Improving energy efficiency in an ammonia plant

Similar documents
Post Combustion CO 2 Capture Scale Up Study

Steam balance optimisation strategies

Grand Composite Curve Module 04 Lecture 12

Equipment Design. Detailed Plant Conceptual Design. Version 9.0

Pinch Analysis for Power Plant: A Novel Approach for Increase in Efficiency

Development of Integrated Flexi-Burn Dual Oxidant CFB Power Plant

Conceptual Design of Nuclear CCHP Using Absorption Cycle

Chapters 5, 6, and 7. Use T 0 = 20 C and p 0 = 100 kpa and constant specific heats unless otherwise noted. Note also that 1 bar = 100 kpa.

MIT Carbon Sequestration Forum VII Pathways to Lower Capture Costs

Understand boiler performance characteristics. Use these suggestions when buying, designing or optimizing steam generators

ENERGY RECOVERY IMPROVEMENT USING ORGANIC RANKINE CYCLE AT COVANTA S HAVERHILL FACILITY

Heat Recovery. Integrated CHP Systems Corp.

TRONDHEIM CCS CONFERENCE

4.0 HYDROGEN GENERATION UNIT (PREP) 4.1 INTRODUCTION

Downsizing a Claus Sulfur Recovery Unit

COMBINED CYCLE OPPORTUNITIES FOR SMALL GAS TURBINES

Low temperature cogeneration using waste heat from research reactor as a source for heat pump

Reforming Natural Gas for CO 2 pre-combustion capture in Combined Cycle power plant

OPTIMIZATION OF PARAMETERS FOR HEAT RECOVERY STEAM GENERATOR (HRSG) IN COMBINED CYCLE PLANTS

Benchmarking of power cycles with CO 2 capture The impact of the chosen framework

FLEXI BURN CFB WP4: Boiler design and performance

Cogeneration. Thermal Chillers. and. .. ASHRAE National Capital Chapter. Arlington, VA 10/10/2012

Your partner for the right solution

OUTCOME 2 TUTORIAL 2 STEADY FLOW PLANT

Combined cycle with detailed calculation of Cp in the HRSG

Simple Dew Point Control HYSYS v8.6

Efficient Technologies for Down Stream Gasification Process and Integration with IGCC Power Production

Item Hydrogen Gas Plant

2. TECHNICAL DESCRIPTION OF THE PROJECT

Thermodynamic analysis on post combustion CO 2 capture of natural gas fired power plant

CO 2 Capture and Storage: Options and Challenges for the Cement Industry

Multi-Variable Optimisation Of Wet Vapour Organic Rankine Cycles With Twin-Screw Expanders

Optimal Design Technologies for Integration of Combined Cycle Gas Turbine Power Plant with CO 2 Capture

Hydrogen is a particularly

NEW RECYCLE PROCESS SCHEME FOR HIGH ETHANE RECOVERY NEW PROCESS SCHEME FOR HIGH NGL RECOVERY INTRODUCTION. Abstract PROCESS FUNDAMENTALS

EXERGY ANALYSIS OF GAS-TURBINE COMBINED CYCLE WITH CO 2 CAPTURE USING PRE-COMBUSTION DECARBONIZATION OF NATURAL GAS

Modelling of CO 2 capture using Aspen Plus for EDF power plant, Krakow, Poland

Feasibility of Utilizing Boiler Blowdown Waste Heat for Operating an Absorption Refrigeration Chiller

TransPacific Energy Advantage: Case Studies

20/06/2011 Seminar on Geothermal Exploitation Santiago de Chile

Quiz Questions. For Process Integration. Fill in the blanks type Questions

Lurgi s MPG Gasification plus Rectisol Gas Purification Advanced Process Combination for Reliable Syngas Production

Chapter 2.7: Cogeneration

A New Optimisation Based Retrofit Approach for Revamping an Egyptian Crude Oil Distillation Unit

EFFECT OF AMBIENT TEMPERATURE, GAS TURBINE INLET TEMPERATURE AND COMPRESSOR PRESSURE RATIO ON PERFORMANCE OF COMBINED CYCLE POWER PLANT

Modelling and Optimisation of the Otahuhu B Combined Cycle Gas Turbine Power Station

