Guide for Misereor partner organisations on commissioning external evaluations locally

Similar documents
ToR for the External Evaluation of the AMEDIP project

DURATION : 30 working days over the period 20 September November 2016

MEMORANDUM OF AGREEMENT

Purpose of the evaluation

External Evaluation of the Mahatma Gandhi Institute of Education for Peace and Sustainable Development (MGIEP) Terms of Reference

ROSTERS OF JUNIOR AND SENIOR EXPERTS Specifications of the Call for expression of interest

United Nations Children s Fund (UNICEF) Supply Division, Copenhagen, Denmark

TERMS OF REFERENCE. Partnership Advisor. Resource Mobilization and Partnership Strategy for UNDP Belize

INDIVIDUAL CONSULTANT PROCUREMENT NOTICE

Terms of Reference EXTERNAL EVALUATION ( ) OF FOKUS PROGRAMME WOMEN S ECONOMIC PARTICIPATION AND RIGHTS IN UGANDA

TERMS OF REFERENCE. Independent Evaluation of the ILO Action Plan for Gender Equality

EU PROJECT MANAGER (PART-TIME) ATLANTIC SOCIAL LAB (27 MONTH CONTRACT)

RULES GOVERNING THE SECONDMENT OF NATIONAL EXPERTS TO THE EUROPEAN PARLIAMENT BUREAU DECISION 4 MAY 2009

Evaluation Policy for GEF Funded Projects

Terms of Reference (ToR) End-of-the Programme Evaluation UNDP Support to Inclusive Participation in Governance May 2013

Terms of Reference for a Gender Analysis

Plan International AU Liaison Office ToR for PAO Advocacy Strategic Review

Guidance: Quality Criteria for Evaluation Reports

SEARCH FOR COMMON GROUND MOROCCO is seeking Midterm Evaluator [Consultant] Region Tangier - Tetouan, Morocco

Assessment of the national capacities for child rights monitoring

UNLIREC TERMS OF REFERENCE

0.2 The Remuneration and Appointment Committee is a standing committee of the Supervisory Board.

UNESCO AMMAN OFFICE. Call for Proposals for Senior Individual Consultant JOR/CONS/17/09

STATE OWNED ENTERPRISES REMUNERATION GUIDELINES

EXPATRIATE CONTRACT OF EMPLOYMENT TEMPLATE

TITLE OF CONSULTANT: Individual Consultant (IC) to Develop a Strategic Plan and Implementation Program for Business Botswana

The PSM Consultant will work in close collaboration with UNDP Country Office staff, governments, UN agencies in the areas of their expertise.

INDIVIDUAL CONSULTANT PROCUREMENT NOTICE. for individual consultants and individual consultants assigned by consulting firms/institutions

ACORD (Agency for Cooperation and Research in Development) Enhancing Iddir s Engagement in Slum Upgrading in Dire Dawa, Ethiopia ( )

TERM OF REFERENCE. Consultant: Technical Adviser to support the PRAIA Group on Governance Statistics Location : Praia, Cabo Verde. 4 April h00

LETTER OF APPOINTMENT FOR INDEPENDENT DIRECTOR

TERMS OF REFERENCE FOR INDIVIDUAL CONTRACTOR

Head of Finance, Governance and Risk Management in the Residential Tenancies Board (RTB) Assistant Director (Professional Accountant Grade I)

So, in application of and with reference to the above points, this agreement is concluded between:

ARN2016 Procurement Regulations Utility Sectors 2016

Request for proposals International Team Leader, Phase 1 of EU-financed project on Administrative Service Centres

IAS EVALUATION POLICY

Two International Consultants Data and Statistics for the SDGs

Working Party on Aid Evaluation

VACANCY NOTICE 06/04/2017 AT NOON, BARCELONA GMT+1

CI-GEF PROJECT AGENCY MONITORING AND EVALUATION POLICY FOR GEF-FUNDED PROJECTS

Open Call for Consultancy Services. Reference Number: Expert on Public Consultations on Draft Legislation and Public Policy Documents

