Sample Project Working As Project Manager / Project Engineer

Similar documents
Transmission Pipeline Opportunities. Advancing Project Development in India through Public Private Partnerships

195LiquidsCatalog.

TCO Future Growth Project - Wellhead Pressure Management Project Construction Contractors Forum

A new pipeline cleaning technology: Hydraulically Activated Power Pigging (HAPP TM )

Floating Production / Offshore solutions for tough challenges

Company Profile. Atlas Offshore Co. No.8, Negar Ave. Vali e Asr St., Tehran, Iran

Your partner for the right solution

COMPANY PROFILE. A: 36b Freedom Way, Lekki Phase 1, Lekki, Lagos Nigeria. T: M: E:

MECTHROLEUM NIG LTD READ + THINK + ACT = SOLUTION

INCREASING THE CAPACITY OF NGL RECOVERY TRAINS. Stéphane MESPOULHES XVI CONVENCIÓN INTERNACIONAL DE GAS Caracas de Mayo de 2004

Saudi Aramco General Bid Slates (GBS)

COMBINED CYCLE OPPORTUNITIES FOR SMALL GAS TURBINES

Natural Gas STAR Methane Challenge Program: Supplementary Technical Information for ONE Future Commitment Option

Machining, Bolting and Flange Management

AKAKUS OIL OPERATIONS- LIBYA Gas Utilization& Flare Emission Reduction Project

Atlas Copco Solutions. Serving the Oil and Gas Industry

CO2 Transport via Pipeline and Ship

NORTH CASPIAN OPERATING COMPANY (NCOC)

PRS INTERNATIONAL BV COMPANY INTRODUCTION

Brownfield Projects. Equinox Engineering

THE TECHNICAL STANDARDS AND SAFETY ACT, 2000, S.O. 2000, c. 16 ( the Act ) and

OUR EXPERIENCE: BALLAST WATER MANAGEMENT SYSTEM (BWMS) RETROFIT

Pipeline Systems PIP PLSC0013 Non-Destructive Examination of ASME B31.4 and B31.8 Metallic Pipelines

Development of HK Electric Gas Receiving Facilities at

Atlas Copco Solutions. Gas Sector

Natural Gas Gathering Lines. John Williams Director Service Monitoring and Enforcement Department

Kurnell Refinery Conversion Project

MLNG DUA DEBOTTLENECKING PROJECT

GAS CONDITIONING FOR GAS STORAGE INSTALLATIONS

CQ ENGINEERING a Division of

CO 2 Capture Utilization and Sequestration (CCUS)

Natural Gas Processing

High Resolution Ultrasonic In-Line Inspection Using InVista at the Ain Dar Area Project in Saudi Aramco

Stratus Development in Joint Venture with Middle East Petroleum Services (Offshore) SAL

Till date, Rotary has built more than 60% of independent storage tanks in Singapore.

SCHNEIDER-KESSEL BERLIN

ABOUT EIL. more than 5000 projects including over 400 major projects worth USD 200 Billion in total cost.

CONSTRUCTION MANAGEMENT

Saad El-Khadem Future Pipe Industries

Technowrap composite repairs for the maintenance of piping, pipelines, vessel or structural integrity Simon R. Frost, Walker Technical Resources

CP DESIGN OF A SUPER 13% CR FLOWLINE. Are Sjaastad and Harald Osvoll FORCE Technology Norway AS Hornebergveien Trondheim Norway

Division II Contractors

PetroVietnam Cooperate Structure

Inland Technologies Inc

maximize productivity in your operations

Note: Eastern Shore Natural Gas Company is referred to as ESNG thoughout this form. PART 1: CUSTOMER PROFILE PART 2: CUSTOMERS FACILITY DESCRIPTION

Maintenance Customized Service Speed, Flexibility and Professionality for OEM, EPC and Final Customers with High Quality and Competitivity!

6 th Pipeline Technology Conference 2011

Oman LNG LLC. Pre-Qualification Questionnaire. QEN EPC to Construct Car Parking Sheds with Solar Photovoltaic Panels

MEC-CSW-E-2001 Senior Commissioning Engineer PERSONAL DATA EDUCATION LANGUAGES COMPUTER SKILLS TRAINING COURSES AND CERTIFICATIONS

Natural Gas Facilities & Pipelines

DOUBLE WALLED PIPING SYSTEMS

TVU CCS Pre FEED Study Outline Execution Strategy for delivery of SSI Anchor Project including CO 2 Transportation & Storage Infrastructure

