TONGASS NATIONAL FOREST SITKA RANGER DISTRICT FINGER MOUNTAIN FAA COMMUNICATION SITE

Similar documents
Joint Public Notice. LOCATION: In Salmon Bay, Lake Washington Ship Canal, at Seattle, Washington.

Decision Memo Tongass National Forest. Wrangell Ranger District. Pre-Commercial Thinning CE 2010

DECISION MEMO. West Fork Blacktail Deer Creek Hardened Crossing

DECISION MEMO. USDA Forest Service. Butte District Silver Bow County T4N, R8W, Section 36

Public Notice of Application for Permit

Public Notice of Application for Permit

Preliminary Decision Memo 2015 Recreation Residence Projects Odell Lake

PUBLIC NOTICE LOS ANGELES DISTRICT. APPLICATION FOR PERMIT Port of Los Angeles Berths : Wilmington Waterfront Promenade

The project will be conducted in partnership with the Nez Perce Tribe.

J O I N T P U B L I C N O T I C E

DECISION MEMO Divide Creek Barrier Enhancement

JOINT PUBLIC NOTICE May 14, 2018

PUBLIC NOTICE US Army Corps of Engineers, Honolulu District

Public Notice ISSUED: March 14, 2018 EXPIRES: April 13, 2018

Chapter 3 Affected Environment and Environmental Consequences

PROJECT INFORMATION Manchester Ranger District Apple Tree Release and Maintenance Project

3-13 Other Required Findings and Regulatory Compliance

SECTION 4(f) EVALUATION ALASKA RAILROAD MOODY TUNNEL REMOVAL FEDERAL TRANSIT ADMINISTRATION U.S. Department of Transportation

DECISION MEMO. Missoula Electric Cooperative Point 118. MEC - Buried Electric Powerline (Along West Fork Butte Access Road #37 to Point 118)

FINDING OF NO SIGNIFICANT IMPACT OWL CREEK GRAVEL PIT EXPANSION U.S. FOREST SERVICE

THE CORPS REGULATORY AUTHORITY

CESAM-RD-C April 24, 2013 PUBLIC NOTICE NO. SAM AFM JOINT PUBLIC NOTICE SAM AFM U.S. ARMY CORPS OF ENGINEERS

PUBLIC NOTICE. REPLY TO: Denver Regulatory Office 9307 South Wadsworth Blvd 30 DAY NOTICE Littleton, CO FAX (303)

Navigating the U.S. Army Corps of Engineers Regulatory Process

PUBLIC NOTICE. Section 404 of the Clean Water Act (33 U.S.C. 1344) Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C.

SAN LUIS VALLEY PUBLIC LANDS CENTER

ARTICLE 16 - WIND ENERGY CONVERSION FACILITIES

JOINT PUBLIC NOTICE, 2014

Paradise and Watson Creek Headcut Treatment Project (see map on next page)

Sugarbush Valley House Lift Replacement Project

J O I N T P U B L I C N O T I C E

Nance County Zoning Regulations for Wind Energy Conversion Systems

Notice No Closing Date: May 12, 2017

PROJECT INFORMATION AMEREN POWERLINE RECONSTRUCTION PROJECT April 2014

NOTICE DATE: May 04, Joint Public Notice U.S. Army Corps of Engineers and State of Arkansas

J O I N T P U B L I C N O T I C E

CATEGORICAL EXCLUSION WORKSHEET: RESOURCE CONSIDERATIONS

Public Notice of Application for Permit

DECISION MEMO. Steve Simpson and Associates, Inc. Simpson #114 & #116 Gas Well Project Compartment 106

Nationwide Permit General Conditions

JOINT PUBLIC NOTICE SAM PAH U. S. ARMY CORPS OF ENGINEERS MISSISSIPPI DEPARTMENT OF ENVIRONMENTAL QUALITY OFFICE OF POLLUTION CONTROL

