Rock Island Powerhouse 2 Rehabilitation. Board Presentation. November 20, 2017

Similar documents
Priest Rapids Turbine Upgrade Project. May 26 th, 2015

Prospect No. 3 Hydroelectric Project FERC Project No. P-2337 Initial Study Report: Ramping May 2015

Power plant Asset. Thermal power Hydro power Geothermal power. QuestIntegrity.com CHALLENGE CONVENTION

Engineering for SH Operations Voith s new StreamDiver technology. StreamDiver B Murtha, NWHA Sisters Oregon

Alden Turbine Development: Overview of Preliminary Engineering

Presentation Outline. Review of CEATI Background Conventional Hydro Program Update

Range of utilization. Envelope

Field Technology Services

Solutions for hydro power plants Machined seals

MC/TM INFORMATION TO BETTER MANAGE YOUR MACHINES. Complete Monitoring Solutions for the HYDRO INDUSTRY

Pratt & Whitney. Power Systems MOBILEPAC. Gas Turbine Package. It s in our power.

Published by and copyright 2009: Siemens AG Energy Sector Freyeslebenstrasse Erlangen, Germany

SUBMERSIBLE ELECTRIC PUMPS

NUCLEAR TRAINING CENTRE COURSE 134 FOR ONTARIO HYDRO USE ONLY

SUBMERSIBLE ELECTRIC PUMPS

FLOWSERVE CORPORATION Guardian Pumps. Centrifugal ANSI Pumps Product Training Program

Recent Technologies for Steam Turbines

Annex V Concrete Structures Removal Plan

Meter, PD Series, H8-S1, S3, S5, S6 and S7

HORIZONTAL CONCRETE MIXING PLANTS. Horizontal Concrete Mixing Plants HN 1.5 HN 4.0 H 5 H 6

Micro Hydro In a Municipal Water and Power System

MECHANICAL OVERSPEED TESTING OF NUCLEAR SAFETY-RELATED TURBINES WITHOUT DRIVING STEAM

CHAPTER - 6 BEST PRACTICES IN OPERATION & MAINTENANCE OF HYDRO POWER STATIONS

TURBINE VENTING FOR DISSOLVED OXYGEN IMPROVEMENTS AT BULL SHOALS, NORFORK, AND TABLE ROCK DAMS

John Hart Generating Station Replacement Project. November 2017 Community Construction Update Report #53

DEPARTMENT OF THE ARMY ER U.S. Army Corps of Engineers CECW-E Washington, DC Engineering and Design HYDROELECTRIC DESIGN CENTER

SUMMER 15 EXAMINATION

Eska Creek Preliminary Feasibility Analysis

Bringing Untapped Hydropower to Reality

Columbia River System Operations Environmental Impact Statement Newsletter

Update on Development of Auto-Venting Turbine Technology

ROW: Siting, Vegetation Management, and Avian Issues - Program 57

Quantifying the Maintenance Costs Associated with Variable Operating Conditions

PARR. PARR HYDROELECTRIC PROJECT PARR HYDRO DEVELOPMENT & FAIRFIELD PUMPED STORAGE FACILITY DEVELOPMENT FERC PROJECT No SC JANUARY 2013

Types of Hydropower Facilities

PERFORMANCE MEASUREMENTS ON REFURBISHED TURBINES OF 770,000 kw AT GURI HYDROELECTRIC COMPLEX

Swansea Bay tidal powerplant: Bi-directional bulb pump-turbine with variable speed

HyCon MD Monitoring, Analysis and Diagnosis

SECTION 2110 PRODUCT INFORMATION TYPE HBB SOLIDS-HANDLING WASTEWATER PUMPS COMPLETE HBB PUMP INCLUDES:

NEW LP TURBINES FOR NE KRŠKO

SECTION COOLING TOWER

Combined Cycle Power Plants. Combined Cycle Power Plant Overview (Single- and Multi-Shaft) Training Module. ALSTOM (Switzerland) Ltd )*+,

Overhaul Issues on Vertical Pumps

Fundamentals of Asset Management. Step 1. Develop Asset Registry A Hands-On Approach

- CONSTRUCTIONS 300 SECTIONAL VIEW 300 SECTIONAL TABLE 301 QUANTITY FOR MODEL 302 MECHANICAL SEAL 303 BEARINGS 304

Subject: October and November Fish Kill Incidents, Article 406

SUGGESTED SPECIFICATIONS Pump Frames through 64132

SK75/100. Performance Data TOTAL HEAD IN FEET HEAD-METERS 6 SK100 SK Liters/Second Capacity-U.S. G.P.M.