URGENTLY REQUIRED FOR SUDAN Oil Exploration - Operation & Maintenance (O&M) JOBS

Subsea Expo East Africa Tanzania. Eaen McKenzie GE Oil & Gas Aberdeen 3 rd February. Mozambique

AN INNOVATIVE APPROACH TO MANAGING THE INTEGRITY OF OIL AND GAS PIPELINES: PIPELINE INTEGRITY MANAGEMENT SYSTEM

ADVANCED PROCESS CONTROL QATAR GAS ONE YEAR EXPERIENCE

KASHAGAN / KAZAKHSTAN >>>

FT-GTL UNLOCKS VALUE FROM NATURAL GAS

Gas Holder Tank Maintenance, Design, Fabrication & Installation

Geothermal Power Plant

Modular Oil & Gas Equipment Onshore & Offshore

Worldwide Machinery and related companies under WW Group, USA. Executive Vice President Latin America

Process Cooling. Refrigeration Engineering International.

A COMPLICATED PROJECT FOR POWER AND WATER CO- GENERATION: THE RAF SITE

DESIGN AND SAFETY PRINCIPLES LEONTI CHALOYAN DEPUTY CHIEF ENGINEER ON MODERNIZATION

SASKENERGY/TRANSGAS FORECAST FOR 2017 AND BEYOND THE SASKATCHEWAN OIL & GAS SUPPLY CHAIN FORUM

Introduction to the Safe Design of LNG, CNG and Hydrogen Refueling Stations

Section ARMORED MEDIUM VOLTAGE CABLES SHIELDED 3 CONDUCTOR POWER CABLE - INTERLOCKED ARMOR

Qualitative Phase Behavior and Vapor Liquid Equilibrium Core

ELECTRICAL, INSTRUMENTATION & CONTROL SOLUTIONS FOR OIL & GAS INDUSTRY

Corrosion: The New Process Variable Online, Real-time, Saving Money

On Board Regasification for LNG Ships. 22 nd World Gas Conference WS 3-2 Tokyo 2003 Wayne Perry

Pipeline Integrity. QuestIntegrity.com CHALLENGE CONVENTION

Engineering solutions to eliminate waste. Offshore Services

Pipeline Oil & Gas Equipment, Inc.

Transportation and regasification infrastructures

Alaska South Central LNG (SCLNG) Project

The fresh approach to engineering and project management.» Rich in experience» Responsive & flexible» Delivery certainty

TURN-KEY MANUFACTURING PLANT for PE PIPE FITTINGS SAUDI ARABIA

Appendix A: Project Characteristics

LEASE AUTOMATIC CUSTODY TRANSFER UNITS (LACT UNITS)

CAIRN INDIA LTD Rajasthan Site Visit

Observations from Several Condition Assessments of Prestressed Concrete Cylinder Pipe used at Energy Generation Facilities

MyCelx Technologies Corporation

Keys to Excellence in the Practice of Process Engineering. An overview by Scott D. Love, P.E. October 2016

Siirtec Nigi in Russia

Management System. Updated Document Review

Natural gas saving opportunities in gas supply system of Iran. 22 April 2014

192GasCatalog.

AEP 69-kV Oil-Insulated Transmission Line Removal Project

SECTION HIGH DENSITY POLYETHYLENE PIPE AND FITTINGS (PRESSURE PIPE)

Total Facilities Management. We enhance your energy, engineering, mechanical and maintenance issues

Underground Residential Distribution (Specifications for Installation) PES March 2008 Spec 11

POWER RECOVERY IN FLOATING LNG REGASIFICATION PLANTS

Seminar: March ADNEC Exhibition Center Abu Dhabi. Managerial and technical life-cycle of a pipeline system

Atlas Copco Oil & Gas

Fluid Mechanics, Heat Transfer, Thermodynamics. Design Project. Production of Ammonia

COMBIMASS Thermal Gas Flow

General Discussion of Corrosion Monitoring Considerations in Pipeline Design

Transcription:

1. Akik Gas Plant Project Sample Project Working As Project Manager / Project Engineer Project: AKIK Gas Plant EPC project Client: Khalda Petroleum Co. "APACHI" / Egypt Start Date: September 2009 Duration: 2 Years Project Value: 10 MMUS$ Engineering, Procurement and Construction for Akik Gas Plant to process 16 MMSCFD of inlet gases at 73 bar inlet pressure from Salam to achieve the following: Water and Vapors dehydration and dew pointing Hydrocarbon dehydration and dew pointing Recover and stabilize maximum amount of condensate at 12 RVP The project scope was include basic and detailed engineering (Process, Civil, Mechanical, Piping, Hazop Study, Engineering Review, E&I Provision of Commissioning and Start-Up Manual,..etc), Procurement of all skids, piping, instrumentations, PCS,...etc, Construction works from Civil till final tie-in and commissioning & start-up The plant has been handed over to KPC on August 2011 with performance exceed the acceptance criteria has been agreed on the signed contract 2. Laying of 16`` Pipeline, 71 Km Project Project: Laying of 16`` Pipeline 71 Km from Dahshour to Fayoum Client: Shell / Egypt Location: Fayoum Egypt Start Date: 2008 Years Project Value: 6 MMUS$ The scope of work was limited to engineering, fabrication, laying, commissioning & start-up for 16`` underground pipeline for 71 KM between Dahshour and Fayoum Cities. In addition to the construction, E&I, Mechanical installation, civil works, commissioning & start-up for 2 pressure reduction stations.

3. Karama Power Station and Distribution Network Project Project: KARAMA Power Station and Distribution Network Project Client: Qarun Petroleum Co. "APACHI" / Egypt Start Date: 2009 Years Duration: 18 Months Project Value: 20 MMUS$ KARAMA site is 30,000 BPD crude oil production plant and one of the most important site of QPC, wells was supplied with electricity via diesel generators Both operational and maintenance cost of the site was high due to Diesel cost and maintenance of more than 120 Diesel Generators. KARAMA power plant is 32 Mega Watt electrical power field was constructed to secure the power for the entire area. The project has been constructed into 2 phases: Phase 1: is ongoing through 5 turbines total 20 Megawatt with about 120 km OHTL (22 KV) to switch than 100 well to the new plant Phase 2: well be through switching additional wells through 50 km OHTL power lines EMC was assigned to work in this project as a main EPC contractor; our scope was include the engineering works, procurement of all bulk materials, packages, treatment and utilities skids (Fuel Gas Skid, Diesel Generator, Portable Water Pumps, Power Transformers, Fire Fighting Pumps, Fire Detection, PCS and ESD, Bus duct, Instruments air skid, MV SEG, LV SWG, UPS and DCS,...etc) All the procurement has been handled by EMC except the power turbines units. Also all construction works has been executed by EMC, including buildings, civil works, piping, electrical, OHTL laying and poles fabrication. The scope also include the commissioning and start-up of the plant, the plant was commissioned and start-up was competed on April, 2011

4. Western Dessert Main Shipping Pipeline 16`` Underground pipeline, 166 Km Upgrading Project Project: Meliha to El-Hamra 16`` Underground Pipeline Upgrading project Client: Agiba / ENI Egypt B.V. Location: Western Desert Egypt Start Date: 2008 Years Project Value: 2.4 MMUS$ The project purpose is to increase the capacity and capability of the pipeline for shipping, the pipeline has been adapted to increase the operating pressure to be 100 Bar instead of 70 bar MAOP, The execution of such project has been implemented on three phases, (Inspection & Engineering phase, Verification phase & Repair and Execution phase), the project duration is 12 Months. This project has been implemented by EMC through internal resources, except for the intelligent pigging services have been provided through T.D. Williamson S.A. All project phase have been carried out without any stoppage or shutdown to the pipeline, considering the heist level of safety and emergency precautions. The Inspection phase; have been carried out using MFL Intelligent Pigging techniques, a pre runs of Mechanical cleaning, Proofing & Geometry runs have been provided also. Upon completion of the Intelligent pigging run and issuing the Final Fitness For Purpose Report by TDW, EMC start carrying out the required engineering works (Hydraulic Calculations & Stress Analysis) to identify the minimum wall thickness; which is required to meet the new operating conditions (Pressure, Flow & Temperature of Fluid); then EMC prepare a complete & enhanced repair program considering several affecting factors like (the type of corrosion (Internal or External), Number of defects per section, % of metal loss,..etc), this program recommend to use several types of repairs, each type of repair will be applied to fix a certain type of defects, with adhering to safety and cost optimization The used techniques during the pipeline repair were changed and could be summarized as follows: Hot Tapping & Stopling Services to fabricate and install about 1 km of the pipeline with new bypass pipeline with diameter 12``. Using Repair Sleeves with different lenghs (0.5 & 1 Meter) for all types of external and internal corrosions Using Composite wrapping to fix all types of external corrosion and till 85% of the wall thickness corrosion defects. Repair all cathodic protection network 5. GOS Offshore Platforms Control Rooms Upgrading

