NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR & BR

Similar documents
DESIGN & CONSTRUCTION STANDARD SPECIFICATIONS. Wireline Occupancies

Georgia Department of Transportation Railroad Coordination Submission Checklist

NORFOLK SOUTHERN CORPORATION UNDERPASS GRADE SEPARATION DESIGN CRITERIA

MetroLink Operations 700 South Ewing Street Saint Louis, Missouri

SCRRA RIGHT-OF-WAY ENCROACHMENT PROCESS

Public Projects Manual. For Projects Which May Impact

SECTION CONSTRUCTION SERVICES

UNIFORM DESIGN AND CONSTRUCTION STANDARDS FOR EXTENDING WATER DISTRIBUTION SYSTEMS SECTION 2 DESIGN STANDARDS

Challenges and results of Using hand mining to tunnel the mcalpine creek relief sewer

Overview of City of Dallas and DART Interlocal Agreements

UPRR criteria for sizing waterway openings under bridges and through culverts are as follows:

CITY OF ASTORIA PUBLIC WORKS ENGINEERING DIVISION ENGINEERING DESIGN STANDARDS FOR IN-FILL DEVELOPMENT

Cherokee Nation Entertainment Casino Ramona, Oklahoma. WORK PACKAGE: Existing Casino Demolition and Dismantling 8/7/12

CHAPTER 12 BRIDGE DECK DRAINAGE SYSTEMS

EL PASO ELECTRIC COMPANY SECTION 3 LINE EXTENSION POLICY AND CONSTRUCTION CHARGES

Constructability Guidelines

7. EXCAVATION IN PUBLIC STREETS The E-Permit & U-Permit

In the event of any occurrence that does or could pose a hazard to rail traffic or the public, contact Canadian Pacific Railway at

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

Application for Underground Pipeline Crossing or Longitudinal of Railroad Property and or Track

Permitting. Information Packet

BNSF RAILWAY COMPANY

THE KANSAS CITY SOUTHERN RAILWAY COMPANY 427 West 12 th Street Kansas City, Missouri

Structural - Engineering Review Checklist

APPENDIX A DEFINITION OF PROFESSIONAL ENGINEERING CONSULTING SERVICES

I-35W Retaining Wall Design Exhibit A - Draft Scope of Work

RAIL-HWY PROJECT DEVELOPMENT GUIDE AND

Implementation of this Special Provision requires a complete understanding of the following documents:

Table of Contents. Section 11,010 - Construction Survey Section Includes Description of Work Submittals 1. 1.

Forsyth County General Services Department Construction Management Division 201 North Chestnut Street Winston-Salem, NC 27101

Pattullo Bridge Replacement Project. Cost Report

White Paper April 23, 2018

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

3.0 DESIGN CRITERIA FOR SANITARY SEWER FACILITIES

CHAPTER 13 R-5 MANUFACTURED MOBILE HOME PARK RESIDENTIAL DISTRICT

LAFAYETTE RAILROAD RELOCATION, NORFOLK SOUTHERN CORRIDOR

CHAPTER 13. New January 1, 2013 SUE. Subsurface Utility Engineering. Designation and Location. Chapter Contents

SCRRA GRADE SEPARATION GUIDELINES

DIVISION 33 - UTILITIES SECTION UTILITY PIPE BORING AND JACKING DIVISION 33 UTILITIES SECTION UTILITY PIPE BORING AND JACKING

TECHNICAL MEMORANDUM

APPLICATION FOR PUBLIC INFRASTRUCTURE PERMIT

REQUEST FOR STATEMENT OF QUALIFICIATIONS FOR WATER SOURCE RAW WATER TRANSMISSION MAIN

BRIDGE CONSTRUCTION USING SELF-PROPELLED MODULAR TRANSPORTERS (SPMT)

