GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012
TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown Independent School District 2
2010 BOND PROGRAM UPDATE General Contractor EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 Original: $25,574,000 CATE Addition $2,121,338 Baseball & Softball Turf - $880,000 Total - $28,575,338 I I J H H New Athletic Addition F G H J First Floor J Bid Package 1 A B Existing East View High School J D CR E J B C 10 4 9 2 ay hw Hig A. B. C. D. E. F. G. H. New Athletic Addition New Fine Arts Addition New Academic Addition New CTE Building New ROTC Addition (Alt.) New Tennis Courts New Tennis Building New Baseball/Softball Fieldhouse, Bleachers, Lighting & Pressbox I. New Practice Fields J. New Parking (1,070 spaces) New Fine Arts Addition New Academic Addition New Academic Addition CTE Building Second Floor Academic Wing Softball Field House Georgetown Independent School District New CTE/ROTC Addition 3
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 Academic Addition Interior partition installation is nearing completion. Exterior masonry veneer is currently being installed around the academic wing. Roof structure, decking and insulation are in place. Finished metal roof panels will start being installed next. Athletic Addition Exterior masonry veneer is complete at the locker room addition Ceiling installation and wall painting has begun at the locker rooms. Exterior masonry veneer is currently being installed around the gym and is nearing completion. Veneer installation at the gym enrty will begin next. Roof installation is complete at the gym roof. Roof installation at the gym entry will begin next. Painting and lighting inside the gym will begin next. CATE/ROTC Steel super-structure is in place for both east and west sides of the CATE. Masonry walls at the exterior are being constructed. Masonry walls for the storage mezzanine are being constructed. Once these are complete the slab for the storage mezzanine will be poured. Academic Corridor Georgetown Independent School District 4
EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 Academic Wing Gym & Locker Rooms Georgetown Independent School District 5
Gym Entry CATE Georgetown Independent School District 6
2010 BOND PROGRAM UPDATE Construction Manager GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS BAIRD WILLIAMS CONSTRUCTION BAIRD WILLIAMS CONSTRUCTION GEORGETOWN HIGH SCHOOL 3D Rendering Project Manager Front Entry Boards.indd 4 CTE Wing 7/26/11 8:55 AM Cafeteria Athletics Academic Athletics Athletics Auditorium Computer Labs Science Labs Library Athletics Academic Special Education Fine Arts Georgetown Independent School District 7
GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS Phase I CAFETERIA/CLASSROOM ADDITION Steel super-structure is in place. Steel roof decking is being installed. Perimeter and interior masonry walls are being constructed. ATHLETICS ADDITION Masonry wall construction has begun. The remaining slab for the locker rooms is set to pour next. KITCHEN RENOVATION Utility rough-in at existing slab is complete. Utility rough-in for new slab will begin next. Once rough-in is complete, the new kitchen slab can be poured. New steel structure supporting the existing roof is in place. EXISTING GYM & LOCKER ROOM RENOVATION Demolition of existing wood floor at lower gym is complete. Demolition of locker rooms at lower gym and upper gym is ongoing. Once demolition in these areas is complete, utility rough-in for new locker rooms and restrooms can begin. Cafeteria Interior Georgetown Independent School District 8
georgetown high school additions and renovations Cafeteria Exterior Locker Room Addition Georgetown Independent School District 9
Kitchen Renovation Locker Room Demolition Georgetown Independent School District 10
GEORGETOWN HIGH SCHOOL AND RENOVATIONS Athletic Addition Kitchen Expansion Cafeteria Expansion Greenhouse Classroom Addition Aerial Georgetown Independent School District 11
COMPLETED PROJECTS EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1 Contract Amount: $5,321,000 Substantial Completion Date: August 19, 2011 General Contractor: Charter Builders NEW WAREHOUSE FACILITY Contract Amount: $641,000 Substantial Completion Date: November 9, 2011 General Contractor: CSS, Inc. ANNIE PURL ELEMENTARY SCHOOL ROOF AND HVAC MODIFICATION Contract Amount: $229,000 Substantial Completion Date: August 12, 2011 General Contractor: Saratoga Field House Locker Room Interior View of Warehouse New HVAC Unit and Roofing Field House Weight Room Storage Shed New Ceiling and Light Fixtures Georgetown Independent School District 12