ME ENGINEERING THERMODYNAMICS UNIT III QUESTION BANK SVCET

Packaged AHR (Advanced Heat Recovery) Systems for Engines, Gas Turbines, & Industrial Waste Heat. Tom Pierson

Guidance Document for Cogeneration Emissions. (Cogeneration Guidelines)

Eng Thermodynamics I: Sample Final Exam Questions 1

NLP optimization of a methanol plant by using H 2 co-product in fuel cells

Technical And Economical Aspects Of Thermal Efficiency Of Grate-Fired Waste-To- Energy Plants

SOME ENERGY-EFFICIENT TECHNOLOGIES IN JAPAN

BLUE OPTION White space is filled with one or more photos

Exploitation of Low-Grade Heat in Site Utility Systems

Lecture No.3. The Ideal Reheat Rankine Cycle

In The Name OF God Hampa E ner ner Ener y gy Engineering EEngineering & & Design Company Design Compan

The DeltaV Virtual Power Plant. Todd Anstine Director of Operations MYNAH Technologies

VIRIDOR WASTE MANAGEMENT ARDLEY EFW PLANT EP APPLICATION - NON TECHNICAL SUMMARY

5. Steam Turbine Performance

Coupling of power generation with syngas-based chemical synthesis

Impact of novel PCC solvents on existing and new Australian coal-fired power plants 1 st PCC Conference, Abu-Dhabi

natcom burner solutions Advanced burner technology for stringent emissions requirements

Fluid Mechanics, Heat Transfer, Fluid Mechanics Design Project. Production of Ethanol

Preparatory study for Steam Boilers Ecodesign

CASE STUDY WITH COMPARISON AND EVALUATION OF DIFFERENT ALTERNATIVES TO A COMBINED CYCLE POWER PLANT UPRATE

Conception of a Pulverized Coal Fired Power Plant with Carbon Capture around a Supercritical Carbon Dioxide Brayton Cycle

Fluid Mechanics, Heat Transfer, Thermodynamics. Design Project. Production of Ammonia

IDRIST Temporal pinch-point analysis for energy demand reduction in batch production. Thorsten Spillmann

Development status of the EAGLE Gasification Pilot Plant

POST COMBUSTION CO 2 CAPTURE SCALE UP STUDY

Synthesis Gas Processes for Synfuels Production

Chapter 9: Applications of the Laws of Thermodynamics

Hitachi H-25 & H-80 Gas Turbine. Bucharest, Apr.23, 2013

Heat and Power Integration Opportunities in Methane Reforming based Hydrogen Production with PSA separation

An Opportunity for Methanol; the Production Starting from Coal

Second Law of Thermodynamics

SCHNEIDER-KESSEL BERLIN

Kalex Kalina Cycle Power Systems For Use as a Bottoming Cycle for Combined Cycle Applications

ADVANCED PROCESS CONTROL QATAR GAS ONE YEAR EXPERIENCE

Nilan VPL Active heat recovery and cooling (air/air)

Gas Turbine Inlet Air Cooling System

EFFECT OF INLET AIR COOLING ON GAS TURBINE PERFORMANCE

Hydrogen Key to any Refinery

16 th NATIONAL CERTIFICATION EXAMINATION FOR ENERGY MANAGERS & ENERGY AUDITORS September, 2015

Canada. Iron and Steel Sector - PI Specifics

MODELLING STEAM SYSTEMS TO EVALUATE ENERGY OPTIMISATION OPPORTUNITIES TO SAVE COAL AND EXPORT ELECTRICITY

MLNG DUA DEBOTTLENECKING PROJECT

PINCH ANALYSIS: For the Efficient Use of Energy, Water & Hydrogen. PULP AND PAPER INDUSTRY Energy Recovery and Effluent Cooling at a TMP Plant

High Bridge Combined Cycle Plant

Geothermal Steam Turbines for Various Purposes

Challenges in Designing Fuel-Fired sco2 Heaters for Closed sco2 Brayton Cycle Power Plants

ES Fluid & Thermal Systems Page 1 of 6 STEAM TURBINE LABORATORY

Low-Grade Waste Heat Recovery for Power Production using an Absorption-Rankine Cycle

Texas Hospital. Central Plant Redesign. Central Utility Plant SECOND PLACE HEALTH CARE FACILITIES, EXISTING 2013 ASHRAE TECHNOLOGY AWARD CASE STUDIES