DECISION MEMO IDAHO DREAM PLAN OF OPERATIONS

Draft Decision Notice Maroon Bells - Snowmass Wilderness Overnight Visitor Use Management Plan

Blanche Park Reservoir Decision Notice and Finding of No Significant Impact

Proposed Action: In response to resource specialist concerns raised during internal scoping, the following restrictions will apply:

DECISION MEMO. Bull Bear 1H-18 Oil and Gas Pipeline

Decision Notice and Finding of No Significant Impact

Wind Energy Development Specialist Report

J O I N T P U B L I C N O T I C E

Huron-Manistee National Forests Mio Ranger District 107 McKinley Road Mio, MI 48647

J O I N T P U B L I C N O T I C E

PRELIMINARY DECISION MEMO

PUBLIC NOTICE. Dredging with ten-years maintenance, return flow to the waterway and upland placement. Georgica Cove, tributary of Georgica Pond

DEPARTMENT OF THE ARMY JACKSONVILLE DISTRICT CORPS OF ENGINEERS PRINCESS PALM AVENUE, SUITE 120 TAMPA, FLORIDA

Keefer Pasture Drift Fence Project. Challis-Yankee Fork Ranger District Salmon-Challis National Forest

Record of Decision for Issuing a Presidential Permit to Champlain Hudson Power Express,

Decision Memo. National Ecological Observatory Network Long Term Research Project

DECISION NOTICE FINDING OF NO SIGNIFICANT IMPACT (FONSI)

Department of the Army Permit Application

DECISION MEMO CATARACT CREEK-MOUNTAIN MEADOW PLAN OF OPERATIONS

DECISION MEMO. Non-Commercial Thinning on the Ocala National Forest (PALS project # 39238)

COST-BENEFIT ANALYSIS. Categorical Exclusions for Oil and Gas Exploration and Development Activities. USDA Forest Service

BANFIELD #9 LODE CLAIM (Plan of Operations) Umpqua National Forest Tiller Ranger District June, 2011

CESAM-RD-M February 28, 2018 PUBLIC NOTICE NO. SAM PAH JOINT PUBLIC NOTICE U.S. ARMY CORPS OF ENGINEERS

PN Comment Period: February 9, 2015 to March 9, 2015

Decision Memo. Administrative Site Disposal Old Agness Guard Station Compound

DECISION MEMO. Aurora New Horizons Project

Public Notice U.S. ARMY CORPS OF ENGINEERS, GALVESTON DISTRICT AND TEXAS COMMISSION ON ENVIRONMENTAL QUALITY

Updates on FAA Order F. Agenda. Communicate FAA Order Updates. Educate attendees on the changes to FAA Order

DECISION NOTICE & FINDING OF NO SIGNIFICANT IMPACT OUTFITTER GUIDE MOTORIZED TOURS SPECIAL USE PERMIT ISSUANCES

Regulatory Guidance Letter 93-02

DRAFT GREATER MOOSES TOOTH TWO (GMT2) DEVELOPMENT PROJECT PERMITTEE RESPONSIBLE WETLANDS MITIGATION PLAN NATIONAL PETROLEUM RESERVE-ALASKA

ARTICLE X TRANSMISSION TOWER REGULATIONS

Background. Purpose and Need. Proposal. Mitigation and Design Features

DECISION MEMO Mt. Hood Meadows Ski Resort 2011 Maintenance Projects September 2011

STATE OF ALASKA DEPARTMENT OF NATURAL RESOURCES DIVISION OF MINING, LAND AND WATER LAND USE PERMIT APPLICATION AS

DECISION MEMO Besson Special Use Permit Ottawa National Forest

APPENDIX A. NEPA Assessment Checklist

Draft Decision Notice and Finding of No Significant Impact (DN/FONSI)