Project: GOS Offshore Platforms Control Room Upgrading Client: GUPCO / British Petroleum (BP) Egypt Location: Ras Shukier Red Sea, Egypt Start Date: 2007 Years Project Value: 980,000 US$ Maintenance and upgrading for 12 platform control rooms in R/SHfield for pressurization System. The scope is engineering, procurement and construction or modification required high customer satisfaction and with zero safety incident over the project duration 6. Laying of 16`` Pipeline, 71 Km Project Project: Over Head Transmission Lines 11kVA EPC Project Client: Khalda Petroleum Co. / APACHI Egypt Start Date: 2006 Years Duration: 18 Months Project Value: 10 MMUS$ EMC was assigned to work in this project as EPC project to feed about 250 well with the required electricity for operation. EMC established this activity for both construction and maintenance for the existing OHTL

List of Projects Working as Project Manager for AKIK Onshore Gas Plant Project KHALDA Petroleum Co. /APACHI Egypt (2010): EPC project, engineering, procurement, installation, commissioning & start-up for 16 MMSCFD gas process plant, including all construction works and tie-ins, electrical, mechanical hook-up with the existing process plants SGT1&2 and SGT3&4, scheduled duration was 12 months. Working as Project Manager for MELIHA To El-HAMRA 16`` Underground Oil Pipeline 166Km Upgrading Project Agiba Petroleum Co. / Egypt (2009): the aim is to increase the capacity and capability of the pipeline for shipping, the pipeline has been adapted to increase the operating pressure to be 100 Bar instead of 70 bar MAOP, The execution of such project has been implemented on three phases, (Inspection & Engineering phase, Verification phase & Repair and Execution phase), the project duration is 12 Months. Working as Project Manager for MELIHA Onshore New Oil Facilities Project AGIBA Petroleum Co. / ENI Egypt (2009): EPC project, Engineering, procurement, construction, installation, commissioning & start-up for new oil facilities required to produce additional 17,000 BOPD, the scope were include the supply and install of new two heater treater 10,000 & 7,000 BPD at MELIHA site including supporting utilities and two transfer pumps, the scope include construction works and Mechanical tie-in s with the existing facilities, scheduled duration 14 months. Working as Project Control Manager for GOS Offshore Platforms control Rooms Upgrading GUPCO / BP Egypt (2008): Control rooms & pressurization system upgrading. Working as Project Engineer for HULDRA Platform Compression Station Project Statoil / Norway (2008): EPC project including engineering, procurement, fabrication & installation, commissioning & start up for compression station skid, the scope were include extension to the existing platform for the 2 decks to guarantee the required space to install the new compression equipment, Working as mechanical discipline engineer during engineering phase, Evaluating and commenting supplier documentation, working in the engineering information system (EIS) database. Working as Project Engineer for HAYAT Gas Compression Station Project KHALDA Petroleum Co. / Apachi Egypt (2008): EPC project include, engineering, materials procurement, fabrication & construction, commissioning & start-up, Participate in engineering review and cost estimation phase Working as Project Engineer for 16`` Onshore Pipeline Intelligent Pigging Services at SHUKIER Field GUPCO / BP Egypt (2007): Mechanical & smart pigging for 16`` pipeline at R/SH field including final report and fitness for purpose (FFP) assessment report and applications of the required actions / repair concluded in the final report. Working as Project Engineer for KAHRAMAN & UMBARAKA Overhead Transmission Line Project KHALDA Petroleum Co. / APACHI Egypt (2007): Engineering, Procurement and Construction for power distribution network at KAHRAMAN & UMBARAKA fields to feed 250 wells with the required power through OHTL network, including supply and fabrication of over than 1000 poles with its transformers, cables and accessories, including engineering & site survey, excavation, concrete works and electrical equipment installation,...etc. Working as Project Engineer for Electrical building (Shelter) Fabrication B-300 to be installed on Platform B ZEITCO /Ocean Egypt (2006): Fabrication and installation of electrical building. Working as Site Engineer for Scarab Saffron Gas Plant S/D Activities Rashid Petroleum Co. / BG Egypt (2006): Shutdown activity including, mechanical works, water flushing, Nitrogen purging & Inspection for 21 Onshore vessel & 4 offshore vessels, the work performed according to the schedule. Working as Project Engineer for BALTIM Power Generation Package PTROBEL / ENI Egypt (2006): EPC Project, Engineering, Procurement, fabrication, commissioning & start up for two power generation packages 1.3 MW., to be installed on BALTIM Platform. Working as Site Engineer For OBAYIED Gas Plant S/D Activities BADRELDIN Petroleum Co. /Shell Egypt (2004): Shutdown activities including mechanical works, tightening works, water flushing, chemical cleaning & N2 purging