Project Initiation Form

PENNSYLVANIA TURNPIKE COMMISSION

SPECIAL CONDITIONS FOR PIPE JACKING (PJ) October, 2006

REQUEST FOR CONSTRUCTION BIDS May 23, 2017

REQUIREMENTS FOR WORK WITHIN ROAD RIGHTS-OF-WAY IN UNION COUNTY

PUBLIC INFRASTRUCTURE DESIGN STANDARDS

APPROVAL PROCESS FOR NEW SEWER SYSTEMS & LINE EXTENSIONS

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

KANSAS DEPARTMENT OF TRANSPORTATION SPECIAL PROVISION TO THE STANDARD SPECIFICATIONS, 2007 EDITION

Phase 2 Exposition Metro Line Project

Section 13. Guidelines for the Design of Ground Mounted Sign Supports

BIDS WILL BE CONSIDERED NON-RESPONSIVE WITHOUT THE REQUIRED SIGNATURE ACKNOWLEDGING THE FOLLOWING:

1 Introduction. 2 Office Locations/Map. 3 General Requirements. 4 Structures and Planting. 5 Equipment Crossings. 6 Excavations. 7 Utility Crossings

PENNSYLVANIA TURNPIKE COMMISSION

Zoning Permits 11-1 ZONING PERMITS

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

Burlington Northern Santa Fe UTILITY ACCOMMODATION POLICY

LOCATION AND DESIGN DIVISION

REQUEST FOR PROPOSAL. Construction Management Services Not at Risk

Region of Waterloo Stage 1 Light Rail Transit Project. Definitions, Acronyms, Cited References Article 1 Definitions.

ATTACHMENT D SCOPE OF SERVICES

Supported Scaffold Inspections

EXISTING ROADWAY CONDITION ASSESSMENT REPORT (ERCAR) SAMPLE OUTLINE

1. All underground utilities under railroad tracks shall be encased in a larger pipe or conduit called the casing pipe.

FENCES. This hand out is for REFERENCE ONLY. For more details see specific code sections.

THE COMMONWEALTH OF MASSACHUSETTS NON-NHS BRIDGE R&R POLICY

REQUEST FOR BIDS BUILDING DEMOLITION 102 W. Main St.

Qualified Products Policy #49 Page 1 of 8

SUPPLEMENTAL TECHNICAL SPECIFICATION

Progress Report Sounder Program

Carpinteria Avenue Bridge Replacement Project Description Introduction

I. Project Overview and Limits. Project Goal

CONSTRUCTION PROCEDURES HANDBOOK

Sidewalk Repair Program. Charter Township of Canton Engineering Services

Section Safety Section Cleanup. None Required

SECTION 616 TEMPORARY TRAFFIC CONTROL

SECTION 3 STAKING REQUIREMENTS

Port Jervis Line Service Strategy Report. Appendix C: Port Jervis Line Capacity Improvements Analysis

Network Safeworking Rules and Procedures

City of Kingston Engineering Department. Application for New Outdoor Patio. Note: Agreement:

Appendix C Canadian Pacific Rail License of Entry Document

Bi-Directional Static Load Testing of Drilled Shafts

REQUEST FOR PROPOSALS OREGON CITY ANNEX FIBER OPTIC ENGINEERING & INSTALLATION. Date Due: Friday, September 8, Time Due: 4:00 p.m.

CONTRACT AGREEMENT. This CONTRACT AGREEMENT is entered into by and between the CITY OF WINDER (the

BID FORMS AND SPECIFICATIONS FOR THE DEMOLITION OF COMMERCIAL STRUCTURES IN THE 1700 BLOCK OF M STREET. CITY OF BELLEVILLE

Railway Alignment Design and Geometry

0100 GENERAL 0200 PROJECT MANAGEMENT

Specifications for Asphaltic Paving of Clark Road in Salem Township and Ludlow Road in Union Township both in Champaign County, Ohio.

REQUEST FOR QUALIFICATIONS CAMP HALL RAILROAD BUILD-IN DESIGN-BUILD PROJECT

SECTION TRENCHING & BACKFILLING

MEETING DATE: March 22, 2017 PREPARED BY: DEPT. DIRECTOR: Jim Gilliam, Arts Administrator. Jennifer Campbell

SPECIFICATION : BORING AND JACKING

Bridge Manual - Part I - June CHAPTER 5 SPECIAL PROVISIONS AND ESTIMATE

Fence and Wall Requirements

SEWER SYSTEM DESIGN GUIDELINES

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

Transcription:

NORFOLK SOUTHERN RAILWAY COMPANY FILES: BR0013844 & BR0013846 CHARLESTON, CHARLESTON COUNTY, SOUTH CAROLINA CHARLESTON PORT ACCESS ROADWAY PROJECT (1) SITE - 1 - REPLACEMENT OF EXISTING US78/52 OVERHEAD GRADE SEPARATION RAILROAD MILEPOST SC-3.8 DOT/AAR #721391M FILE: BR0013846 (2) SITE 2 - REMOVAL OF EXISTING US78/52 OVERHEAD GRADE SEPARATIONS RAILROAD MILEPOST SC-3.6 DOT/AAR #721392U FILE: BR0013844 (3) SITE 3 - CONSTRUCTION OF NEW FLYOVER OVERHEAD GRADE SEPARATIONS RAILROAD MILEPOST SC 3.4 FILE: BR0013844 SCDOT PROJECT ID: P027003 Railroad requirements are provided to assist bidders and are based on Norfolk Southern s understanding of the project described above. Requirements for these locations are included; however, upon receiving plan submittals, Norfolk Southern will provide a complete list of project specific requirements. Norfolk Southern Railway Company is hereinafter referred to as Norfolk Southern. South Carolina Department of Transportation is hereinafter referred to as SCDOT. Successful Design Build Team is hereinafter referred to as Design Build Team or Contractor. REQUEST FOR RAILROAD ENGINEERING REQUIREMENTS FOR INCLUSION INTO DESIGN-BUILD PROJECT BID PACKAGE: 1) Visit project site to identify existing or potential issues or conflicts, including, but not limited to: utilities, wayside signals, etc., based on project information provided by SCDOT Site investigations were performed on June 2, 2015 and the following comments pertain to the three sites described above. The three project sites will hereinafter be referred to as Site 1, Site 2, Site 3, or all three sites. Site All three sites are located on Norfolk Southern s SC- Line. The SC- Line runs from Railroad East (Charleston, SC) to Railroad West (Columbia, Page 1 of 8

SC). There is currently one Norfolk Southern main line track at all three sites. Along this rail corridor, there are two public roadways adjacent to Norfolk Southern s track. Meeting Street (US52) is located on Railroad North side of the track and King Street Extension (US78) is located on Railroad South side of the track. See attached maps. Signal Conflict There were no way side signals observed in the proximity of either Site 1, Site 2 or Site 3. The proposed project should not impact the railroad s signal facilities. Access Roadway See description of site for description of Access Roadway. It is anticipated that the parallel roadways eliminate the need for temporary construction rail crossing(s). See attached maps. Utilities There are numerous overhead utilities (phone, electric service, cable, etc.) located at all three sites. Existing sewer manholes were observed and appeared to be running between King Street and Norfolk Southern s track. What appeared to be a fiber optic line was also noted. The Contractor is responsible for locating utilities at all three sites on Norfolk Southern s Right-of-Way. Utilities installed longitudinally along the tracks on Norfolk Southern Right-of-Way are not typically identified by SC811. Access onto Norfolk Southern s Right-of-Way to locate utilities requires a Right-of-Entry Permit, Railroad Protective Liability Insurance, other insurance requirements, railroad flag protection, etc.. Right-of-Entry application and requirements can be obtained at the Norfolk Southern website at the following URL: http://www.nscorp.com/content/nscorp/en/real-estate/norfolk-southernservices/access-norfolk-southern-property.html The Design Build Team is responsible for determining the location of existing utilities and coordinating required utility adjustments and/or changing the design to resolve utility conflicts. Utility installations and/or adjustments require a separate License Agreement from Norfolk Southern Property Services. License Agreement application can be obtained at the Norfolk Southern website at the following URL: http://www.nscorp.com/content/nscorp/en/real-estate/norfolk-southernservices/wire-pipeline-fiber-optic-projects.html 2) Provide a Val Map establishing Railway ROW width Valuation Maps V-39/11 & V-39/12 are included with this submittal. Norfolk Southern Right-of-Way, along all three sites, is forty-six (46) feet wide; twenty-five (25) feet from track centerline on Railroad South Side toward King Street Extension and twenty-one (21) feet from track centerline on Railroad North Side toward Meeting Street. 3) Provide additional track and/or service road requirements, location of such, and spacing requirements Page 2 of 8