INDIVIDUAL CONSULTANT PROCUREMENT NOTICE. Reference: PN/FJI

Strategic Evaluations I. GUIDANCE FOR PROCESS & CONTENT

UNESCO AMMAN OFFICE. Call for Proposals from Senior Individual Consultants AMN/CONS/17/07

SENIOR CONSULTANT -FORMULATION OF AN ACTION DOCUMENT (PROJECT PROPOSAL) ON GOVERNANCE CAPACITY DEVELOPMENT IN THE CONTEXT OF PALOP-TL /EU COOPERATION

REQUEST FOR PROPOSALS

Agence canadienne de développement international 200, promenade du Portage Gatineau (Québec) K1A 0G4 Tél. : (819) Sans frais :

A DECREE ON PROCLAMATION OF THE LAW ON CONCESSIONS AND PUBLIC PRIVATE PARTNERSHIP

Pangani River Basin Management Project. Terms of Reference for Project Internal Review

UTKARSH SMALL FINANCE BANK LIMITED

Appointment Letter for Independent Directors

Terms of Reference Audit Consultant UN Women Audit Unit Office of Audit and Investigations

The APIC Audit Programme Version 3, August 2010

GENERAL TERMS AND CONDITIONS

TERMS OF REFERENCE Bangkok, Thailand with possible travel to countries in Asia Pacific.

FRAMEWORK PARTNERSHIP AGREEMENT WITH HUMANITARIAN ORGANISATIONS

EXTERNAL EVALUATION OF THE EUROPEAN UNION AGENCY FOR FUNDAMENTAL RIGHTS DRAFT TECHNICAL SPECIFICATIONS

Terms of reference for the evaluation of the project co-financed by Secours Catholique Caritas France and implemented by its local partner:

Terms of Reference Development of a Resource Mobilisation Strategy and Action Plan for the UN in Rwanda

INDIVIDUAL CONSULTANT PROCUREMENT NOTICE. Terms of Reference. Kiribati SDG Voluntary National Review to High Level Political Forum

WORK PLACEMENT CONTRACT FOR WORK PLACEMENTS, INTERNSHIPS AND GRADUATION ASSIGNMENTS IN THE NETHERLANDS

This Agreement (hereinafter: "the Agreement") is made and entered into on May 13 th, 2003, by and between

Terms of Reference. Projects Outputs Evaluation

GENERAL AND ORGANISATIONAL REQUIREMENTS

Translation from Polish

Development of Gender Analysis and Gender Action Plan for the MRCS. Duration: A maximum of 30 working days tentatively during April-May 2017

Guidelines for FIBAA Experts in Accreditation & Certification Procedures

Terms of Reference. Scope of the Required Services

CONTRACT WITH THE TEMPORARY WORKERS (TERMS OF ENGAGEMENT/CONTRACT FOR SERVICES) 1.1. In these Terms of Engagement the following definitions apply:

REPUBLIC OF SUDAN MINISTRY OF HUMANITARIAN AFFAIRS

Selection Procedure to renew the Banking Stakeholder Group (BSG)

Role Type Pay Band Location Duration Reports to:

Evaluation of the NepalMonitor Project (NMP)

This tender material elaborates the tender advertisement published at cf. annex 1.

Auditing of Swedish Enterprises and Organisations

ADVERTISEMENT CALL FOR CONSULTANCY (CFC) NO. 2016/11- International Consultant: Market Resilience to Climate Change Project, Suva, Fiji

Country Portfolio Evaluations I. GUIDANCE FOR PROCESS & CONTENT

United Nations Children s Fund (UNICEF) Phnom Penh, Cambodia

TERMS OF REFERENCE FOR DEVELOPMENT OF A PROJECT DOCUMENT FOR ECOSYSTEM-BASED ADAPTATION PROJECT UNDP LESOTHO

MADHYA PRADESH GOVERNMENT Madhya Pradesh Forest Department Satpura Bhawan, Bhopal (M.P.) EXPRESSION OF INTEREST (EOI)

POLICY EXPERT (Credit/Market Risk)

Terms of Reference. 1. Evaluation Summary. 2. Background and context Concerned for Working Children CWC projects

TERMS OF REFERENCE. Consultant, Market Resilience to Climate Change Project, Fiji CFC No. 2016/11 RE-ADVERTISEMENT

Subject: Letter of Appointment/ Re- appointment as an Independent Director of the Company.

