Highway Construction Program

Similar documents
Highway Construction Program

Implementing Asset Management: WSDOT s Experience

Mega Projects at WSDOT

NW La Center Road/I-5 Interchange Improvement Project (MP 16.80)

Conclusions & Lessons Learned

Final Recommendations Identification of Improvements, Strategies, and Solutions

Overall project. The $288 million Phase 2 DesignBuild project starts construction. this spring, with completion by December 31, 2016

Florida s Turnpike Enterprise Tentative Five-Year Work Program - FY 2015/16 thru FY 2019/20 Summary of Projects in FDOT District Four

THE PROJECT. Executive Summary. City of Industry. City of Diamond Bar. 57/60 Confluence.

The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges

Exit 73 I-29 Interchange Modification Justification Study

ADOT Yuma District. Alvin Stump, P.E. ADOT Yuma District Engineer Rural Transportation Summit January 20, 2012

Maine Turnpike Authority FINAL 4-year Capital Investment Plan ( )

Maryland Transportation Authority (MDTA)

TRANSPORTATION 101 Today and Tomorrow. Moving People and Goods

Washington State Department of Transportation Case Study. Guidelines for the Preservation of High-Traffic-Volume Roadways (R26)

SR 99 Incident Response After- Action Plan

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

I-15 South, MP 0 to MP 16 Environmental Assessment. Public Hearing. August 7, :00 PM to 7:00 PM

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION

SHRP2 SOLUTONS. Innovative Bridge Designs for Rapid Renewal. Peer-to-Peer Exchange Workshop Atlanta, GA November 2015

2 Purpose and Need. 2.1 Study Area. I-81 Corridor Improvement Study Tier 1 Draft Environmental Impact Statement

Interchange Workshop Report (August 2004)

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

1.1 Purpose of the Project

South Dakota Department of Transportation. Interchange Modification Justification Report. Interstate 90 Exit 44 (Bethlehem Road - Piedmont)

BMI Precast PRECAST & PRESTRESSED CONCRETE PRODUCTS

NORTHWEST CORRIDOR PROJECT. NOISE TECHNICAL REPORT 2015 Addendum Phase IV

I-10 CORRIDOR IMPROVEMENTS STAGE 0 FEASIBILITY STUDY STATE PROJECT NUMBER H FEDERAL AID PROJECT NUMBER H004100

State Route 8 Bridge Replacement Project

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

IOWA TRANSPORTATION BY THE NUMBERS:

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation

extent feasible. Per the and low constructability,

Life Cycle Cost Analysis July 2011 Materials Division Page 1 TABLE OF CONTENTS V. ASPHALT PAVEMENT CONSTRUCTION/RECONSTRUCTION...

SR 9/I-95 Interchange at 45th Street PD&E Study Palm Beach County, Florida FPID No.: FAP No.: ETDM No.

Accelerated and Innovative Bridge Construction In Washington State

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

PLAN 2040 Regional Transportation Plan Update. Final Recommendations. Transportation and Air Quality Committee March 13, 2014

King County Flood Control District approves grants for flood prevention projects Regional projects to benefit from district funds

Current Trends in Traffic Congestion Mitigation

FTBA 2018 Construction Conference Major Projects Update

MONITORING IMPLEMENTATION AND PERFORMANCE

Standard Performance Attributes for Transportation Projects

Central Phoenix Transportation Framework Study

INTERACTIVE HIGHWAY SAFETY DESIGN MODEL (IHSDM)

CUY-90-Innerbelt ODOT PID No 77510

ODOT Asset Management Plan 0

Performance Based Practical Design (PBPD)

Cost Estimating Guideline February, 2017

Asset Management Performance Measures for Privatized Highway Concessions in British Columbia

REPORT Condition D19 Permanent Noise Barriers

Sunrise Project South I-205 Corridor Improvement Project

CHAPTER 11 PAVEMENT TYPE DETERMINATION

State of Ohio. Department of Transportation ~ Innovative Contracting Manual

500 Interchange Design

GEOMETRIC DESIGN CRITERIA for Non-freeway Resurfacing, Restoration, and Rehabilitation Projects

