Hang-On Platform. Inspection Handbook. Version 1.1. Buildsafe Hang-On Inspection Handbook All Rights Reserved - Document not current once printed

Similar documents
Safety on Heights: Our Policy

Reliant Holdings Ltd Safety Management System

Universal Panels & Accessories

SAFE WORK METHOD STATEMENT

TANK REPAIRS INCLUDING SCRAP DISPOSAL SCAFFOLDING JOBS

Chapter 7. Roof Framing

SCAFFOLDS Revision No: 3

SCREEN PORCHES 101 DEVELOPMENT RESOURCES, INC Permit Requirements

Panel Jack Pro System BRACING, ALIGNMENT AND SCAFFOLDING EQUIPMENT

Configuration. User Guide. Version: Copyright 2017 Computer and Design Services Ltd GLOBAL CONSTRUCTION SOFTWARE AND SERVICES

HILLSBOROUGH TOWNSHIP CODE ENFORCEMENT

Section 8. Walking/Working Surfaces. 8.1 Objective. 8.2 Roles and Responsibilities. 8.3 General Requirements. Competent Person

Safe Work Procedure for installation of

Scaffolding and Raised Platforms

CITY OF FRUITLAND DIVISION OF PLAN REVIEW & PERMITTING DECK GUIDE. This design guide assumes all lumber to be pressure-treated Southern Pine.

Introduction. Estimated length: 30 minutes Audience: construction workers

References. EM , Sections 22 OSHA 29CFR (Subpart L ) UFGS [Latest] ANSI A

SCAFFOLDING PROCEDURE

WORKING AT HEIGHT PROCEDURE

NEBOSH International Certificate in Construction Safety and Health Unit ICC1 MANAGING AND CONTROLLING HAZARDS IN INTERNATINAL CONSTRUCTION ACTIVITIES

DEPAUL UNIVERSITY. Scaffolding Program. Environmental Health & Safety. April 2017

BP OIL -- TOLEDO REFINERY

Sales Hire Erections

Assessment. Challenge Assessment for Restricted Certificate of Competence. Advanced Scaffolding Elementary Scaffolding.

BASIC SCAFFOLDING KNOWLEDGE QUESTIONS

Contents DESIGNER S STRUCTURAL PRODUCTS GUIDE. Tegral Purlins & Rails

H 12 Heavy Duty Modern Tripod 8 Seat Swing Heavy Duty Hangers

BP U.S. Pipelines and Logistics (USPL) Safety Manual Page 1 of 7

The original WACO RED premium frame scaffolding and shoring systems.

METHOD STATEMENT First Fix Joinery

STANDARD PRACTICE INSTRUCTION

Walking-Working Surfaces

Systems Scaffold Tubular Scaffold Access Unit Installation Instructions

LEGAL SUPPLEMENT 43. to the Government Gazette of Mauritius No. 13 of 8 February 2014

CARROLL COUNTY BUREAU OF PERMITS AND INSPECTIONS RESIDENTIAL CODE COMPLIANCE GUIDELINES FOR DECKS

Layher. Keder Roof and Keder Hall. More Possibilities. The Scaffolding System. Layher Keder Roof and Keder Hall Instructions for Assembly and Use

DECK PLANS City Of Grand Rapids Building Safety Division

Scaffold Inspection Procedures for the Competent Person. Merle Errthum

SCAFFOLDING - Part 2 SELF INSPECTION CHECKLIST

Open-Web Trusses. Including Red-L, Red-W, Red-S, Red-M and Red-H Trusses. Design Flexibility. Outstanding Strength-to-Weight Performance

Scaffolding Update Including TG20:13 2 years on NEW SG4:15. Ray Johnson BSc Joint Managing Director

Guideline for the erection of Supaloc Steel Trusses Pre- Delivery preparation by the supplier Installing Supaloc Steel roof trusses...

Scaffolding Safety. Scaffolding

Anchor bolts ASTM F1554, Gr. 36 Wide flange beams ASTM A992, Fy = 50 ksi Misc. structural steel ASTM A36, Fy = 36 ksi

Document Number: HSE Created: February 21, 2013 SCAFFOLDING. Author: A Holland

SECTION CHAIN LINK FENCES AND GATES (GALVANIZED) A. Fence framework, fabric, gates, and accessories.

OSHA Rules for Scaffolding

General Requirements Yes N/A 1. Is the designer qualified for the proposed work?

