Stakeholder Engagement Session on Long-Term Load and DER Forecasting July 14, 2017

Similar documents
Con Edison. Evolution of Con Edison efforts in Energy Efficiency and Demand Management:

Initial Distributed System Implementation Plan

LONG ISLAND LONG ISLAND

Pathways to an Open Grid, O'ahu: Project Launch. September 7, 2017

CON EDISON, INC. Edison Electric Institute Finance Conference. November 6-8, 2016

Value of DER Implementation. AEE Presentation May 16, 2017

Electrification and its Implications for the California Electricity System

Utility 2.0 Long Range Plan 2016 Annual Update Prepared for Long Island Power Authority. December 29, 2016

Value of DER Implementation. ULI Electric Cities July 26, 2017 Stephen Wemple, Utility of the Future

UNDERSTANDING YOUR UTILITY PARTNERS UTILITY ENERGY EFFICIENCY DRIVERS AND DESIGN CONSIDERATIONS

MINIMIZING DISTRIBUTED ENERGY RESOURCES (DER) ACQUISITION COST THROUGH AUCTIONS

Solar Integration into the PJM Grid

Con Edison Non-Wires Solutions Response to RFP Clarification Questions

IMPROVING DISTRIBUTION SYSTEM PLANNING TO INCORPORATE DISTRIBUTED ENERGY RESOURCES

Innovation & Grid Modernization at ComEd. Laura García García Grid Strategy & Analytics Commonwealth Edison

2018 Draft Policy Initiatives Roadmap. Market and Infrastructure Policy December 7, 2017

Joint Utilities of New York - Advisory Group

Data analytics: How BGE is benefiting from AMI data. March 26, 2013

MTEP18 Futures. Planning Advisory Committee June 14, 2017

MISO Distributed Generation (DG) Presentation. October 27, 2015

SCE Distributed Energy Resource Interconnection Map (DERiM)

Using the Whole Toolbox: Integrating Demand-Side Potential Studies Presented at the 2017 ACEEE National Conference on Energy Efficiency as a Resource

Full Value Tariff Design and Retail Rate Choices

Energy Storage Value for New York

Integrating Energy Efficiency and Demand Response

Presentation to the U.S. Department of Energy by the IEEE Joint Task Force on QER

ERCOT in 2018: Challenges & Opportunities

StorageVET Applications and Demonstration Energy Storage Valuation Workshop

Southern California Edison

Anne Pramaggiore President & Chief Executive Officer ComEd

2014 Integral Analytics, Inc.

Review TAC Structure Revised Straw Proposal Stakeholder Meeting

Calculation of Demand Curve Parameters

Evolution of the Grid in MISO Region. Jordan Bakke, David Duebner, Durgesh Manjure, Laura Rauch MIPSYCON November 7, 2017

CASE: UM 1910/1911/1912 WITNESS: BRITTANY ANDRUS PUBLIC UTILITY COMMISSION OF OREGON STAFF EXHIBIT 100

An economic assessment of the benefits of storage in South Africa

DATA AND THE ELECTRICITY GRID A ROADMAP FOR USING SYSTEM DATA TO BUILD A PLUG & PLAY GRID

Please contact the undersigned if you have any questions.

Guiding Utility Performance:

THERMAL ENERGY STORAGE AS AN ENABLING TECHNOLOGY FOR RENEWABLE ENERGY

State Policies to Fully Charge Advanced Energy Storage

ENTERGY NEW ORLEANS 2015 IRP RENEWABLES TECHNICAL CONFERENCE

Patrick McHugh. Vice President Con Edison

NYSolar Smart DG Hub Resilient Solar Project. June 10, 2015

Distributed Energy Resources (DER) Update Behind the Meter Generation (BtMG) Visibility

Marcus Garvey Apartments: A Solar+Storage Microgrid for Affordable Housing in Brooklyn, NY. November 16, 2017

Final Flexible Capacity Needs Assessment for 2016

DCAS Energy Management. August 15, 2014 Ellen Ryan & Mike Dipple

Portland General Electric 2016 Integrated Resource Plan. OPUC Public Meeting December 20, 2016

Open Networks Project

The new role of DSO. David Trebolle Trebolle Manager, Active Networks and Network Analysis Applications Gas Natural Fenosa

Evolving Distribution Operational Markets

LT Load Forecast and Scenarios

Flexible Resource Adequacy Criteria and Must-Offer Obligation

Load Shift Working Group.