The designs for Site 1 and Site 3 shall accommodate one (1) future track, spaced at fourteen (14) foot track centers located on Railroad South Side toward King Street Extension. 4) Provide train counts and define whether or not this is an Amtrak Line The rail corridor along all three sites handles approximately four (4) freight trains per day. This is not an Amtrak Line. Maximum authorized speed is ten (10) miles per hour for freight trains. 5) Provide the Right-of-Entry requirements for surveying, soil borings, etc. (Railway web-site and path is acceptable) Right-of-Entry application(s) for soil borings, surveying and other access to property can be found at the Norfolk Southern website at the following URL: http://www.nscorp.com/content/nscorp/en/real-estate/norfolksouthern-services/access-norfolk-southern-property.html The Design Build Team shall be responsible for negotiating and securing all necessary right-of-entry agreements. All costs associated with the railroad right-of-entry process shall be borne by the Design Build Team. 6) Provide Railway current standards, clearances, construction criteria, insurance requirements, etc. (Railway web-site and path is acceptable) Current Standards Information regarding design and construction can be found in the Public Projects Manual. The Public Project Manual can be found at the Norfolk Southern website at the following URL: Information regarding Wireline and Pipeline Licenses can be found at the Norfolk Southern website at the following URL: http://www.nscorp.com/content/nscorp/en/real-estate/norfolk-southernservices/wire-pipeline-fiber-optic-projects.html Additional requirements, restrictions, and/or limitations may be imposed by Norfolk Southern based on PE review of the Preliminary Design Plans. Clearances - Temporary clearances are to be maintained throughout the work on all three sites. duration of the project. A temporary minimum vertical clearance of twenty-two (22) feet or the existing vertical clearance, whichever is lower shall be maintained above the top of the highest rail to the lowest point of the superstructure. A temporary minimum horizontal clearance of thirteen (13) feet from the centerline of track shall be maintained at tangent sections of track and fourteen (14) feet from the centerline of track shall be maintained at curved sections of track. For Site 1 and Site 3, permanent clearances are to be achieved at the completion of the project. A permanent minimum vertical clearance of twenty-three (23) feet shall be provided, measured from top of high rail to Page 3 of 8

lowest point of superstructure, measured from a point offset 5-6 from the centerline of track. Assume future track top of rail same as existing track top of rail. On the Railroad South side of existing track, a permanent minimum horizontal clearance of forty (40) feet as measured from face of pier to centerline of existing track should be maintained. A permanent horizontal clearance of twenty-six (26) feet as measured from face of pier to centerline of future track should be maintained. All piers located leshan twenty-five (25) feet from face of pier to centerline of nearest track (existing or future) shall be designed with crash wall protection. Edges of footings shall not be closer than thirteen (13) feet from centerline of track (existing or future). For additional information please refer to the Public Projects Manual: Construction Criteria - Additional requirements, restrictions, and/or limitations may be imposed by Norfolk Southern based on Preliminary Engineering review of the Preliminary Design Plans and review of the Construction Submittal Plans and calculations provided by the Contractor. When performing calculations and designs for review, the contractor s engineer shall conform to American Railway Engineering and Maintenanceof-Way Association (AREMA) Manual for Railway Engineering. For additional information please refer to the Public Projects Manual: Note Appendix E, Norfolk Southern Special Provisions for Protection of Railway Interests Section 7. Flagging Services bullet point A. Requirements is revised to include item 4: For Projects exceeding 30 days of construction, Contractor shall provide the flagmen a small work area with a desk/counter and chair within the field/site trailer, including the use of bathroom facilities, where the flagman can check in/out with the Project, as well as to the flagman s home terminal. The work area shall provide access to two (2) electrical outlets for recharging radio(s), and a laptop computer; and have the ability to print off needed documentation and orders as needed at the field/site trailer. This should aid in maximizing the flagman s time and efficiency on the Project. The cost of all railroad flagging services shall be borne by the Design Build Team. Insurance Requirements Norfolk Southern Insurance Requirements can be found in Appendix E. Norfolk Southern Special Provisions for Protection of Railway Interests - Section 14 of the Public Projects Manual: Page 4 of 8

