CDM 2015 In Practice. Craig Foyle CFIOSH IMaPS / Raymond Bone CMIOSH CFaPS. Version 1.0

Similar documents
Curo Group HEALTH & SAFETY POLICY: CONSTRUCTION SAFETY MANAGEMENT & CDM PROCEDURE

CDM Regulations 2015 (Construction Design and Management)

WE ARE UNDERWAY! CDM 2015 CDM 2015 HAS NOW KICKED OFF. ARE YOU AWARE OF THE CHANGES? WALKER MANAGEMENT

CDM comes into force on 6 April 2015

Managing Contractors (Scotland)

CDM FAQ Sheet

C D M R e g u l a t i o n s

Notes to be Read Before Completing the Questionnaire

Managing health and safety in construction

Safe System of Work Policy

CDM 2015: Planning and managing construction work Paul Harvey HM Principal Inspector of Health and Safety

What is CDM 2016 about?

FACT SHEET CONSTRUCTION (DESIGN AND MANAGEMENT) REGULATIONS 2015 THE PROPERTY PROFESSIONALS AUGUST 2016

CDM (Set Construction) Information Sheet and Template Introduction

Client Requirements to make Particular Safety & Health Appointments

HEALTH & SAFETY ASSESSMENT SCHEME CONTRACTOR & PRINCIPAL CONTRACTOR APPRAISAL QUESTIONNAIRE

Health and Safety Guidance Principal Designer Construction Design and Management Regulations 2015

CDM 2015: The regulator s experience to date. Simon Longbottom Head of HSE Construction Sector. Thoughts for Conference and Beyond

The Construction (Design and Management) Regulations 2015

CHAS Assessment Standards

Abu Dhabi EHSMS Regulatory Framework (AD EHSMS RF)

Annex G to Loughborough University Facilities Management Health and Safety Procedure

An overview of CDM 2016 the UK experience.

Health and Safety Guidance - Designers Construction Design and Management Regulations 2015

Mini Tender PART B External Wall Insulation, Mechanical and Electrical Installation

In preparation for Retail Expo 2018 we would like to make you aware of a UK law that is compulsory for all events in the UK.

CHANGES TO THE CDM REGULATIONS

Designer and CDM Co-ordinator Guidance

Construction (Design and Management) Safety Guidance Document

Title of presentation. goes here CDM2015. Implementing the role of Principal Designer

The safe management and control of Temporary Works

Work Health and Safety Management Systems and Auditing Guidelines

Want construction work done safely?

Designer and CDM Co-ordinator Guidance

Managing health and safety in construction

CONTRACTORS ON SITE POLICY

CDM-C Guidance. Five or more employees. Health and Safety 1. CMD-C Guidance Notes V

A2B. Construction (Design and Management) Regulations 2015 PRE CONSTRUCTION INFORMATION PACK (V ) PROJECT:

CDM 2015: The regulator s experience to date

WHS Management Plans

The Construction (Design and Management) Regulations 2015

Managing Contractors Safely

2 Ensure there are arrangements in place for managing and organising the project

JK 1. RIBA stages JK START OF MAIN CONTRACT WORKS 1. DEFINITION 2. PURPOSE 3. PROCEDURE 3.1 PROJECT MANAGEMENT TEAM ROLE

BHC-P-03.1 Training, Competence and Induction

Health, Safety and Environmental Manager

Construction Regulations 2014 vs Construction Regulations 2003

Protocol for Consultation with Trade Union Safety representatives.

Establish health and safety requirements

CHAS Health & Safety Training Requirements July 2017

CIF TRAINING SERVICES PROSPECTUS

UNIVERSITY OF LEICESTER ESTATES & FACILITIES MANAGEMENT DIVISION ASBESTOS MANAGEMENT PLAN

CDM Note 002: Principal Designer Appointment

Asbestos Management Plan

University of Portsmouth Safe System of Work Policy

HEALTH & SAFETY POLICY

HEALTH AND SAFETY POLICY

DRAFT Health and Safety Authority

GUIDELINES FOR CONTRACTOR ENVIRONMENTAL MANAGEMENT PLANS CS-ENV-08

Health and Safety Executive HSE UPDATE. Mark Dawson Netherwood Hotel, 17 th September 2015

Risk Assessment Policy

Evaluation of Occupational Health & Safety Management System

Policy, Responsibilities & Procedures

EDUCATION SUPPORT OFFICER Cardijn College Position Information Document

Waste Management Policy

Construction Waste Measurement Guide

Occupational Health and Safety Regulation 2001

CDM Regulations 2015 and 2 topical issues

Page1. Asbestos (Health & Safety) Policy. Issue Date 07/03/2017 Issue 1 Document No: 010 Uncontrolled when copied

Managing Workplace Health Hazards Strategies & Approaches

Health & Safety Xpert User Guide

Occupational Health and Safety Act 2000

Level 6 NVQ Diploma in Construction Site Management (Construction)

Bowmer. & Kirkland. Kirkland. & Accommodation. Health & Safety Policy.