CENTRIFUGAL COMPRESSORS MAINTENANCE & FAILURE ANALYSIS

NZQA registered unit standard version 5 Page 1 of 6. Operate hydro-electric generating plant from enterprise control room

Working with BC Hydro. Capital Infrastructure Project Delivery

Model EVMS Vertical Multistage Pumps for the Global Market

Capacity Performance FAQ Response

Compact - Effi cient - Reliable. DIVE-Turbine An innovative turbine concept for small hydro power plants

SKF marine solutions. Improving fleet efficiency and predictability in a sustainable way. The Power of Knowledge Engineering

SECTION PACKAGE BOOSTER PUMP STATIONS

compact efficient reliable

REPLACEMENT PARTS MANUAL 5' x 12' 2-Deck Vibrating Screen

ITEM 686 TRAFFIC SIGNAL POLE ASSEMBLIES (STEEL)

[4163] T.E. (Mechanical) TURBO MACHINES (2008 Pattern) (Common to Mech. S/W) (Sem. - II)

VOGEL - Submersible Pumps in Stainless Steel Design TVS

Water Quality Monitoring During Turbine Venting Tests at the Iron Gate Powerhouse, Klamath Hydroelectric Project

Item 442 Metal for Structures

- CONSTRUCTIONS 300 SECTIONAL VIEW DRAWING 300 SECTIONAL VIEW TABLE 301 QUANTITY FOR MODEL 302 MECHANICAL SEAL and BEARINGS 303

Power Recovery Turbines

PROJECT BRIEF for the John Hart Generating Station Replacement Project

700-m 400-MW Class Ultrahigh-head Pump Turbine

National Hydropower Association Operational Excellence Event Report. Environmental

FAIRBANKS NIJHUIS SUBMERSIBLE SOLIDS HANDLING PUMPS.

Digital Asset Management: Optimizing the Asset Life-cycle with new generation of tools. Filip Kowalski, SAP CEE

Realization of the Holtwood Expansion Project

National Maritime Center

Pumps, Turbines, and Pipe Networks. Ch 11 Young

Elliott Engineered Solutions SERVICES

Rehabilitation of Kidatu Power Plant Project Presentation

SECTION SLUDGE HOLDING TANK DECANTER PUMP

The information contained in this document is the property of Meggitt Sensing Systems and is proprietary and/or copyright material.

Fabrication and Study of the Parameters Affecting the Efficiency of a Bladeless Turbine

TECHNIQUES, MATERIALS AND DESIGN CONSIDERATIONS: REHABILITATION & STRENGTHENING OF WATER AND WASTEWATER PIPELINES. Solutions & Case Studies

SOUTH FORK AMERICAN RIVER (CHILI BAR), CALIFORNIA

TECHNICAL REPORT TYPE 3

NUCLEAR POWER CORPORATION OF INDIA LTD TECHNICAL SPECIFICATION ON SUBMERSIBLE PUMPS PAGE NO: 1 OF 4 REV NO : 0 DATA SHEET A

Water-Energy Nexus: Economics of Hydropower

Index January 23, 2015 MANITOBA HYDRO 2015/16 & 2016/17 GENERAL RATE APPLICATION

CONTENTS LIST OF TABLES LIST OF FIGURES

Laser Cladding AKMELOGI. Engineering Hi-tech Machinery Remanufacturing Services Flexible Manufacturing Systems

Cooling Tower Depot, Inc. 651 Corporate Circle, Suite 206 Golden, CO Phone (720) Fax: (720)

White Paper April 23, 2018

HUP. Performance Data. Wholesale Products Page: Section: Performance Data Dated: January RPM: 1550 Discharge: 1" Solids: 1/8" GPM: TDH:

Applied Maintenance Supplies & Solutions

CONTACT US OUR SERVICES OUR PRODUCTS QUALITY CERTIFICATIONS EN9120/AS9100, SC21 BRONZE AWARD

Bulb/pit/S-turbines and generators

Design and Construction of a Mini Hydro Turbine Model

FULL PAPER FP_A.5_CLP_CCGT Upgrade

Remote Digital Video Inspection

HYDROPOWER SYSTEMS BY APPOINTMENT TO H.M. THE QUEEN WATER TURBINE ENGINEERS, GILBERT GILKES & GORDON LTD, KENDAL

20/06/2011 Seminar on Geothermal Exploitation Santiago de Chile

HÄNY-POWERLINE. Energy from drinking and waste water. Pumps, turbines and systems

BEST ONE SUBMERSIBLE SUMP PUMPS EPA. Page Features & Applications 100 Exploded View 101 Pump & Motor Specifications 102 Selection Chart / Type key 103

Standards Summary Sheet

Transcription:

Rock Island Powerhouse 2 Rehabilitation Board Presentation November 20, 2017

Objectives Present recommendation for scope, schedule and budget for Rock Island Powerhouse 2 (RI PH2) Rehabilitation program Seek Board concurrence of RI PH2 Rehabilitation program Seek Board approval to execute new service agreement in support of RI PH2 Rehabilitation program 2

Discussion Topics Background Condition Indicators Alternatives Explored Recommendations Economics Ongoing Risks and Issues Planning and Coordination Resources Next Steps 3

4 Team Alternatives and recommendations include input and review from a District wide team comprised of: Risk Accounting Licensing Dam Safety Fish & Wildlife Transmission Generation Energy Planning and Training Safety Human Resources Finance Legal Central Maintenance Shared Services

Rock Island PH2 Background Eight horizontal bulb units rated at 51 MW each with ~40 years of service Designed for low head, high flow installations and extremely efficient Commercial operation in 1977/78 Generator frame cracking issues 1985. Generators replaced/repaired in 1988-1990 5

Condition Indicators Stator windings Rotor poles Trunnion seals Turbine blades Lube oil injection pumps 6

Alternatives Explored New turbines and generators Rehabilitated turbines and generators 7

New Turbines and Generators 8 Lower return on investment (ROI) relative to rehabilitation option Potential impacts to relicensing efforts Significant time and cost to evaluate how new design may impact habitat conservation plan (HCP) and total dissolved gas (TDG) programs New design creates uncertainty with reliability, operations and maintenance

9 Efficiency Comparison

Scope Recommendation Rehabilitate major components that have > 40 years of remaining life if rehabbed (turbine runner, shafts, rotor, stator) Replace wear components (bushings, seals, fasteners, instrumentation, motors, pumps) Procure new one generator for first unit to accelerate overall schedule by approximately 2 years Procure some new components for schedule and cost risk mitigation 10

Proposed Wear Components to Replace All seals and wear elements High pressure bearing pumps Heat exchangers and oil filters Wicket gate pins Wicket gate link bearings Wicket gate bushings, thrust washers and wear elements Discharge ring Expansion joint to draft tube and associated hardware, gland rings, etc. Piston rings for runner blade position Turbine shaft bolt cover, instruments, and directional valves Turbine shaft coupling hardware Intermediate shaft coupling hardware Carbon seal segments and keeper rings Inflatable shaft seal 11 All piping inside the bulb All wire and instrumentation inside the bulb Stator winding, core and clamping system Generator cooling fans Generator air coolers Generator air cooler and fan removal system Brake pads and seals Bulb heaters Fire detection Generator supports Generator shaft coupling hardware Blade restoring mechanism parts Exciter diodes and heat sinks Slip rings Generator humidifier All varistors

Risk Mitigation Components Major components to purchase new to mitigate cost and schedule risk: Outer wicket gate ring Inner wicket gate ring Turbine guide bearing supports Turbine shaft Intermediate shaft Turbine hub cover Wicket gates for 1 unit (20) Stator frame Rotor poles for 1 Unit (72) 12

Recommendation - Schedule Outages start 2021, and complete 2029 First unit outage planned for 16 months Second unit outage starts after first unit outage is complete Third unit outage overlaps second unit outage Subsequent unit outages have similar planned durations and overlap to optimize schedule Schedule supports having all units in operation for expected 2030 HCP check-in 13

14 Recommendation Schedule Supports fish passage and asset management objectives

Recommendation Budget (in $Nominal) Total budget $313M Additional $39M for balance of plant (BoP) projects BoP projects have been (or soon will be) justified and funded as standalone projects through the normal budgeting process $352M total RI PH2 expenditures between now and 2029 $1.8M included in 2018 capital budget 15

