Louisiana Transportation Conference February 17-20, 2013

Similar documents
Grade separated interchange at the intersection of U.S. Hwy 17 Bypass and Farrow Parkway

Performance of Mechanically Stabilized Earth walls over compressible soils

ODOT Design & Construction Requirements for MSE Walls

SPECIFICATIONS FOR PRECAST MODULAR BLOCK RETAINING WALL SYSTEM (revised 5/8/7)

MSE WALLS CASE STUDIES. by John G. Delphia, P.E. TxDOT Bridge Division Geotechnical Branch

Ground improvement support using Confined aggregate piers in soft soil. Brian Metcalfe, P.E. Director of Engineering Geopier Foundation Company

SCG INTERNATIONAL TRINIDAD AND TOBAGO LIMITED COUVA CHILDREN S HOSPITAL

or (800)

MECHANICALLY STABILIZED EARTH (MSE) WALL SYSTEMS

REPORT STATUS: DATE: Report n :

A CASE HISTORY ON DESIGN, CONSTRUCTION, AND PERFORMANCE OF STONE COLUMN GROUND IMPROVEMENT BENEATH AN MSE EMBANKMENT

SECTION EXCAVATION AND EMBANKMENT. B. Subbase Grading A samples for gradation analysis.

GEOTECHNICAL RESISTANCE FACTORS

Chapter 15 SHALLOW FOUNDATIONS

RIGID INCLUSIONS. Rigid Inclusions offer an economical approach for building on sites underlain by soft soil.

Anchorplex retaining wall construction guide. Building. Anchorplex. Retaining Wall Systems

ENGINEERING DIRECTIVE

CE 240 Soil Mechanics & Foundations Lecture 4.1. Soil Compaction: Field work (Das, Ch. 5)

AMERDRAIN. Prefabricated Vertical Soil Drainage Systems ICK. Soil drainage method for accelerating settlement through vertical drainage

DESIGNING AND CONSTRUCTION OF T-WALL RETAINING WALL SYSTEM

I-35W Retaining Wall Design Exhibit A - Draft Scope of Work

SCDOT Geotechnical Manual Updates. Nicholas E. Harman, MS PE

GEOTECHNICAL LRFD DESIGN

by Dr. Mark A. Ketchum, OPAC Consulting Engineers for the EERI 100 th Anniversary Earthquake Conference, April 17, 2006

October 1, Re: Contract ID A Plans, Proposal, EBS, Questions & Answers October 8, 2013 Letting

Experience of a Large Scale Unintentionally Long Surcharge on Organic Soils

MSE Walls Problems and Solutions

Numerical Modeling of Dynamic Soil-Structure Interaction in Bridges with HP Driven Piles

Geotechnical Specification and Construction Update

2. Pavement Materials: Consist of flexible or rigid pavements, typically HMA or PCC, respectively, or a composite of the two.

Introduction to Foundations on Fill and Backfilling

ICC-ES Evaluation Report Issued July 1, 2011 This report is subject to renewal in one year.

Description. This work shall consist of furnishing materials and placement of modular block wall constructed in accordance with

Improving Engineering Properties of Soft Soil Using Preloading and Prefabricated Vertical Drains

SECTION SPECIFICATION FOR STONEBRIDGE RETAINING WALL SYSTEM

Behavior of Reinforced Embankment on Soft Ground with and without Jet Grouted Soil-Cement Piles

CHAPTER 3 CONSTRUCTION AND TESTING OF SUBGRADE

Experiences on embankment fill in land expressway over soft ground

This paper describes the salient features of a

GEOSYNTHETICS ENGINEERING: IN THEORY AND PRACTICE

SECTION PERMEABLE INTERLOCKING CONCRETE UNIT PAVEMENT

PROPOSED STOCK PILE YARD PHASE 1 SITE: MYRA FALLS MINE

Simple Design Alternatives to Improve Drainage and Reduce Erosion at Bridge Abutments

Study of Various Techniques for Improving Weak and Compressible Clay Soil under a High Earth Embankment

