GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

Similar documents
Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

BOND CONSTRUCTION UPDATE

LOVEJOY Independent School District

Capital Projects Update

Capital Projects Update

LANSDOWNE HIGH SCHOOL RENOVATION PRELIMINARY DESIGN PRESENTATION. The Board of Education of Baltimore County Verletta White, Interim Superintendent

*Additional Projects were not part of the voter-approved 2006 Bond. They were able to be completed due to savings from other projects.

Facility Improvements

Facilities Construction

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

CENTENNIAL SCHOOL DISTRICT

MADISON HIGH SCHOOL // Executive Summary

1.0 Total Points % 2.1 Building Exterior Elements % 2.2 Accessibility % 2.3 Structural %

LEWIS ELEMENTARY SCHOOL

PLUMMER ELEMENTARY SCHOOL

Madison School District. Strategic Five-Year Facility Maintenance Plan

WILKINSON ELEMENTARY SCHOOL

Portsmouth Middle School Additional Funding Request

LOGAN SCHOOL SCHOOL WITHOUT WALLS AT LOGAN

LECKIE ELEMENTARY SCHOOL

FACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture

Cheldelin Middle School

Yardmen Arena Expansion & Renovation Project Update

Subject: Lucretia Mott School No. 3 Rehabilitation. Figure 1 Figure 2 Figure 3

Scripps Ranch High School

FACILITY NEEDS ASSESSMENT CURRENT PRIORITY ONE PROJECTS

LASALLE - BACKUS EDUCATION CAMPUS

Crockett Elementary School Renovations

Exhibit B TOWSON WEST ELEMENTARY SCHOOL BALTIMORE COUNTY PUBLIC SCHOOLS. September 9, Design Collective Project Number

Arbor Heights Elementary School. Concrete for South Building Foundation Stem Walls

Material Report - [Trade Contractors] for plan: [E:\SoftPlan14\Projects\Sample Drawings.spf\2-Storey sqft.spf] Page 1 of 5

STUART-HOBSON MIDDLE SCHOOL

SECTION ALTERNATES

Facility Study Update

Facilities Construction

Structural Inspection

Facilities Construction

BRUCE MONROE AT PARK VIEW ELEMENTARY SCHOOL MODERNIZATION PROPOSED MAIN ENTRY - EXTERIOR RENDERING

Rebuilding your Home after the storm? Adding on, renovating, or remodeling your home? Here's information YOU need to know about the 50% Rule.

2451 Bert Drive, Hollister, CA

Facilities Systems Upgrades

The parking lot is in varying condition depending upon location. The vehicular and pedestrian traffic flow is generally good.

CONSTRUCTION UPDATE JUNE 2015 THIS IS AUBURN.

Creative Performing Media Arts Middle School

Projects Currently in Planning, Design and Construction. April 12, 2017

School Without Walls

Montrose Community Recreation Center Update & MRD Outdoor Facility Plan

90% Draft - NOT FINAL. A Presentation For: the architectural studio. By Principals: George Moore & Curt Santee October 28th 2014

Section 4 - Design and Construction Overview

January 18, 2010 Report No. 7 MONTHLY CONSTRUCTION PROGRESS REPORT

ORANGE VISTA HIGH SCHOOL PHASE I

NEW YORK STATE MAIN STREET PROGRAM BEFORE & AFTER

STRUCTURAL ABBREVIATIONS S-001 GENERAL NOTES CONCRETE MASONRY NOTES DESIGN NOTES SOF NSWG-10 UAS SUPPORT FACILITY FY 2016 MILCON P-225

Stevens & Associates, Inc. Building Construction Projects. Fact Sheets

RESIDENTIAL CONSTRUCTION PERMIT FEES

CONSTRUCTION UPDATE NOVEMBER 2016 THIS IS PROGRESS. THIS IS AUBURN.

