I-91 Viaduct Public Information Briefing

Size: px
Start display at page:

Download "I-91 Viaduct Public Information Briefing"

Transcription

1 I-91 Viaduct Public Information Briefing Project File No MassDOT Contract No Briefing no. 10 December 18, 2017

2 Agenda Welcome Update on Construction Activities (Full Beneficial Use) Next: Steel Repairs, Bridge Painting, Surface Street Work Adjacent I-91 project Continued Public Involvement and Outreach

3 The Joint Venture Constructing the Project J.F. White Contracting Co. A General Contractor performing heavy civil work in Massachusetts for over 90 years. Schiavone Construction Co. A General Contractor performing heavy civil work in the northeast region for over 50 years.

4 Project Limits

5 Project Scope Rehabilitation includes the following: Complete deck replacement Painting of structural steel, replacement of bearings, structural steel repairs, concrete substructure repairs Improved bridge drainage and highway lighting (on the highway, surface streets under the viaduct, upper levels of the north and south garage, and the Columbus Avenue railroad underpass) Other safety improvements, such as at the I-291/I-91 merge Comprehensive Traffic Management

6 Fast Facts Viaduct length is approximately ¾ mile Over 22,350 cubic yards of concrete for bridge deck and barriers all 22,350 cubic yards placed Over 7.2 million pounds of reinforcing steel 7.2 million pounds placed in total Over 450 bearing replacements all 450+ bearings replaced 27 subcontractors to date From April through October, an average of over 145 workers per day on the project with over 70% from the Greater Springfield area

7 Fast Facts (continued) 246 separate concrete deck placements required Completed Approximately 21,000 feet (4 miles) of concrete barrier required Completed 12,500 feet of snow fence required Completed 65 highway lighting fixtures required Completed

8 Construction Schedule Milestone Contractor Forecasted Contract Required Date Date Stage 1A Complete N/A Stage 1B Complete N/A Stage 2A Complete N/A Stage 2B Complete N/A Full Beneficial Use December 2017 August 6, 2018 Substantial Completion Fall 2018 November 6, 2018 Field Completion January 2019 February 4, 2019

9 Definition of Full Beneficial Use I-91, I-291 & Assoc. Ramps The majority of the contract work has been completed and the asset(s) has been opened for full multi-modal transportation use, except for limited contract work items that do not materially impair or hinder the intended public use of the transportation facility. All anticipated lane takings have been completed. This includes completion of superstructure work, bridge barrier, permanent guardrail, removal of temporary concrete barriers, final paving, permanent traffic markings and signage, permanent lighting.

10 Definition of Substantial Completion The majority the roadway and utility work is complete on the municipal streets and the remaining work not directly requiring lanes taken on the I-91, I-291, and the associated lanes is complete. Completed work includes all structural steel repairs, painting of structural steel, bearing replacements, installation of municipal street lighting, final paving and traffic markings at the municipal street level, Restoration of all disturbed areas.

11 Definition of Field Completion All physical contract Work is complete including punchlist. The Contractor has fully demobilized from field operations.

12 Next Steps (3 month look-ahead) Removal of temporary signs and RTTM system Continue painting of structural steel Continue structural steel repairs Clean drainage systems/prepare for final drainage work Assess pier repairs needed in the North and South garages Begin intersection restoration work

13 Project Photos Blast Prime coat

14 Project Photos Intermediate coat Prime coat

15 Project Photos Finish coat Finish coat

16 Project Photos Pier repairs

17 Adjacent MassDOT work Highway and bridge work south of the viaduct is underway. This project runs from the Connecticut state line to the Viaduct. This work includes the rehabilitation of the I-91 bridge deck over Main Street (South End) and the full bridge deck replacements of I-91 over Broad St. and Union St. Emerson Street bridge work is complete. Phase 1 bridge work for the Union and Broad Street bridges is 90% complete. All bridge work will be complete in April 2018 Work also includes pavement preservation and retaining wall repairs Traffic flow is reduced to two lanes at these locations All paving and remaining items should be complete in June 2018

18 Project Photos I-91 over Union Street I-91 over Broad Street

19 Other adjacent work MGM mitigation work at multiple locations in the area. Work includes signals, pavement markings, sidewalks. Meetings with MassDOT, MGM, prime contractors from all three projects, and the City of Springfield are held on a regular basis.

20 Speed Limits Speed reduced from 50 to 45 MPH approaching the work zone, with 40 MPH limit in the zone Double fines in the work zone State Police enforcement for driver and construction team safety

21 MassRIDES Programs

22 Public Involvement Additional public briefings, as needed Regularly updated project website: Project fact sheets & community briefings as needed Frequent notices and e-blasts on traffic changes during construction and responses to inquiries Project updates on social media English and translated materials and interpreters available upon request

23 THANK YOU! Contact Us Sign up on the project website for information and updates: Send questions or concerns to: Questions?