Babcock Borsig Steinmüller GmbH. Bełchatów - Retrofitting the EU s Largest Power Plant Site

Coal gasification and CO 2 capture

Dynamic Modeling of a Combined-Cycle Plant

Plant construction and waste heat systems for the chemical industry

MODELLING THE LOW-TAR BIG GASIFICATION CONCEPT

Transcription:

Improving energy efficiency in an ammonia plant D. Velázquez, F. Rossi and J. Rodríguez of DVA Global Energy Services and F.Galindo of Fertiberia present the results of an energy study carried out in an ammonia plant in Spain. A comprehensive energy audit of the main equipment (furnaces, syngas, air and ammonia compressors, turbines, cooling towers and refrigeration systems), pinch analysis and modelling resulted in the proposal of 34 projects, some of which have cost savings of more than one million euros per year with payback times of less than one year. Fertiberia s ammonia plant in Spain. The directives 2003/87/EC and 2009/29/EC 1,2 set strict CO 2 emission limits for some chemical industries and can have a significant impact on companies profits. Because of this, as well as the increase in the price of natural gas in recent years, many European ammonia producers have been forced to carry out important energy efficiency improvements, in order to maintain their competitiveness within the international market. During recent years, the average specific consumption of ammonia production has been globally quantified as 36.6 GJ/ tnh 3 (LHV base). Performance indicators of ammonia plants located in Canada and western Europe show the best values 3. Within the most efficient regions, natural gas costs represent more than 80% of total ammonia production costs, reaching 90% in some cases. Current best available technologies for ammonia production from natural gas allow specific consumption levels of about 28 GJ/tNH 3 to be achieved 4. Among the methodologies aimed at finding energy saving opportunities, pinch analysis linked to power and modelling has proved to be a powerful way for determining projects to improve the overall energy efficiency of industrial sites. This procedure has been applied successfully in many industrial facilities, allowing optimal energy recovery in the process and hence reduction of fuel consumption. Plant description Process description The ammonia site for which this energy audit has been carried out was designed to produce 1,130 t/d of ammonia, via catalytic reforming of natural gas, using Kellogg technology with ICI license. The ammonia produced is either exported or consumed by a urea plant located in the same facility. Its utility services are also connected to a nitric acid plant. Figure 1 shows a simplified diagram of the process. Energy structure Steam reforming is an endothermic process, which is carried out at high temperatures. Thermal energy demand is supplied by a furnace located in the first reform- Nitrogen+Syngas 322 March - April 2013 1

Fig 1: Simplified diagram of the ammonia production process air combustion air aux boiler reformer I reformer II conversion CO CO 2 boiler feed water superheated HRSG HRSG desulphurization solution synthesis compressor CO 2 removal methanation COx CH 4 solution + CO 2 separation NH 3 NH 3 water Fig 2: Main inlet and outlet energy flows involved in the ammonia production process Stream Energy losses 3% Inlet Feed () 58,3% Fuel () 39,8% Electricity 1,9% Ammonia 60,2% Cooling water 25,9% total energy 98.1% 58.3% natural gas 1.9% 39.8% electricity combustion process 60.2% NH 3 Outlet Steam export 6,1% flue gas 4.9% Flue gas 4,8% Other loses 3,0% export 6.1% system cooling water 25.9% ing step. This furnace is the main energy consumer at the site, consuming more than 70% of the overall fuel supplied to the factory. Combustion gases from this equipment are sent to a gases channel where thermal energy is recovered through several heat exchangers that preheat process streams and generate at different pressure levels before gases are sent to the stack. There is no requirement for thermal energy in the second stage of the reformer (secondary reformer), since it is supplied by the combustion reactions produced by introducing process air into the syngas stream. Heat recovery boilers generate high pressure downstream of the reforming unit, as well as after the COto-CO 2 conversion unit, where exothermic reactions take place. Additional high pressure is generated in an auxiliary boiler, whose combustion gases are sent to the same combustion exhaust gas channel of the reforming furnace. The auxiliary boiler is the second largest energy consumer of the facility, representing over 20% of total energy consumption. The third-largest thermal energy consumer is the furnace upstream of the desulphurisation reactor, where natural gas is heated. In addition to natural gas, the purge stream of the synthesis loop is also used in the fuel feed network, as it contains high levels of hydrogen. Due to the exothermic reaction of ammonia production, the thermal energy contained in the ammonia synthesis reactor outlet stream is used to preheat the boiler feed water. As shown in Fig. 2, heat supplied to the process through the combustion of natural gas is subsequently recovered for production (power production) and heating combustion air and other process streams. Unrecovered heat is removed by cooling towers and air coolers. High pressure is 2 Nitrogen+Syngas 322 March - April 2013