International Open Call for Consultancy Services. Expert on justice and judicial training. Reference Number 031/017

Draft Terms of Reference Strategic planning consultant

2.1 The place of employment will be at the office of the Employer in [place].

LONG-TERM AGREEMENT (LTA) FOR ON-CALL LEGAL AND EVIDENCE MANAGEMENT TECHNICAL ADVISER

STAFF VACANCIES Ref. 1714SNE02

Template for ToR for Transaction Advisory Services

INDIVIDUAL CONSULTANT PROCUREMENT NOTICE

Consultant to support monitoring and evaluation planning for Capacity Development Partnership Fund (CDPF) Phase III

INSTRUCTIONS TO TENDERERS

Summative Evaluation Guidelines for Jobs Fund Partners

Mid-term Project Evaluation Guidance Note For EIF TIER 1 Funded Projects: Support to National Implementation Arrangements

TERMS OF REFERENCE CNF/2015/GEO-004

NOTICE OF RECRUITMENT N AST-7/ 2015

FRAMEWORK BORDER-CROSSING AGREEMENT

VACANCY NOTICE TRAINING SPECIALIST REF: PAC CA 01/2018

Transcription:

Guide for Misereor partner organisations on commissioning external evaluations locally Greetings from Aachen, Germany! For many years our partner organisations in Africa, Asia and Latin America have been drawing benefit from evaluations. They provide important occasions and opportunities for reflecting on, reviewing and further improving the work done in the projects and programmes. As part of our efforts to assess outcomes, impacts and success more systematically, Misereor expects its project partners to commission regular evaluations of projects that are implemented with Misereor support. To ensure that these evaluations are also accepted by our donors and supervisory bodies as part of our reporting obligations, certain points must be observed. We have therefore produced this guide, which we would ask you to observe when you are about to prepare an evaluation. It comprises: information for partner organisations on commissioning external evaluations, and tips for partner organisations on drafting agreements with expert consultants. On completion, please forward the evaluation report to Misereor. If you have any questions about your evaluation, please do not hesitate to contact us (evaluation@misereor.de). With our best wishes and kind regards, Enclosures: 1a) Information for Misereor Partner Organisations on Commissioning External Evaluations Locally 1b) Recommended Structure for the Terms of Reference of Evaluations 2a) Tips for Misereor Partner Organisations on drafting Agreements with Expert Consultants 2b) Specimen Agreement for the Assignment of an Expert Consultant