I-91 Viaduct Public Information Briefing

I-91 Viaduct Public Information Briefing I-91 Viaduct Public Information Briefing Project File No. 607731 MassDOT Contract No. 85020 Briefing no. 9 September 13, 2017 Agenda Welcome and Presenter Introductions Update on Construction and Demolition

More information

Welcome! Route 1 Viaduct Rehabilitation Project Chelsea Project File No

Welcome! Route 1 Viaduct Rehabilitation Project Chelsea Project File No Welcome! Route 1 Viaduct Rehabilitation Project Chelsea Project File No. 605287 25% Design Public Hearing Chelsea City Hall January 24, 2018 6:30 p.m. Introduction Welcome & Introductions by MassDOT PM

More information

Northeast Bridge Preservation Partnership Meeting

Northeast Bridge Preservation Partnership Meeting Northeast Bridge Preservation Partnership Meeting Superstructure Preservation Strategies Aetna Viaduct Superstructure Repairs Route I-84 City of Hartford, CT State Project No. 63-648 David A. Cutler, P.E.

More information

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 1 Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project. 2 During this public meeting, we will explain the 75 th Street Corridor Improvement

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2018.05 EXIT 103 SOUTHBOUND UNDERPASS BRIDGE REHABILITATION MILE 103.0 The bid opening date is Thursday March 15, 2018 at 11:00 a.m. The following changes

More information

PUBLIC INFORMATION MEETING June 24, 2015

PUBLIC INFORMATION MEETING June 24, 2015 Gallows Road (RTE. 650) over Arlington Boulevard (RTE. 50) Fairfax County Bridge Rehabilitation, Preventive Maintenance and Pier Repairs Phase 1 - Project No. 0650-029-235; UPC 106956, Pier Repair Phase

More information

PCL Definitions for the Local Program J01 3R Policy J04 3P Policy J06 Local Bridges and Township Bridge Program Bridge Work Activities

PCL Definitions for the Local Program J01 3R Policy J04 3P Policy J06 Local Bridges and Township Bridge Program Bridge Work Activities PCL Definitions for the Local Program Projects that are administered by the Central Bureau of Local Roads. Engineering, utilities and land acquisition are coded with the PCL for the type of construction

More information

CUY-480-Valley View Bridge. Matchmaker April 20, 2017 Bureau of Workers Compensation 4800 E. 131 st Street

CUY-480-Valley View Bridge. Matchmaker April 20, 2017 Bureau of Workers Compensation 4800 E. 131 st Street CUY-480-Valley View Bridge Matchmaker April 20, 2017 Bureau of Workers Compensation 4800 E. 131 st Street Agenda Welcome Project Overview Prequalification & Work types Procurement Overview Matchmaker 2

More information

Maine Turnpike Authority FINAL 4-year Capital Investment Plan ( )

Maine Turnpike Authority FINAL 4-year Capital Investment Plan ( ) Total preliminary Value for Project shown in initial year is for project duration. Projects have been listed in each year there are major Preliminary 4.8 Beech Ridge Road Underpass Repairs York $410,000

More information

Bids JANUARY 25, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $3,600,000)

Bids JANUARY 25, 2017 AT 2:00 P.M. (EASTERN TIME) (Estimated Cost: $3,600,000) General Info Number: PROJECT NO. 43-7-05 Description: BRIDGE DECK REPAIR AND REHABILITATION, BOSTON MILLS ROAD OVER OHIO TURNPIKE M.P. 78.0, OLDE EIGHT ROAD OVER OHIO TURNPIKE M.P. 79.5, NICHOLS ROAD OVER

More information

General Info. Number: PROJECT NO

General Info. Number: PROJECT NO General Info Number: PROJECT NO. 43-16-04 Description: BRIDGE DECK REPLACEMENT AND REHABILITATION, RAKER-BARDEN ROAD (CR. 7-2) OVER OHIO TURNPIKE M.P. 41.9, DELTA-SANTEE ROAD (CR. 7) OVER OHIO TURNPIKE

More information

JANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25

JANUARY 4, 2017 AT 2:00 P.M. (EASTERN. (Estimated Cost: $4,600,000) Bids J D WILLIAMSON CONSTRUCTION CO INC $3,799,476.25 General Info Number: PROJECT NO. 43-17-03 Description: BRIDGE DECK REPAIR AND REHABILITATION, ARLINGTON ROAD OVER OHIO TURNPIKE M.P. 122.3, JOPPA ROAD OVER OHIO TURNPIKE M.P. 128.5, DEAN ROAD OVER OHIO

More information

Bridge Asset Management City of Battle Creek Planning and Projects

Bridge Asset Management City of Battle Creek Planning and Projects Bridge Asset Management City of Battle Creek Planning and Projects Michigan Bridge Conference, March 20, 2013 Gregory B. Rickmar P.E., Public Works Department, City of Battle Creek Alan Halbeisen, P.E.

