Center Sanitation District

Similar documents
Integrated Activated Sludge and Biosolids Treatment to Conserve Energy & Waste Solids Disposal

ISAM INTEGRATED SURGE ANOXIC MIX

WASTE WATER T*R*E*A*T*M*E*N*T T*E*C*H*N*O*L*O*G*I.E

Energy Optimized Resource Recovery Project Presented By: Curtis Czarnecki, P.E.

Case History: Anaerobic and Aerobic Treatment of Textile Wastes at South Carolina Textile Plants. Introduction

NAWT Septage Processing What are my disposal resources and how do they fit

Kenosha Wastewater Treatment Plant - Energy Optimized Resource Recovery Project

COMPARISON OF SBR AND CONTINUOUS FLOW ACTIVATED SLUDGE FOR NUTRIENT REMOVAL

CHEMICAL FREE PHOSPHOROUS ELIMINSTION P-UPTAKE PROCESS

Tour of Regional Water Reclamation Facility

CHAPTER 1 - WASTEWATER SYSTEM DESCRIPTION

HOW TO SAVE COSTS AND IMPROVE SUSTAINABILITY WHILE REDUCING EFFLUENT NITROGEN

Aqua MSBR MODIFIED SEQUENCING BATCH REACTOR

Indian Health Service Sanitation Facilities Construction Program Wastewater Lagoon Operation & Maintenance

BEING GOOD STEWARDS: IMPROVING EFFLUENT QUALITY ON A BARRIER ISLAND. 1.0 Executive Summary

Why THP Made Sense for TRA

Application of the AGF (Anoxic Gas Flotation) Process

Lowering The Total Cost Of Operation

6 WASTEWATER. 6.1 Overview. 6.2 Darvill Wastewater Works

Wastewater Treatment Processes

DEVELOPMENT OF THE. Ken Mikkelson, Ph.D. Ed Lang Lloyd Johnson, P.E. Aqua Aerobic Systems, Inc.

Removal of High Ammonia Levels from Municipal Wastewater Using Humic Acid and Selective Bio-Augmentation

Comparison on the Treatment Performance of Full-scale Sewage Treatment Plants using Conventional and Modified Activated Sludge Processes

CEDAR CREEK Wastewater Treatment Facility

Treatment of palm oil mill effluent using biological sequencing batch reactor system

TWO YEARS OF BIOLOGICAL PHOSPHORUS REMOVAL WITH AN ADVANCED MSBR SYSTEM AT THE SHENZHEN YANTIAN WASTEWATER TREATMENT PLANT

WWETCO FlexFilter and Bio-FlexFilter

Copies: Mark Hildebrand (NCA) ARCADIS Project No.: April 10, Task A 3100

Appendix D JWPCP Background and NDN

Troubleshooting Activated Sludge Processes. PNCWA - Southeast Idaho Operators Section Pocatello, ID February 11, 2016 Jim Goodley, P.E.

Metropolitan Water Reclamation District of Greater Chicago

Need-to-Know Criteria Wastewater Treatment Operator Class IV

NEW BIOLOGICAL PHOSPHORUS REMOVAL CONCEPT SUCCESSFULLY APPLIED IN A T-DITCH PROCESS WASTEWATER TREATMENT PLANT

Startup and Performance of the World s first Large Scale Primary Dissolved Air Floatation Clarifier ABSTRACT KEYWORDS INTRODUCTION

Providing Infrastructure Redundancy at the Rocky River WWTP. Timothy McCann AECOM Keith Bovard Rocky River WWTP

Flocculation Flotation Pretreatment Improves Operation of MBR Installed to Treat Snack Food Manufacturing Wastewater

by M k h GROVER Degremont

Wastewater Treatment Technology and Applications in Industrial Facilities

Advanced Wastewater Treatment Plant Plant Profile

AquaNereda Aerobic Granular Sludge Technology

Need-to-Know Criteria Wastewater Treatment Operator Class III

Zero Discharge for Textile Industry

Odor Threshold Emission Factors for Common WWTP Processes

CITY OF OXFORD WASTEWATER TREATMENT FACILITY ANNUAL PERFORMANCE REPORT FOR THE CALENDAR YEAR OF 2012

Biological Phosphorus Removal Technology. Presented by: Eugene Laschinger, P.E.

