Planned Islanding and Energy Storage at BC Hydro

Similar documents
Innovation & Grid Modernization at ComEd. Laura García García Grid Strategy & Analytics Commonwealth Edison

LONG ISLAND LONG ISLAND

XXXX. Bremner Trio Small Hydro Project. Interconnection System Impact Study

Smart Grid Concept, Applications and Lessons Learned from Recent Deployments

Integration issues and simulation challenges of high penetration PV

CERTS Microgrids. Tom Jahns Professor, University of Wisconsin-Madison. LPPC Rates Roundtable May 21, 2013

Adrian Constable Asia Pacific Microgrid Manager

Integration of renewables and reliable power supply in Alaska

Communication and Control for Microgrid Optimal Energy Efficiency

Slide 1. ABB August 23, 2016

Con Edison. Evolution of Con Edison efforts in Energy Efficiency and Demand Management:

The Role of Microgrids in Grid Modernization Initiatives Sima Seidi Principal Consultant, Microgrids and Distributed Energy Resources Tetra Tech

XXXXX. Bremner Trio Small Hydro Project. Interconnection Facilities Study and Project Plan

Session 9: Photovoltaic System Case Studies And Electric Distribution Planning for DER October 21, 2015 Santiago, Chile

Virtual Power Plant Simulation

Medium voltage products. Technical Application Papers No. 17 Smart grids 1. Introduction

Dynamic Pricing. June 2, 2016 Harvard s Electricity Policy Group

Active Distribution Networks

Schedule 2 TECHNICAL INFORMATION

Energy Storage and the Built Environment. Steve Saunders Associate Director Arup t +44 (0)

Microgrid Planning and Design MCAS Miramar, US Air Force Academy, and Fort Carson

Gas Natural Fenosa s Experiences on Renewable Energy Integration

The Challenges of Integrating Renewable and Distributed Energy Resources what we can learn from smart grid research and demonstrations

The Effect of the Volt/Var Control of Photovoltaic Systems on the Time-Series Steady-State Analysis of a Distribution Network

Smart Grid Demonstrations Cost and Benefit Analysis Methodology

Study of Using Energy Storage to Mitigate the Impact of High Renewable Energy Penetration to the Grid

PUBLIC UTILITY COMMISSION OF OREGON STAFF REPORT PUBLIC MEETING DATE: February 11, 2015 REGULAR X CONSENT EFFECTIVE DATE N/A

Energy Storage for micro- and minigrids in urban and rural Africa. Maxine Ghavi, Group SVP, Program Director Microgrid, ABB

The new role of DSO. David Trebolle Trebolle Manager, Active Networks and Network Analysis Applications Gas Natural Fenosa

EDF and Integration of Distributed Energy Resources

Environmental Security Technology Certification Program (ESTCP) LARGE SCALE ENERGY STORAGE AND MICROGRIDS

Asset Care Optimisation & Investment Planning: A Strategic Paradigm Shift

South Fork RFP LIPA Board of Trustees REV Committee Briefing. September 21, 2016

Using Clean Energy to Reshape the Way We Generate, Distribute, and Consume Electricity

Renewables, Smart Grids

DATA, BENCHMARKING AND RATIONALE BC Hydro Service Plan 2018/19 to 2020/21

EMS of the Future. EMS Users Conference Chicago, Illinois. John McDaniel September 20, Proprietary 1 Experience you can trust.

Automating LV Distribution networks using sensor technologies

California Grid Operations: Current Conditions and Future Needs

Solar + Storage. Behind and In front of the meter. Becca Gillespie UniEnergy Technologies

Presentation Overview

Distributed Energy Resources

Energiewende braucht keine Speicher? Restricted Siemens AG All rights reserved

Variable Renewable Energy Sources in Distribution Networks Martin Braun Fraunhofer IWES & Universität Kassel

Renewable Energy Development and Microgrids With Energy Storage

MICROGRIDS. U.S. Activities

Distribution System Operator (DSO) Construct as a Bridge for End-to-End Transactive Operation