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

Applications of Waste Tire Products in Civil Engineering

Topic #4 Soil Compaction

5-20 FOUNDATION REPORT/GEOTECHNICAL DESIGN

INSPECTION GUIDE FOR SEGMENTAL RETAINING WALLS TEK 18-11B

CONCRETE SEGMENTAL RETAINING WALL SYSTEM

Chapter 18 EARTH RETAINING STRUCTURES

Structural - Engineering Review Checklist

GEOSYTHETIC SLOPE SPEC-V0704rev.doc STANDARD SPECIAL PROVISION FOR GEOSYNTHETIC REINFORCED SLOPE CONSTRUCTION

2.1 Backfill - General

LIGHTWEIGHT FILL DESIGN GUIDANCE

Ground Improvement for Mitigation of Failure Risks to Existing Embankment Dams

JOB BB0113 SHELL LAKE STR. & APPRS. (S) MARCH 10, 2015 LETTING QUESTIONS PREVIOUSLY ASKED UNDER JOB BB0106.

StormTech Construction Guide

aggregate piers / vscs

Construction Procedures

Design of Geofoam Embankment for the. Steven F. Bartlett, Ph.D., P.E. Research Project Manager, UDOT

Student Services & Classroom Addition

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

TABLE OF CONTENTS. Background of Existing Facility 3. Proposed Work 4

Design Considerations. Pursuing Dynamic Compaction. waste considered. Pursuing Dynamic Compaction. Page 1 of6

Design of Rigid Pavements

Mix Design & Construction -1-

Bureau of Materials Materials Approval Procedures

GEOTECHNICAL STUDY PROPOSED CONCRETE ROADWAY TIKI ISLAND COMMUNITY GALVESTON COUNTY, TEXAS PROJECT NO E

SPECIFICATION FOR REINFORCED SOIL WALL

Applied GeoScience, Inc Hammond Dr., Suite 6 Schaumburg, Illinois

Long-Term Instrumentation Program to Monitor Various Geo-Technologies Used on the I-15 Reconstruction Project, Salt Lake City, Utah

Tasman Retaining Wall System

Table of Contents. July

CHAPTER 23 PILES TABLE OF CONTENTS TABLE OF CONTENTS. 23.TOC Table of Contents... 30Jan Introduction... 30Jan2018

Alberta Bridge Inventory STANDARD BRIDGE & CULVERT COMPONENTS. Standard Bridges. Typical Bridge Components. In Alberta there are about 13,300 bridges.

Redi Rock Specification and Installation Manual

Section 25 Aggregate Subbase

Ground Improvement Techniques: Dynamic Compaction Martin Larisch & Tim Pervan

PDPI 2015 STATIC ANALYSIS LATERALLY LOADED PILE DESIGN. Chapter 9

SECTION FOUNDATION DRAINAGE

Designer Supplement: AS-2-15 Approach Slab Installation January 16, 2015

Seismic Design of Long-Span Bridges

Engineering Properties of Foamed Recycled Glass as a Lightweight Fill

Scoping & Design Project Level. By Robert J. Blight Principal Engineer Pavement Management & Technology

Installation Manual. ArchCast Bridge. 3-Sided Precast Concrete Bridge Structure

DESIGN CONSIDERATIONS FOR NSWS NATURAL STONE RETAINING AND FREE-STANDING WALL SYSTEMS

Applications. 5 reasons why you should choose Hebden X Grid cellular paving

Geoguide 6 The New Guide to Reinforced Fill Structure and Slope Design in Hong Kong

A Case Study: Foundation Design in Liquefiable Site

Recommended Specifications, Commentaries, and Example Problems

How to Select the Appropriate Pavement Rehabilitation Option. David Rettner, PE American Engineering Testing, Inc.

MOA Project # Golden View Drive Intersection & Safety Upgrades

SECTION RIPRAP, BOULDERS, AND BEDDING

BASE CONSTRUCTION MATERIALS A Aggregate

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

ENGINEERING MATERIALS Assignment #8: Concrete Mix Design

SELECTIVE FLEXIBLE PAVEMENT REHABILITATION BASED ON FORENSIC INVESTIGATION AND DEFLECTION ANALYSIS: SEVENTEEN YEARS CASE STUDY IN VIRGINIA

Transcription:

Case Study: Rapid Embankment Construction of US 17 Bypass Interchange Over Soft Compressible Soils Using Lightweight Aggregate Myrtle Beach, South Carolina Presented By: Ed Tavera, PE Louisiana Transportation Conference February 17-20, 2013 Jeff Speck, PE Big River Industries, Inc.