The cost of all insurance associated with this project, shall be borne by the Design Build Team. 7) Provide any additional information/requirements specific to the Project site, such as MSE and/or crash walls requirements, etc. Approval of the proposed work at all three sites will be provided once the Preliminary Engineering review has been completed. If MSE walls are used at the bridge ends, the end bents must be founded on piling and if constructed on the Railroad s R/W must be protected by a crash wall. The face of the crash wall should be, at a minimum, twenty-five (25) feet from the centerline of the closest track (existing or future). If piers are to be constructed within twenty-five (25) feet, they shall be designed for crash wall protection as specified in the Public Project Manual: Pedestrian Fencing shall be provided for the proposed grade separations at Site 1 and Site 3 if a pedestrian access (sidewalk) is provided. A detailed Demolition Plan for the existing structures located at Site 1 and Site 2 will have to be approved by Norfolk Southern prior to beginning any demolition work. A detailed Erection Plan for the bridge/bridges at Site 1 and Site 3 will have to be approved by Norfolk Southern prior to beginning any erection of the bridge/bridges. For Demolition, Erection & Hoisting procedures and requirements refer to Appendix E Norfolk Southern s Special Provisions for Protection of Railway Interests, Section 5 Construction Procedures of the Public Projects Manual: The foundations of the existing structures (Site 1 and Site 2) shall be verified with the as-built drawings to determine the necessary procedures to remove the existing substructures below grade. The depth of removal of the existing substructures should be verified to determine the need for shoring and location of shoring with respect to the existing track. When determining the location of shoring, the engineer shall reference Appendix I. Norfolk Southern Typical Drawings & Details Drawing No. 4. Shoring Design Guide Shoring Requirements and Drawing No. 5 Shoring Design Guide Lateral Pressures from Train Loads of the Public Project Manual: All costs associated with this section, shall be borne by the Design Build Team. 8) Provide an estimated cost for the preliminary engineering review of the Project s plans Actual expenses related to the Preliminary Engineering Review for all three sites may vary from the estimate provided in the Preliminary Engineering Page 5 of 8

Agreement due to project conditions, duration of reviews, number of submittals and other variables. Based on experience, for projects requiring two (2) reviews of preliminary design plans plus a final review of the plans, the Preliminary Engineering review cost usually ranges between $20,000 and $30,000 per site. This estimated cost assumes no significant changes to the span lengths and structure type to be made after an initial review. This estimated cost does include one (1) site visit, two (2) reviews of preliminary roadway and bridge plans, and one (1) review of final roadway and bridge plans with calculations, the development of the construction engineering cost estimate, routing of the construction agreement, ongoing project administration and coordination, and distribution of a Notice to Proceed to mobilize Norfolk Southern forces to assist in construction activities. This estimated cost does not include expenses related to the Construction Reviews as outlined below. Assuming the conditions aforementioned are met, the Preliminary Engineering review for this type of construction project is estimated to cost approximately $50,000 for all three sites. Additional PE reviews are required whenever project plans are revised and resubmitted. Also additional Preliminary Engineering expenses may be incurred for work performed by Norfolk Southern and/or Norfolk Southern s Representative for attendance in pre-design meetings, design development coordination correspondence, documentation, reports, review of design concepts, and other work performed in support of the design-build team prior to delivery of the preliminary design plans and calculations for initial Preliminary Engineering review. Once the Preliminary plans are submitted, a detailed estimate of Preliminary Engineering costs will be prepared to include the cost of all services that Norfolk Southern will perform during the preliminary engineering review. 9) Provide a brief description of the typical required Railway services, with a schedule of typical project expenditures, which are required during project design and construction. This schedule is for informational purposes only to identify typical project expenditures and understood not to be all inclusive or to infer actual Preliminary and/or Construction costs Preliminary Engineering (PE) Review - Scope and cost estimates described in Comment 8 represent a typical PE review consisting of up to three (3) submissions of the plans and calculations, as required. Turnaround for a typical review is thirty (30) days. Additional reviews may be necessary depending on design changes made to accommodate comments and adherence to Norfolk Southern standards and requirements. See Public Projects Manual for Review Schedule. Estimated cost for Preliminary Engineering is approximately $50,000 for all three sites. Construction Engineering Management and Inspection (CEM&I) - Construction Engineering Management and Inspection services will be provided on behalf of Norfolk Southern by a contract engineering firm. All applicable designs, calculations and plans submitted, as indicated in the Public Projects Manual, must be reviewed and approved by the Norfolk Southern representative before work related to those submissions are Page 6 of 8