More information

Maryland Transportation Authority (MDTA)

Maryland Transportation Authority (MDTA) Maryland Transportation Authority (MDTA) I-95 Major Deck and Superstructure Rehabilitation South of the Fort McHenry Tunnel Northeast Bridge Preservation Partnership Conference September 20, 2016 David

More information

STRUCTURE AND BRIDGE DIVISION

STRUCTURE AND BRIDGE DIVISION Sheet 1 of 8 VIRGINIA DEPARTMENT OF TRANSPORTATION STRUCTURE AND BRIDGE DIVISION INSTRUCTIONAL AND INFORMATIONAL MEMORANDUM GENERAL SUBJECT: State of Good Repair Bridge Project Selection and Eligible Work

More information

Department of Street Services

Department of Street Services Department of Street Services FY 07-08 Proposed Budget Briefing to the City Council September 5, 2007 Purpose An overview of the Department of Street Services Scope of operation and maintenance activities

More information

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016

Rehabilitation of West Main Street Culvert and Shirley Street Bridge. Town of Ayer. November 22, 2016 Rehabilitation of West Main Street Culvert and Shirley Street Bridge Town of Ayer November 22, 2016 Agenda Outline Introductions Project Goals and Objectives Existing Conditions Review Design Considerations

More information

December 19, 2012 ADDENDUM NO. 11. To Prospective Bidders and Others on:

December 19, 2012 ADDENDUM NO. 11. To Prospective Bidders and Others on: 601096-12 December 19, 2012 ADDENDUM NO. 11 To Prospective Bidders and Others on: Technical/Price Proposals Postponed To: Thursday, January 17, 2013 @ 2:00 PM Transmitting the following Documents and Clarifications:

More information

Roadway Surfaces and Traffic Control Elements

Roadway Surfaces and Traffic Control Elements Roadway Surfaces and Traffic Control Elements Lines of Business: General Liability, Public Officials Liability www.tridentinsurance.net Risk Control Strategy/Key Issues: To establish and document a program

More information

IMPROVING I 81 IN MARYLAND

IMPROVING I 81 IN MARYLAND IMPROVING I 81 IN MARYLAND April 25, 2017 Stephen A. Bucy, P.E. Improving I 81 in Maryland Overview: Facts SHA s Comprehensive I 81 Strategy Current Phase 1 Widening Project Update Closing Improving I

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page SECTION 14 RESTORATION OF SURFACES... 14.1 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01

More information

Berkshire Region TIP Project Data Form

Berkshire Region TIP Project Data Form BASIC INFORMATION: 1. TIP ID #: 2. MUNICIPALITY: 3. ROUTE# AND/OR NAME: Berkshire Region TIP Project Data Form 4. PROJECT TYPE (CHECK BEST DEFINITION OF PROJECT): Intersection Improvement Road Resurfacing

More information

PRESERVING LOUISIANA S INFRASTRUCTURE: US190 MISSISSIPPI RIVER BRIDGE

PRESERVING LOUISIANA S INFRASTRUCTURE: US190 MISSISSIPPI RIVER BRIDGE PRESERVING LOUISIANA S INFRASTRUCTURE: US190 MISSISSIPPI RIVER BRIDGE Overview 1. Project Objectives 2. Bridge Data 3. Timeline 4. Existing Condition 5. Sequence of Coating and Repair Operations 6. Major

More information

Bridge Preventative Maintenance.Act now before this happens to you! Keith Cooper, P.E. Local Bridge Program Manager

Bridge Preventative Maintenance.Act now before this happens to you! Keith Cooper, P.E. Local Bridge Program Manager Bridge Preventative Maintenance.Act now before this happens to you! Keith Cooper, P.E. Local Bridge Program Manager 1 Local Bridge Program Asset Management for Local Bridges 2008 started approving Rehabilitation

More information

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction Chapter 1 Bridge Design Manual General Design Information Section 1.02 Selection and Geometry Introduction Selection or Rehabilitation Report This section of the design manual provides guidance on the

More information

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc.

SPECIAL PROVISION Detours, Barricades, Warning Signs, Sequence of Work, etc. 2004 Specifications CSJ 0299-04-049, Etc. SPECIAL PROVISION 000---979 Detours, Barricades, Warning Signs, Sequence of Work, etc. 1. Description of Project. A. General. This project provides for the construction

More information

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/01/2017 to 10/07/2017

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 10/01/2017 to 10/07/2017 AECOM Field Office 3550 Water Street, NW Under the Key Bridge North Abutment REHABILITATION OF FRANCIS SCOTT KEY BRIDGE FROM ROSSLYN, ARLINGTON, VIRGINIA TO GEORGETOWN WASHINGTON, DC. DC Contract No.:

More information

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016

Cleveland Opportunity Corridor Project Section 3. Subcontractor Informational Meeting August 12, 2016 Cleveland Opportunity Corridor Project Section 3 Subcontractor Informational Meeting August 12, 2016 Agenda Welcome and Opening Remarks Project Overview Prequalifications & Work Types Procurement Overview

More information

36 JASPER THPMAS ROAD CRAWFORDVILLE, FL.

36 JASPER THPMAS ROAD CRAWFORDVILLE, FL. N ARRAN RD. N US 319 CRAWFORDVILLE HWY SR 61 SHADEVILLE RD. WAKULLA HARVEY MILL ROAD US 319 PREBLE-RISH INC CIVIL SURVEYING SITE PLANNING 36 JASPER THPMAS ROAD CRAWFORDVILLE, FL. 32327 GENERAL NOTES: 1.