Presentation Agenda Project Overview & Design Requirements Project Constraints Geotechnical Challenges Rapid Embankment Construction Lightweight Aggregate Borrow Proposed Compaction Verification Lightweight Aggregate Supply & Delivery Automated Geotechnical Instrumentation & Results Project Construction Pictures Closing

PROJECT OVERVIEW

Project Location Myrtle Beach, SC

Project Location

Project Site Murrels Inlet SC 707 US17 Bypass N. Myrtle Beach East

Purpose Relieve growing traffic congestion Provide a facility to handle future development and growth Construct a safe, signature project for the stakeholders (Horry County, SC)

Project Layout SC 707 US 17 Bypass Ramp C Ramp D Ramp B Ramp A Farrow Parkway

Proposed Interchange

Bridge Span Lengths (Bridge Length 1,240 Feet) 175 225 300 225 175 140

Bridge Aesthetic Features

Bridge Features Interior Bent Cap Extensions

Retaining Wall Features (Rendering)

Wall Features Columbia International Airport Interchange

Schedule Local Funding - led to higher expectations for project completion Heavy traffic volumes necessitated accelerated construction Elimination of long settlement waiting period Led to innovative geotechnical design and construct techniques

DESIGN REQUIREMENTS

Design Requirements AASHTO LRFD Design Strength Limit State Service Limit State Extreme Event I Limit State (Seismic) Extreme Event II Limit State (Collision) Performance Based Design Service Limit State Extreme Event I Limit State (Seismic) Extreme Event II Limit State (Collision)

US Earthquakes 1705-1996 Seismic Hazard 1886 Charleston Earthquake MW 7.3

SC Seismic Hazard Charleston fault zone ( Woodstock fault) and the Zone of River Anomalies (ZRA) fault source Moment magnitude from 7.0 to 7.5. 1886 Charleston Earthquake

SC Seismic Hazard FEE PGA 0.06g @ B/C Boundary SEE PGA 0.24g @ B/C Boundary

Extreme Event I Limit State SC Design Earthquakes Safety Evaluation Earthquake (SEE), ground shaking having a 3% probability of exceedance in 75 years (2,500 year return period) PGA = 0.39g Functional Evaluation Earthquake (FEE), ground shaking having a 15% probability of exceedance in 75 years (500 year return period) PGA = 0.13g

PROJECT CONSTRAINTS

Traffic Control High existing traffic volume No lane closures during summer months Maintaining access to numerous businesses Complex construction traffic control plan 8 proposed stages of construction Maintain existing number of lanes Temporary pavement Multiple traffic shifts Temporary alignments Detour routes

Project Constraints Traffic Control Maintain Existing Number of Lanes & Access to Numerous Business Embankment Construction Traffic Control Stages 2, 3, and 4 Project Geometry and Layout Existing Alignment Limited R/W Limited Construction Staging Areas Construction Time Requirements 3.5 years

GEOTECHNICAL CHALLENGES

Myrtle Beach, SC Regional Experience Fantasy Harbour 2 Miles Away! US 17/SC 707 (Backgate)

Fantasy Harbour 2 Miles North of US 17 /SC 707 Interchange New Alignment Bridge Over the Atlantic Intracoastal Waterway 3.1 Miles Roadway Approaches and Bridge

Fantasy Harbour West Abutment Subsurface Soils SB2 RB-24 RB-25 RB-27 SB1 RB-28 RB-29 Very loose to medium SANDs (SP/SC/SM) 0 ftmsl Very soft to medium CLAYs (CL/CH) -50 ftmsl Pee Dee Formation