Fig 3: Steam model reformer aux boiler GROSS heat 36,441 MW 3,4 t/h total all users 30,012 aux boiler absorbed heat 25,417 MW BlowDn process heat to HPS generation 150,1 MW total heat to HPS generation 175,61 MW aux 69,5 t/h process generation 159,9 t/h total SS generation 229,4 t/h HS 100,2 bara 3207 437,3 C 3207 kj/kg 223,4 t/h 6,0 t/h 11,935 MW 2742 kj/kg dh 103-JTB 2,57 MW total 103 JT 103-JTA 9,36 MW 232,8 t/h 220,9 t/h delta P 36,7 bara 16,1 t/h 3054 3,0 bar 331,1 C 3054 2479 leakage 204,8 t/h MS 6,0 t/h 3054 kj/kg 39,7 bara 3207 kj/kg 335,9 C 3058 kj/kg 6,7 t/h 13,8 t/h 0,9 t/h 81,3 t/h 108,0 t/h 0,14 MW 14,12 MW 118 JT 101 J 39,31 t/h MS traps MS users 0,50 MW 116 JT 102 VTFT 105 J 26,2 t/h 3,6 t/h 1180 JT 104 J 9,1 t/h 105 JLOT 107 A 3,4 t/h 2527 2434 flash 2,5 t/h 103 JLOT 107 B 3,4 t/h 2,1 t/h 3207 kj/kg ES 6,7 t/h 13,8 t/h 2741 kj/kg 4,2 bara 3058 kj/kg 2929 kj/kg 255,8 C 2976 kj/kg 5,4 t/h 0,0 t/h 5,3 t/h 14,3 t/h control T 1,0 t/h vent 2568 145,7 C 15,3 t/h desup 0,60 MW ES users urea plant 101 BJT 0,1 bara 2562 0,1 bara 2441 2,5 6,3 t/h 97,4 t/h 111-CA/B 8,0 4187 kw 1160-C 2,0 61765 kw 1180-E 103-L 1161-C 0,6 5,0 t/h NEW 0,0 0,6 t/h 614 kj/kg 159 kj/kg 159 kj/kg traps 2,2 C C 106-C 38,0 38,0 C 95,7 C 181,1 t/h 95,7 C 166,7 t/h 100,1 42,0 C 401 kj/kg 401 420 176 0 kw 12240 kw desuperheaters 1,0 t/h 47,4 C 14,0 t/h 109-C REF jackets 233,8 t/h to 199 20 C 76,9 t/h treated water 465 kj/kg 84 kj/kg 109,1 C 2446 kw 47,9 t/h 934 kw 411 kj/kg 44,0 C driver 14,4 t/h 184 kj/kg from urea plant 103-JTA 9,36 MW 37,3 t/h stripper condensate 99,0 C 415 kj/kg heat loss 634 kw 10,6 t/h ES condensate 223,4 t/h 11,935 MW 103-JTB 2,57 MW total 103 JT 220,9 t/h leakage 3054 delta P 36,7 bara 16,1 t/h 3,0 bar 331,1 C 3054 2479 204,8 t/h 95,0 C 398 kj/kg 145,7 C 614 kj/kg mainly consumed by turbocompressors for process air, syngas, the ammonia cooling system and injection to the reforming process. A significant amount of the is also exported to the urea plant. The natural gas consumption for this site represents more than 95% of the overall energy consumption of the factory. The main objective of the proposed energy efficiency assessment is to reduce natural gas fuel consumption, corresponding to 39.8% of the total energy inlet. Approach Equipment audit The largest energy consumers were identified, with the aim of performing an energy efficiency analysis and subsequent efficiency enhancement assessments for each one of them. Furnaces, boilers, compressors and cooling systems in the facility were evaluated. A trap and insulation infrared thermography surveys were also carried out. Pinch analysis The aim of the pinch analysis is to improve the existing energy recovery from the process streams to reduce natural gas consumption. This analysis is closely linked Table 1: Projects summary Area to the model that was developed for the thermal and power systems of the factory. The study also considered the identification of appropriate residual heat sources, with the purpose of assessing the feasibility of implementing an absorption refrigeration system. Thermal and power model A model was developed of the generation and power systems, in order to predict and economically assess the effects Number of projects Maximum saving (ke/year) Pinch projects 9 1.214 0.3 Natural gas saturation 1 437 <1 Cooling towers enhancement 1 63 0.7 Natural gas expander 1 285 1.9 Auxiliary boiler combustion control 1 209 <1 Payback (years) Insulation maintenance 1 17 <0.5 Steam trap repairing 1 78 <0.5 Compressors and absorption cooling 19 106 >7 Total 34 2.409 <2 of the different energy savings projects identified in the previous stages of the study. The inputs to the model are linked to the results obtained from pinch analysis. All turbines, heat exchangers, boilers, generators and consumers of the facility are included in the model. In addition, the model allows the specification of turbine performance curves, which are needed for correct prediction of their performance under different operating conditions. Nitrogen+Syngas 322 March - April 2013 3