Tower Site Inspection Procedures

Manchester Ranger District. Apple Tree Release and Maintenance Project

Conger Rock Harvesting Project

Cross-Cutting Environmental Laws A Guide for Federal/State Project Officers

Public Notice ISSUED: August 11, 2015 EXPIRES: September 10, 2015

9.2 Definitions. The following terms are defined, for purposes of Section 9, as follows:

PROPOSED ACTION Cooperative Horse Removal with Fort McDermitt Paiute-Shoshone Tribe

Dam Safety Modifications at Cherokee, Fort Loudoun, Tellico, and Watts Bar. SUMMARY: This notice is provided in accordance with the Council on

Sitka Access and Travel Management

Public Notice. Applicant: City of Dallas Project No.: SWF Date: April 18, Name: Chandler Peter Phone Number:

Fiscal & Regulatory Impact Analysis

A. Product Data shall be provided for each type of product indicated.

Sitka Access and Travel Management

CEQA and its Role in Historic Preservation. Darcy Kremin, AICP Bay Area Environmental Practice Leader Michael Baker International, Oakland, CA

George Washington and Jefferson National Forests Eastern Divide Ranger District Giles County, Virginia

Structural Tests and Special Inspections Form. Inspection of Fabricators (1704.2)

Public Notice of Application for Permit

CATEGORICAL EXCLUSION REVIEW - NEPA COMPLIANCE RECORD

DECISION NOTICE AND FINDING OF No SIGNIFICANT IMPACT HOPKINS FIRE SALVAGE

AGENCY: Department of the Army; Corps of Engineers; and Texas Commission on Environmental Quality

Ketchikan-Misty Fiords Outfitter and Guide Management Plan

Transcription:

DECISION MEMO TONGASS NATIONAL FOREST SITKA RANGER DISTRICT FINGER MOUNTAIN FAA COMMUNICATION SITE DECISION It is my decision to authorize the Federal Aviation Administration (FAA) to reconstruct, operate and maintain a communication site on Finger Mountain. Authorization will occur through issuance of a special use permit to the FAA for a period of 20 years. The site is approximately 45 miles north of Sitka. It is located in the Copper River Meridian, Township 48 South, Range 61 East, section 26. The latitude and longitude of the site is 57 41' 09" Nand 135 31' 55" W at about 2600 feet above sea level. The facilities will occupy approximately 75 feet by 65 feet or 0.1 acres. This activity falls within a category of actions which normally do not individually or cumulatively have a significant effect on the quality of the human environment and, therefore, may be categorically excluded from documentation in an environmental impact statement or environmental assessment. This category of actions is identified in 36 CFR 220.6 (e)(3) as: Approval, modification, or continuation of minor special uses of NFS lands that require less than five contiguous acres of land. No extraordinary circumstances exist which would result in additional impacts. No irreversible or irretrievable commitment of resources is anticipated. PROJECT DESCRIPTION The following presents the key elements of the work. 1. Removal of existing infrastructure by helicopter. 2. Establish camp, identify hazard areas, and mark off boundaries for safe travel, staging, and installation of equipment. 3. Preparation of site grounds to include clearing of encroaching vegetation or small boulders and minor grading and/or leveling as required. Work will be done using hand tools, small engine-power tools, and a mini-excavator. No vegetation will be burned. Rocks will be moved to the perimeter of the project area or crushed and used as fill to level areas around the building and towers. 4. A total of one pre-fabricated equipment-building, a nominal 7' by 9' and matte grey in color, will be installed onsite to house FAA communication and power generation/storage electronics. This building requires the excavation, installation, backfill, and compaction of four 18" diameter concrete pier foundations to support the building. Reinforcing steel and embedded support materials will be installed; concrete piers will be sucured to existing bedrock as required using high strength epoxy and rock anchors. A nominal 4' by 5' aluminum deck will be mounted to the building frame, with stairs and a handrail for safe 1