Fantasy Harbour East Abutment Subsurface Soils SB3-A 0 ftmsl RB-13 SB6 SB1 RB-11 RB-16 SB2-A Very loose to medium SANDS (SP/SM/SC Very soft to medium CLAYs (CL/CH) SB5-50 ftmsl Pee Dee Formation

Fantasy Harbour Geotechnical Experience 10 42 Embankment, Settlement 9 to 67 Liquefaction Loose Sands Embankment Slope Instability (Static/Seismic) Ground Improvement!!! 2 Year Embankment Construction Contract 2-3 Year Bridge Construction Contract

Let s Return To US 17/ SC707 Interchange (Backgate) South Bridge Approach North Bridge Approach

South Bridge Approach Subsurface General Profile

North Bridge Approach Subsurface General Profile

Geotechnical Challenges 30 to 60 - Soft to Firm Clay Pockets of Loose Sands in upper 10 Intermediate Medium Sands (253+00 to 256+00) Loose Sands above Dense Sands (Liquefiable) Pee Dee Formation

Bridge Abutment Settlement (Normal Weight Fill 120 pcf)

Geotechnical Challenges Poor Site Subgrade (2 3 Bridging Required) Excessive Settlement (Total & Differential) Static Slope Embankment Instability/Bearing Seismic Slope Embankment Instability (Liquefaction)

RAPID EMBANKMENT CONSTRUCTION

Rapid Embankment Construction Project Constraints Geotechnical Challenges

Geotechnical Key Design Issues Settlement Total & Differential Embankment Slope Instability / Bearing (Static/Seismic) Bridge Abutment Foundation Performance - Extreme Event I and II Limit States MSE Wall Construction Over Soft Soils

Geotechnical Design Approach Lightweight Aggregate Borrow Reduce Magnitude of Settlement Prefabricated Vertical Drain (PVD) / Granular Surcharges Increase Rate of Settlement and Facilitate Rapid Construction Deep Soil Mixing Improve Seismic Slope Stability and Bridge Abutment Foundation Performance Mechanically Stabilized Earth (MSE) Walls 2-Stage and 3-Stage MSE Wall Construction Vertical Slip Joints

Granular Surcharge & Lightweight Aggregate Borrow Granular Surcharge Properties: = 32 degrees Unit Weight: 125 pcf Granular Surcharge ½ Normal Weight Lightweight Aggregate Borrow Material Lightweight Aggregate Properties: = 40 degrees Short Term Unit Weight: 60 pcf Long Term Unit Weight: 70 pcf MSE Wall Backfill Properties Normal Weight Lightweight Aggregate

Lightweight Aggregate Borrow (Rotary Kiln Produced) 226,000 CY

PVD Installation 3 Million LF

PVD Installation S s = 3 and 4 PVD PVD Triangular Installation Pattern PVD 2 Drainage Sand Layer Geotextile Separator Fabric

PVD Installation Obstructions!!! 309,000 LF Predrilling PVD Installation

MSE Walls Permanent MSE Walls Two-Stage Construction Three-Stage Construction (w/drainage Structures) Temporary MSE Walls (Welded Wire Mesh Facing) 30,500 SF 51,500 SF

Deep Soil Mixing Columns (Overlap Block Pattern) 35,600 CY Seismic Slope Stabilization Shear Key Improved Performance of Bridge Abutment Foundations 2013

Deep Soil Mixing Columns (Overlap Block Pattern) Longitudinal DSM Bridge Abutment DSM Longitudinal DSM

10 Feet Min. Deep Soil Mixing Test Sections 10 Feet Min. 1 2 4 3 Test LCC No. 1 2 3 4 Test Pile 1 (HP 14x117) DSM-LCC Test Section 1 (Block Type Pattern) Test LCC Sampling Quadrants DSM-LCC Test Section 2 (Single Line Pattern) Legend Test Lime-Cement Columns (Test LCC)

CONSTRUCTION SEQUENCE

Project Construction Stages (North Abutment 252+01) Ramp D Stage 3 Bridge Approach Embankment Stage 4 Ramp B Stage 2

Bridge Abutment Construction (North Abutment End Bent 7)