Conceptual Design for a Future Wastewater Treatment Plant

FAYOUM CITY SEWAGE TREATMENT PLANT, DEVELOPMENT STAGES, CASE STUDY

Current Treatment Approaches and Planning for the Future A Panel Discussion

Primary Clarifier Odor Control Replacing Nitrates with D.O. Kevin Jacobs, P.E. ECO Oxygen Technologies

ATTACHMENT 1 GENERAL FACILITY INFORMATION. BOD5 mg/l mg/l TSS mg/l mg/l NH3-N mg/l mg/l

Prepared by the Operation of Municipal Wastewater Treatment Plants Task Force of the Water Environment Federation

Need-to-Know Criteria Wastewater Treatment Operator Class II

AquaPASS. Aqua MixAir System. Phase Separator. System Features and Advantages. Anaerobic. Staged Aeration. Pre-Anoxic.

Evaluation of Conventional Activated Sludge Compared to Membrane Bioreactors

ENHANCING THE PERFORMANCE OF OXIDATION DITCHES. Larry W. Moore, Ph.D., P.E., DEE Professor of Environmental Engineering The University of Memphis

Constructed Wetlands

Anaerobic Digester Optimization with Bio-Organic Catalyst. NYWEA 81 st Annual Meeting February 3, 2009 One Year Study November 07 - November 08

Fixed-Film Processes

Deicing Fluid and Stormwater Management At Cincinnati/Northern Kentucky International Airport

MEETING WASTEWATER DISCHARGE REQUIREMENTS FOR A SOYBEAN OIL PLANT IN COSTA RICA

GRANULAR ACTIVATED SLUDGE

Watertown Wastewater Facility Plan. August 11, 2015

Water Quality Permitting Program Monitoring Matrix 1,2,3

Fremont Water Pollution Control Center Plant Expansion for Nutrient Removal and Wet Weather Flow Treatment

19. AEROBIC SECONDARY TREATMENT OF WASTEWATER

Your Problem. Current Practices. Survey about Storage. Thinking about Cost. Mixed waste {Your truck} Your Resources Options Future

Aerobic Treatment Units

Advantages & Applications of MBBR Technologies

Decentralized WW Management: Issues for Small-Scale WWTPs. Mike Stephens MWEA Local Sections Committee Frankenmuth, MI

International Society of Beverage Technologists Beverage Production Seminar January 24-27, 2000 Wastewater Minimization and Treatment

Membrane Bioreactors

Module 19 : Aerobic Secondary Treatment Of Wastewater. Lecture 24 : Aerobic Secondary Treatment Of Wastewater

Review of WEFTEC 2016 Challenge & Overview of 2017 Event. Malcolm Fabiyi, PhD, MBA Spencer Snowling, PhD. P.Eng

Activated Sludge Process Control:

EVALUATION OF ENERGY RECOVERY OPTIONS FOR CONVERSION OF AEROBIC DIGESTERS TO ANAEROBIC DIGESTION

Volatile Solids Reduction (VSR): Considerations for Accurate Measurement and Reporting

Chapter 2: Conventional Wastewater Treatment (continue)

WASTEWATER TREATMENT SYSTEM

Construction of first wastewater treatment plant in Kosovo: an EU pilot project

Efforts for use of methane gas in wastewater treatment of Japan

Industrial Wastewater Pretreatment Challenges at a Beef Processing Facility

Tour of Altamonte Springs Regional Water Reclamation Facility

Lagoon And Wetland Treatment Of Dairy Manure

POTW s As An Emergency Option For Dairy Manure Disposal

W O C H H O L Z R E G I O N A L W A T E R R E C L A M A T I O N F A C I L I T Y O V E R V I E W

Chapter 2: Description of Treatment Facilities

City of Portsmouth Portsmouth, New Hampshire Public Works Department RFP #52-14 REQUEST FOR PROPOSAL