access. 5. A total of three new RADIAN SSG antenna towers will be installed on site for aircraft communications and solar power generation. The top of each tower must be at the same height as the others to avoid radio interference. Based on the steep terrain, one tower will be approximately 26' above the ground and the other two towers will be approximately 32' above ground. Each tower requires one 18" diameter concrete pier foundation and three guy-wire anchors for secure support against wind and icing. Guy-wire anchors wil be constructed using rock anchors, soil anchors, and concrete piers based on the soil conditions at each anchor point. Reinforcing steel and embedded support material will be installed; concrete piers will be secured to existing bedrock as required, using high strength epoxy and rock anchors. Each tower will be guyed using 5/16" diameter, tensioned cable guy-wires to provide tower support. 6. A total of one bi-directional satellite dish will be installed onsite. The satellite dish will be mounted on a 9' tall pedestal. The dish pedestal requires on 24" diameter concrete pier foundation. As required, reinforcing steel and embedded support materials will be installed; concrete piers will be secured to existing bedrock with high strength epoxy and rock anchors. 7. A total of seven %" diameter by I0' long copper grounding rods or seven 24" by 24" copper ground plates will be installed along with approximately 300' bare 4/0 cable to a depth of approximately 2' below ground to create the grounding counterpoise loop. Warning tape will be placed in the trench before it is backfilled and compacted. All connections to the grounding counterpoise will be made using exothermic welds or appropriate metallic clamp connections in accordance with FAA-STDF-19E for Grounding and Bonding. 8. Batteries will be positioned and installed inside equipment building per FAA design requirements. Rigid cable conduit will be installed between the building and towers and supported on all-weather wood cribbing at the base of each tower. Conductors for the radio antennas, weather sensors, and solar panels will be pulled through the conduit and terminated inside the building per FAA design requirements. All electronics equipment will be tested onsite by FAA installers, then certified for operation by FAA technicians responsible for ownership and maintenance of the site. 9. Any required remedial work will be conducted at the completion of construction. A final clean up of the site will be performed; all tools, equipment, old shelter/building and foundation materials, old batteries, leftover matrials, trash, and waste will be packaged for transport and demobilized from the site to Anchorage or other approved, specified location. Work is estimated to be completed within one month and occur between June and August 2014. A six to eight person crew will live on-site in wall tents during project installation. All waste will be containerized and removed from site on a weekly basis, or as required. Crews are familiar with high site installations and receive safety training to include safe work, travel, and habitation in bear country. PUBLIC INVOLVEMENT On August 1, 2011 a letter providing information and seeking comment was sent to Central Council Tlingit & Haida Indian Tribes of Alaska, Sitka Tribe of Alaska, Angoon Community Association, Sealaska Corporation, Shee Atika Incorporated, and Kootznoowoo, Inc. No comments were received. 2

On September 1, 20 I I a letter seeking comment was sent to the following groups: Sitka Field Office, US Army Corps of Engineers Alaska Department of Fish and Game City & Borough of Sitka Kettleson Memorial Library Citizens Advisory Commission on Federal Areas Greenpeace, Sitka Field Office Sitka Conservation Society City & Borough of Sitka asked for additional detail. No comments were received. My intention is to authorize this use as published in the Tongass National Forest Schedule of Proposed Actions (SOPA) beginning July 1,2011. BIOLOGICAL EVALUATION Biological Evaluations were completed for sensitive plants and animals. No sensitive species will experience impacts that would cause or contribute to a trend towards federal listing or cause a loss of viability to the population or species. FINDINGS REQUIRED BY OTHER LAWS 2008 Tongass Land and Resource Management Plan This decision is consistent with the 2008 Tongass Land and Resource Management Plan (Forest Plan). The project is located within an area identified in the Forest Plan as having a Land Use Designation of Timber Production. Direction for management of this area is to provide a sawtimber and other wood projects on an even-flow, long-term sustained yield basis. An extensive road system provides access for timber management activities, recreation uses, hunting and fishing, and other public and administrative uses. Although the permanent communication site has existed on Finger Mountain, East of Hoonah Sound, on Chichagof Island since October 1, 1982, the site was inadvertently left off the list of communication sites identified in the 2008 Tongass Land and Resource Management Plan (Forest Plan), Appendix E. An errata was completed to add this site into the list of communication sites in Appendix E. All structures will be made to blend in with the surrounding environment to meet the intent of the scenery objectives as identified in the 2008 Forest Plan. ANILCA Section 810, Subsistence Evaluation and Finding The effects of this project have been evaluated to determine potential effects on subsistence opportunities and resources. There is no documented or reported subsistence use that would be restricted as a result of this decision. For this reason, this action would not result in a significant possibility of a significant restriction of subsistence use of wildlife, fish, or other foods. ANILCA Section 811, Access Evaluation and Finding There is no documented or reported access that would be restricted as a result of this decision. For this reason, this action would not result in a significant possibility of a significant restriction 3

