Capital Projects Update

Similar documents
Capital Projects Update

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

Cheldelin Middle School

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

BOND CONSTRUCTION UPDATE

Program Update. Chino Health Science Parking Lot

Facility Improvements

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

Applying for Permits to build a new house in Linn County

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #160 Douthit Hills Student Community, Clemson University Project Tony Greene

Laker Hall Program Study Intercollegiate Athletics. Preferred Concept & Project Phasing SUCF Project No

Yardmen Arena Expansion & Renovation Project Update

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

The Homeowner s Building Application Checklist for Constructing a Residential Addition

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number

THE CONSTRUCTION SUPERVISOR

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3

WILKINSON ELEMENTARY SCHOOL

School Without Walls

Christopher Glinski Construction Management. AE Senior Thesis Columbia Heights Community Center. Appendix B. Project Summary /Detailed Schedule

NEW YORK STATE MAIN STREET PROGRAM BEFORE & AFTER

Schedule of Values Cruise Terminal 2 Expansion

HOUSE REPAIRS & RENOVATIONS BUILDING PERMIT REQUIREMENTS

BuildingAdvisor.com Estimating Checklist

Table of Contents. Division 2 Site Work Site Preparation Site Demolition Tree Protection Excavation, Trenching, and Backfilling for Utilities

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

St. Germain Facility Study

Morehouse School of Medicine

Section 4 - Design and Construction Overview

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #154 Douthit Hills Student Community, Clemson University Project Tony Greene

LOVEJOY Independent School District

Toronto Community Housing Executive Summary 2016/2017. BCA Report. Sample House High FCI

Project Green House. Green Team. Making the world greener one house at a time

Division 09 FINISHES TABLE OF CONTENTS

Residential Building Inspections

Detached Garages and Building Permits. 1 and 2 Family Dwellings

Successful Home Contracting

Property Condition Assessment

Sri Ganesha Temple HTNT Construction Update (June, 2016) Copyright All Rights Reserved.

SPACE TYPE: OUTSIDE PARKING (STRUCTURE)

OWNER S REPONSIBILITIES AND PREPARATION INSTRUCTIONS. Schedule "C"

M-DCPS DESIGN CRITERIA Table of Contents

BUILDING PERMIT INFORMATION GUIDE FOR THE HOMEOWNER

Application for Commercial Plan Review and Building Permit. Address:

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

Montgomery County Public Schools Facilities Guide DIVISION 0 - CONDITIONS OF THE CONTRACT

Davis Frame Co., Inc. Construction Budget Considerations

The Inspection Process. Waxhaw N.C.

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form.

CENTENNIAL SCHOOL DISTRICT

HOLDER CONSTRUCTION COMPANY Superintendent s Weekly Activity Report #139 Douthit Hills Student Community, Clemson University Project Tony Greene

Structural Inspection

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

BIDDING SHEET CHECKLIST--SUBCONTRACTORS AND SUPPLIERS SUBCONTRACTOR/ PHONE DATES SUPPLIER NAME: CALLED BID. Sample

STRUCTURAL ASSESSMENT OBSERVATION REPORT

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

RESIDENTIAL NEW CONSTRUCTION PLAN REVIEW CHECKLIST

Basic Information for Obtaining Permits, Submitting Plans, Scheduling Inspections, etc.

Built to Order. Stile. Frames. Section Contents. Profiles. Elevations. Double Egress Frames Pocket Frames

Pembridge The Country Club Collection TOWNHOMES AT CRYSTAL SPRINGS

Quality Inspection 8618 London Heights San Antonio, TX Phone: (210)

PROGRAM COST MODEL. for. PEER Tall Buildings Study Concrete Structural Option Los Angeles, California

EVALUATION AND ASSESSMENT TROY ELEMENTARY SCHOOL 44 SCHOOL STREET TROY, NEW HAMPSHIRE

LECKIE ELEMENTARY SCHOOL

Technical Assignment 2

Home Building Planner

Premier Inn, Wilson Street, Middlesbrough, TS1 1AE. Site progress report. February 2017

TOWN OF ROTTERDAM RESIDENTIAL BUILDING PERMIT APPLICATION Ext. 395 Needed to Obtain Permit:

SECTION ALTERNATES

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised

1 AND 2 FAMILY DWELLING REQUIREMENTS

COOLIDGE SENIOR HIGH SCHOOL

Budget Estimate Basic Tenant Improvement

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.