Microgrid R&D in KERI

Integration of Distributed Generation and Wind Energy in Canada

Building Resilient Integrated Grids

RESPONSE: The corrected numbers are: June 30, June

DISTRIBUTION SYSTEM PLANNING TUTORIAL. MN Power Systems Conference November 6, 2014

Standard TPL Transmission System Planning Performance Requirements

Microgrids in New England Technical Challenges & Opportunities

Planification du réseau, exploitation et gestion : nouvelles approches dans la recherche

MAUI SMART GRID PROJECT

Benefit Analysis of Energy Storage: Case Study with the Sacramento Utility Management District

Facility Interconnection Requirements

Patrick McHugh. Vice President Con Edison

(D2-01_28) ROLE OF ICT in Power System

Getting Smart Answers! Kevin W. Chiu. Siemens AG

Eversource - Building a More Resilient Grid for Our Customers

Benefit-Cost Analysis Summary Report

Technical considerations for integration of distributed renewables on the grid

A*STAR Funded IEDS Project - Microgrid Energy Management System. by H B GOOI

Thailand Smart Grid Policy Plan and

Setting the Stage for Microgrid Discussions NGA Energy Resilience Retreat June 29, 2017

Volatility Prediction and Management by Active Network Management & Future Generation Management. Siemens, Sept 8 th 2017

NASEO 2017 Northeast Regional Meeting Energy Storage Initiative. DOER Commissioner Judith Judson

Energy storage in intelligent energy networks

2014 Integral Analytics, Inc.

DEMONSTRATIVE PROJECT ON GRID-INTERCONNECTION INTERCONNECTION OF CLUSTERED PHOTOVOLTAIC POWER GENERATION SYSTEMS

Accommodating High Levels of Distributed Energy Resources

Investigation of Impacts of Solar PV on Transmission System Voltage Stability Considering Load Characteristics and Protection

Technical Requirements for Distributed Generation Connection

Extreme Weather Event Analysis & System Hardening Qualifications

Public Utility District Number 1 of Snohomish County

Microgrid EPFL Méthodes innovantes issues de la recherche

BC HYDRO REAL TIME OPERATIONS OPERATING ORDER 1T 11D. POWER SYSTEM OPERATION FORCED OUTAGES Supercedes 1T-11D issued 03 June 2009

Why Distributed Energy Systems Becoming More Popular in Remote Areas, City Districts and Industrial Facilities ACEF 2017, Decentralized Energy Systems

Toronto Hydro s Climate Adaptation Actions

Integrating Building Automation Systems with Microgrid Controls. Mingguo Hong, Associate Professor Case Western Reserve University Cleveland, OH

Water & Energy Consulting Lon W. House, Ph.D.

Phasor measurement units gain credibility through improved test and calibration standards

The Idaho Power Company

Bosch Energy Storage Solutions Smart integration of storage

The Smart Grid - Constant Energy in a World of Constant Change. Smart Grids and Energy Storage - MicroGrids. Unrestricted

Information Document Protection System Information ID# R

ANTICIPATING AND ADDRESSING SECURITY CHALLENGES IN AN EVOLVING POWER SYSTEM

ERCOT in 2018: Challenges & Opportunities

What new capabilities

A PV, diesel, ESS hybrid case study: The DeGrussa solar project

School of Electrical Engineering and Computer Science. Expansion: Analysis, and Formulation. Washington State University

SMART GRID SCENARIO. Marina Egea,

ELECTRIC INFRASTRUCTURE RELIABILITY PERFORMANCE INDICATORS

Survey and Summary of Best Practices for Distribution Reliability Improvement. December 8, p.m. EST

POTOMAC ELECTRIC POWER COMPANY

Withlacoochee River Electric Cooperative, Inc. P.O. Box 278 Dade City, FL Billy E. Brown, Executive V.P.