More information

Riverside County Transportation Commission RFP Number TP ATTACHMENT 4-1 WORK BREAKDOWN STRUCTURE

Riverside County Transportation Commission RFP Number TP ATTACHMENT 4-1 WORK BREAKDOWN STRUCTURE TP ATTACHMENT 4-1 WORK BREAKDOWN STRUCTURE TP Attachment 4-1 Work Breakdown Structure Page 1 The following Work Breakdown Structure (WBS) must be the basis for organizing all Work under the Contract Documents

More information

Riverside County Transportation Commission RFP Number TP ATTACHMENT 4-1 WORK BREAKDOWN STRUCTURE

Riverside County Transportation Commission RFP Number TP ATTACHMENT 4-1 WORK BREAKDOWN STRUCTURE TP ATTACHMENT 4-1 WORK BREAKDOWN STRUCTURE TP Attachment 4-1 Work Breakdown Structure Page 1 The following Work Breakdown Structure (WBS) must be the basis for organizing all Work under the Contract Documents

More information

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION

BOSTON REGION METROPOLITAN PLANNING ORGANIZATION PLANNING ORGANIZATIO BOSTON REGION MPO NMETROPOLITAN BOSTON REGION METROPOLITAN PLANNING ORGANIZATION Stephanie Pollack, MassDOT Secretary and CEO and MPO Chair Karl H. Quackenbush, Executive Director,

More information

BRIDGE DISTRICT. City of West Sacramento. Phase 1 Infrastructure Improvement Project. Monthly Status Report

BRIDGE DISTRICT. City of West Sacramento. Phase 1 Infrastructure Improvement Project. Monthly Status Report BRIDGE DISTRICT Phase 1 Infrastructure Improvement Project (for work completed thru November 2011) Cover Photo: Joint Utility Trench installation along Fifth Street just north of Bridge Street. Page 1

More information

Second Avenue Subway

Second Avenue Subway Second Avenue Subway Community Board 8 Second Avenue Subway Task Force Update January 22, 2015 Tom Peyton Second Avenue Subway Project Director 0 Scope: Q train service Tunnels from 92nd St to 63rd St

More information

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012 PROJECT UPDATE Rendering View from the City of Chesapeake Elizabeth River Boat Landing and Park looking across the Elizabeth River at Portsmouth CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA The new 5,375

More information

Stevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets

Stevens & Associates, Inc. Tunnel Construction Projects. Fact Sheets Stevens & Associates, Inc. Tunnel Construction Projects Fact Sheets Stevens & Associates, Inc. 4 Knights Court Newbury, MA 01951 978-764-9886 glen@stevensai.com Massachusetts Water Resources Authority

More information

UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management)

UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management) UPCOMING DESIGN & CONSTRUCTION PROJECTS 3 rd Quarter 2018 Rev 2 (Project & Construction Management) DESIGN PHASE PROJECTS BCT - Building Program Development and Design for Maintenance and Administration

More information

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014

Agenda. PRE-CONSTRUCTION PUBLIC MEETING September 18, 2014 Agenda Welcome FTA Full Funding Grant Agreement Update GLX Phase 1 Construction Update GLX Phases 2/2A, 3 & 4 Construction Contracts Upcoming Early Construction Work Construction Mitigation Night & Weekend

More information

STATUS REPORT Congestion-Relief Program. Steve Gillen Illinois Asphalt Pavement Association March 12, 2007

STATUS REPORT Congestion-Relief Program. Steve Gillen Illinois Asphalt Pavement Association March 12, 2007 STATUS REPORT Congestion-Relief Program Steve Gillen Illinois Asphalt Pavement Association March 12, 2007 Beginning Year 3 of Congestion-Relief Program Governor s $5.3 billion Congestion-Relief Program

More information

Whittier Bridge/I-95 Improvement Project. Public Information Meeting

Whittier Bridge/I-95 Improvement Project. Public Information Meeting Whittier Bridge/I-95 Improvement Project Public Information Meeting October 23, 2013 Agenda: WHITTIER BRIDGE / I-95 IMPROVEMENT PROJECT Introduce the Design-Build Team Current Project Schedule Design Project

More information

DESIGN PUBLIC HEARING APRIL 3, 2017 THE LEE MEMORIAL (TOWN) HALL LEE, MASSACHUSETTS :00 PM FOR THE PROPOSED

DESIGN PUBLIC HEARING APRIL 3, 2017 THE LEE MEMORIAL (TOWN) HALL LEE, MASSACHUSETTS :00 PM FOR THE PROPOSED DESIGN PUBLIC HEARING APRIL 3, 2017 AT THE LEE MEMORIAL (TOWN) HALL LEE, MASSACHUSETTS 01238 7:00 PM FOR THE PROPOSED SUPERSTRUCTURE REPLACEMENT PROJECT CHAPEL STREET OVER GREENWATER BROOK Project No.