Date Issued: June 2010 Revision Date: February 2013 Review Date: February 2016 Revision #

Erection manual. Tube-Lock Concept. van Thiel United b.v Page: 1 of 15

APPLICATION GUIDE PERFORM WITH PRECISION

At last! Construction bracing made easy...

Smarter. Safer. Leaner.

HATFIELD TOWNSHIP DECK/PATIO PERMIT PROCEDURES

CEILING & WALL SYSTEMS

CLIMA AGR. Mobile Aluminium Tower with Climbing Frames 1450/850 Camlock Advanced Guardrail USER GUIDE

Installation Guide for Domestic Decking in Recycled Plastic

INSPECTION GUIDELINES: JOIST AND UNDERFLOOR COMBO

TAMPA ELECTRIC COMPANY ENERGY SUPPLY SCAFFOLD PROGRAM

Installation Manual. Orion. TL-3 Steel Barrier. VHD (v2)

Scaffolding Procedures

TIMBER BARNS AND GARAGES

Conergy SolarFamulus II

The following are details of the code requirements of the 2015 International Residential Code for single-story decks.

Copies of the written program may be obtained at Where are copies of this written plan kept? (Insert building/room, etc.).

Scaffolding. Safety Guide. STOP! Before you climb

Management Plan for Walking/Working Surfaces & Fall Protection (29 CFR , 23, 66 App.C; 29 CFR ) ISD #535

Cavity ShAftwall System

DUQUESNE UNIVERSITY SAFETY PROGRAM FOR WORKING AT ELEVATED HEIGHTS

P: F: Resi-Ply FORMING SYSTEM BY DAYTON SUPERIOR

CITY OF CEDAR FALLS DEPARTMENT OF DEVELOPMENTAL SERVICES INSPECTION SERVICES DIVISION PHONE Residential Accessory Structures

INSULATION RETROFIT DESIGN ENERGY SOLUTIONS CENTRE YUKON GOVERNMENT

SPACE ONLY STAND FORM (To be filled by the Exhibitor)

City of Hughson Building Safety Division 7018 Pine Street Hughson, CA (209)

OCCUPATIONAL HEALTH AND SAFETY ACT SCAFFOLDING REGULATIONS

One and Two Family Additions

TAKING YOU TO NEW HEIGHTS IN SAFETY... kwikstage

Agenda. Safety Decking Basics Decking Issues Felt Kick Out Flashing Fascia

FrameSAFE Site-Specific Fall Protection Plan Template. Instructions for Use DO NOT INCLUDE THIS PAGE IN YOUR MANUAL SAMPLE

CUPLOK SGB CUPLOK SGB Group

Administrative Changes

We store: high. wide. deep. safe. Shelving racks. System C 50 single-tier multi-tier

FACT SHEET #2 DECK INFORMATION

ACE Jobsite Inspection Report Habitat for Humanity

EXCEL MODULAR STANDARD SCAFFOLD COMPONENT TECHNICAL MANUAL

Shaftwall and Area Separation Wall Systems.

SECTION ELEVATED BLEACHERS (Angle Frame Semi-Closed Deck)

Introduction to the Trade

4188 East Andrew Johnson Highway Morristown, TN

Temporary Construction Loads Over I-Joist Roofs And Floors

ACCESSORY STRUCTURE Building permit information For 1 & 2-family dwellings

Colorado Chapter of the International Conference of Building Officials. Building Guide. The Colorado Chapter of the International

Consequences Workers put in dangerous positions Fall

(6) Crawl boards and ladders used for roof work shall be securely fastened over the ridge of the roof or be otherwise effectively anchored.

Special Provision No. 540S01 March OPSS 540, Construction Specification for Highway Fence, is deleted and replaced with the following:

CHAIN LINK FENCES AND GATES

LINCOLN COUNTY REQUIRED INSPECTIONS (Last updated August 23, 2017)

1 Man Mobile Aluminium Tower System

Span 300 Instruction Manual

SAFE ERECTION AND USE OF ALUMINIUM TOWERS/SCAFFOLDS

Transcription:

Hang-On Platform Version 1.1 Inspection Handbook 1

BUILDSAFE Contents INSPECTION CHECKLISTS 3 INSPECTION CHECKLISTS 4 SIGNAGE 5 SIGNAGE 6 FIXING DETAIL / Connection 7 FIXING DETAIL / Connection 8 platform 9 platform 10 platform 11 platform 12 platform 13 platform 14 rail 15 Summary 16 2