SECTION PAVEMENT STRUCTURE ANALYSIS

Stage One Reference Design Enhancements. Date: 2 October Cabinet-in-Confidence

I. Project Overview and Limits. Project Goal

Technical Memorandum MULTIMODAL NEEDS. Prepared for: Oklahoma Department of Transportation. Prepared by:

Hampton Roads Bridge-Tunnel Expansion Feasibility Study. Design Considerations

I-11 Project Nevada Transportation Conference. Ryan Wheeler, P.E. NDOT, Senior Project Manager. Nevada Department of Transportation

CITY OF SAFETY HARBOR ENGINEERING

M D 355 [FR E D E R IC K R O A D] OVER

A Unique Application of Railroad Preemption with Queue Mitigation at a Roundabout Interchange

FY STATEWIDE TRANSPORTATION IMPROVEMENT PROGRAM New Jersey Department of Transportation Project Descriptions ($ millions)

Pavement Management Systems

MAINE TRANSPORTATION BY THE NUMBERS:

Life Cycle Cost Analysis

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS

Jim Alexander Director of Design and Engineering, Southwest Light Rail Transit Project

PROJECT CHARTER South Coast 101 HOV Lanes Project Design Decision Phase

Re: EX8.12 F.G. Gardiner Expressway Strategic Rehabilitation Plan Procurement Strategy

THE FIVE GOALS FOR SCDOT S STRATEGIC PLAN ARE: GOAL 1: Improve safety programs and outcomes in our high-risk areas.

GNC Coalition Update. Washington Public Ports Association Trade and Transportation Committee November 18, 2015

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR

3.6 Construction Methods

Appendix B Highway 407 Interchange Review - Cochrane Street Area

South Boston. Transportation Plan. Transportation Planning Division. Virginia Department of Transportation

MAINE TRANSPORTATION BY THE NUMBERS:

CITY OF TACOMA RIGHT-OF-WAY RESTORATION POLICY. Guidance on restoration of City Rights-of-Way

MDX Contract #: RFP MDX Work Program #: ETDM #: 11501

Louisiana Road And Bridge Conditions Threatened By $12.5 Billion Transportation Funding Backlog

USING REMAINING SERVICE LIFE AS THE NATIONAL PERFORMANCE MEASURE OF PAVEMENT ASSETS

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

CITY OF JACKSONVILLE 2030 MOBILITY PLAN STUDY UPDATE GOALS, OBJECTIVES, AND PERFORMANCE MEASURES PREPARED FOR: CITY OF JACKSONVILLE

Rt. 29 Solutions Project Delivery Advisory Panel. February 18, 2016

I-35W Retaining Wall Design Exhibit A - Draft Scope of Work

Maine Turnpike Authority Ten Year Planning Report

Maintenance of Traffic for Innovative Geometric Designs Work Zones

Tech Brief PRECAST CONCRETE PAVEMENT IMPLEMENTATION BY U.S. HIGHWAY AGENCIES

Chapter URBAN & RURAL FREEWAY DESIGN

CONNECTICUT TRANSPORTATION BY THE NUMBERS:

Are We Prepared for the Energy Movements? JEANNIE BECKETT THE BECKETT GROUP ENERGY EXPORT PERMITTING IN THE NW JUNE SEA-TAC CONFERENCE CENTER

Project History Interchange Innovation Existing Conditions Proposed Design Approval Process Final Details PRESENTATION FOCUS

Transcription:

Highway Construction Program Monthly Delivery Progress Report Watch List February 2017 This report focuses on Capital Highway Program projects, which have, or may have significant changes in scope, schedule, or budget. These projects are reported monthly by CPDM to identify when and how these delivery issues are resolved. The Monthly Delivery Progress Report Watch List replaces the quarterly delivery progress report previously known as The Gray Notebook Watch List. A monthly report allows for timely reporting and improves transparency on delivery progress. This report sorts projects into three categories: new projects being reported on, changes from last month, and projects previously reported that have no changes and are not yet resolved. o o o o New projects this month. These projects have been added to the watch list due to potential changes or issues in scope, schedule, or budget. This category also includes projects with changes that occurred and were resolved within the current month. Changes from Prior Month. Changes discussed in this section were on the previous month s watch list and have other issues that have happened; or they may have been resolved. No Changes from Prior Month. These projects were on the previous month s watch list and are being followed while an issue is in the process of being resolved. Projects are Removed when delivery has been delayed out of the Six-Year Plan, when delivery has been attained, or when a significant issue has been mitigated and/or approved by WSDOT. For additional information on scope, schedule and budget for all projects, please visit WSDOT's project pages. This is the link that leads to the websites of individual projects: http://www.wsdot.wa.gov/projects/search/ To search for a particular project, please enter the state route, county, project title or PIN. 1 February 2017