Information for Misereor Partner Organisations on Commissioning External Evaluations Locally Misereor expects its project partners to commission external evaluations of their work at appropriate intervals. The reports on these evaluations are important to Misereor in that they enable us to assess and document the success of project work and to meet our own reporting and accountability obligations. The evaluations commissioned by our partner organisations must therefore fulfil certain criteria, which are outlined below. What is an independent evaluation? Selecting the expert consultant An independent evaluation requires the perspective of an independent expert consultant. We would ask you to identify and enter into an agreement with this person yourself, bearing in mind the following: 1. The person must have the professional/technical expertise necessary to analyse and assess the project. 2. The person must have the methodological know-how necessary to carry out the evaluation. In terms of the two points above, the suitability of the potential expert consultant is best judged by referring to the written curriculum vitae and, if possible, by conducting a personal interview. 3. The person must not have close links to the project or the legal holder of the project. The following are therefore excluded: Employees or former employees of the legal holder, their direct relatives and spouses, Members of supervisory bodies of the legal holder of the project, their direct relatives and spouses, Persons who provided advisory etc. inputs during project implementation, Persons who are in some other way dependent on the project or the legal holder. Expert consultants who have had previous contact with the project exclusively within the context of evaluations may be commissioned. Evaluation methodology Generally, Misereor recommends that a participatory procedure be adopted, i.e. project staff and beneficiaries should be included in the collection and assessment of data. This does not prejudice the independent nature of the evaluation. Self-evaluations can also be accepted as long as these are conducted in collaboration with an independent expert consultant who provides the independent external perspective and documents this in a separate or supplementary report. Evaluation report For each evaluation, a report must be produced that is wholly or partly written by the independent expert consultant, and for which he/she accepts responsibility. Contents of the evaluation (terms of reference) The evaluation must, at any rate, address the following aspects mentioned in the DAC Criteria for Evaluating Development Assistance 1 : 1 Development Assistance Committee of the Organisation for Economic Cooperation and Development (OECD): DAC Criteria for Evaluating Development Assistance (http://www.oecd.org/document/22/0,2340,en_2649_34435_2086550_1_1_1_1,00.html) - 1 -

Relevance are we doing the right things? Outcomes and impacts what has actually changed for the target groups as a result of the project? Effectiveness are we achieving the project objectives? Efficiency are the project objectives being achieved cost-efficiently? Sustainability are the achievements sustainable in the longer run? The enclosed specimen evaluation format ( Recommended Structure for the Terms of Reference of Evaluations ) provides further assistance. Within this framework, the questions should be formulated so as to provide you with valuable information for further and improved project work. - 2 -

Recommended Structure for the Terms of Reference of Evaluations The Terms of Reference (ToRs) set out the evaluation objectives and are agreed between all parties involved in the task to be performed by the evaluation team. In order to ensure that an evaluation fulfils the expectations of all stakeholders, it is necessary that the ToRs are formulated as clearly and precisely as possible. The following information and explanations may be of help in this task. The Terms of Reference should be formulated individually for each evaluation in order to ensure that they are appropriate to the individual project setting and the evaluation objectives. 1. Introduction This section should describe the project to be evaluated, outline the history of the evaluation (Who initiated it? Why was it initiated?), and state the period considered by the evaluation (in addition to the present project, one or more previous projects as well?). If relevant, some general background information on the region and sector can be included. 2. Objectives of the evaluation This section should state as precisely as possible the proposed objectives of the evaluation. This is especially important for the evaluation team, as the evaluation objectives critically affect exactly what information is to be collected and the collection methods to be applied. 3. Key issues We recommend that the key issues to be addressed in the evaluation are formulated as concrete questions that are expected to be answered by the evaluation. When drawing up the list of questions, the DAC criteria 2 for evaluations should be taken into account: relevance, impact (for MISEREOR "effects" or "outcomes and impacts"), effectiveness, efficiency, and sustainability. The following table includes a description/explanation of each criterion complete with example questions. These key questions should be tailored to the requirements of the individual evaluation (i.e. they can be modified, formulated more precisely, or omitted). Relevance: The extent to which the project is suited to the priorities and policies of the target group, the organisation responsible for the project and the donor organisation. It is useful to consider the following questions: - To what extent is the intervention important for the target group (for example, does it focus on an important problem/bottleneck)? - To what extent are the initial objectives of the project still appropriate? - Are the planned activities and outputs of the project consistent with the project objective and the development goal (coherence of the planned chain of causality)? 2 See: http://www.oecd.org/document/22/0,2340,en_2649_34435_2086550_1_1_1_1,00.html - 1 -