Bridge Abutment Construction Bridge Wing Wall Vertical Slip Joints MSE Wall Concrete Panel Facing DSM-LCC Block Type Pattern MSE Wall Leveling Pad HP 14x117 22 Piles/row PVD (Wick Drains) 30 Feet

LIGHTWEIGHT AGGREGATE BORROW PROPOSED

Lightweight Aggregate Borrow (Proposed New Material)

Lightweight Aggregate Borrow (Rotary Kiln Produced)

% Passing Grain Size Curve 1 ½" ¾" 3/ 8" # 4 # 30 # 40 # 100 # 200 100 90 80 Big River Proposed Lightweight Aggregate LWF Min LWF Max 713 Min 713 Max 70 BR Min BR Max 60 LWA (S15922) 50 40 30 Section 713 MSE Wall 20 10 0 1000.000 100.000 10.000 Grain Size (mm) 1.000 0.100 0.010

Lightweight Aggregate Density Properties Lightweight Aggregate Borrow Soil Properties (Item 2033020) Soil Properties SCDOT Specified Proposed Minimum: Dry Unit Weight, g Dry (pcf) 55 43 * Maximum: Dry Unit Weight, g Dry (pcf) 60 45 ** Minimum: Wet Unit Weight, g Wet (pcf) 60 55 ** Maximum: Wet Unit Weight, g Wet (pcf) 70 60 ** * 95% Maximum Density ** Estimated based on laboratory testing submitted by Big River Industries

Lightweight Aggregate Borrow (Proposed New Material Differences) Higher Fines Content Lower Dry Unit Weight Total Unit Weight 15% Less Than Designed High Absorption Gradation Coarse Sand Vs. Aggregate Compaction Verification Required by SCDOT

Test Section #1 (Dry)

Test Section #1 (Wet)

Granular Surcharge & Lightweight Aggregate Borrow Granular Surcharge Granular Backfill Lightweight Aggregate Borrow Material Design Team Performed a Redesign Reduced the Lightweight Quantity by 15% Saved Horry County $2 Million

COMPACTION VERIFICATION

Lightweight Aggregate Borrow Compaction Verification Challenges Interparticle Voids Particle Absorbed Moisture Particle Ceramic Solids Particle Pore Voids Interparticle Moisture

Compaction Control Laboratory Compaction Curves Target 95% Max Dry Density = 43 pcf Moisture Content Varied Significantly for the same Dry Density

Test Section #2 Compaction Control Test Section #2 - Evaluate Compaction Control Methods Compaction Control - 1 Cu. Ft. Steel Box, Calibrated Nuclear Density Gauge, Sand Cone, and EDG.

Test Section #2 Field Testing Set NG-1 MT-1 MT-3 MT-2 MC-1 MT-4 SC = Sand Cone NG = Nuclear Gauge EDG = Electric Density Gauge STB = Steel Test Box SC-1 EDG-1 SC-2 MTB-1 MC-2 MTB-2 MTB-3 STB NG-2 MT-5 SC-3 EDG-2 MC-3 MT-7 EDG-3 MT-6 MT-8 Compacted Lightweight Aggregate Borrow NG-3 MC = Hot Plate & Oven Moisture Content MT = Moisture Tester MTB = Moisture Tester in Steel Box

Test Section #2 1 Cu. Ft Steel Box (Control Test)

Test Section #2 Field Testing Sets Test Set Moisture Added Process Compaction Effort 1 As delivered Compact 3 passes with vibratory roller 2 No Water Added Scarify & Compact 4 passes with a vibratory roller 3 Added Water - 1 Pass Scarify & Compact 8 passes with a walk behind vibratory flat plate compactor 4 Added Water - 2 Passes Scarify & Compact 3 passes with a vibratory roller 5 No Water Added Scarify & Compact 4 passes with a vibratory roller 6 No Water Added Scarify & Compact 8 passes with a vibratory roller Added Water- 2.5 Passes Scarify & Compact 7 (Saturated) 3 passes with a vibratory roller