Pepco s Reliability Enhancement Model Using Predictive Reliability to Plan Investment in Electrical Infrastructure

Smart Distribution Applications and Technologies - Program 124

Transcription:

Planned Islanding and Energy Storage at BC Hydro Workshop: International Smartgrid projects review December 10, 2010 Jaime Peralta M.Sc., P.Eng. Distribution Planning T&D Asset Investment Management BC Hydro 1

Agenda BC Hydro Emerging Trends Planned Islanding Islanding Assessment & Tech. Req. BCH Islanding Projects Energy Storage Conclusions & Future Challenges 2

BC Hydro Gov't Owned Crown Corp. 1.8 Million Customers 10 GW Domestic Peak Load Serves 94% of British Columbia Integrated G, T, & D Utility Aprox. 5,600 Employees 18,286 km transmission lines 225 Substations 1,300 Feeders Overhead 48,000 km Underground 8,500 km Voltages D: 12, 25 kv T: 60kV-500kV F2010 Normalized Reliability SAIFI=1.52 Target = 1.27 CAIDI=2.28 hrs Target = 2.15 hrs CEMI>=4 =13% Target = 8.5% Two-Step Residential Rate Step 1 (up to 1,350 kwh) 5.91 cents/kwh Step 2 (> 1,350 kwh) 8.27 cents/kwh Calculated per billing cycle (typically 2 months) 3

BC Hydro s business environment Ageing utility infrastructure reliability Changing demographics knowledge retirement Customer expectations access to information, reliability Technology advances IEDs, telecom, data management, automation Climate change introduction of Clean Energy Act 2010 in BC Vertical integration of BC Hydro with Transmission (BCTC) Self-sufficient by 2016 Reduce future incremental demand by 66% through DSM Meet remaining demand through 93% clean or renewable Encourage fuel switching to reduce GHG Key projects not subject to BCUC ruling Encourage economic development through Clean Technology 4

Emerging Trends Going from Centralized Generation to Decentralized Gen. Distributed Generation: Customer Owned Generation High Penetration of DERs (multiple DGs, IPPs, PV clusters, wind farms, etc.) Active Network (Community Energy Storage, Planned Islanding, Microgrids) Distribution CHP ~ Generation On-site Gen Source: SMUD Premier Garden Community Energy Systems PV Clusters 5

Planned Islanding Two approaches for islanding: Current practice Protection against islanding Disconnect DG subsequent to fault or any other switching event and loss of grid, IEEE 1547 Planned (intentional) islanding Supervised transitions to an island condition in order to allow DG continue operation and serve the local load (Ride-through Scheduled/Black-start) Distribution Substation Distribution Feeders Distribution Load PG 6 Islanded Section

Planned Islanding Why Planned Islanding? To avoid safety concerns, and power quality issues When Planned Islanding? Source is not secure: long transmission lines, long-duration interruptions Opportunity to defer capital investments for reliability improvement Special levels of reliability performance required by large customers PG Islanding Capability Is the ability of a PG to continuously supply part of the distribution system that is separated from the rest of T/D system Electric supply must be safe, controlled, reliable, and provide acceptable power quality (V, Hz) 7

PG Islanding Assessment Feasibility of PG Islanding: PG islanding capability Cyclic generation output PG output > feeder/area peak load (>4 months) Planned islanding strategy Ride-through vs. black-start Significant reliability improvement (SAIDI) No power quality issues Reasonable system upgrades and costs No operation and safety concerns Special commercial, or contractual considerations 8

PGs Technical Requirements Distribution Power Generator Islanding Guidelines, BC Hydro, June 2006 Load following capabilities Generators with broader VAR control (power factor ±0.8) Fast acting speed governor and exciter Inertia and controls to pick up dead-feeder load Black-start capability (scheduled islanding) PG with sufficient excitation current to allow fault detection Dual overcurrent protection settings (for parallel and islanded operation) Capability to maintain power quality (Machines with large inrush current or cyclic loads) Operating data/status telemetry (no SCADA) 9

BCH Upgrades & Requirements Feeder/area load > PG MVA rating/output if not, feeder sectionalization plan required Bi-directional line voltage regulators and fault detection elements Voltage supervision at feeder substation CB (out-of-phase reclosing) Reclosers upgrade (disable/delay reclosing function, replace to electronic) Line fuses upgrade (replace/relocate/remove) PG real-time operating data/status at Control Centre and inter-operator communications PG commissioning tests for both grid-connected and islanded mode System impact study (steady-state and dynamic) for islanding operation, and DOO 10

