Environmental and Social Action Plan Adjaristskali Hydropower Plants

Similar documents
Darial Energy LLC. Dariali Hydro Power Plant Construction and Operation Project. Environmental and Social Action Plan, Dariali HPP

MANAGING CONTRACTORS ENVIRONMENTAL AND SOCIAL PERFORMANCE

Armenia: ENA-Modernisation of Distribution Network Stakeholder Engagement Plan: Draft Final Report

Chapter 13 Management and Implementation

CONDUCTING E&S DUE DILIGENCE ALIGNED WITH IFC PERFORMANCE STANDARDS A FOCUS ON FINANCIAL INTERMEDIARIES

Environmental and Social Review Summary. Hoi Xuan Hydropower Project

Annex 1: Project Tropicalia Sustainable Tourism, Dominican Republic

Environmental and Social Impact Assessment Part 1. GEO: Adjaristsqali Hydropower Project

NON TECHNICAL SUMMARY

EBRD Performance Requirement 1

Case of MIGA s Guarantee Linked to the Engineering and Feasibility Phase of Developing the PT Weda Bay Nickel Project. Summary

PROJECT CONCEPT PRELIMINARY QUESTIONAIRE PART I: GENERAL INFORMATION. GEF: OTHER(S) (Specify)

EBRD Performance Requirement 10

Environmental and Social Policy

ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT GUIDELINES FOR HYDROPOWER PROJECTS IN MYANMAR

ENVIRONMENTAL & SOCIAL REVIEW AND AUDIT LUKOIL OVERSEAS SHAH DENIZ - STAGE 2 OF THE SHAH DENIZ PROJECT

Principles for environmental and social responsibility

Environmental and Social Management Plan Çanakkale Bridge and Malkara - Çanakkale Motorway Project Final Draft. December 2017.

Briefing Summary. Board Meeting on Nam Theun 2 Project: November 22, 2010

Environmental and Social Review Summary. Kribi and Dibamba Operations

9 ENVIRONMENTAL MANAGEMENT PLAN 9.1 OVERVIEW AND SCOPE Introduction

Environmental and Social Compliance Assurance Plan

BOSKOV MOST HYDRO POWER, REQUEST NUMBER: 2011/05

Environmental and Social Management Plan

Ouarzazate Solar Power Complex, Phase 1, Morocco

ab0cd ENVIRONMENTAL AND SOCIAL PROCEDURES

Contractor Management and Purchasing

Environmental and Social Review Summary. Congo Equipment - Expansion

Panama Canal Expansion Program Stakeholder Engagement

The World Bank s Safeguards Policies in Context of Hydropower Projects International Conference on Sustainable Hydropower in the Dinaric Arc

GOOD PRACTICE NOTE. Managing Contractors Environmental and Social Performance

Request Number 9: Accidents & Malfunctions Dam Safety Cumulative Effects

BASICS OF ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA)

Ecological Impact Assessments in Developing Countries: challenges faced and lessons learned. Dr Mihai Coroi

Table A1 - Environmental and Social Safeguard Policies Policy Objectives and Operational Principles

UPMC POLICY AND PROCEDURE MANUAL. Links to policies referenced within this policy can be found in Section V.

Level of Reporting on GRI Indicators, 'in accordance' Core. Fully Significant Changes during 2016

Evaluation of Occupational Health & Safety Management System

REQUEST FOR EXPRESSIONS OF INTEREST. (Long Term Individual Consultants, Environmental and Social Safeguards - Energy Sector)

Stakeholder Engagement Plan Code Of Practice

Trends in CMS Audits and Enforcement Actions Against Medicare Advantage and Part D Plans

This document sets out how AIB complies with these Regulations. 1. Governance

Environmental and Social Review Summary Novomet (#33480) Overview of IFC scope of review

COMPLIANCE APPRAISAL: SUMMARY OF RESULTS

SMITH & NEPHEW PLC TERMS OF REFERENCE OF THE AUDIT COMMITTEE

Environmental and Social Data Sheet

Environmental and Social Impact Assessment for Rogun Hydro Power Plant

SUMMARY 2013 EDITION

Construction Environment Management Plan

Environmental and Social Review Summary. Ejuva One and Ejuva Two Solar Projects

Operations OPERATIONS

Trends in CMS Audits and Enforcement Actions Against Medicare Advantage and Part D Plans

ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN...