Taylor Creek Treatment Plant. Metropolitan Sewer District of Greater Cincinnati

Winery FAST & Floating FAST

Membrane Bio-Reactors (MBRs) The Future of Wastewater Technology, Science and Economy Aspects

Environmental Dynamics International

Developing a Sustainable Water Supply Strategy for the City of Plantation, Florida

Biological Wastewater Treatment

EVALUATING ALTERNATIVES FOR DISPOSING OF WATER PLANT SOLIDS INTO A WASTEWATER PLANT

Nutrient Removal Processes MARK GEHRING TECHNICAL SALES MGR., BIOLOGICAL TREATMENT

FAIRMONT WASTEWATER TREATMENT PLANT

Wastewater Treatment Works... The Basics

Nutrient Removal Optimization at the Fairview WWTP

OPERATION AND MANAGEMENT OF WASTEWATER TREATMENT PLANTS

Transcription:

EHLS Center Sanitation District EHLS Engineering Erik Jorgensen Suzanne Givler Heath Anderson Leryn Gorlitsky Outline of Presentation Background Current and Future Conditions Decision Matrix Description Regulations and Permits Alternatives and Preliminary Design Sequenced Batch Reactors Dewatering Composting Final Costs and Construction Staging Questions Project Scope and Objectives Background The Sanitation District distributed a Request for Proposal to analyze their agricultural wastewater treatment plant. EHLS responded to this RFP on Sept 6 th Goals of the RFP: Discharge to meet permit levels Biosolids management plan Dewatering Composting EHLS was awarded the contract Deliver a Preliminary Design (0% Design) Mainly an agricultural city 8.% of the total industry Influent from 4 potato processing plants 75% Coming from Idaho Pacific Plant Average flow of 00,000 gal/day BOD of,500 lbs/day Center Current Conditions Current Conditions Plant Overview S B R S B R S B R Aerobic Digester Influent Wastewater Effluent Sludge Effluent Gravity Thickener Shed

Current Conditions Current Conditions-Sludge During our plant visit on Sept. 4 th : 4-6 truck loads of Biosolids per day, and SBR acting as a sludge holding tank During normal operation 0 loads per month are expected Future Conditions Decision Matrix Description Idaho Pacific to double plant capacity by 006 Idaho Pacific installed 60 micron filter in replace of a /8 filter Estimated 40% reduction in solids A constraint is anything that would completely eliminate an option from being a feasible solution. Meeting the current effluent standards in the current permit. The ability to handle the plant s current flow rate. Must not exceed the Sanitation Districts budget. The flow regime of the plant must be free of sludge back up. Criteria: Important factors to the project that are weighted according to importance. A low score of indicates that the option did not meet any of the qualifications A high score of 0 means it met every qualification SBR Matrix Raw Weighted Biosolids Matrix Raw Weighted Weight % Weight % Costs: Costs: Present Value 40 Present Value 7 Non-Costs: Non-Costs: Regulatory and Permit Compliance 5 New permit requirement 5 Complexity 0 Complexity 0 Reliability 8 Reliability 0 Safety Safety Use of existing facilities Use of existing facilities 4 Sustainability of design choice Sustainability Public Effects: Public Effects: Public approval Public approval Aesthetics and Noise Aesthetics and Noise Odor Odor Social Benefits Social Benefits Total: 00 Total: 00

Current Regulations Effluent Parameters 5-Day BOD (mg/l) Total Suspended Solids (mg/l) Oil and Grease (mg/l) ph (min-max) 0 Day Average 6.0-9.0 Plant has had trouble meeting these when solids are too high in the SBR s High BOD and TSS has been sealing the irrigation ditch, preventing groundwater recharge. 0 0 7 Day Average 45 45 Daily Maximum 0 Permits Current Effluent Stream Requirements State Colorado Upgrade Requirements Policy 96- Licensee Operator Class B Policy 00 Land Application 50 Seasonal startup and new filter Reseeding Time to new steady state condition Eliminated Alternatives Decant process Influent solids concentrations Temperature sensitivity Biological clogging of aerators Equipment maintenance Insufficient mixing Influent nutrient characteristics Anaerobic pretreatment Membranes Alt. : Baffle and Cycle Time Adjustment Current flow vs. Design Flow Current cycle times vs. SBR Manual FILL: hours vs. 4 hours SETTLE/DECANT: 8 hours vs. hours TOTAL: + hours vs. 8 hours Filamentous growth, F/M Baffle Costs - a big savings! Alt. : Decanter Cleaning Calculations show sufficient capacity Cheap! Permit Effluent changes