INSPECTION CHECKLISTS Use the Installation checklist provided below to conduct installation audits, make sure that you reference the content in the handbook for further information. If further information is required please contact Buildsafe. Questions which are not applicable put N/A in Yes field. 1300 558 027 buildsafe.net.au HANG-ON INSTALLATION CHECKLIST 12/02/15 Construc on Company: Site Address: Installer (name on the Handover Cer ficate): Buildsafe Inspection Checklist should be used only by competent individuals. If the Installation does not look or feel structural DO NOT access the Installation, if this is the case the installation needs to be locked out by the principle contractor preventing use/access. If issues are identified with the installation or further information is required please contact Buildsafe to arrange for appropriate measures to be taken. ITEM YES NO SIGNAGE 1 Is there a Light Duty Pla orm sign a ached at the first access bay on the Hang-On system? 2 Is there an Access Point sign located at the access point on the Hang-On system? 3 Has the "Handover Cer ficate" been posi oned at the access point? FIXING DETAIL / CONNECTION 4 Has the system been installed outside of Electrical No Go / Exclusion Zones? Are all screws present in the hanger assembly? Hanger installed internal (of wall): Minimum 4 in foot, 1 in head Hanger installed external (of wall): Minimum 1 in foot, 2 5 in hook over top plate 6 Are all pins present in the knuckles? (Bo om, Middle and Top) PLATFORM 7 Is there a safe access to the working pla orm for all trades? 8 Is the maximum spacing between internal rail and the external face of the structure less than 225mm? 9 Is the maximum span of standards / transoms less than 3.6m? 10 Are the planks at the right height below the roof / gu er line for its intended use and pitch of roof? ( 26 = 1000mm, >26 <35 = 300mm) 11 Is the maximum distance of planks can levered to a non-returning corner less than 1150mm? 12 Is the maximum span of the suppor ng lower planks on a can levered corner less than 1450mm? 13 Have all plank tabs been ghtened so the planks are secure and si ng flush? 14 Are all step ups less than 500mm? If not, has a stop end been installed to eliminate the fall hazard? ITEM YES NO 15 Have back braces been used on this install, if so have the back brace floor plates been secured with two L-pins? Page 1 of 2 BRANCH ACCESS GROUPS AUTHOR/AUTHORISED REVISION DATE GLOBAL Admin / Manager / Office / Sales / Field / Yard / VIP B.Ceprnja 2 12/02/15 3

INSPECTION CHECKLISTS 1300 558 027 buildsafe.net.au RAIL 16 Are all cams on Supa and corner posts locked down? 17 Are rail joiners u lised on all internal and external corners of internal rail and on straight runs with an overlap is greater than 500mm? 19 If Hang-On runs into a scaffold system, is the rail joined to the scaffolding? 18 Is rail straight and plumb throughout the installa on? 20 Are rail stop ends present at the end of a straight run of pla orm? ACCESS AND EGRESS 21 Is there a safe access and egress point to the Hang-On system? Addi onal Comments: Person Conduc ng Inspec on : Date of Inspec on : Page 2 of 2 BRANCH ACCESS GROUPS AUTHOR/AUTHORISED REVISION DATE GLOBAL Admin / Manager / Office / Sales / Field / Yard / VIP B.Ceprnja 2 12/02/15 4

SIGNAGE 1. Is there a Light Duty Platform sign attached at the first access bay on the Hang-On system? 2. Is there an Access Point sign located at the access point on the Hang-On system? 3. Has the Handover Certificate been positioned at the access point? Handover Certificate must be completed and fixed in a pouch next to the Access Point. If the Hang-On Platform has been altered or re-installed a new Handover Certificate must be issued. Light Duty Platform Sign > Handover Certificate Access Point Sign Handover Certificate next to or below the Access Point sign. 5

SIGNAGE The Hang-On Platform install requires signage to be considered compliant and also for marketing purposes. Buildsafe takes great pride in the products we offer which is why all installations must have a Buildsafe sign installed. We want the world to know who we are and what we do. Hang-On Platform installation requires the following signs to be displayed; Access Point signs must be attached to the frame of the building in front of the Access Point. Light Duty Working Platform sign must be attached to Handrail directly at the point of access. Scaffold Incomplete Sign must be attached when the Hang-On Platform is deemed incomplete and dangerous to use. Elevator Acess Gate Sign must be attached next to a material access point. Large Buildsafe Sign is to be hung in the most visible location. 6