Fig 4: Composite curves temperature, ºC 2000 1500 1000 500 0 pinch: 20ºC heating: 31 MW cooling: 242 MW hot composite cold composite 0 100 200 300 400 enthalpy, x 000kW The model was developed in Excel format, which makes it easy to implement in any industrial facility, and represents a fast and accurate calculating tool that can be used for economic assessment of changes introcuced in the plant. The reliability of the model is based on the possibility of using real operating data to adjust the efficiencies and consumptions of each unit. Figure 3 shows the main interface of the model. Results Table 1 shows a summary of the main energy saving projects identified and assessed in the analysis. Pinch analysis Pinch analysis allows the quantitative assessment of existing energy recovery, graphically represented by hot and cold grand composite curves which are shown in Fig. 4. The composite curves of the process represent the process energy demand (heating and cooling) versus their temperatures. These curves are obtained by adding the demand of hot streams, which need to be cooled, and cold ones, which oppositely need to be heated, for each temperature interval. In spite of the proper level of existing energy recovery in the process, a big potential improvement was detected by means of retrofitting the existing heat exchanger network. For the analysis, a minimum approach of 20 C between composite curves was chosen. Figure 4 shows the optimised energy recovery case, corresponding to 20 C minimum approach. Potential savings Table 2 shows potential savings and objectives of energy consumption for the target situation, in which the energy recovery is improved at 20 C minimum approach. Although these values should not be considered as strict objectives to be fulfilled, they still provide a useful guideline for energy recovery enhancement from the process. For the same natural gas consumption in the auxiliary boiler and desulph urisation furnace, high pressure generation could be increased by 7.9 t/h. Auxiliary boiler Savings shown in Table 2 suggest the potential for reducing natural gas consumption in the boiler while maintaining the same total production (229.6 t/h). Load reduction in the boiler can be compensated by enhancing thermal energy recovery from the process through the installation of new heat exchangers. Thermal and power effects in the primary reformer All combustion gases of the plant are sent to the primary reformer gases channel, where thermal recovery takes places for the heating of different streams. The stack of the desulphurisation furnace is connected to the gases channel in the last section, affecting only air heating. It is worth noting that a reduction of natural gas burned in the boiler and/or primary reformer will have important effects on the performance of heat exchangers used for energy recovery in this duct. The gas channel was simulated and it was observed that the exchangers most affected are the boiler feed water and combustion air preheaters. Since generation is linked to the whole and power model, the global balance is affected once the amount of burned natural gas is changed. This also affects the flow rate of high pres- Table 2: Potential savings Utility Base Target energy use Energy saving potential kw t/h kw t/h KW t/h Natural gas 30.012 30.012 0 Low pressure (consumed) 6.254 10,6 0 0 6.254 10,6 High pressure (generated) 175.543 229,6 181.583 237,5 6.040 7,9 Condensate 13.798 13.798 0 Air 14.562 14.562 0 Cooling water 109.167 101.955 5.913 NH 3 13.682 12.383 1.299 4 Nitrogen+Syngas 322 March - April 2013