More information

MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION

MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION MINNESOTA HISTORIC PROPERTY RECORD PART I. PROPERTY IDENTIFICATION AND GENERAL INFORMATION Common Name: Camp Ripley Bridge Bridge Number: 4969 Identification Number: Location: Feature Carried: TH 115 Feature

More information

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND RAIL-HWY PROJECT DEVELOPMENT GUIDE AND New procedures for Railroad Right-of-Entry Agreements & Bid Documents (SP Item 007) Bridge Division Webinar - July 18, 2013 GUIDE TO RAILROAD PROJECT DEVELOPMENT

More information

BARRY S CORNER. Draft Construction Management Plan

BARRY S CORNER. Draft Construction Management Plan 1. Introduction Project description BARRY S CORNER Draft Construction Management Plan 11-21-2013 Prepared for: Boston Transportation Department Project Proponent: Samuels & Associates Construction Manager

More information

SECTION 9000 MAINTENANCE SERVICES

SECTION 9000 MAINTENANCE SERVICES SECTION 9000 MAINTENANCE SERVICES 9000 MAINTENANCE SERVICES... 1 9001 LEGISLATIVE AUTHORITY... 1 9002 GENERAL MAINTENANCE... 1 9003 PEDESTRIAN OVERPASSES... 1 9003.1 GENERAL MAINTENANCE... 1 9003.2 WINTER

More information

NJDOT Bridge Preservation and Asset Management Strategies. Gerald P. Oliveto, P.E. Roger Estivalletti

NJDOT Bridge Preservation and Asset Management Strategies. Gerald P. Oliveto, P.E. Roger Estivalletti NJDOT Bridge Preservation and Asset Management Strategies Gerald P. Oliveto, P.E. Roger Estivalletti Bridge preservation is defined as actions or strategies that prevent, delay or reduce deterioration

More information

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 06/04/2017 to 06/10/2017

CONSTRUCTION MANAGER S WEEKLY PROGRESS REPORT From 06/04/2017 to 06/10/2017 AECOM Field Office Water Street, NW Under Key Bridge along Water Street, NW REHABILITATION OF FRANCIS SCOTT KEY BRIDGE FROM ROSSLYN, ARLINGTON, VIRGINIA TO GEORGETOWN WASHINGTON, DC. DC Contract No.: DCKA-2014-C-0074

More information

CTA Capital Construction Update August 8, 2007

CTA Capital Construction Update August 8, 2007 Block 37 Signals Project Brown Line Howard CTA Capital Construction Update August 8, 2007 1 Capital Construction Update Agenda Howard Station Reconstruction Brown Line Capacity Expansion Project Block

More information

Elizabeth River Crossings OpCo, LLC Elizabeth River Tunnels Project Monthly Report Owners and Holders Pursuant to Continuing Disclosure Agreement

Elizabeth River Crossings OpCo, LLC Elizabeth River Tunnels Project Monthly Report Owners and Holders Pursuant to Continuing Disclosure Agreement Elizabeth River Crossings OpCo, LLC Elizabeth River Tunnels Project Monthly Report Owners and Holders Pursuant to Continuing Disclosure Agreement November 2015 From: Greg Woodsmall, Chief Executive Officer,

More information

ASSOCIATED PENNSYLVANIA CONSTRUCTORS SUPPLEMENTAL ECMS ADVANCED INFORMATION LETTING MAY 24, 2018 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL)

ASSOCIATED PENNSYLVANIA CONSTRUCTORS SUPPLEMENTAL ECMS ADVANCED INFORMATION LETTING MAY 24, 2018 (ALL WORK TO BE COMPLETED TO APPEAR IN THE PROPOSAL) ASSOCIATED PENNSYLVANIA CONSTRUCTORS Updated May 4, 2018 FULTON COUNTY SR 0000(FMC) #109343 PROPOSAL:$21.36 PLANS:$9.02 12X18:$11.07 24X36:$159.90 X-SEC:$7.48 12X18:$9.18 24X36:$132.60 This project involves

More information

Pattullo Bridge Replacement Project. Cost Report

Pattullo Bridge Replacement Project. Cost Report Pattullo Bridge Replacement Project Cost Report January 2018 Cost Report Page i TABLE OF CONTENTS 1 PURPOSE... 1 2 BASIS FOR THE ESTIMATE... 2 2.1 Scope of the Works... 2 2.2 Scope of Capital Costs...

More information

Traffic Management Guide to Concrete Overlay Solutions. Dale S. Harrington P.E. Representing CP Tech Center

Traffic Management Guide to Concrete Overlay Solutions. Dale S. Harrington P.E. Representing CP Tech Center Traffic Management Guide to Concrete Overlay Solutions December 5, 2014 ACPA Annual Meeting Dale S. Harrington P.E. Representing CP Tech Center Traffic Management- Concrete Overlays Traffic Management

More information

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS Section Page 14-1 GENERAL... 14.1 14-2 PRIVATE ROADS... 14.1 14-3 STREETS AND PARKING LOTS... 14.1 14-3.01 Aggregate Base... 14.1 14-3.02 Asphalt

More information

CHAPTER 3 SCOPE SUMMARY

CHAPTER 3 SCOPE SUMMARY CHAPTER 3 SCOPE SUMMARY GENERAL The SDDOT is an active member of AASHTO to share common national design standards for the state highway system. The AASHTO Task Force on Geometric Design has completed the

More information

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company

ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING. Kansas City Terminal Railway Company James P. Hyland Page 1 ARGENTINE CONNECTION BRIDGE TRIPLE TRACK CROSSING Kansas City Terminal Railway Company James P. Hyland, P.E. Senior Bridge Engineer TranSystems Corporation James P. Hyland Page 2