Outcomes and impacts: The positive and negative changes produced by a project, directly or indirectly. This involves the main outcomes and impacts resulting from the project. The evaluation should be concerned with both intended and unintended outcomes and impacts. It is useful to consider the following questions: - What real difference has the project made to the beneficiaries in terms of social, economic, political, cultural, and ecological changes, taking into account the gender dimension? - How many people have been affected? - Which other factors contributed to the changes that were generated, and to what extent can the changes be attributed to the project activities (plausibility)? - Has the real chain of causality been consistent with the chain of causality established at the planning stage? If not, what were the differences? Effectiveness: A measure of the extent to which a project achieves its objectives as laid out in the project contract, i.e. a comparison of the intended outcome with the observed outcome (see 'Outcomes and impacts' above). It is useful to consider the following questions: - To what extent were the objectives achieved or are likely to be achieved? What information is available with regard to the agreed indicators that will help answer this question? What other information is available with regard to the achievement of the objectives? - What were the major factors influencing the achievement or non-achievement of the objectives? - Were the initial objectives realistic? Efficiency: In general terms, efficiency is a measure of the relationship between outputs and inputs. In the first instance this means looking at the qualitative and quantitative products and outputs of the project in relation to the resources (i.e. inputs) used. In particular cases, it is helpful to relate the effects of the project to the resources used. It is useful to consider the following questions: What evidence is there to indicate that the project was implemented with due efficiency under the given circumstances? Did the project act in an economical and cost-conscious way? What are the parameters on which this assessment is based (e.g. costs per project output: costs per training course or trainee, or costs per hectare of converted agricultural land; costs per beneficiary )? Are any benchmarks for these parameters available from other projects or institutions? How well is the organisation able to perform? Possible areas to consider may include e.g. management and administration systems, communication structures, an appropriate PME system, regional and thematic breadth or concentration. (Where appropriate) What is the relation between the observed effects and the resources used? Sustainability: Sustainability is concerned with measuring whether the benefits of a project are likely to continue after funding has been withdrawn. Benefits need to be environmentally as well as economically, technologically and socially sustainable. It is useful to consider the following questions: - To what extent are the benefits of the project likely to continue once donor funding has ceased? - What were the major factors which influenced the achievement or non-achievement of sustainability of the project? - 2 -

If relevant to the context and the project, we recommend that questions on cross-cutting issues to be answered by the evaluation should also be included, for example relating to gender, human rights, community participation, peace-building and civic conflict transformation, good governance, civil society involvement, HIV/Aids, health and the environment. 4. Methodology It is important to bear in mind that a project not only affects a single homogeneous target group, but different groups with different interests and perspectives. Evaluations should take adequate account of the perspectives of these groups. Generally, a set of varied and adapted methods is adopted (usually applying a gender-sensitive approach) that focuses on quantitative and qualitative aspects in the following steps in the evaluation: - Prior to the field visit: a review of the documents, preparation of interview guidelines, quantitative survey,... - During the field visit: kick-off workshop, document review, participant observation, quantitative survey, in-depth interviews, semi-structured interviews, focus group discussions, contextual analysis, key informant interviews, debriefing workshop, 5. Organisation of the mission This section includes details of: - The expertise required, the members of the evaluation team and their roles - The schedule: - duration of preparatory activities - dates of the mission (including kick-off workshop) - date of the debriefing workshop at the project location, which should provide the project partner with an opportunity to give feedback on the preliminary results of the evaluation mission - deadline for the (draft) report, and further procedure for submission and acceptance of the report (including time slot for debriefing at MISEREOR Head Office). 6. Report This section covers the preparation and content of the report. The report documents the evaluation activities and results and serves as a reference for followon activities. It must therefore have a clear structure and be complete. The following questions should be clearly addressed in the Terms of Reference: - Who will write the report? Who will have overall responsibility? - How long is the report expected to be? - What should be included in the report? - What are requirements with respect to the reporting format? The following outline, based on past experience, has proven useful for this purpose: - The detailed section of the report should be preceded by a brief (2- to 3-page 3 ) summary. This should briefly outline the objectives of the mission, the procedure followed, the main results 3 For cross-sectoral evaluations the summary may be up to five pages in length. - 3 -