FIXING DETAIL / Connection 4. Has the system been erected within the Electrical No Go Zone for power lines? NO GO / EXCLUSION ZONES VICTORIA Domestic/low voltage power lines Less than 4.6m horizontally and 5m vertically. Industrial/high voltage power lines Less than 8m all round. QUEENSLAND Domestic/low voltage power Less than 3m all round. Industrial/high voltage power lines Less than 6m all round. NSW Any work within 4m of ALL power lines need referral to the network operator for any special conditions which need to be complied with. 5. Are all screws present in the hanger assembly? Hanger installed internal (of wall): Minimum 4 in foot, 1 in head Hanger installed external (of wall): Minimum 1 in foot, 2 in hook over top plate. The Hook of the Uni-Head retracted and fixed with 2 x 50mm screws into the top plate. Foot is secured in place with 2 x 50mm screws into the floor and 2 x 50mm into the bottom plate. Uni Head is secured to the frame by fixing 2 x 50mm screws into the top plate. There will be 55mm of the lower slot showing if the Pin is bearing at the bottom of the slot above. Foot is secured in place with 2 x 50mm screws into the floor and 2 x 50mm into the bottom plate. 7

FIXING DETAIL / Connection 6. Are all pins present in the knuckles? (Bottom, Middle and Top) Below is a photo showing the Knuckle installed to the Standard supporting the Transom. The Knuckle must have 3 security Pins installed, they are circled below in white. The Pins are critical to the safety of the Hang-on System and ensure the Hanger set up is structural. Note: There is a 4th pin once the transom is installed. 8

platform 7. Is there a safe access to the working platform for all trades? Look to identify safe and unobstructed access point for tradeperson to get on to of off the platform. 8. Is the maximum spacing between internal rail and the external face of the structure less than 225mm? Less than 225mm. 9

platform 9. Is the maximum span of standards / transoms less than 3.6m? 3.6 m max 10

platform 10. Are the planks at the right height below the roof / gutter line for its intended use and pitch of roof? ( 26 = 1000mm, >26 <35 = 300mm) Is the rail installed at the correct height for the application? (min 900mm above projected roof line). 900mm min to the top rail where that rail is horizontally less than 1m from the roof edge (d) (i) Catch Platform for less than 26 0 Posts may be vertical or incline away from roof as illustrated to a maximum angle of 26 0 Intersection of the projected roofline & a line vertically below the centre of the top rail 100mm Max (k) The platform deck shall have a clear minimumidth of 450mm - 2 plank (675mm planks in QLD. No obstructions are permitted above the platform serface (a) (b) Catch Platform for greater than 26 (c) Distance between platform and bottom edge of bottom rail must be no less than 150mm & no greater than 275mm Spread loads between two wall studs and/or bottom plate. 0 +26 0 For a roof pitch not greater than 26 0,where it is intended to locate a platform below the roof edge. The platform shall be located at a distance not greater 1m (d) Distance from cladding to platorm less than or equal to 225mm (g) Distance between roof line & top rail no less than 900mm & no greater than 1100mm (h) (i) Bottom Rails or toeboard as appropriate (c) Platform Deck (a) (b) 450mm nominal max. Between all rails. (j) Distance between platform and bottom rail must be no less than 150mm and no greater than 275mm (c) +26 0 For a roof pitch greater than 0 26, the platform must be no greater than 300mm below the roof edge (e) Distance from cladding & platform less than or equal to 225mm (g) 11

platform 11. Is the maximum distance of planks cantilevered to a non-returning corner less than 1150mm? 12. Is the maximum span of the supporting lower planks on a cantilevered corner less than 1450mm? Cantilever Returning Corner The maximum combined length of "B" & "A" is 2900 mm. ("A"cannot exceed 1450 mm) 2900mm All cantilevered Planks must be supported over 2 Transoms and nonreturning spans can span 1150mm max. Maximum cantilever 1450 mm = Minimum. "Back Span" 2900 mm. The "Back Span" must be a Minimum of 2 x the cantilever. If the cantilever of "A" is reduced to 900mm The allowable maximum cantilever of "B" would be 2000 mm. "A" A 1450mm Max Cantilever Canterliver "A" Distance from Transom to outside line or returning Planks The maximum span for the supporting (Lower Planks) is 1450 mm. 2125mm "B" B 1450mm Max Cantilever Canterliver 250mm minimum Overhang The maximum span for the supported (Upper Planks) is 1450 mm "B" Distance from Transom to inside line or returning Planks. 250mm minimum Overhang In the case of a 3 Plank system (675 mm wide) the maximum cantilever for the supported Planks is 1450 mm + 675 mm = 2125 mm. 12