More information

APPROACHES AND BRIDGE OVER TYE RIVER (RTE. 29 NBL) RFP QUESTIONS AND ANSWERS-REVISION 2

APPROACHES AND BRIDGE OVER TYE RIVER (RTE. 29 NBL) RFP QUESTIONS AND ANSWERS-REVISION 2 Project: APPROACHES AND BRIDGE OVER TYE RIVER (RTE. 29 NBL) PROJECT: 0029-005-130, C501, B645 RFP QUESTIONS AND ANSWERS-REVISION 2 Date: 12/04/09 Approaches and Bridge over Tye River (Rte. 29 NBL) Subject:

More information

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017

VT 14 East Montpelier Bridge Project Informational Meeting. February 22, 2017 VT 14 East Montpelier Bridge Project Informational Meeting February 22, 2017 Welcome & Introductions VTrans Mark Sargent, Project Manager Wayne Symonds, Structures Program Manager Chris Barker, Resident

More information

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201

Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING Oak Avenue. Evanston, IL 60201 Evanston Avidor Construction Site Management Plan AVIDOR EVANSTON APARTMENT BUILDING 1727 Oak Avenue Evanston, IL 60201 General Contractor Owner Architect Construction Management Plan Phase 1 3 October

More information

Bridge Preservation: Thin epoxy overlays

Bridge Preservation: Thin epoxy overlays Bridge Preservation: Thin epoxy overlays and anti-skid surfacing Structurally Deficient Bridges Source: US DOT, 2008 Estimate to eliminate all bridge deficiencies: $9.4 billion per year for 20 years Source:

More information

I-64 Peninsula Shoulder Usage Evaluation. Eric Stringfield VDOT Hampton Roads Transportation Planning April 3, 2013

I-64 Peninsula Shoulder Usage Evaluation. Eric Stringfield VDOT Hampton Roads Transportation Planning April 3, 2013 I-64 Peninsula Shoulder Usage Evaluation Eric Stringfield VDOT Hampton Roads Transportation Planning April 3, 2013 Briefing Purpose Evaluation Area / Existing Conditions Code and Policy Engineering Facts

More information

Reconstruction Project Update

Reconstruction Project Update I-65/I-70 North Split Interchange Reconstruction Project Update September 18, 2017 Agenda Welcome/introductions Project overview Scope and limits Need Environmental Assessment Maintenance of traffic Financial

More information

Implementing Asset Management: WSDOT s Experience

Implementing Asset Management: WSDOT s Experience Implementing Asset Management: WSDOT s Experience 6 th National Conference on Transportation Asset Management Aaron Butters, P.E. Systems Analysis and Program Development Manager November 2, 2005 1 Highway

More information

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director

Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH John R. Kasich, Governor Jerry Wray, Director Ohio Department of Transportation Central Office 1980 West Broad Street Columbus, OH 43223 John R. Kasich, Governor Jerry Wray, Director 11/21/2014 Project 140560 Addendum No. 2 PID No. 82972 HAM IR 275

More information

CITY OF SOUTH LAKE TAHOE APPLICATION FOR ENCROACHMENT, EXCAVATION and GRADING WITHIN THE CITY RIGHT OF WAY

CITY OF SOUTH LAKE TAHOE APPLICATION FOR ENCROACHMENT, EXCAVATION and GRADING WITHIN THE CITY RIGHT OF WAY CITY OF SOUTH LAKE TAHOE APPLICATION FOR ENCROACHMENT, EXCAVATION and GRADING WITHIN THE CITY RIGHT OF WAY The Right-of-Way Encroachment, Excavation & Grading Permit issued by the Public Works Department

More information

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA

SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA ASHE NATIONAL PROJECT OF THE YEAR SR 0136-G10 ABC BRIDGE REPLACEMENT in Eighty Four, PA For the PENNSYLVANIA DEPARTMENT OF TRANSPORTATION Engineering District 12-0 Submitted By: January 29, 2018 AMERICAN

More information

PortMiami Rail Intermodal and Bascule Bridge Rehabilitation Project TIGER II Grant

PortMiami Rail Intermodal and Bascule Bridge Rehabilitation Project TIGER II Grant PortMiami Rail Intermodal and Bascule Bridge Rehabilitation Project TIGER II Grant Quick Facts PortMiami is located in Miami-Dade County, one of the most diverse, multilingual populations in the U.S. making

More information

PLAN PREPARATION GUIDE CHAPTER 3 QUANTITY COMPUTATIONS AND INFORMATION

PLAN PREPARATION GUIDE CHAPTER 3 QUANTITY COMPUTATIONS AND INFORMATION PLAN PREPARATION GUIDE CHAPTER 3 QUANTITY COMPUTATIONS AND INFORMATION SECTION DESCRIPTION PAGE 1 General Quantities 3-1 2 Maintenance of Roadway and Drives 3-1 3 Liquid Asphalt Binder in Paving Mixture

More information

Date: May 4, Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis

Date: May 4, Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis MEMORANDUM To: CAJA Environmental Services, LLC Date: From: Subject: Clare M. Look-Jaeger, P.E. Kevin C. Jaeger Linscott, Law & Greenspan, Engineers Weingart Projects Construction Traffic Analysis LLG