Test Section #2

Compaction Control Calibrated Nuclear Gauge

LIGHTWEIGHT AGGREGATE SUPPLY & DELIVERY

Big River Industries Livingston, AL Myrtle Beach, SC

Big River Industries 500 Mile Radius Livingston, AL

Livlite Big River Industries

Lightweight Aggregate Borrow Pre-conditioning

Lightweight Aggregate Borrow Pre-conditioning

Ramp B Construction Pre-conditioned Lightweight Aggregate CONSTRAINTS

Ramp B Construction Pre-conditioned Lightweight Aggregate CONSTRAINTS

GEOTECHNICAL INSTRUMENTATION

Geotechnical Instrumentation Settlement Monitoring 4 Magnetic Extensometer 10 Settlement Plates 12 VW Settlement Sensors 17 VW Piezometers 2 VW Data Collection Centers Slope Stability 6 Slope Inclinometers

VW Magnetic Extensometers Pre-Assembled ME Spider Magnet Telescoping Section

Settlement (Inches) Elevation (feet) Embankment Height (Feet) Instrumentation Results ME Extensometers 1.0 20 10 0-10 -20-30 -40-50 -60 0.0-1.0 Settlement (Inches) -2.0-3.0-4.0-5.0-6.0-7.0-8.0-9.0-10.0 12/1/2011 12/7/2011 12/14/2011 12/19/2011 12/21/2011 12/27/2011 12/29/2011 1/4/2012 1/12/2012 1/18/2012 1/25/2012 2/1/2012 12 11 10 9 8 7 6 5 4 3 2 1 0-1 -2-3 -4-5 -6-7 -8 12-22-2011 Embankment Construction Finished Embankment Height Top of LWF Datum Magnet 0 7 14 21 28 35 42 49 56 63 70 Days SA-1 SA-2-70

VW Piezometers

Instrumentation Results VW Piezometers

Settlement Plates

VW Settlement Sensors

VW Settlement Sensor Data Collection

Automated Data Collection VW Data Collection Center VW Settlement Sensors Cellular Phone Database Server VW Device Connection Board VW Data Collection Logger Internet VW Piezometers Power Source (Solar Power) Engineer

VW Device Connections VW Devices connected to 16-channel Board

Data Collection Center isite Logger with Solar Controller Charging Battery Inside DCC Enclosure & Solar Panel

X-Section End Bent 1 (South Bridge Abutment, 237+50)

Settlement Transverse Profile (South Bridge Abutment 237+83) Ramp A

0 7 14 21 28 35 42 49 56 63 70 77 84 91 98 105 112 119 126 133 140 147 154 161 168 175 182 189 196 203 210 217 224 231 238 Settlement Embankment Height (Feet) Ramp A Settlement Measurements 14 13 12 11 10 9 8 7 6 5 4 3 2 1 0-1 -2-3 -4-5 -6 2-12-2011 Embankment Construction Finished US-17 Bypass Settlement Sensor A-VWSS-2 2-14-2012 Surcharge Removed Days Since VWSS Installed Embankment Height Lightweight Fill Height SS Reading No. 1-5:00 SS Reading No. 2-12:00 SS Reading No. 3-19:00 SS Reading No. 4-23:00

Settlement Transverse Profile (South Bridge Abutment 237+83) Ramp C

0 7 14 21 28 35 42 49 56 63 70 77 84 91 98 105 112 119 126 133 140 147 154 161 168 175 182 189 196 203 210 217 224 Settlement (Inches) Embankment Height (Feet) Ramp C Settlement Measurements 13 12 11 10 9 9-13-2012 Emankment Construction Finished 12-14-2012 Surcharge Removed 8 7 6 5 4 3 Embankment Height Lightweight Fill Height SS Reading No. 1-5:00 SS Reading No. 2-11:00 2 1 0-1 -2-3 Days Since VWSS Installed

X-Section End Bent 7 (North Bridge Abutment, 250+26)