16 Economics (in $Nominal) Key metrics of economic analysis with selected sensitivities: Estimated Project Budget $352M 16.2% - Internal rate of return (IRR) Values include energy capacity, carbon, and encroachment using forward price curves Cost includes unit costs, risk mitigation components, on-site rehab capability, necessary balance of plant work, District labor, additional material and labor costs to support schedule Utilized Asset Management to inform unit failure impacts to identify preferred scheduled Sensitivities 10.9% IRR using the lower future energy prices Sensitivities pencil out to provide economic value to customers Before District awards contract, key assumptions and value components will be revisited to confirm economic value

Ongoing Risks and Issues Component condition failure rate Recommended schedule balances predicted failure rate with achievability. Expect forced outages during the term of the project Impacts to plant operations Other necessary RI Projects Site Facilities 17

Planning and Coordination Bid prep and solicitation of proposals Safety evaluation Site Utilization Facilities Improvement Program RI PH1 Rehabilitation RI Spillway Modernization 18

Resources Significant resources required to execute project scope Dedicated staff of 10 people Includes District and contracted staff Includes project managers, construction managers, engineers, admin support Three new limited assignment positions required Additional contracted support estimated at $5.25M between now and 2022 19

Next Steps Rehab Contract Future Board Actions 11/20/2017 Resolution for service agreement for consulting engineering support Q2 2018 Request to Advertise Q4 2018 Authorization to Award Re-evaluation of project feasibility Release one unit at a time Q3 2021 Start first unit outage 20

21 Appendix

Decision Evaluation Criteria 1. What are the impacts to our customer owners? Economic value to customer owners returning an expected internal rate of return of ~16% with increased energy, capacity, carbon and encroachment values Many of existing components have remaining life of 40 or more years Rehabilitation provides the earliest schedule to mitigate failure risk of units out at the end of the rehab schedule period Rehabilitation provides more operational certainty and reduces the overall failure risk, particularly early in the life 22

Decision Evaluation Criteria 2. Are there stewardship implications? Supports reinvestment in District hydro assets Rehabilitation is the most cost-effective path that reduces failure risk seeking long-term sustainability of operations Hydraulic capacity is maintained through rehabilitation Rehabilitation is likely the most efficient path forward from an HCP perspective Schedule considers avoiding rehabilitating two adjacent units at the same time which could create a predator rich environment o if working on adjacent units concurrently is necessary, then mitigation steps will be taken 23

Decision Evaluation Criteria 3. What are the legal implications? Rehabilitation is the most efficient path forward from a relicensing perspective o it will most likely be considered maintenance from FERC s perspective and not result in a lengthy amendment process 24

Decision Evaluation Criteria 4. What are the workforce/operations implications? Rehabilitation has condition uncertainty on existing components that could result in project delays and/or new scoping for future units Resource requirements for staffing, contracted employees, and consultants increase beginning in 2018 through the duration of the project, particularly during simultaneously PH1 work. o results in 4 additional District FTEs during those years Proposed bidding strategy creates optionality for future units to allow the benefit of time and further development of known unknowns to inform project scope 25

Decision Evaluation Criteria 5. What are other stakeholder implications? Maintaining capacity and energy capability and operational flexibility will be preferred by power purchasers Cost-plus purchasers have contract provisions that provide capital support Rating agencies would be supportive of the most cost-effective solution Fish agencies and the HCP Coordinating Committee should be supportive of rehabilitation Rehabilitation does not result in decreased hydraulic capacity, thus FERC should be supportive 26

Decision Evaluation Criteria 6. What are impacts to Values? Safety: PH2 offers unique challenges due to the bulb design and confined space, however there may be opportunities to improve conditions through engineering and design of rehabbed units Stewardship: maintains hydraulic capacity, supportive of maintaining fish passage, provides incremental value to customer owners Trustworthiness: supports long-term relationships with power purchasers through value creation, supports current power contracts, avoids costs and uncertainty associated with alternatives, consistent with strategic plan Operational Excellence: supports reducing failure risk by pursuing a known design, creates opportunities for continuous knowledge building for engineers and crews, supports prudent financial decision making during a period of many District priorities 26

31 Questions?

32