TERMINAL BUILDING EVALUATION

FLOORPLAN /ELEVATION SQ.FT. BDRM BATHS GARAGE BASE PRICE

MADISON HIGH SCHOOL // Executive Summary

Completed projects. Projects in progress. Program developments

CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS PROGRESS. THIS IS AUBURN.

Project #1139 Budget #82. $ Budgeted $ Billed to Date $ Paid to Date $ Due 210, , , ,158.50

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised

SCREEN PORCHES 101 DEVELOPMENT RESOURCES, INC Permit Requirements

HOLDER CONSTRUCTION COMPANY Superintendents Weekly Activity Report #92 Douthit Hills Student Community, Clemson University Project Joe Jett

Feature Zone IECC 2009 IECC

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28-

Building Construction Occupations

UPPER ARLINGTON SCHOOLS 2015 FACILITIES ASSESSMENT. Windermere Elementary School Physical Assessment

STRUCTURAL CONDITION ASSESSMENT

CITY OF HAGERSTOWN PLANNING & CODE ADMINISTRATION DEPARTMENT. Submittal Requirements

Manufacturing Facilities Proposal

ORANGE VISTA HIGH SCHOOL PHASE I

Single Family Detached home submittal Workbook

UNC Charlotte Residence Hall Phase X. Bid Results February 16, Alternate #7A Pinehall Brick Pavers. Alternate #6A Tile Student Bath

TOWN OF PORT ROYAL BUILDING CODES DEPARTMENT Building Permit Submittal Requirements

BUILDING PERMIT APPLICATION PACKAGE

ORANGE VISTA HIGH SCHOOL PHASE I

SANDTOWN CROSSING PROFESSIONAL OFFICE PARK Atlanta, GA

Transcription:

Issaquah School District Issaquah High School Reconstruction December 2009 West side of the site: North classroom building is being sheet-rocked, taped, and primed. Data and electrical wiring is being pulled in the building along with HVAC equipment. In the central classroom, building sprinkler, plumbing, electrical, and insulation is continuing in preparation for sheet-rock. The south classroom is not as far along as all workers are working from the north building to the south. This allows us to keep schedule while using workers who are familiar with the previous work. This also reduces the learning curves and adds to the quality of the work and completed project. Concrete is being prepped and poured for the connector corridor between the classroom buildings. Eastside of the site: Steel stud framing continues in the kitchen, gyms, and various classrooms and the exterior sheathing is being installed on various walls. Sprinkler, plumbing, and electrical are keeping pace with the framing. Roof installation proceeds as weather permits over the main gym and the upper floors with hopefully enough breaks to proceed to the central core by the holidays. This may be optimistic as only 4 days in November were dry enough to proceed with roofing. The current cold but dry weather is helping get the roofing completed. Site work: The retaining wall between the tennis courts and the softball fields is completed and once it's waterproofed it can be backfilled. The east fire road retaining walls are nearly complete and the generator enclosure should start soon. The retaining wall and seating around the north end of the track has been excavated and waiting for concrete forming. Earthwork and slab preparation has started on the east side of the grandstand by taking advantage of the season s end of the fall sports program. Capital Projects Department Steve Crawford Director Mike Archer Debbie Massaro Tom Mullins Royce Nourigat Ladd Stejskal Phone: 425-837-7040 Fax: 425-837-7041 Aerial view of Issaquah High School, November 2009.

Page 2 Issaquah High School Reconstruction View of three classroom wings and west stairwells. South wall of south classroom building. Two-level circulation corridor connecting the east end of the classroom wings. View of the south and central classroom wings from the east. Courtyard, classrooms on the left with Commons, Library and Gym to the right. North side of construction.