VIA ELECTRONIC FILING. August 29, 2014

Integrated Capacity Analysis Working Group - Long Term Refinement Topics Scoping Document

Power Potential webinar

Expanding Hydropower and Pumped Storage s Contribution to Grid Resiliency and Reliability RFI#: DE-FOA

Report of the Market Design and Platform Technology Working Group

Customer Engagement Plan

Briefing on 2018 Policy Initiatives Roadmap and Annual Plan

Utility Ownership of Combined Heating & Power (CHP) as a Base Load Supply Resource

TasNetworks Transformation Roadmap 2025

Roadmap to Distributed Generation: Innovative Tools for CHP Adoption Sam Witty, Gita Subramony, ERS

The Transformation of the New England Electric Grid and the Importance of Situational Awareness Tools

Final 2014 Flexible Capacity Needs Assessment

Final Flexible Capacity Needs Assessment for 2018

PI as a Utility- Scale PV Monitoring Platform

Capacity Performance Training. June 24, 2015

Solar and Smart Grid Training Design, Installation, Business Saving Energy Together

Distributed Energy Resources and the Distribution System Planning Process PEPCO HOLDINGS LLC September 23, 2016

ReEDS Capacity Expansion Model and the Value of Efficiency in Long Range Planning Scenarios

Business Practice Manual for The Transmission Planning Process

Eastside System Energy Storage Alternatives Screening Study. Prepared for:

PUBLIC UTILITY COMMISSION OF OREGON STAFF REPORT PUBLIC MEETING DATE: February 11, 2015 REGULAR X CONSENT EFFECTIVE DATE N/A

Solar PV Capacity Additions Forecast for PJM States:

Municipal Energy Planning Made Easy

California Distribution Resources Plan (R ) Integration Capacity Analysis Working Group Final ICA WG Long Term Refinements Report

CONSERVATION FRAMEWORK MID-TERM REVIEW

OVERVIEW & SUMMARY. Fig. 1: DG IV Categories

Beyond the Meter ADDRESSING THE LOCATIONAL VALUATION CHALLENGE FOR DISTRIBUTED ENERGY RESOURCES ESTABLISHING A COMMON METRIC FOR LOCATIONAL VALUE

Distribution GIS & Grid Model Data Management

Economic Viability of Residential Microgrids in Ontario

APRIL 23, Capacity Value of Wind Assumptions and Planning Reserve Margin

Market Impact Assessment: Preliminary DAM Results Overview

Dynamic Pricing. June 2, 2016 Harvard s Electricity Policy Group

Pathways to Integrate 175 Gigawatts of Renewable Energy into India s Electric Grid

Greater Ottawa Region Local Advisory Committee Meeting #5. June 21, 2016

STATE OF NEW YORK PUBLIC SERVICE COMMISSION. At a session of the Public Service Commission held in the City of Albany on June 17, 2015

DEW-ISM Implementation at PEPCO: A Model and Data Driven Approach to Automating PV Interconnection Studies

RESULTS OF CL&P PLAN-IT WISE ENERGY PILOT

New York Battery and Energy Storage Technology Consortium, Inc.

NASEO 2017 Northeast Regional Meeting Energy Storage Initiative. DOER Commissioner Judith Judson

Modeling the Value of Energy Storage

Portland General Electric Decarbonization Study: Summary of Draft Findings

Integrated Hourly Electricity Demand Forecast For Ontario

2018 FORRESTER. REPRODUCTION PROHIBITED.

Witness Addressing or Summarizing. Line Decision No. Proceeding No. Statement or Direction

EMS of the Future. EMS Users Conference Chicago, Illinois. John McDaniel September 20, Proprietary 1 Experience you can trust.

Transcription:

Stakeholder Engagement Session on Long-Term Load and DER Forecasting July 14, 2017 Draft for Discussion Purposes Only 1

AGENDA Introduction Addressing Stakeholder Feedback from prior Engagements Consolidated Edison Presentation Orange & Rockland Presentation Stakeholder Input on Use Cases Lunch Deep Dive Discussion Summary & Next Steps Draft for Discussion Purposes Only 2

Addressing Stakeholder Feedback From Prior Engagements Stakeholder Input Discussion Points Next Steps Use Cases Documentation The Joint Utilities welcomed the opportunity to engage and discuss use cases with stakeholders JU mentioned that Con Edison and Orange & Rockland s case studies during the 7/14 EG session would provide details on how aspects that inform forecast planning JU described elements of their current planning process as illustrated by case studies and data that draw on pertinent issues related to forecasting load and DER on the system JU Forecasting Working Group is coordinating with the System Data group to incorporate stakeholder input to inform forecast use cases The Joint Utilities will continue coordinating to explore opportunities to drive greater consistency in forecasting roadmap as part of ongoing DSIP efforts Input received is posted to the JU website and will inform the utilities 2018 DSIP filings CLOSED Feedback solicited from stakeholders on use cases and planning process. OPEN Utility DSIP filings preparations will continue through the end of the year and into 2018 Draft for Discussion Purposes Only 3