(particularly those with a direct bearing on action to address the main issues), plus an overall assessment of the work evaluated and the key recommendations. - A section on methodology should describe and explain precisely the evaluation assignment itself and the methodology selected and applied in relation to the assignment (see also Annex 1 of the Information Document Evaluation in the Development Cooperation Activities of MISEREOR and its Partners) 4. - The following section of the main part of the report should describe the project and the project context as a basis for the analytical and evaluative sections that follow. Aspects to be considered: o Project context and framework conditions o Project goals and objectives o Project strategy/approach o Description of project activities. Was there a difference between the planned activities and those actually implemented? Were there any lobbying or networking activities? o Description of target groups. How many were reached through the activities? o Organisational structure. How does project administration work? o Description of the cooperation with MISEREOR - The next section should focus on the findings related to the questions listed above under 'Key issues'. This is the main section for data presentation and analysis. It deals with the issues addressed by the mission, one by one under the corresponding headings. In this section the observed outcomes and impacts should be substantiated; please include materials to support the arguments put forward (tables, texts, tools used such as questionnaires etc.) in the annex. - The conclusions follow logically from the findings but are clearly distinguishable from these. The conclusions should provide answers to the main evaluation questions, include an overall assessment of the work evaluated and list any lessons learnt. - The recommendations follow logically from the conclusions. They should be actor oriented (Who should do what?) and prioritised (What is most important? What could be improved above and beyond that?). If the concluding workshop showed that evaluation results, conclusions or recommendations were not shared by the project actors, then the different perspectives should be clearly explained in the report. In terms of formal layout, the report should include: Cover sheet (including project and evaluation numbers) Page numbers List of contents List of acronyms and abbreviations Annexes, containing: o Terms of reference o Chronology of the mission o List of interviewees o (If applicable:) List of documents on which the evaluation was based EQM 2014 4 http://www.misereor.org/cooperation-and-service/evaluation.html - 4 -

Tips for Misereor Partner Organisations on drafting Agreements with Expert Consultants 1. Establishing the terms of reference The terms of reference are the basis of an evaluation. They provide the criteria for selecting the expert consultant: What qualifications and experience must the expert consultant have in order to achieve the objectives stated in the terms of reference and to address the problems at hand? We would therefore suggest that you draft the terms of reference right at the beginning (please refer to the enclosed text: Recommended Structure for Terms of Reference of Evaluations). 2. The agreement to be concluded with the expert consultant Before concluding an agreement with an expert consultant, we first of all recommend that you: check whether the expert consultant meets the requirements resulting from the terms of reference; find out what fees are usually paid for such services in your country (as a basis for negotiation). Please take into account that freelance consultants may demand higher fees than expert consultants who are employed, have secure incomes, and take on such assignments from time to time in addition to their regular jobs; calculate, on the basis of the terms of reference, the number of working days the expert consultant will realistically need for preparation, the work in the project (field phase) and producing the report. In this context, we also recommend that the expert consultant be given adequate time and opportunity to familiarise him/herself with the essential information on the project well before the field phase. The agreement and the terms of reference, which are an integral part of the agreement, stipulate the services and tasks that you expect the expert consultant to perform, and the remuneration and reimbursement of expenses the expert consultant expects from you. We recommend that the following points always be included: total number of days of the expert consultant s assignment; fee to which s/he will be entitled (either as a per-diem amount or a lump sum); reimbursement of expenses incurred by the expert consultant during the assignment (board and lodging while working in the project; travel to and from the project; transport on site where these costs are not covered by the partner organisation; working materials, if applicable); deadline for delivery of the written report; a clause stipulating that the expert consultant is responsible for arranging and paying for adequate health and life insurance cover for the duration of the assignment; a clause setting out the arrangements that apply if the expert consultant does not perform his/her duties (either at all or only in part) or if the services provided do not satisfy quality requirements. Please find enclosed our recommended Specimen Agreement. If you have any queries we will be pleased to help. Thank you for your cooperation. - 1 -