Introducing the WBG Guidelines for selecting EFlow assessment methods. Cate Brown

COGNIZANT TECHNOLOGY SOLUTIONS CORPORATION. Audit Committee Charter. Updated December 12, 2017

Environmental and Social Review Summary

Health & Safety Officer. Donegal County Council

Corporate Policy Statement

China Airlines Co., Ltd. Corporate Social Responsibility and Sustainable Development Best Practice Principles. Chapter I General Principles

ENVIRONMENTAL IMPACT ASSESSMENT

Alfa Financial Software Holdings PLC Terms of Reference of The Audit and Risk Committee of The Board of Directors of The Company

CAPRA National Accreditation Standards

SUBCONTRACTOR MANAGEMENT

Service Suppliers Engaged in Condition Monitoring of Machinery Onboard Ships and Mobile Offshore Units

General Counsel Manager, Governance, Risk and Compliance

GRI Content Index 2016

Virginia Department of Environmental Quality EMS Manual

(Adopted by the Board of Directors on 13 May 2009 and amended on 24 September 2009, 13 September 2012 and 27 November 2013)

JAPAN BANK FOR INTERNATIONAL COOPERATION GUIDELINES FOR CONFIRMATION OF ENVIRONMENTAL AND SOCIAL CONSIDERATIONS

GROUP 1 AUTOMOTIVE, INC. AUDIT COMMITTEE CHARTER

Implementing the Mitigation Hierarchy

OH&S MANAGEMENT SYSTEM CHECKLIST - AS 4801:2001 (STATUS A = Acceptable; N = Not Acceptable; N/A = Not Applicable)

Environmental and social impacts of smallscale. Issues and Challenges. Glenn Morgan (LCSEN) World Bank Water Week February 18, 2009

AUDIT COMMITTEE CHARTER (updated as of August 2016)

Section 1: Management Involvement. 1.1 Corperate Health and Safety Policy. Nivek Oilfield Hauling Ltd.

CONTRACTOR SAFETY MANAGEMENT PROGRAM (CSMP) PRE-QUALIFICATION SAFETY QUESTIONNAIRE

1. Number. Except as otherwise permitted by the applicable NASDAQ rules, the Audit Committee shall consist of at least three members of the Board.

ENVIRONMENTAL AND SOCIAL REVIEW SUMMARY

Yes: Y No: N (a) (b) (c) (d) (a) (a) (b) (c) (d) (e)

Quality and Environmental Business Process Manual

ANNEXE 2: THE TERMS OF REFERENCE FOR ESIA AND RAP. 1. Objectives. The aim of the study is to achieve the following objectives:

Revision No. 2 May 18, ENVIRONMENTAL AND SOCIAL REVIEW SUMMARY (ESRS) PROJECT Nachtigal # Disclaimer

See revision section. Resources, Roles, Responsibility, Accountability, and Authority. Section in OHSAS 18001:2007

POSITION DESCRIPTION

BOARD CHARTER TOURISM HOLDINGS LIMITED

RISK AND AUDIT COMMITTEE TERMS OF REFERENCE

CULTURAL HERITAGE MANAGEMENT PLAN

2017 Archaeology Audit Program Procedure Manual. April 2017

SAMSUNG HEAVY INDUSTRIES

Global Reporting Initiative (GRI) G4 Content Index

A. Independence/Composition. The Committee shall be comprised of not less than three members. The members of the Committee:

Climate Smart Agriculture /Climate Change Adaptation in Simiyu Region, Tanzania

Chapter 14 Overall Project Assessment

Environmental and Social Review Summary. Dakar Port, DP World Container Terminal Modernization and Operation

BUJAGALI ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT SUMMARY

Policy No: 67. Driving at Work Policy

CATEGORY Policy SUBJECT Work Health & Safety ISSUED BY Human Resources APPROVAL DATE 05/08/2015

1. Introduction to the Project

South Stream: The Evolution of a Pipeline - Management of Environmental and Social Issues

Environmental and Social Management Plan

Transcription:

Environmental and Social Plan Adjaristskali Hydropower Plants The International Finance Corporation (IFC), the Asian Development Bank (ADB), and the European Bank for Reconstruction and Development (EBRD) (collectively, the Lenders or IFIs) are considering financing the Shuakhevi hydropower plant, the first phase of the Adjaristskali Hydropower Project on the Adjaristskali River in the Adjara region of southwestern Georgia. Adjaristskali Georgia LLC (AGL) is a Georgian special purpose vehicle (SPV) owned by Clean Energy Invest AS (CEI) and Tata Power (together, the Sponsors). The SPV was established for the sole purpose of constructing and operating a cascade of hydroelectric power plants (HPPs). AGL has prepared and disclosed an Environmental and Social Impact Assessment (ESIA). This ESIA described the project and the natural and human resources that could be affected, and evaluated the potential impacts the project could have on those resources. The ESIA also described a series of actions that will need to be taken to prevent, control, or otherwise mitigate potential impacts and comply with the lenders environmental and social safeguards. Those s are described in this Environmental and Social Plan (ESAP). The ESAP in the table below will be included in AGL s financing agreements with the Lenders. Performance of the required actions will be reported to the Lenders by AGL and will be audited or otherwise evaluated by the Lenders during construction and operation of the project. of the actions is the ultimate responsibility of AGL. When other companies perform work under contract, AGL will be responsible for their compliance with the s of the ESAP, even if direct oversight of the work is by a contractor. This is expected to be accomplished by inclusion of s in contracts and subcontracts, and by direct oversight and supervision by AGL and/or its oversight contractor. As agreed by Lenders and AGL, this ESAP may be revised from time to time during project performance. No changes will allow violations of Georgia law or of the Lenders s for environmental and social performance, which are found in IFC Performance Standards on Environmental and Social Sustainability (2012), ADB Safeguard Policy Statement (2009), and EBRD Performance s (2008). Page 1 of 10

1 Report to Lenders on the status of each ESAP and compliance with PRs/PSs/SRs. - Semi-annually throughout construction until commissioning - Annually during operation Submission of reports in format to be mutually agreed, acceptance by Lenders ESHS Reporting : - Completeness and adequacy of ESHS Report 2 Finalize development of the ESHS Management System to include (as required by ESIA, vol. IV, sec.4.2.2): - Register of environmental and social aspects - Register of s and conditions in legislation, consents, permits, etc. - of monitoring program, including required and recommended surveys / inspections/audits (EHS Monitoring ) - Development of Environmental Improvement Plan through development of: - E&S Management and Monitoring procedures construction works and then prior to commercial operation - Finalized ESHS with all aspects included. - Lender approval of monitoring program - Monitoring of environmental management (including design change management) and mitigation as per AGL ESHS. - Status of ESHS Management System development - Metrics of key performance indicators as set down in AGL ESHS - Summary of audit results of AGL ESHS implementation Page 1 of 10

- Environmental Operating procedures - Preparation of action lists and responsibilities - Development of training materials and key performance indicators. - Design Change Management procedure 3 Acquire and comply with all required permits and authorizations Prior to beginning any activities that require permits or authorizations - Permits & authorizations received - Reports submitted to authorities as required - Compliance status - Report immediately any formal enforcement actions for noncompliance 4 Implement ESMP and all associated plans Best practice Throughout and operation construction - ESMP and all plans implemented - ESHS impacts avoided, minimized, mitigated or compensated - Highlights of implementation, including major deviances 5 Use best efforts to ensure ESIA on Batumi-Akhaltsikhe transmission line is completed Throughout development of ESIA and construction/ operation of line - Transmission line ESIA meets international standards - Construction and operation in Page 2 of 10

accordance with agreed mitigation - Status of transmission line ESIA and approval process - Summary of construction and operation - OHS plan further developed, adopted, and implemented - Minimum lost time incidents and fatalities - Monitoring of environmental and social management and mitigation as per AGL ESHS Monitoring - Status of updating of OHS plan - Outcome of OHS monitoring as per ESHS Monitoring. - Summary of OHS issues, including incident and enforcement statistics, status of training, etc. Report to cover AGL and contractor workforces - Report to Lenders immediately in case of major accidents in accordance with international best practice and that required mitigation measures are fully implemented. 6 Further develop OHS plan to be specific to Adjaristskali project(s) and ensure that the procedures and HSE manuals referred within it are an integral part of health safety and environmental management on site EBRD PR2 IFC PS 2 Prior to construction Page 3 of 10

7 Implement Labor Grievance Plan (2012), including grievance mechanism made available to all AGL and contractor workers 8 Review Spoil Management Plan to ensure: - Plan is consistent with ESIA and project design, including estimated spoil quantity - Specific method statements and risk assessments are completed for each spoil disposal site - Clarity on potential land acquisition - Site specific subsidiary plans to cover management of each individual site during fill and subsequent site reinstatement - Designs sufficient to prevent erosion due to specified flooding events EBRD PR2 IFC PS 2 EBRD PR3 IFC PS3 Throughout construction and operation and/or fatalities - Plan implemented, mechanism made available. - Timely resolution of all grievances - Outcome of labor grievance monitoring as per ESHS Monitoring - Summary of grievances and resolutions Prior to spoil generation - Site specific spoil management plans developed/approved by AGL - Spoil managed according to plan - Monitoring of environmental management and mitigation as per AGL ESHS Monitoring - Status of site specific spoil management plans - Outcome of spoil monitoring as per EHS Monitoring Page 4 of 10