platform 13. Have all plank tabs been tightened so the planks are secure and sitting flush? Hang-On System walk way is constructed out of aluminum planks, the Planks are supported by the transom and secured using Plank Tabs and Plank Locks as shown below. High setting - Two Planks. Low setting - One Plank. Plank Tab is tight and secured. Plank Lock needs to be installed on every 2nd trasom from start of every run. 13

platform 14. Are all step ups less than 500mm? If not, has a stop end been installed to eliminate the fall hazard? All step ups and downs in the platform height must be no greater than 500mm, if greater than 500mm there needs to be a stop end barrier to prevent a fall from height. 15. Have back braces been used on this install, if so have the back brace floor plates been secured with two L-pins? The Back Brace Setup is unique to Buildsafe in that it enables the Hanger to have no structural bearing on the wall and doesn t require the Floor Plate to be secured to the floor joists. Minimum Distance of 2.0m between the wall frame and the Floor Plate. Uni Head is not resting against the top plate. approx 5-10mm. Plate Tie with a Hanger less than 500mm away. Plate Ties are to be installed on all corners that are internal to the house. Foot Plate secured and attached the bottom hook of the Back Brace. 14

rail 16. Are all cams on Supa and corner posts locked down? 17. Are rail joiners utilised on all internal and external corners of internal rail and on straight runs with an overlap is greater than 500mm? 18. Is the rail straight and plumb throughout the installation? Rail Joiner Rail runs straight and is plumb Rail is secured into the Supa Post Rail Supports by the Cam locking system. Unlocked Locked 19. If Hang-On runs into a scaffold system, is the rail joined to the scaffolding? The system needs to be tied into the scaffold if there is a prexisting scaffold system, this ensures that risks such as falling from height are eliminated, the system will be tied in at the rail section and the planks will run into the prexisting scaffold decks. 20. Are rail stop ends present at the end of a straight run of platform? Where the system is installed without returning corners and is not tied into a prexisting scaffold installation a stop end needs to be installed. 21. Is there a safe access and egress point to the Hang-On system? The system needs to have clear and unobstructed access on and off the platform from tools, materials and rubbish, this must be maintained for the duration of the hire period of the system. 15

Summary Use the following summary point as a guide when conducting the inspection: There is a Light Duty Platform sign attached at the first access bay on the Hang-On system. There is an Access Point sign located at the access point on the Hang-On system. The Handover Certificate has been positioned at the access point. The system has been installed outside of The Electrical No Go / Exclusion Zones. All screws are present in the hanger assembly? Hanger installed internal (of wall): Minimum 4 in foot, 1 in head Hanger installed external (of wall): Minimum 1 in foot, 2 in hook over top plate. All pins are present in the knuckles? (Bottom, Middle and Top). there is safe access to the working platform for all trades. The maximum spacing between internal rail and the external face of the structure are less than 225mm. The maximum span of standards / transoms are less than 3.6m. The planks are at the right height below the roof / gutter line for its intended use and pitch of roof? ( 26 = 1000mm, >26 <35 = 300mm). The maximum distance of planks cantilevered to a non-returning corner are less than 1150mm. The maximum span of the supporting lower planks on a cantilevered corner are less than 1450mm. All plank tabs have been tightened so the planks are secure and sitting flush. All step ups are less than 500mm? If not, has a stop end been installed to eliminate the fall hazard. Back braces have been used on this install, if so have the back brace floor plates been secured with two L-pins? All cams on Supa and corner posts are locked down. Rail joiners areutilised on all internal and external corners of internal rail and on straight runs with an overlap is greater than 500mm. If Hang-On runs into a scaffold system, is the rail joined to the scaffolding? Rail is straight and plumb throughout the installation. Rail stop ends are present at the end of a straight run of platform. There is a safe access and egress point to the Hang-On system. 16

www.buildsafe.net.au 17