CDM Regulations: The role and duties of churches regarding health and safety during building works. (June 2015)

East Riding of Yorkshire Council Corporate Health and Safety Policy

COSBEDO01 - SQA Unit Code F50H 04 Produce and recommend detailed design solutions in built environment design

ENVIRONMENT, HEALTH & SAFETY POLICY Up date

Site Safety Plus. Site Management Safety Training Scheme (SMSTS) Course appendix G

ICL Asbestos Management Plan 2017

(7 February 2014 to date) OCCUPATIONAL HEALTH AND SAFETY ACT 85 OF 1993

Keeping People Safe CHURCH HEALTH & SAFETY TOOLKIT ASBESTOS

HEALTH AND SAFETY TRAINING COURSES

Health, Safety and Welfare Policy

Responsible to: REAch2 Inspiration Ltd Senior Health & Safety Coordinator.

HOW TO SAFELY REMOVE ASBESTOS

UCLH Asbestos Management Plan. July 2017

SITE SAFETY RULES - SILVERSTONE CLASSIC 2018

Education Infrastructure Service. Asbestos Management Process

THIS IS THE HEALTH AND SAFETY POLICY STATEMENT OF GLASGOW KELVIN COLLEGE

Work Health and Safety Consultation, Cooperation and Coordination

Guidance Note: CSCS Cards

Construction (Design & Management) Regulations 2007

Health & Safety at Work Act 1974

Health & Safety Officer. Donegal County Council

Guidance Note: CSCS Cards

RISQS Audit Protocol. Plant Operations Scheme. Document no.: RISQS-AP-004. Plant Operations Scheme

A handbook for the construction regulations Working safely in the housing construction industry

UNIVERSITY COLLEGE LONDON STANDARD ASBESTOS MANAGEMENT PLAN

Transcription:

CDM 2015 In Practice Craig Foyle CFIOSH IMaPS / Raymond Bone CMIOSH CFaPS Version 1.0

Speakers Craig Foyle Involved in engineering construction / construction projects for over twenty years working in estimating and operational roles before moving into safety management. IOSH Council / IOSH Chair of Consultancy Group Raymond Bone Involved in civil construction projects for over twenty five years working in civil engineering and then construction management. APS CDM Co-ordinator of the year 2015 / IOSH CG Vice Chair

Background / Key Changes

History of the CDM Regulations European Directive 92/57/EEC - Temporary or Mobile Construction Sites Directive CDM 1994 Planning Supervisor CDM 2007 CDM Co-ordinator CDM 2015 Principal Designer The changes were an attempt by the UK to comply with the full requirements of the Directive.

Key changes Some key changes in the new CDM 2015 Regulations: The role of CDM Co-ordinator has been replaced. A new role of Principal Designer has been created. Appointment is required where more than one contractor will be working on a project at any time. The CDM Approved Code of Practice has been replaced with a guidance document.

Key changes Principal Designer In real terms, the role of the principal designer is fundamentally similar to the CDM co-ordinator (for the pre-construction phase). but there is a significant exception Apart from assisting the client with preparation of the pre-construction information, the principal designer is not specifically required to give advice and guidance to the client.

Key changes Domestic clients The exemption for domestic clients has been removed. General householders have duties under CDM 2015. These duties can be transferred to the principal contractor or principal designer.

CDM Regulations Managing Health and Safety in Construction (CDM 2007) ACOP RRC RRC International International Managing Health and Safety in Construction L153 Guidance Statutory Instrument No51 The Construction (Design and Management) Regulations 2015

CITB guidance documents RRC RRC International International

Back to Basics

What is construction? Construction work means the carrying out of any building, civil engineering or engineering construction work. What does this mean?