BC Hydro s Islanding Projects 1995 2000 2005 2010 2012 Antiislanding P&C Single DG islanding under operator control Manual switching Remote control DER automated islanding Fully automated islanding with multiple DERs (Microgrids) DER Installations 2x8 MW IPP hydro plant Planned islanding guidelines 6 MW IPP hydro plant 10 MW IPP hydro plant 7.5 MW IPP hydro plant Golden Battery Storage Project Off Grid HARP: Integration of hydro plant, fuel cell, diesel, control systems and flow battery Intelligent microgrid research at BCIT 11

BC Hydro Project 2, 2007 6 MW run-of-river IPP connected to a 25 kv feeder Outages > 6 hours, from May to Sept. & affect 1,000 customers Black-start, manual switching 4,000 3,500 3,000 2,500 Monthly Back-up Capacity and Feeder Peak Demand [kw] 2,000 1,500 1,000 500 0 April May June July August September October November December January February March PG Firm Capacity Peak Demand 12

BC Hydro - Project 2, 2007 Islanding study and test results: Technical study performed by IPP consultant and BCH Load-bank used to test PG s islanding capability. Load following and load pick-up capability EMTP simulations confirmed test results Load blocks (500-800kW) may be picked up by PG Installation of switches at BCH feeder. Load-isolation switching points BCH prepared PIR and DOO which includes an islanding plan MACHINE SPEED [PU] 1.1 1.08 1.06 1.04 1.02 1 0.98 0.96 0.94 0.92 MACHINE SPEED RESPONSE TO A 500 kw LOAD STEP 0.9 0 5 10 15 20 25 30 35 40 45 50 TIME [S) 13

BC Hydro Project 2, 2007 Major Achievements: BCH successfully contracted an agreement with an existing IPP to provide emergency back-up Very few modifications and upgrades were required to implement the project One successful islanded operation occurred in 2008 (6hrs, 1000 customers) Significant customer reliability improvement (~50%) BC Hydro Feeder SAIDI SAIFI CAIDI 2008 3.77 5.05 0.75 2007 7.20 6.65 1.08 2006 34.16 8.87 3.85 2005 4.30 4.06 1.06 14

BC Hydro Project 3, 2010 10 MW run-of-river IPP connected to a 25 kv feeder Large industrial customer (~2 MW + 1 MW BCH customers) Black-start & ride-through, automated switching (reclosers) R-3 R-9175 R-2 R-9176 R-1 PG 2 MW R-81133 R-4 15 PHR SUB SUBST.

BC Hydro Project 3, 2010 Studies done in CYMDIST/CYMSTAB 16

BC Hydro Project 3, 2010 Special PQ requirements for islanding conditions: V, f, harmonics Voltage: % of Nominal Voltage Clearing Time Clearing Time Islanding Mode Normal Mode V < 50% 0.16 sec 0.16 sec 50% < V < 85% 5.0 sec 2.0 sec 85% < V <90% 60.0 sec 2.0 sec 90% < V <106% Normal Operation Normal Operation 106% < V < 110% 60.0 sec 1.0 sec 106% < V < 120% 5.0 sec 1.0 sec V >= 120% 0.16 sec 0.16 sec Frequency: Under Frequency Limit Minimum Time Islanding Mode Minimum Time Normal Mode 60.0-60.5 Hz Continuous Continuous 60.6-61.5 Hz 10 minute 3 minutes 61.6-61.7 Hz 1 minute 30 seconds 61.8-62.5 Hz 1 minute Instantaneous 62.6-67.0 Hz 10 seconds Instantaneous Greater then 67.0 Hz Instantaneous Instantaneous Over Frequency Limit Minimum Time Minimum Time Islanding Mode Normal Mode 60.0-59.5 Hz Continuous Continuous 59.4-58.5 Hz 10 minute 3 minutes 58.4-57.9 Hz 1 minute 30 seconds 57.8-57.5 Hz 1 minute 7.5 seconds 57.4-56.9 Hz 10 seconds 45 cycles 56.8-56.5 Hz 10 seconds 7.2 cycles 56.4-53.0 Hz 10 seconds Instantaneous Less than 53.0 Hz Instantaneous Instantaneous 17