Summary Delivery Progress Report Summary Table as of February 28, 2017, with issues based on a monthly update. New in February 2017 Project I-5/NB S 260th St to Duwamish River Bridge - Concrete Pavement Rehab (King) 100506G Phase/Issue Construction: cost increase I-5/Northbound Boeing Access Rd to NE Ravenna Bridge - Pavement Repair (King) 100515B I-82/Red Mountain Vicinity - Construct Interchange (Benton) 508207R SR 518/Des Moines Memorial Drive - Interchange Improvements (King) 151801K Changes from Prior Month Project I-5/NB I-90 Vic to James St Vic - Concrete Pavement Replacement (King) 100519B I-5/NB Spokane St to Lake WA Ship Canal Bridge - Special Bridge Repair (King) 100522C Phase/Issue No Changes from Prior Month Project I-5/SR 510 Interchange - Reconstruct Interchange (Thurston) 300502C (CWA Revenue Package) Phase/Issue Design: scope change, design element 2 February 2017

SR 14/West Camas Slough Bridge-Bridge Widening (Clark) 401419A (CWA Revenue Package) SR 99/S King St Vic to Roy St - Viaduct Replacement (King) 809936E US 395/North Spokane Corridor - New Construction (Spokane) 600015A (CWA Revenue Package) Design: scope change, design element Construction: cost estimate, schedule update Removed in February 2017 Project I-5/NB S 260th St to Duwamish River Bridge - Concrete Pavement Rehab (King) 100506G I-5/Northbound Boeing Access Rd to NE Ravenna Bridge - Pavement Repair (King) 100515B I-5/NB I-90 Vic to James St Vic - Concrete Pavement Replacement (King) 100519B I-5/NB Spokane St to Lake WA Ship Canal Bridge - Special Bridge Repair (King) 100522C I-82/Red Mountain Vicinity - Construct Interchange (Benton) 508207R SR 518/Des Moines Memorial Drive - Interchange Improvements (King) 151801K Phase/Issue Construction: cost increase Project Detail Below is the detail behind the above summary. 3 February 2017

New in February 2017 I-5/NB S 260th St to Duwamish River Bridge - Concrete Pavement Rehab (King) 100506G Issue: Continuing pavement deterioration has worsened and increased the project s costs. This project is being reported and removed from this list. This project rehabilitates the concrete pavement along northbound I-5 from South 260th Street to the Duwamish River Bridge. It replaces about 440 broken concrete panels, repaves about four miles of asphalt between SR 516 and South 178th Street, grinds off ruts and bumps, replaces eight expansion joints, and rehabilitates the Interurban Avenue and Duwamish River bridge decks. The current cost estimate has increased by $8.9 million, from $30.9 million to $39.8 million. The increase is mainly due to the concrete pavement deteriorating more than anticipated. An updated engineers estimate at advertisement reflected the revised unit bid quantities and costs. Finally, WSDOT received high bids, which increased the cost at award. I-5/Northbound Boeing Access Rd to NE Ravenna Bridge - Pavement Repair (King) 100515B Issue: The cost estimate has increased by $3.7 million. The operationally complete date is delayed 10 months to fall 2019. This project is being reported and removed from this list. This project repairs the concrete pavement through select panel replacements and diamond grinding concrete pavement surfaces along the full width of northbound I-5, from NB I-90 to James Street Vicinity. It will address roadway drainage through grinding and paving the inside and outside shoulders, adjusting catch basins and junction boxes as needed, as well as paving 20 mainline ramps. The current cost estimate has increased by $3.7 million, from $13.2 million to $16.9 million. An updated engineer's estimate reflects additional reinforced concrete panel replacement work and bridge approach slabs. Also added to the project was a contract incentive to reduce the number of weekend closures. Further increases included an update of unit bid prices on several bid items, based on recent projects costs. Due to recent expansion joint failures, WSDOT began looking for opportunities to reduce delays to the traveling public and gain construction efficiencies. As a result, 37 expansion joints on seven bridges on I-5 were identified and added to the I-5/NB Spokane St to Lake WA Ship Canal Bridge - Special Bridge Repair (100522C) project. This added work increased the construction duration for the Design-Build project from one season to two, delaying the operationally complete date by one year from fall 2018 to fall 2019. 4 February 2017