What is construction? (a) the construction, alteration, conversion, fitting out, commissioning, renovation, repair, upkeep, redecoration or other maintenance (including cleaning which involves the use of water or an abrasive at high pressure, or the use of corrosive or toxic substances), decommissioning, demolition or dismantling of a structure; (b) the preparation for an intended structure, including site clearance, exploration, investigation (but not site survey) and excavation (but not pre-construction archaeological investigations), and the clearance or preparation of the site or structure for use or occupation at its conclusion;

What is construction? (c) the assembly on site of prefabricated elements to form a structure or the disassembly on site of the prefabricated elements which, immediately before such disassembly, formed a structure; (d) the removal of a structure, or of any product or waste resulting from demolition or dismantling of a structure, or from disassembly of prefabricated elements which immediately before such disassembly formed such a structure; (e) the installation, commissioning, maintenance, repair or removal of mechanical, electrical, gas, compressed air, hydraulic, telecommunications, computer or similar services which are normally fixed within or to a structure.

Competence / Notification / Resources

Competence criteria The competence criteria set out in Appendix 4 (of CDM 2007) has been removed and replaced with a requirement for appropriate training and skills (as set out in Section 2(2)(c) HASAWA 1974). the provision of such information, instruction, training and supervision as is necessary to ensure, so far as is reasonably practicable, the health and safety at work of his employees The guidance refers to third party schemes within SSIP. Is this enough?

Competence criteria In-house / third party schemes Check the company is accredited (not member only / suspended) Review the scope of accreditation (determined by the contractor) Review sample documentation Complete the Stage 2 assessment, e.g. past experience, performance and resources HSE Review enforcement pages (notices and prosecutions) Record the date of the above checks

Notification requirements The project notification threshold was changed to: Work lasting more than 30 working days and have more than 20 workers working simultaneously, or if The project exceeds 500 person days The number of notifications submitted to the HSE has reduced on small to medium sized projects, however, be aware that the Regulations apply whether a project is notifiable or not.

Transitional period There were enhanced transitional provisions to cover projects which were already underway prior to 06 April 2015. CDM co-ordinators who were already appointed on projects which commenced before 06 April 2015 were permitted to remain in the post for six months or to the end of the project, whichever was earlier. Beware PCI & CPP continually make reference to both CDM 2007 and a CDM Coordinator!

Types of Project

Two types of project Irrespective of the size or duration, 2015 Regulations separate construction projects into two types: Those with one contractor Those with more than one contractor

Projects with one contractor A contractor has been awarded a contract to rewire part of a building and no other trades are required to do any work. The project will require only two people and it is anticipated that the work will take six weeks, working five days per week. State the requirements for the project. 5 working days per week x 6 weeks = 30 working days 2 people x 5 days x 6 weeks = 60 person days Notification is not required (<500 person days / 30 days + 20 people) PCI is required CPP is required PD and PC are not required H&S file is not required

Projects with >1 contractor You have obtained capital approval to install a new production line. The project is expected to require fifteen people working for twenty weeks. State the requirements for the project. 5 working days per week x 20 weeks = 100 working days 15 people x 5 days x 20 weeks = 1500 person days Notification is required (>500 person days) PCI is required CPP is required PD and PC must be appointed in writing H&S file is required

Projects with >1 contractor This will be the majority of projects. If work requires steelwork erectors, scaffolders, ground-workers, mechanical fitters and electricians it is five contractors.

Duty Holders / Responsibilities

Client duties Make suitable arrangements for managing a project including: Appoint or engage Make appointments early enough and in writing Provide sufficient time and resources Ensure adequate welfare is provided Provide information for PCI Ensure CPP is in place

Principal designers Plan, manage, monitor and co-ordinate health and safety in the preconstruction phase Prepare and provide relevant information to other duty holders Co-ordinate arrangements during the design and planning Liaise with the principal contractor Assist the client in the provision of pre-construction information Revise or develop the health and safety file

Principal contractors Plan, manage, monitor and co-ordinate construction phase of a project including: Preparing the construction phase plan Organising co-operation between contractors and co-ordinating the work Suitable site inductions are provided Reasonable steps are taken to prevent unauthorised access Workers are consulted and engaged in securing their health and safety Welfare facilities are provided and maintained Liaise with the principal designer for the duration of their appointment and share relevant health and safety information.