9 Complete all necessary additional surveys, reviews and consultations identified in the ESIA and project permit approval conditions. Modify ESMP and associated plans as needed to incorporate findings into environmental and social management. 10 Identify mitigation measures for concrete within CEMP11 and ensure appropriate management techniques are employed through the ESMP. 11 Identify within CEMP09 specific solutions with regards to the need for management of waste at appropriately licensed landfill or other sites. /SR2 EBRD PR3 IFC PS3 EBRD PR3 IFC PS3 EBRD PR3 IFC PS3 construction construction construction - Surveys, reviews, consultations completed - ESMP modified as needed - Status of additional surveys and impacts of outcomes on ESMP - Mitigation measures identified - ESMP modified as needed - Updated CEMP12 - Outcome of CEMP12 implementation monitoring as per EHS Monitoring - Solutions identified - CEMP09 modified - Updated CEMP09 - Status of site specific spoil waste disposal site risk assessments and method statements - Outcome of monitoring spoil management practices as per EHS Monitoring 12 Identify and evaluate risks to Prior to creation of - Community H&S risk Page 5 of 10

community health and safety from construction and operation of the project, develop and implement commensurate preventive measures and plans to address them. 13 Develop and enforce a Code of Conduct for Security Personnel 14 Develop and enforce Worker Code of Conduct in accordance with the Worker Behavior Guidelines EBRD PR4 Best practice EBRD PR4 IFC PS4 potential risks assessment for all project stages - Mitigation/prevention measures developed and implemented - ESMP monitoring and reporting - Status of risk identification and mitigation, and planning - Outcome of monitoring of H&S management of risks to the community as per EHS Monitoring construction the construction phase Code of Conduct developed and enforced - Status of Code of Conduct development - Outcome of monitoring of effectiveness of Code of Conduct for Security Personnel as per EHS - Code of Conduct developed and enforced - Status of Code of Conduct Page 6 of 10

development - Outcome of monitoring of effectiveness of Worker Code of Conduct as per ESHS 15 Implement the LALRP, including timely disclosure of up-to-date land acquisition and resettlement documentation, summary of LALRP and information on progress (e.g. monthly Information Letters, booklets, brochures, etc.) ADB SR2 EBRD PR5 IFC PS5 Throughout acquisition process land - LALRP implemented - Up-to-date land acquisition and resettlement documentation available on AGL s website and locally. - Status of acquisition - Summary of disclosures 16 Implement the BAP, including: - developing and implementing detailed monitoring for evaluation and reporting of ecological impacts and recognizing findings of additional surveys undertaken - monitoring flow upstream and downstream of all dams to verify required minimum flows are met - Ecological assessments as performed to verify flows are adequate to preserve biodiversity, or to redefine minimum flows EBRD PR6 IFC PS4, 6 - Develop : Prior to construction - Implement monitoring : as specified in BAP throughout during construction and operation - Monitor flow: throughout operation - Ecological assessments: as per BAP - BAP implemented - ESMP monitoring and reporting - Status of development - Outcome of ecological monitoring as per Monitoring - Summary of minimum flows against s - Summary of ecological assessments, including need for adjustments in minimum flows. Page 7 of 10

17 Conduct additional surveys to determine presence of graveyards, and if needed work with communities to minimize impacts 18 Update CEMP01, Chance Finds Procedure, to call for archaeologist to be on site as needed to verify archaeological finds, provide advice to a nominated AGL representative, and liaise with relevant authorities. 29 Implement Stakeholder Engagement Plan 20 Evaluate and update SEP to improve/ refine stakeholder list, /SR2 EBRD PR8 IFC PS8 ADB SR 1 0 0 - Survey of area: prior to disturbance of the area - Consultation with communities to minimize impact: prior to disturbance of graves - Surveys conducted - Consultations held and actions agreed - Summary of surveys and actions taken (consultations, etc.) - Outcome of monitoring of graveyard protection as per EHS Monitoring Prior to construction - Updated Chance Finds Procedure Status of EBRD PR4 - updated Chance Finds Procedure - Outcome of chance finds procedure implementation, monitored per EHS Monitoring Throughout construction - SEP implemented and operation - Summary of stakeholder engagement Evaluation and update: annually during - SEP evaluated and updated if needed Page 8 of 10

communication media, etc. methods, construction, biennially thereafter - Updated SEP Page 9 of 10