More information

Douglas Woods Wind Farm

Douglas Woods Wind Farm Traffic Evaluation and Access Management Report Douglas Woods Wind Farm Douglas,Massachusets Prepared for American Pro Wind 195 Libbey Parkway - Unit Two Weymouth, MA 02189 Prepared by Transportation,

More information

Construction Cost Estimation Preparation Manual for Preliminary Design (English Units)

Construction Cost Estimation Preparation Manual for Preliminary Design (English Units) 10/16/2014 Construction Cost Estimation Preparation Manual for Preliminary Design (English Units) July 2002 Prepared by Construction Cost Estimating Unit Program Support Services 10/16/2014 Table of Contents

More information

TENDER BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 1

TENDER BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 1 TENDER 2334-2019 BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 1 This addendum shall be read in conjunction with and considered as an integral part of the Tender Contract 2334-2019. Revisions

More information

SECTION TRAFFIC REGULATIONS

SECTION TRAFFIC REGULATIONS PART 1 GENERAL 1.1 DESCRIPTION A. Traffic Control permits, notifications, mobilization, temporary signs, barriers, lights, flagging personnel, striping, markings, and demobilization and removal. 1.2 RELATED

More information

Lesner Bridge Replacement

Lesner Bridge Replacement Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on

More information

Lesner Bridge Replacement

Lesner Bridge Replacement Lesner Bridge Replacement Rendering of the Completed Lesner Bridge Structure Construction Camera A Construction Camera has been installed to view images of the bridge construction. Images are updated on

More information

Feasibility Assessment Study

Feasibility Assessment Study August 19, 2010 Feasibility Assessment Study Historic Sites Council Meeting Today s Agenda Historic Overview Project Overview Barrier Issues Concrete Parapet Recommendations Steel Parapet Recommendations

More information

RATIONALE AND REASONING The following information is provided in response to the issues raised by the Board of Regents at the September 2012 meeting:

RATIONALE AND REASONING The following information is provided in response to the issues raised by the Board of Regents at the September 2012 meeting: a contract within the Total Project Cost budget of $123.2 million, and to proceed with project construction not to exceed a Total Project Cost of $62.6 million. This motion is effective September 27, 2012.

More information

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT

MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT MAINE TURNPIKE AUTHORITY ADDENDUM NO. 1 CONTRACT 2018.04 CLEANING AND PAINTING STEEL STRUCTURES - CIDER HILL ROAD UNDERPASS BRIDGE - MILE 6.2, CAPTAIN THOMAS ROAD UNDERPASS BRIDGE - MILE 14.8, ROUTE 126

More information

Construction Coordination & Management Planning MassDOT-Highway/MBTA. 495/MetroWest Partnership Briefing July 11, 2018

Construction Coordination & Management Planning MassDOT-Highway/MBTA. 495/MetroWest Partnership Briefing July 11, 2018 Construction Coordination & Management Planning MassDOT-Highway/MBTA 495/MetroWest Partnership Briefing July 11, 2018 Overview The Construction Coordination and Management Planning exercise was a 100-day

More information

Cumberland Viaduct Rehabilitation Project Contract No. AL R Presenter Bob Bofinger MDSHA Office of Structures

Cumberland Viaduct Rehabilitation Project Contract No. AL R Presenter Bob Bofinger MDSHA Office of Structures Cumberland Viaduct Rehabilitation Project Contract No. AL4095180R Presenter Bob Bofinger MDSHA Office of Structures Project Justification & Improvements Condition State The deck, superstructure and substructure

More information

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION CECIL COUNTY 2018 TRANSPORTATION IMPROVEMENT PROGRAM AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION DESCRIPTION: On-going program to provide major upgrades to state owned bridges that are structurally

More information

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel Albany Park Stormwater Diversion Tunnel Frequently Asked Questions The Basics Who, What, When, Where, Why, How Why is the project being performed? The project is being constructed to reduce flooding in

More information

Albany Park Stormwater Diversion Tunnel

Albany Park Stormwater Diversion Tunnel Albany Park Stormwater Diversion Tunnel Why is the project being performed? Frequently Asked Questions The Basics Who, What, When, Where, Why, How The project is being constructed to reduce flooding in

More information

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix.

APPENDIX C INLETS. The application and types of storm drainage inlets are presented in detail in this Appendix. Storm Drainage 13-C-1 APPENDIX C INLETS 1.0 Introduction The application and types of storm drainage inlets are presented in detail in this Appendix. 2.0 Inlet Locations Inlets are required at locations

More information

October 16, Virginia Department of Transportation 1401 E. Broad Street Richmond, Virginia 23219

October 16, Virginia Department of Transportation 1401 E. Broad Street Richmond, Virginia 23219 Request for Proposal Letter of Submittal Design-Build I-264 Pavement Rehabilitation From: Railroad Bridge West of Witchduck Road (East Abutment) To: Parks Avenue Virginia Beach, Virginia State Project

More information

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT

PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT SCOPING PHASE ~ SCOPE OF SERVICES MAIN STREET BRIDGE OVER WINOOSKI RIVER CITIES OF BURLINGTON & WINOOSKI VERMONT PROJECT DESCRIPTION McFarland-Johnson, Inc. (MJ) has prepared this proposal to perform