I-82/Red Mountain Vicinity - Construct Interchange (Benton) 508207R Issue: Delays with attaining the Interchange Justification Report (IJR) approval has delayed the project start by two years. This project is being reported and removed from the list. This project will construct a new interchange on I-82 east of Benton City. The new interchange will provide direct access to West Richland and the surrounding Red Mountain area, and a new connection to SR 224. This improved access for the 1.5-mile section on the I-82 corridor east of Benton City to the I-182 junction is critical for continuing economic development. WSDOT is working with the Federal Highway Administration (FHWA) on preparation of a required Interchange Justification Report (IJR). The IJR effort is being accomplished under the I-82/Red Mountain Vicinity - Pre-Design Analysis (508207M) project and this process is taking longer than originally anticipated. Additional study and analysis of the Tri-Cities road network is being prepared in cooperation with the local Metropolitan Planning Organization to support the IJR. Due to the delay with attaining IJR approval, the project start was delayed by two years from fall 2015 to fall 2017, which has delayed the right-of-way certification and advertisement by one year to fall 2019, and operational completion by one year to summer 2020. SR 518/Des Moines Memorial Drive - Interchange Improvements (King) 151801K Issue: The construction duration changed has delayed the operationally complete date by one year. This project is being reported and removed from this list. This project will add a new two-lane off-ramp from eastbound State Route 518 that will cross over 8th Avenue South and join Des Moines Memorial Drive. The new off-ramp will provide direct access for freight and drivers using State Route 509 to Des Moines Memorial Drive. The project s cost, estimated at $13.5 million, will advertise in spring 2017. Originally, the construction phase was planned to be completed in fall 2017, in one construction season. During design, an error in the construction duration schedule was identified. Projects with bridge work typically need two construction season. As a result, the construction duration has changed from one to two seasons, which has delayed the operationally complete date by one year from fall 2017 to fall 2018. Changes from Prior Month 5 February 2017

I-5/NB I-90 Vic to James St Vic - Concrete Pavement Replacement (King) 100519B Changes from Prior Report: The cost estimate has increased by $1.9 million. The operationally complete date is delayed 10 months to fall 2019. This project is being reported and removed from this list. Previously reported: This project was combined with a larger, single Design-Build contract (I-5/NB Martin Luther King Jr Way to NE Ravenna Br - Pavement Repair & More) to gain construction efficiencies and minimize associated traffic impacts. This delayed the construction delivery by one year, delaying the advertisement date to fall 2016 and the operationally complete date to fall 2018. Update to the August 2016 report: An updated engineer's estimate reflects an increase to the unit bid prices on several items, based on recent projects costs. The estimated cost has increased by $1.9 million, from $7.4 million to $9.3 million. Due to recent expansion joint failures, WSDOT began looking for opportunities to reduce delays to the traveling public and gain construction efficiencies. As a result, 37 expansion joints on seven bridges on I-5 were identified and added to the I-5/NB Spokane St to Lake WA Ship Canal Bridge - Special Bridge Repair (100522C) project. This added work increased the construction duration for the Design-Build project from one season to two, delaying the operationally complete date by one year from fall 2018 to fall 2019. I-5/NB Spokane St to Lake WA Ship Canal Bridge - Special Bridge Repair (King) 100522C Changes from Prior Report: WSDOT advanced the replacement of six additional expansion joints, and increased the cost estimate by $781,000. The operationally complete date is delayed by one year to fall 2019. This project is being reported and removed from this list. Previously reported: Due to recent expansion joint failures, WSDOT began looking for opportunities to reduce delays to the traveling public and gain construction efficiencies. As a result, 31 expansion joints on seven bridges on I-5 near this project were identified as needing replacement and were added to this project. The additional work expanded the project limits by five miles and increased the cost estimate by $3.9 million, from $271,000 to $4.2 million. This work can be accomplished within the original schedule and is on track to be advertised in fall 2016 and operationally complete in fall 2018. Update to the March 2016 report: Further analysis identified an additional six expansion joints needing replacement within the current project limits. In addition, the engineer's estimate was updated to reflect current unit bid prices on several items. The estimated cost has increased by $781,000, from $4.2 million to $5 million. 6 February 2017