sure expanding through the turbines and therefore generated shaft work. Heat recovery in the gases channel was therefore carefully modelled with the aim of accurately quantifying these effects and linking it to the general and power model. Projects Table 3 summarises the identified and proposed projects resulting from pinch analysis. Nine different projects were identified, which indicated relevant reductions of natural gas consumption at the site. Economic savings achieved by single projects are between e200,000 and e1,200,000, with payback times of less than one year for most of them. The high profitability of one of the proposed projects is worth highlighting and is described in the following section. This project considers the installation of a new low-pressure generator in the gases channel. Low-pressure generator in gas channel Table 3: Pinch analysis projects summary Nº Project Saving (ke/year) P1 Low pressure (LPS) generation in gases channel to reduce auxiliary boiler natural gas consumption As previously mentioned, pinch analysis showed the possibility of increasing high pressure generation and reducing the natural gas consumption by 9% in the auxiliary boiler. Further reduction of natural gas consumption would affect the heat recovery process through the exhaust gases channel, preventing the possibility of achieving a new thermal and power equilibrium in the whole plant unless major investments were carried out to revamp the current heat exchanger network. This project proposes the installation of a new LPS (low pressure ) generator in the gases channel with the aim of achieving 9% reduction of fuel consumption, while maintaining generation. The amount of LPS generation predicted by the model was 7.2 t/h. The appropriate place for the installation of the LPS generator in the gases channel is before the last thermal recovery section, dedicated to combustion air preheaters. The reduction of fuel consumption affects the energy recovery through the gases channel downstream of the auxiliary boiler, altering the operating conditions of all the coils downstream. Figure 5 shows these new operating conditions. In the proposed situation, combustion gases will be exhausted at a lower temperature (approximately 125 C) than the current 154 C. A total cost saving value of e729,000 per year for the project has been calculated. Considering cost savings associated with CO 2 emissions reduction, total savings increase up to e801,000 (CO 2 emission tax: 15e/t). The project investment for a new LPS generator, piping and insulation is of the order of e155,000, which means a payback time of less than four months. Equipment audit Compressors 729 0,2 P2 Increasing combustion air preheating 191 1,2 P3 P1+P2 874 0,6 P4 Natural gas preheating 281 1,4 P5 P1+P4 738 0,7 P6 Increasing boiling feed water preheating 445 0,6 P7 P1+P6 1.214 0,4 P8 P4+P6 725 1,4 P9 Increasing boiling feed water heating 628 0,8 Payback (years) Two energy efficiency enhancement projects resulted from the compressors assessment, both of them aimed at reducing the consumption of their driving turbines: l Surge control improvement for the ammonia refrigeration centrifugal compressor. During periods of cold weather (5 months per year) the compressor operates at reduced loads, which causes the surge control to act Fig 5: Simulation of gases channel and generation 212,0 C 227,0 C 278,1 C 91,38 89,08 311,8 C SR-Air2 New LPS new Air %O2 Basis 6,0% 227,9 t/h Hact = 2729 %O2 Now 5,0% 4552 kw 0 kw new BFW Reformer Eff'y 50,0% 109,1 ºC 227,9 t/h MCP 2,30 109,1 C 147,1 t/h 286,4 C 27272 kw 101-CA 465 1123-C 1269 25327 kw 101-CB 465 kj/kg 157,7 C 458,0 C 0 kw 32856 kw 62,3 t/h 7404 kw 102-C 103-B Flue Gas 8344 kw 103-C 29,2 t/h 1409 114-C blowdown to HP gen 149028 kw excluding Aux Boiler 6520 kw aux Boiler 3,4 t/h to HP gen 171883 kw including Aux Boiler losses 22855 kw aux Boiler 143255 kg/h to rad 1901 kw 1269 0 kw compensating for lost heat to combn Air, SR-airProc & SR-GN 60489 kg/h to aux 286,8 ºC 0 kg/h extra for reformer combustion 51,5 t/h 22855 kw 224,5 t/h 60,56 MCP 575,0 C 438,2 C 473,0 C 157,7 C 5,0% O2 625,6 C 63242,35 kg/h 3207 0 kw 0 kw required compensating fuel 126,7 C 212,0 C 227,0 C 278,1 C 278,1 C 271779 kg/h 407,2 C 542,0 C 532,0 C 770,5 C 869,4 C 993,3 C 91,38 89,08 89,08 MCP MCP 89,08 74,61 74,61 74,61 New LPS SR-BFW 208537 SR-Air1 SR-Air2 new Air SR-Reh1 SR-Reh2 SR-airProc SR-GN 4552 kw 0 kw 11507 kw 12005 kw 17793 kw 7378 kw 9244 7792 kw kw 1740 kw 2922 16,37 61,26 lost heat pickup= MCP 2,30 29,0 458,0 C 175,0 C 322,1 C C 157,7 C C 350,0 103-B Flue Gas Nitrogen+Syngas 322 March - April 2013 5