of subsistence users having reasonable access to subsistence resources on National Forest System Lands. Coastal Zone Management Act of 1972, as Amended The Alaska Coastal Management Program expired under State law on June 30,2011. Consequently, there are no longer any requirements for consistency determinations or reviews under the Coastal Zone Management Act for Forest Service activities in Alaska. Endangered Species Act of 1973 A Biological Evaluation has been completed for this action which indicates that no federally listed threatened or endangered species will be affected by this activity. National Historic Preservation Act of 1966 The Forest Service program for compliance with the National Historic Preservation Act (NHPA) includes locating, inventorying and evaluating the National Register of Historic Places eligibility of historic and archeological sites that may be directly or indirectly affected by scheduled activities. Regulations (36 CFR 800) implementing Section 106 of the NHPA require federal agencies to consider the effects of their actions on sites that are determined eligible for inclusion in or are listed in the National Register of Historic Places (termed "historic properties"). A Forest Service archeologist reviewed this project and made a determination of No Historic Properties Affected in the area of potential effect for the project. Floodplain Management m.o. 11988), Protection of Wetlands (E.O. 11990) This activity will not impact the functional value of any floodplain as defined by Executive Order 11988 and will not have negative impacts on wetlands as defined by Executive Order 11990. Recreational Fisheries (E.O. 12962) Federal agencies are required, to the extent permitted by law and where practicable, and in cooperation with States and Tribes, to improve the quantity, function, sustainable productivity, and distribution of U.S. aquatic resources for increased recreational fishing opportunities. As required by this Order, I have evaluated the effects of this action on aquatic systems and recreational fisheries and determined there will be no effects to fisheries resources within the project area. Therefore, there will be no direct, indirect or cumulative impacts related to this Order. Environmental.Iustice m.o. 12898) I have determined that, in accordance with Executive Order 12898, this project does not have disproportionately high and adverse human health or environmental effects on minority populations and low income populations. 4

f I Magnuson-Stevens Fishery Conservation and Management Act The Magnuson-Stevens Fishery Conservation and Management Act requires a finding on the effects of this project on Essential Fish Habitat (EFH). The Proposed Action will have "no adverse effects" on EFH because the project will not measurably modify fish habitat in or near the project area. This project will not cause erosion or sedimentation which could reduce quality or quantity of fish habitat in the freshwater or marine environments outside the analysis area. Therefore consultation with the U.S. Fish and Wildlife Service and National Marine Fisheries Service to review the effects of this project on threatened, endangered and candidate species is not required. IMPLEMENTATION DATE This action falls within a category of actions which are not subject to appeal. Implementation of this decision may occur immediately. r, CONTACT PERSON Clay R. Davis, Lands Specialist Tongass National Forest, Sitka Ranger District 204 Siginaka Way Sitka, AK 99835 907-747A22S clayrdavis@fs.fed.us < ~f11(q~{u/ Forrest Cole FOREST SUPERVISOR Distribution John Louie, Federal Aviation Administration, Anchorage, Alaska ~.'..1 I, 5