In addition, adding the expansion joint work to the existing Design-Build project has increased the construction duration from one season to two, delaying the operationally complete date by one year from fall 2018 to fall 2019. No Changes from Prior Month I-5/SR 510 Interchange - Reconstruct Interchange (Thurston) 300502C Status: No Change Previously reported: WSDOT is requesting a scope change to remove the specific interchange type 'Single Point Urban Interchange' (SPUI) from the project description. The available funding for the project is not sufficient to construct an SPUI. Additionally, traffic modeling indicates that a Diverging Diamond Interchange (DDI) performs better and at a significantly reduced project cost. The lead project proponent, the City of Lacey, was part of the Value Engineering workshop that recommended the proposed change. The City Council is in full support of constructing a Diverging Diamond Interchange. SR 14/West Camas Slough Bridge-Bridge Widening (Clark) 401419A Status: No Change Previously reported: WSDOT is requesting a scope change on this project that will defer the improvements and shift funding. Originally, this project was to widen and retrofit the bridge to increase capacity and reduce travel time to accommodate expected residential, commercial, and industrial growth on SR 14. The agency request is to defer the SR 14 West Camas Slough Bridge and shift the funding to another project on the SR 14 Corridor. Funding will go towards addressing congestion on SR 14 from the SR 14/I-205 Interchange to SE 164th Avenue. Initial concepts for the project include constructing auxiliary lanes in both directions between the interchanges and modifying the ramp configuration from I-205 to eastbound SR 14. Community engagement and practical solution implementation will further refine the scope and operational elements of the project. The cities of Vancouver, Camas, and Washougal as well as the Port of Camas/Washougal support this proposed change and are committed to working with WSDOT to identify the best application of these funds to reduce traffic delays along SR 14. 7 February 2017

SR 99/S King St Vic to Roy St - Viaduct Replacement (King) 809936E Status: No Change. Previously reported: The original tunnel contract opening date was November 2016. The Seattle Tunnel Partners (STP), the design build contractor, first delayed the opening to spring of 2018. According to their new schedule, the estimated completion date for the tunnel is November 2018. After STP hands over the tunnel to the state, work must be done to connect the new tunnel to SR 99 in the south and Aurora Avenue North in the north. Based on STP s schedule, WSDOT estimates the tunnel would be open to traffic in early 2019. The state cannot verify STP s schedule. Based on a preliminary review of the budget, the program anticipates a cash-flow need of up to $60 million in the 2017-19 biennium, to ensure continued progress. Looking toward completion of the viaduct replacement program, the program estimates a total provisional budget need of $223 million. Funds from litigation, insurance claims, and savings from unpaid early completion incentives may offset some of the costs. Due to litigation, funding sources may not be resolved until after the tunnel is open to traffic. Update to the November 2016 report: The Program completed a Cost Risk Evaluation that included statistical modeling to update the total program budget. The program total budget need was reduced to $167 million (from $223 million). Of this amount, $18 million will be covered by local funding. For more updates on the Alaskan Way Viaduct Replacement project, please see the Alaskan Way Viaduct website at http://www.wsdot.wa.gov/projects/viaduct/ US 395/North Spokane Corridor - New Construction (Spokane) 600015A Status: No Change Previously reported: WSDOT must find an alternative to capping and covering a railroad black tank site. This roadway project completes the corridor from Francis Avenue to an interim connection with I-90. In addition, it would complete the corridor to the Trent Avenue Interchange. The original plan for this project was to cap and cover the railroad's black tank site and build the roadway over the top. The Department of Ecology no longer supports this solution. Options for cleaning up the Bunker C heavy fuel that is 170 feet underground have not been determined yet. The cleanup of the site may take seven years to complete and will delay the project at least this amount of time. If the roadway alignment is moved to go around the site, there 8 February 2017

will be an additional cost, estimated at $20 million, and WSDOT is likely to see public resistance to it. WSDOT is currently considering alternatives. 9 February 2017