to prevent it from malfunctions. The installation of an automatic surge control system was proposed that minimises operating hours with opened recycle valve. This system adjusts the set-point of these valves as a function of current operating conditions and dynamic surge curves. l Recovering residual heat to produce cold glycol water in LiBr/H 2 O or NH 3 / H 2 O absorption chillers. Results from the economic assessment of these projects showed high payback times (>7 years), mainly due to the high investment required for heat recovery equipment, absorption chillers and dedicated cooling towers. Fig 6: imanergy energy optimisation of operation Cooling water system The cooling water system is properly operated. Nevertheless, it was proposed that the existing cooling tower fans be replaced with more efficient and better designed ones. This results in a reduction of the electric consumption of the driving motors. The estimated saving was e63,000/year with a payback time of less than one year. Improvements were also detected in the cooling network design; a new configuration was proposed, in which warm water is substituted with cold water for condensing. Combustion control Combustion control was operated manually. Combustion optimisation is not a priority and was not performed on a continuous basis, the main focus of the operators being to maintain the production of the plant. Therefore an automatic control system was proposed for the combustion equipment in the auxiliary boiler and primary reformer. The installation of an automatic control system could be difficult considering the age of the primary reformer and the number of burners. The proposed project may therefore require a complete revamp of the combustion system, thus requiring careful evaluation from the company. Total savings of e200,000/ year were assessed for the auxiliary boiler and primary reformer, with a payback time of less than one year for the auxiliary boiler. Natural gas saturator The saturation of natural gas using hot condensates upstream of the primary reformer was simulated and assessed. This measure leads to a reduction of injection demanded by reforming and thus the possibility of reducing generation of the auxiliary boiler. Estimated savings for this project are e437,000, with a payback time less than one year. Natural gas expander Natural gas fuel is currently expanded from 45-50 barg pressure to 2 barg through a valve system. Therefore, the possibility of using this expansion to produce electric power was evaluated. The nominal electric power of the proposed expander is 450 kw, which generates economic benefit of e285,000/year. The investment associated with the acquisition and installation of the expander results in a payback time of two years. The feasibility of the project depends on the speed and reliability of the control system when opening the relief bypass in case of failure of the expander. Maintenance Two main areas were assessed: l Thermal losses, caused by insulation conditions, mainly located in the reformer furnace and main pipelines were evaluated. The economic losses correspond to e17,000/year. l Steam traps do not usually draw the attention of maintenance personnel, either because they are not sufficiently accessible or because they are not considered to have a big effect on global energy efficiency. Through an exhaustive ultrasound analysis of traps, among the 300 traps in the facility, 20 were found to be not working properly, which translates to economic losses of e78,000 per year. Future steps The installation of an energy management system (EMS) is recommended with the aim of maintaining the achieved savings predicted in the study. The objective of the EMS is to keep track of the energy efficiency of the whole site, main equipment and areas, defining achievable objectives for energy efficiency and acting to correct the deviation from those defined targets. In an energy management system it is of paramount importance to properly define the main energy efficiency indicators (EEI) and its variables of influence (VI). The company therefore developed a powerful tool, imanergy (Fig. 6), that allows the definition of dynamic references for the EEI correlated to its variables of influence. The software allows the client to compare its performance with best historical values under homogeneus conditions, which significantly helps to improve the daily operational performance of the plant from an energy point of view. Ammonia producers, considering the need for continuous improvement in its operations should consider the installation of energy manager software. n References 1. Directive 2003/87/EC 2. Directive 2009/29/EC 3. Benchmarking energy efficiency and carbon dioxide emissions. Canadian ammonia producers. 4. Methodology for the free allocation of emission allowances in the EU ETS post 2012. Ecofys, Fraunhofer ISI, Öko-Institut 5. Pinch Analysis: For the efficient use of energy, water and hydrogen. Natural resources Canada. 6 Nitrogen+Syngas 322 March - April 2013