December 2009 Page 3 Issaquah High School Reconstruction Courtyard area between classroom wings. Attendance check-in hallway in north building has been partially primed. North wing classroom gyp board nearing completion. Painting has started in some rooms. North wing classroom. Central wing classroom ready for installation of gyp board. South wing classroom framing complete, installation of utilities underway.

Page 4 Issaquah High School Reconstruction Library Exterior masonry installation has begun. Main Gym with upper Auxiliary Gym in background. View from Weight Room. View of track and field from third floor classroom.

December 2009 Page 5 Skyline High School Expansion and Alteration Site: Asphalt for the driveway and drop-off/pick-up loop has been placed at the new entrance. Concrete walkway and plaza to main entrance is completed. Landscaping is underway. NW & SW Areas: Rooms are nearly complete. Cleaning company is in the process of cleaning all the spaces. Installation of stairway handrails is approximately 80 percent completed. HVAC units are in and the direct digital control system is approximately 85 percent. Scheduled start-up of the HVAC units is set the week of December 7 th. Fire alarm testing is scheduled for week of December 7 th. Punch list is scheduled for week of December 1 st. Commons: Rubber tile is completed at the upper floor. Ceiling grid, tiles and light fixtures are nearly complete at both floors. Stairwell handrails are going in. Casework in DECA store is complete. Punch list is scheduled for week of December 1 st. Gymnasium, Locker Room & Weight Room: Electrical and Mechanical rough-in is complete in the three areas. Windows for the gymnasium and weight room are installed. Interior sheetrock for the gymnasium is complete. Taping and mudding has begun. Ductwork is approximately 50 percent complete in the mechanical room. Roofing is 90 percent complete at the weight room. View of new drop-off/pick-up drive towards the main entrance. Classrooms, Admin and Counseling to the left and Weight Room to the right. Main entrance doors on left with entrance to new reception area nearing completion. Entrance to reception area. Reception desk complete. Store-front and doors nearly complete.

Page 6 Skyline High School Expansion and Alteration Expanded upper level Commons looking back into the existing Commons. View from existing Commons into the expanded area. Main floor expanded Commons with new DECA store to the rear. View from the expanded Commons showing the upper floor classroom corridor and new stair. Third floor corridor. Small group area to left with windows at the end of the corridor. Lower level, central area connection of new classroom wing and existing corridor. New stair extends up to the third floor.

December 2009 Page 7 Skyline High School Expansion and Alteration Large windows at the new north stairwell brighten the interior and open up views. Mid-level of new central stair. Small group area beyond stair and science lab to right. Newly installed carpet in new rectangular classroom. New Science Lab New Main Gym Weight Room

Page 8 May Valley Service Center A Pod Replacement Building E basement walls have been poured and walls framed. Backfilling of large walls is underway. Building F is fully framed, weathered-in and ready for slab pour. Storm pond expansion and liner work to begin shortly. Maywood Middle School Design development is over 50% complete. Design team met with King County and completed the Voluntary Pre- Application Meeting. Design team is now following the direction of King County in preparation of the formal Pre- Application Meeting which is scheduled in early January 2010. Elementary #15 The contractor continues to make good progress with the work. The north classroom wing is now dried in with electrical rough-in nearly complete. Drywall is slated to start in the next week. In comparison, drywall started on the Grand Ridge project the beginning of April. Mechanical rough-in has begun. The south classroom wing is framed and rough-in work has started. Steel floor framing is complete at the library core of the building. Metal will go down in the next week with the concrete deck to follow. Hot mop and metal roofing are proceeding to allow insulation and sheetrock in dry conditions. Roof beams for the commons and gym are scheduled to arrive next week. Masonry work in these areas is complete and ready for the roof structure. View of north classroom wing to right with elevator masonry core work proceeding left. Library and central core area with north classroom wing beyond.

December 2009 Page 9 Elementary #15 View from the southeast with gym to left and classroom wings beyond. View from upper floor, north wing classroom. Rain garden will be located where the temporary pond (ice rink) is located with forested background. View from upper floor, south wing activity areas. North wing, lower floor classrooms. Utility work complete, ready for insulation and drywall. Second floor, south wing view toward playfield. Sand playfield