BC Hydro Project 3, 2010 18

BC Hydro Energy Storage Project 2x1MW ESS in Golden/Field, 25 kv DS Constraint substation (peak shaving) and reliability (islanding) Contribution from NRCan through CEF ISD Sept. 2011 19

BC Hydro Energy Storage Project 35000 30000 25000 20000 15000 10000 5000 GDN Peak Day Load Profile Based on Winter 2008/2009 Data Peak shaving to mitigate capacity risk at Golden substation, includes demand response (~2 MW). 0-5000 12:00 AM 1:00 AM 2:00 AM 3:00 AM 4:00 AM 5:00 AM 6:00 AM 7:00 AM 8:00 AM 9:00 AM 10:00 AM 11:00 AM 12:00 PM 1:00 PM 2:00 PM 3:00 PM 4:00 PM 5:00 PM 6:00 PM 7:00 PM 8:00 PM 9:00 PM 10:00 PM 11:00 PM 2008-12-16 2008-12-20 Limit Projected F2013 F2013 With 2x1 MVA Energy Storage Energy Storage Charge/Discharge Islanding to relieve poor reliability metrics at Field (~ 500kW) 20

BC Hydro Energy Storage Project Business Case Development Major costs: Battery units, Integration (PCS), P&C, Telecom Major benefits Financial Savings of from deferred transformer upgrade costs Avoided cost of 2 MW equivalent diesel generation for peak shaving and outage support Leverage from Clean Energy Fund Non-financial Improve reliability for the community of Field (eliminate estimated 80% of outages) Mitigate risk of demand exceeding capacity at Golden substation Avoid GHG emissions from use of emergency diesel generator back-up Long-term potential Further benefit from deferred upgrade costs by relocating energy storage to another capacity constrained substation Gain critical knowledge in the use of storage technologies: for purposes of peak shaving, reliability, integrating renewables, and managing multiple distributed resources. 21

BC Hydro Energy Storage Project Procurement Process Battery RFP Challenging to develop a specification given the lack of experience in this area Used external expertise, Quanta Technology Developed the spec based on functional requirements: Peak shaving & Islanding Received 5 responses with 5 different technologies Lead-acid, Lithium Ion, Vanadium Flow batteries, NAS batteries, Zinc-air Integrator RFP Schedule: Originally unable to post RFP for systems integrator until the battery contract is complete. One proponent Lessons learned 22

BC Hydro Energy Storage Project Project Challenges Non-technical Site selection: geotechnical instability, flooding risk, footprint Parks Canada property Community relationship and engagement Whether conditions: extreme winter conditions challenge battery technologies Environmental permitting Internal (BHC) change management Technical Telecommunications: remote location Lack of standards: safety P&C, difficult in a long feeder with several reclosers. Low fault contribution from the battery PCS Smooth remote restoration (re-synch) from islanding operation Batteries heating and cooling 23

BC Hydro Energy Storage Project Project Outcomes Performance measurement Project implementation metrics Load profile data at batteries and Golden substation Battery metrics: Efficiency, charge/discharge profiles Reliability metrics for Field: CAIDI, SAIFI Deliverables BC Hydro Storage Deployment and Integration Guideline 2013 BC Hydro Case Study Report 2014 Knowledge dissemination Potential project extensions Demand response pilot programs Integration of renewable distributed generation Integration of energy management systems 24

Conclusion and Future Challenges Planned Islanding for Reliability DGs and IPPs Battery Storage AMR AMR Advanced Planned Islanding Smartgrid (Automated) solutions Several DER/Microgrid Load Control Utility-scale Energy Storage Islanded operation for reliability Peak shaving Integration of renewable generation Planned Islanding guidelines/ieee1547.4 25

Questions? Thanks!! Email: jaime.peralta@bchydro.com 26