Settlement Transverse Profile (North Bridge Abutment - 250+26) Ramp B

0 7 14 21 28 35 42 49 56 63 70 77 84 91 98 105 112 119 126 133 140 147 154 161 168 175 182 189 196 203 210 217 224 231 238 245 252 259 266 Settlement Embankment Height (Feet) Ramp B Settlement Measurements 12 11 10 9 8 7 6 5 4 3 2 1 0-1 -2-3 -4-5 -6-7 -8-9 -10-11 -12 12-22-2011 Embankment Construction Finished Settlement Sensor 4-10-2012 Surcharge Removal Days Since VWSS Installed Embankment Height Lightweight Fill Height SS Reading No. 1-5:0:0 SS Reading No. 2-12:0:0 SS Reading No. 3-19:0:0 SS Reading No. 4-23:0:0

Settlement Transverse Profile (North Bridge Abutment - 250+26) Ramp D

Settlement Embankment Height (Feet) Ramp D Settlement Measurements 24 23 22 21 20 19 18 17 16 15 14 13 12 11 10 9 8 7 6 5 4 3 2-1 01-2 -3-4 -5-6 -7-10 -9-8 -11-12 -13-14 10-26-2012 Emankment Construction Finished 2-5-2013 Surcharge Removed 0 14 28 42 56 70 84 98 112 126 140 154 168 182 Days Since VWSS Installed Embankment Height Lightweight Fill Height SS Reading No. 1-5:00 SS Reading No. 2-12:00 SS Reading No. 3-19:00

PROJECT CONSTRUCTION

Traffic Control Stage 2 Ramp A Ramp B MSE Walls Lightweight Aggregate Borrow Material 2, and 3 Granular Surcharge (Normal Weight) 3 and 4 Triangular Spacing PVD Geotechnical Instrumentation

Traffic Control Stage 2 Ramp A Construction US 17 Bypass NB

Traffic Control Stage 2 Ramp B Construction US 17 Bypass NB

Construction Ramp A & B (PVD Installation)

Construction Ramp A & B (PVD Installation)

Construction Ramp A & B (MSE Wall Embankment Construction)

Construction Ramp A & B (MSE Wall Embankment Construction)

Sloped Lightweight Aggregate Embankment Lightweight Aggregate Borrow Material 4 Feet Long Biaxial Geogrids Placed on 2 Feet Vertical Spacing 2 Feet Thick Cover of Borrow Silty or Clayey Soil Materials

Sloped Lightweight Aggregate Embankment

Traffic Control Stage 3 Ramp C Ramp D MSE Walls Lightweight Aggregate Borrow Material 1, 2, and 4 Granular Surcharge (Normal Weight) 3 and 4 Triangular Spacing PVD Geotechnical Instrumentation

Traffic Control Stage 3 (Ramps A & B Completed) Ramps C/D Under Construction -Stage 3 Existing NB = Stage 3 SB Constructed Ramps A/B (Completed Stage 2)

Traffic Control Stage 3 (Ramps A & B Completed) Traffic on Ramp A Existing NB = Stage 3 SB

Construction Ramp C Traffic on Ramp C US 17 Bypass SB

Construction Ramp C Traffic on Ramp C US 17 Bypass SB

Construction Ramp C US 17 Bypass SB Ramp D

Construction Ramp D Traffic on Ramp B Ramp D

Traffic Control Stage 4 South Bridge Approach Backgate Bridge North Bridge Approach MSE Walls Lightweight Aggregate Borrow Material 1, 2, and 3 Granular Surcharge (Normal Weight) 3 Triangular Spacing PVD Geotechnical Instrumentation Bridge Abutment DSM (South 30 x 133 x 50 deep North 30 x 141 x 70 deep ) Longitudinal DSM (South 5 Wide / North 8 Wide)

CLOSING

Project Status Preliminary Engineering: 2008-2009 Right of Way Acquisition: 2009-2011 Construction: 2011 2014 Approximately 33% complete

Under Construction Traffic Stage 3 Ramps C/D have been constructed and will be ready to be paved in the near future Traffic Stage 4 Scheduled to Start April 2013 Deep Soil Mixing : Test Section / Test Pile / Production Bridge Abutment Foundation Construction Construct Bridge Approach Embankment & MSE Walls

Closing Geotechnical techniques are speeding up construction Positive feedback regarding construction traffic congestion and shifts Estimated project completion: Fall 2014 Project Cost $75.8 Million

Thank You Any Questions?