Specimen Agreement for the Assignment of an Expert Consultant Name and address of partner organisation and Mr/Ms (Name) (Address) Phone:, mobile:, e-mail: hereby agree on the following: - hereinafter called "the Party Ordering" - - hereinafter called "the Expert Consultant - I. Object of the assignment The Party Ordering entrusts the Expert Consultant with the following evaluation: (please see Terms of Reference [ToR], Annex I for details). II. Details of procedure (1) The Expert Consultant's assignment shall start at the point of time he/she begins preparing it. However, the maximum number of days to be devoted to preparatory work shall be, while a maximum of days shall be spent on the compilation of the report and other final assignment completion work. The Party Ordering and the Expert Consultant shall jointly determine the starting date of the field work phase of up to days. The Party Ordering shall set the date of the final debriefing meeting following submission of the report. (2) The Party Ordering shall provide the Expert Consultant with all available records and documents required for a successful execution of the assignment in due time before the field work phase starts. (3) The Expert Consultant shall prepare and provide to the Party Ordering a report (please see ToR Annex I for details). The report shall be written in (language) and submitted to the Party Ordering by (deadline). In addition, a revised version may be required by the Party Ordering at a later date. III. Duration and termination of the Agreement (1) This contractual relationship will end when the written report(s) mentioned above under Article II. (3) has (have) been duly received by the Party Ordering. IV. Remuneration and reimbursement of expenses (1) The Party Ordering shall pay the Expert Consultant a daily fee of (currency) (in words: [currency]) a flat fee 5 of (currency) (in words: [currency]) for the preparation, field work, and writing of the report as per account rendered. 5 A flat fee may include per-diem and overnight accommodation allowances; where this is the case, it must be explicitly mentioned. - 1 -

(2) The Party Ordering shall also pay the Expert Consultant accommodation and per-diem allowances of (currency).00 (daily allowance) and (currency).00 (night-lodging allowance) for the duration of the field work. If and to the extent the Expert Consultant enjoyed free board and/or lodging, no per-diem and/or night-lodging allowances will be paid. (3) All necessary travel and transport expenses shall be reimbursed on submission of receipts up to an amount of (currency).00. Other inevitable disbursements (visa fees, expenses for travel prophylaxis, communication expenses, costs of materials and photocopying etc.) shall also be reimbursed on submission of receipts up to an amount of (currency).00. (However, expenses for insurances of the Expert Consultant shall not be reimbursed). In exceptional cases, expenses can be reimbursed on a flat-rate basis. (4) The Party Ordering shall advance an amount of up to (currency).00 towards travel expenses and the fee on request. The residual amount due to the Expert Consultant shall then be disbursed on completion of the assignment as per account rendered. (5) The final account shall be rendered as soon as possible after completion of the assignment. (6) The two parties agree that all duties and taxes resulting from this Agreement shall be paid by the Expert Consultant. V. Insurance (1) The Expert Consultant hereby assures that he/she is in good health and there are no medical objections to a fieldwork assignment in the country of destination. (2) The Expert Consultant shall take out at his/her own expense adequate insurance(s) covering in particular all risks to his/her life and health. (3) The Party Ordering shall not be liable for any damage suffered by the Expert Consultant as a result of failure to comply with the aforementioned regulations. VI. Secrecy / Dissemination of results (1) The Expert Consultant is bound to secrecy where such facts as may have come to his/her knowledge in connection with the implementation of this assignment are concerned. The Expert Consultant shall not pass on or disclose any of this information without prior permission of the Party Ordering. VII. Final provisions (1) Any alterations or additions to this Agreement shall have to be made in writing in order to be valid. (2) The invalidity of any provision of this Agreement shall not affect any other part of it....... Place, date Place, date......... For the Party Ordering The Expert Consultant Annex I: Terms of Reference EQM/Sprachdienst 03/2010-2 -