allowed to commence on Norfolk Southern Right-of-Way. Typical submissions may take up to thirty (30) days for review however every effort will be made to return sooner. Inspection services will also be provided on-site to ensure that work is being completed in accordance with the approved designs and plans. Once the preliminary design plans have been submitted a detailed CEM&I estimate will be prepared. Based on experience an order of magnitude cost estimate for this service should be approximately $150,000 for all three sites (work at all three sites being performed at same time). Actual expenses related to the Construction Engineering Management and Inspection may vary from the estimate value due to project conditions, construction duration, amount of submittals for review, and other variables. Norfolk Southern` Flagging Services - Flagging services will be required each day that the contractor is working on, over, under, or adjacent to Norfolk Southern Right-of-Way, or when such work may disturb a railroad structure or roadbed. Costs related to flagging services depend on the duration of the project. Approximate cost flagging services is $900 per day per flagger. It may take up to thirty (30) days to obtain flagging initially from the Railroad and due to labor agreements, it is necessary to give five (5) working days notification before flagging services may be discontinued and responsibility for payment stopped. Signal Relocation - The proposed work, at all three sites, should not impact Norfolk Southern s signal facilities. However, if during the PE or CEM&I phase of the project it is found that signal facilities will have to be relocated, an estimate will be provided to relocate (temporarily or permanently) those signals outside of the construction limits. All signal work will be performed by Norfolk Southern forces. Appropriate coordination will be performed during the PE phase of the project to ensure that the signals are relocated prior to the contractor s scheduled start date for work within Norfolk Southern Right-of-Way. The SCDOT shall negotiate and enter into the required Preliminary Engineering and Construction Agreements with Norfolk Southern; however, all costs associated with these agreements will be borne by the Design Build Team. The agreements will include estimated costs for Norfolk Southern services including, but not limited to, Preliminary Engineering Review, Construction Engineering Management and Inspection, Norfolk Southern Flagging Services, Communication and Signal Relocation, Accounting and Administration. The Design Build Team shall be provided a copy of the fully executed agreements. The SCDOT s Railroad Office shall manage and process all progressive invoices received from Norfolk Southern. A copy of each invoice will be provided to the Design Build Team from SCDOT s Construction Manager. 10) Identify if separate Easement Documents are required Depending on the alignment of the replacement bridge/bridges located at Site-1, railroad milepost SC-3.8, and other construction elements, a temporary and permanent easement may be required. The removal of the Page 7 of 8

existing bridge located at Site-2, railroad milepost SC-3.6, may require a temporary construction easement. The construction of the new flyover bridge/bridges located at Site-3, railroad milepost SC-3.4, will require temporary and permanent easements. All R/W plans and descriptions of easements must be submitted by SCDOT for review and approval. Review of the preliminary design plans and calculations will determine the size of temporary and permanent easements. If temporary and permanent easements are required, it will be negotiated by the SCDOT s Rights-of-Way Department. It shall be the responsibility of the Design Build Team to confirm that the SCDOT s Rights-of-Way Department is aware of this requirement. 11) Engineering may also include office reviews, field reviews, attendance at meetings, and preparation of correspondence, reports, and other documentation in connection with the Project. Nothing contained in this Agreement shall oblige Railway to perform work which, in Railway s opinion, is not relevant to Railway s participation in the Project If additional work is required by Norfolk Southern following the execution of the Preliminary Engineering Agreement/Agreements or the Construction Agreement/Agreements for all three sites, the SCDOT or its Contractor shall submit written or email request(s) to Norfolk Southern requesting or authorizing additional services. Norfolk Southern will provide additional field reviews, attend design and coordination meetings, prepare correspondence and reports, or generate other documentation needed to assist in facilitation of project design and/or construction schedule. If additional services will cause the approved PE and/or CEM&I authorization to overrun, a revised cost estimate will be provided to the SCDOT for approval of the increase in PE and/or CEM&I authorization. If required, all costs shall be borne by the Design Build Team. NOTE: ANY ADDITIONAL CHARGES NOT SPECIFIED HEREIN SHALL BE BORNE BY THE DESIGN BUILD TEAM Page 8 of 8