. 3.6.10 Determine the confined space applicability. If the space is considered to be a confined space follow approved, client or Company, confined space procedures. 3.6.11 Use proper Lockout-Tagout (LOTO) procedures when cleaning, performing maintenance and repairing batch plants, mixers and other equipment. 3.6.12 Inspect all hand-held electrically powered tools and cords before use and keep them in good repair, as per the Assured Grounding Program. Plug the tools into Ground-Fault Circuit Interrupters (GFCIs). 3.6.13 Provide and require the use of approved fall protection when workers are exposed to a fall greater than six (6) feet or more. 3.6.14 Use approved tied-off ladders and stairs to access all excavations and elevated heights. 3.6.15 Review Material Safety Data Sheets (MSDS) with the employees concerning the ingredients of the concrete/grout, both the basic and additive ingredients, and other items such as curing compounds and sealants. 3.6.16 Secure the work area to keep untrained personnel out. The risk of injury increases dramatically when workers are distracted by outside hazards.

4 References: 29 CFR 1926.700 through 706 (Concrete and Masonry Construction) 5 Exhibits: None.