CATAMARAN TOWER - 1 Seef Area Plot 19, 20

INSPIRE each student to develop a strong

October 26, 2017 Ref.: Newfoundland & Labrador English School District 95 Elizabeth Avenue St. John s, NL A1B 1R6

Division 09 FINISHES TABLE OF CONTENTS

LEVEL TWO NUMBERS AND TITLES. Introductory Information. Bidding Requirements. Contracting Requirements. Facilities and Spaces. Systems and Assemblies

Program Update. Chino Health Science Parking Lot

KENTUCKY STATE UNIVERSITY

1. Sign-in sheet from the Pre-Proposal Conference on April 19, 2017 at Atherton Elementary.

CONSTRUCTION UPDATE SEPTEMBER 2015 THIS IS AUBURN.

WINNER. Orange County Public Schools. 100% Design Complete/Construction Kickoff Community Meeting Ivey Lane Elementary School May 18, 2016

Kingsborough Community College

ORANGE VISTA HIGH SCHOOL PHASE I

St. Germain Facility Study

2 Main School Building BLDG-124A Building Purpose Building Area Administrative, Classrooms, Cafeteria and Gymnasium 61,905 SF Inspection Date June 28-

Office of Design & Construction State University Plaza Albany, New York

DIVISION 2 SITE DEVELOPMENT DESIGN CONSIDERATIONS SECTION DESIGN GUIDELINES DUVAL COUNTY PUBLIC SCHOOLS

Facility Assessment Report, Montgomery Independent School District

FEASIBILITY STUDY SEPTEMBER 1 8,

Mount Vernon Elementary School Grades PK 5

SCHOOL BASED ASSESSMENT RESULTS - QUESTION RESPONSES

Schematic Design Report Johnson City ISD Football Stadium

The following shall be incorporated into the Contract Documents dated 26 MAR 2018.

The Ashland Project. Total Area: 1,778 Sq.Ft. 3 Bedroom, 2 Bath, 2 Car Garage

Easthampton High School Building Project. Public Information Forum #3

REQUIREMENTS FOR SUBSTANTIALLY DAMAGED AND SUBSTANTIALLY IMPROVED STRUCTURES

CITY OF NOVI. Police Department

Bid Package# 500 Org. 046 Fred Florence Middle School Org. 164 Anson Jones Elementary School

CONSTRUCTION UPDATE. June 2017 THIS IS PROGRESS. THIS IS AUBURN.

Energy Efficiency / Renewable Energy (EE/RE) Projects in Texas Public Schools

A PRESENTATION OF THE SCHEMATIC DESIGN FOR THE CHEMISTRY BUILDING RENOVATION PROJECT WILL TAKE PLACE AT THE MAY MEETING MEMORANDUM

This addendum will be part of the construction documents. All bidders must acknowledge the receipt of this addendum on the bid form.

M-DCPS DESIGN CRITERIA Table of Contents

Implementing Budget Solutions for Schools: Construction Cost and Scheduling Benefits of Using Wood

RESIDENTIAL COMPONENT TECHNOLOGY Mobile Manufactured Housing

Monthly Progress Report November 1, 2011

The Inspection Process. Waxhaw N.C.

SAN FRANCISCO UNIFIED SCHOOL DISTRICT BOND PROGRAM REPORT NOVEMBER 4, 2003 BALLOT

STRUCTURAL ASSESSMENT OBSERVATION REPORT

Copyrighted Home Plan 2011 Natural Element Homes, LLC

Board of Education Meeting

Alterations, disproportionality, and the 20% rule

East Los Angeles College Project Priority List Occupancy Date

BUILDING FOR OUR FUTURE

College of the Desert Athletics Facilities

Transcription:

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE APRIL 2012

TABLE OF CONTENTS East View High School Phase 2 Additions, Package 2 3 Georgetown High School Additions and Renovations 7 Completed Projects 12 Georgetown Independent School District 2