Designers Designers are those who as part of a business, prepare or modify designs for a building, product or system relating to construction work When preparing or modifying designs, to eliminate, reduce or control foreseeable risks that may arise during: Construction; and The maintenance and use of a building once it is built Provide information to other members of the project team to help them fulfil their duties

Contractors Contractors are those who do the actual construction work and can be either an individual or a company Plan, manage and monitor construction work under their control so that it is carried out without risks to health and safety For projects involving more than one contractor, co-ordinate their activities with others in the project team, in particular comply with directions given to them by the principal contractor For single contractor projects, prepare a construction phase plan

Things to consider! Until the client has appointed a principal designer and principal contractor (where appropriate) they will automatically inherit the duties of each duty holder under the Regulations. Once appointed the principal designer and principal contractor may carry out their duties and may be able to give further advice to the client. On projects with only one contractor they (the contractor) should advise the client on how they can assist them with their duties (if appropriate). Appointment is required as soon as practicable.

PCI / CPP / H&S File

Pre-construction information Description of project Project description Project directory Additional requirements Client s considerations and management requirements Arrangements Requirements Environmental restrictions and existing onsite risks Safety hazards Health hazards Significant design and construction hazards Significant design assumptions Arrangements for co-ordination of on-going design work Information on significant risks identified during design Materials requiring particular precautions The health and safety file Significant design assumptions

HSE CPP template (http://www.hse.gov.uk/pubns/cis80.pdf)

Health & Safety File The Regulations state that where more than one contractor works on a project the principal designer must prepare a health and safety file for the project. The contents and format should be agreed and the client should provide relevant information for the document. The principal designer must ensure that the health and safety file is prepared, reviewed or updated as appropriate, reading for handing over to the client on completion of the work (or when their appointment ends). It is strongly advised that the health and safety file is prepared, reviewed or updated as appropriate for all projects, irrespective of the number of contractors working on a project.

Health & Safety File The client must keep the health and safety file safe and make it available to anyone who may need it in the future and explain the purpose of it to them. It must be updated whenever necessary. When interest in a structure is no longer required the file must be passed on to those acquiring it. The client should ensure that the file is being prepared as the project progresses.

Cases

Case study CDM Duty Holder: Designer Principal Contractor Event: Fatality Fine: 195,000 / 60,000 costs

Case study CDM Duty Holder: Designer Event: Musculoskeletal injury Fine: 500 + 1000 costs Mandatory safety training

Case study CDM Duty Holder: Client / CDM-C / Principal Contractor Admission of unsafe working practices including failing to remove asbestos from old buildings before demolition work. Failure to appoint CDM-C as the client ( 5K) Failure to notify construction project to HSE as de jure being the CDM- C ( 5K) Failure to appoint PC in writing as the client ( 5K) Failure to start construction phase as client by not ensuring the PC had prepared a CPP ( 5K) Failure to plan, manage and monitor the construction phase as de jure being the principal contractor ( 15K)

CDM Process Flow

CDM process flow Stage 1 Concept and proposal CDM 2015 Process V.2 Create project file >1 contractor No Yes Assess competence / appoint principal designer (PD) Assess competence / appoint designers CDM project review meeting with PD / OPS / ENG / SHE (Set agenda) Prepare / issue preconstruction Information Set milestones Set programme Stage 2 Pre-construction Phase Notification requirements: 1. 30 working days plus 20 people on site, OR 2. 500+ person days Is project notifiable? Yes Raise F10 Notification* Display F10 in prominent location Principal contractor required if >1 contractor Is Client the PC? * Under CDM 2015 it is the client s responsibility to submit the F10 Yes No Issue PCI to those appointed / considering appointment Plan / hold CDM co-ordination meeting(s) Confirm competence & resources Assess competence / resources / appoint PC Plan / hold CDM co-ordination meeting(s) Issue PCI to those appointed / considering appointment Prepare construction phase plan Review adequacy of construction phase plan Pre-start meeting Issue CPP to all who need it Stage 3 Construction Phase File in project folder Monitor project safety performance Construction phase Confirm CPP and welfare arrangements and maintain them Stage 4 Post-construction Phase Review CDM management arrangements and health and safety file with relevant parties Obtain the health and safety file from the PD and / or PC and review for adequacy File in projects / maintenance V.2 Addition of boxes on right hand side to be dated and filled with green when complete.

What next Brexit? Domestic client Review of construction phase plan Reconsider exemption for erection of marquees Principal designer v CDM co-ordinator?

Questions