Alt. : Adjust Solids Content in SBRs Settling Consuming BOD Influent BOD data, Q Cheap! Alt. 4: Cease Operation July - September Current operations Fewer operator hours Reduction in energy costs Reseed from nearby domestic plant Complex startup Permit issues Alternatives Assessment: SBR Operation Alt. 5: Domestic WW July - Sept Ensure summer bacterial survival Expensive TOTAL SCORE: Cycle Time Adjustment and Baffle Addition 896 Adjust Solids Content in SBRs 847 Clean Decanter 70 Cease Operation Over Summer 76 Pipe Water from Domestic Plant 556 Preliminary Design: Preliminary Design: Baffle addition in SBR only Regular operation, ample V Lowest head losses No new Q measurement equipment No permit changes (Q, # cells) Automatic controls and operation Sludge startup

Preliminary Design: Recommended initial cycle times: Fill: hours () to 8. (.67) hours Full React: hours to 0.5 hours Settle: 4 hours to hours Decant: 4 hours to 0.5 hours Based on F/M, aeration for BOD uptake, 000 mg/l MLSS Startup - current times in one SBR Flow rate increase Alternatives for dewatering Alternatives for dewatering Rejected options Centrifuges Recessed Plate and Belt Press Filters Alternatives for dewatering Accepted Options Drum Thickeners Sludge Dewatering Lagoons Sludge Drying Beds Decision Matrix-Dewatering Options Final option: Drum Thickener Drum thickener Sludge drying Lagoon Sludge drying beds weighted score 9.0 7.9 8. Benefits Unit can be placed in the existing building Can handle the low flow volumes Low Capital Cost Low O&M Cost Low odor High removal rate: 0 to % H O removed

Biosolids Management Problem Over production of biosolids which is causing back up in operations During the design of the Plant no management program was put in place Currently producing 6000 gal/day sludge Outsourcing their waste to a transport company which cost $.0/gal Total cost outsourcing $6,000/ yr Considered Alternatives Option Project Cost 0 year Subsurface Injection $,00,000 Out sourcing $845,000 On-site composting $80,000 Purchasing Truck $90,000 Weighted Matrix Alternatives Total Buying a Truck 750 Onsite Composting 60 Outsourcing 55 Subsurface Injection 470 Final Design Biosolids Management Biosolids vs. Dewatered Biosolids Dewatered Biosolids reduces volume by 50% but still contain enough liquid to use the existing pump for loading Cost associated operation and maintenance of Dewater Machinery Buying a truck to take sludge to composting received the highest score in both present value and non-cost options Projected Costs Water vs. Dewater Current Flow Rates Future Flow Rates Sludge Volume (GPD) 5567 84 998 4949 Total Operation Costs ($/Yr) 500 7 765 008 Present Value 0 Years ($) 5500 7040 807800 48460 # Years DW = W years. years Dewatering will pay for itself with in years Decision Matrix Biosolids Water vs. Dewater Unweighted Total Current Water Sludge 8 Current Dewatered Sludge 78 Weighted Current Water Sludge 660 Current Dewatered Sludge 800 Dewatered option scored significantly higher because of the present value Recommend dewatering and buying a truck

Preliminary Design: COSTS SBR Baffle addition: $5,000 Cycle Time Adjustment: $8,000 saved annually Dewatering Capital costs: Unit approximate cost $0,000 O&M costs: Total energy cost $6 per year Biosolids $6,500 truck $,500 O&M TOTAL CAPITAL: $0,000 TOTAL O&M: up to $5500 saved Preliminary Design: Construction Staging SBR Independent of other options Bidding Process - Summer 005 Dewatering Independent of other options Permit Update - Summer 005 Biosolids Management Independent of other options Immediate QUESTIONS? EHLS