2010 BOND PROGRAM UPDATE General Contractor EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 Original: $25,574,000 CATE Addition $2,121,338 Baseball & Softball Turf - $880,000 Total - $28,575,338 I I J H H New Athletic Addition F G H J First Floor J Bid Package 1 A B Existing East View High School J D CR E J B C 10 4 9 2 ay hw Hig A. B. C. D. E. F. G. H. New Athletic Addition New Fine Arts Addition New Academic Addition New CTE Building New ROTC Addition (Alt.) New Tennis Courts New Tennis Building New Baseball/Softball Fieldhouse, Bleachers, Lighting & Pressbox I. New Practice Fields J. New Parking (1,070 spaces) New Fine Arts Addition New Academic Addition New Academic Addition CTE Building Second Floor Academic Wing Softball Field House Georgetown Independent School District New CTE/ROTC Addition 3

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 Academic Addition Interior partition installation is nearing completion. Exterior masonry veneer is currently being installed around the academic wing. Roof structure, decking and insulation are in place. Finished metal roof panels will start being installed next. Athletic Addition Exterior masonry veneer is complete at the locker room addition Ceiling installation and wall painting has begun at the locker rooms. Exterior masonry veneer is currently being installed around the gym and is nearing completion. Veneer installation at the gym enrty will begin next. Roof installation is complete at the gym roof. Roof installation at the gym entry will begin next. Painting and lighting inside the gym will begin next. CATE/ROTC Steel super-structure is in place for both east and west sides of the CATE. Masonry walls at the exterior are being constructed. Masonry walls for the storage mezzanine are being constructed. Once these are complete the slab for the storage mezzanine will be poured. Academic Corridor Georgetown Independent School District 4

EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 2 Academic Wing Gym & Locker Rooms Georgetown Independent School District 5

Gym Entry CATE Georgetown Independent School District 6

2010 BOND PROGRAM UPDATE Construction Manager GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS BAIRD WILLIAMS CONSTRUCTION BAIRD WILLIAMS CONSTRUCTION GEORGETOWN HIGH SCHOOL 3D Rendering Project Manager Front Entry Boards.indd 4 CTE Wing 7/26/11 8:55 AM Cafeteria Athletics Academic Athletics Athletics Auditorium Computer Labs Science Labs Library Athletics Academic Special Education Fine Arts Georgetown Independent School District 7

GEORGETOWN HIGH SCHOOL ADDITIONS AND RENOVATIONS Phase I CAFETERIA/CLASSROOM ADDITION Steel super-structure is in place. Steel roof decking is being installed. Perimeter and interior masonry walls are being constructed. ATHLETICS ADDITION Masonry wall construction has begun. The remaining slab for the locker rooms is set to pour next. KITCHEN RENOVATION Utility rough-in at existing slab is complete. Utility rough-in for new slab will begin next. Once rough-in is complete, the new kitchen slab can be poured. New steel structure supporting the existing roof is in place. EXISTING GYM & LOCKER ROOM RENOVATION Demolition of existing wood floor at lower gym is complete. Demolition of locker rooms at lower gym and upper gym is ongoing. Once demolition in these areas is complete, utility rough-in for new locker rooms and restrooms can begin. Cafeteria Interior Georgetown Independent School District 8

georgetown high school additions and renovations Cafeteria Exterior Locker Room Addition Georgetown Independent School District 9

Kitchen Renovation Locker Room Demolition Georgetown Independent School District 10

GEORGETOWN HIGH SCHOOL AND RENOVATIONS Athletic Addition Kitchen Expansion Cafeteria Expansion Greenhouse Classroom Addition Aerial Georgetown Independent School District 11

COMPLETED PROJECTS EAST VIEW HIGH SCHOOL PHASE 2 ADDITIONS, PACKAGE 1 Contract Amount: $5,321,000 Substantial Completion Date: August 19, 2011 General Contractor: Charter Builders NEW WAREHOUSE FACILITY Contract Amount: $641,000 Substantial Completion Date: November 9, 2011 General Contractor: CSS, Inc. ANNIE PURL ELEMENTARY SCHOOL ROOF AND HVAC MODIFICATION Contract Amount: $229,000 Substantial Completion Date: August 12, 2011 General Contractor: Saratoga Field House Locker Room Interior View of Warehouse New HVAC Unit and Roofing Field House Weight Room Storage Shed New Ceiling and Light Fixtures Georgetown Independent School District 12