More information

Branch Transportation Operations

Branch Transportation Operations Introduction Transportation Operations enables the smooth operation of the existing transportation network. Branch activities include a wide range of services that affect all citizens, including operating

More information

ATHABASCA RIVER BRIDGE REHABILITATION PROJECT

ATHABASCA RIVER BRIDGE REHABILITATION PROJECT ATHABASCA RIVER BRIDGE REHABILITATION PROJECT PROJECT INFORMATION Project Name Athabasca River Bridge Rehabilitation Project Location Highway 40 (over the Athabasca River), Entrance, Alberta Year Completed

More information

Highway Construction Program

Highway Construction Program Highway Construction Program Monthly Delivery Progress Report Watch List February 2017 This report focuses on Capital Highway Program projects, which have, or may have significant changes in scope, schedule,

More information

Coordinating Minnesota s Transportation Assets and Climate Change and Extreme Weather Vulnerability

Coordinating Minnesota s Transportation Assets and Climate Change and Extreme Weather Vulnerability Coordinating Minnesota s Transportation Assets and Climate Change and Extreme Weather Vulnerability Duane R. Hill, PE District Engineer, District One Minnesota Department of Transportation What is a Transportation

More information

Scott Avenue Bridge Rehabilitation Scott Avenue over Des Moines River

Scott Avenue Bridge Rehabilitation Scott Avenue over Des Moines River Scott Avenue Bridge Rehabilitation Scott Avenue over Des Moines River Previous UDR Meetings: - January 24, 2017: General overview of TIGER Grant Projects - May 16, 2017: Preliminary review of all 4 bridge

More information

City of Berkley, Michigan Harvard Road Reconstruction & Water Main Replacement Project FREQUENTLY ASKED QUESTIONS (FAQ)

City of Berkley, Michigan Harvard Road Reconstruction & Water Main Replacement Project FREQUENTLY ASKED QUESTIONS (FAQ) FREQUENTLY ASKED S (FAQ) The purpose of this document is to provide detailed information about the Harvard Road Reconstruction & Water Main Replacement Project. This project will directly affect residents

More information

Clinton Street Bridge over the Maumee River. ODOT Project DEF December 2, 2014 Stakeholder s Meeting

Clinton Street Bridge over the Maumee River. ODOT Project DEF December 2, 2014 Stakeholder s Meeting Clinton Street Bridge over the Maumee River ODOT Project DEF-15-14.77 December 2, 2014 Stakeholder s Meeting Purpose of Stakeholder Meeting Discuss the project and why it s happening Describe the process

More information

PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56

PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56 PennDOT Pub. 170 Highway Occupancy Permit (HOP) Manual Page 56 Additional Fees Additional fees may be charged by PennDOT consistent with Sections 411 and 420 of the State Highway Law and Regulations 441.4(d)

More information

TENDER BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 2

TENDER BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 2 TENDER 2334-2019 BASTION STREET BRIDGE RENEWAL AND SEISMIC RETROFIT ADDENDUM 2 This addendum shall be read in conjunction with and considered as an integral part of the Tender Contract 2334-2019. Revisions

More information

I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017

I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017 I-64 Capacity Improvements Segment I Financial Plan Annual Update December 1, 2017 State Project # 0064-965-264, P101, R201, C501, B616, B617, B618, B619, B620, B621, D601, D602 Federal # NHS-064-3(479),

More information

Ohio Department of Transportation - Prebid Questions

Ohio Department of Transportation - Prebid Questions Project No. 120625 Sale Date - 12/14/2012 ATB-76747 - IR-90-7.56, PART 1;ATB-90-13.60, PART 2 12/11/2012 8:03:55 AM Per Addendum 5 Item 184 was reduced drastically. With over 35,000 LF of new guardrail

More information

Review of Plans and Specs from a Constructability Perspective

Review of Plans and Specs from a Constructability Perspective Review of Plans and Specs from a Constructability Perspective The Executive Regional Manager and the Project Manager, with approval of the Director of Project Management, may request the Constructability

More information

COUNTY OF SUTTER ENCROACHMENT PERMIT

COUNTY OF SUTTER ENCROACHMENT PERMIT COUNTY OF SUTTER ENCROACHMENT PERMIT PERMIT No. Development Services Dept. Engineering Division 1130 Civic Center Blvd Yuba City, CA 95993 (530) 822-7400 Hours: 8 AM - 5 PM Upon completion, submit application

More information

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS

SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS SECTION 13 - EXISTING FACILITIES TABLE OF CONTENTS Section Page 13-1 GENERAL... 13.1 13-1.01 Preservation of Property... 13.1 13-1.02 Overloading, Pavement Protection & Repair... 13.1 13-2 REMOVING EXISTING

More information

Jobs & Transportation Ramping it Up Roadway and Traffic Dan Groh, P.E.

Jobs & Transportation Ramping it Up Roadway and Traffic Dan Groh, P.E. Jobs & Transportation Ramping it Up Roadway and Traffic Dan Groh, P.E. Ohio DOT Work Zone Process Review Ohio DOT Work Zone Process Review This review was conducted by the Ohio Department of Transportation

More information