Addressing Previous Stakeholder Feedback Stakeholder Input Discussion Points Next Steps Lessons from other jurisdictions JU acknowledged the importance of leveraging lessons learned and valuable insights from other states, regions and countries JU is actively engaged with other utilities within US and the European Union, and outside stakeholders to ensure lessons learned at other utilities are leveraged within New York. JU seek to identify those approaches that can advance the interests of its customers and that will help achieve the objectives of REV. OPEN Efforts by the utilities to inform their processes through best practices and lessons learned from other jurisdictions is ongoing Draft for Discussion Purposes Only 4

Con Edison Case Study Draft for Discussion Purposes Only 5

Electric Network Forecast Approach Additional Growth Actual Load Weather Adjusted New Business, Economy EV, Steam to Elec A/C EE, DR, DMP PV, DG, Batteries Forecast New Business Growth MW Demand (Weather Adjusted) Demand Reduction Programs Demand Reduction Technologies Demand (at Design Weather) Demand (Actual Weather) Current Year Future Year 6 Confidential CONFIDENTIAL

Electric Network Peak Demand Forecast Overview Confidential CONFIDENTIAL 7

Pennsylvania Network Boundaries Confidential CONFIDENTIAL 8

Pennsylvania Network Load Profile 100% Pennsylvania Network Independent Peak Hourly Load Cycle Percent of MW Load 90% 80% 70% 60% 50% 40% 30% 20% 10% 0% 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 Hour Network peak at 3:00 p.m. 9 Confidential CONFIDENTIAL

Base Forecast Weather Adjusted Peak (WAP) A regression analysis is completed and evaluated separately for each network The result of this analysis is the starting point of the network forecast Pennsylvania 2016 WAP (MW) 160 New Business Jobs Three ways to add job growth: Jobs in queue (CPMS): jobs are added to forecast using a ramping matrix Headline jobs: any load information for large projects not yet in CPMS are added to forecast using a ramping matrix Econometric factors: Moody s data provides NYC specific insight (typically used for forecast years 6-10) For the Pennsylvania Network, there was greater insight into job growth for years 6-10 so CPMS and headline jobs were used Pennsylvania 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 Job Growth (MW) 22 51 82 102 117 128 133 134 143 154 Note: All values incremental in 2017 and then cumulative 10 Confidential CONFIDENTIAL

Load Modifiers (+) Electric Vehicles (EV) Forecast uses registered EVs from DMV data and uses top-down approach based on growth rates required to meet state goals Pennsylvania 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 EV (MW) 0.0 0.0 0.0 0.0 0.0 0.0 0.1 0.1 0.2 0.3 (+) Steam to Electric A/C Conversions Forecast uses steam customer data to estimate conversion of steam chillers to electric Pennsylvania 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 Steam A/C (MW) 0.2 0.5 0.7 0.9 1.2 1.4 1.6 1.9 2.1 2.4 (-) Photovoltaics (PV) Forecast includes PV projects in queue for first few years and then uses top-down approach based on industry growth rates Pennsylvania 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 PV (MW) 0.0 0.0 0.0 0.0 0.1 0.1 0.1 0.1 0.1 0.1 Note: All values incremental in 2017 and then cumulative 11 Confidential CONFIDENTIAL

Load Modifiers (-) Energy Efficiency (EE) Forecast includes estimates for programmatic EE programs (EEPS, NYPA, NYSERDA) Pennsylvania 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 EE (MW) 0.1 0.6 0.6 0.7 0.8 0.9 0.9 1.0 1.0 1.1 (-) Demand Management Program (DMP) Forecast includes projects in queue enrolled in DMP Pennsylvania 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 DMP (MW) 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 (-) Demand Response (DR) Forecast includes non-special Case Resource (SCR) DR programs only Pennsylvania 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 DR (MW) 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 0.1 Note: All values incremental in 2017 and then cumulative 12 Confidential CONFIDENTIAL

Load Modifiers (-) Battery Forecast includes projects in queue as well as a top-down approach in which the growth rate doubles in 2019 and then remains constant Pennsylvania 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 Battery (MW) 0.1 0.1 0.2 0.2 0.2 0.3 0.3 0.3 0.4 0.4 (-) Distributed Generation (DG) Forecast includes projects in queue for the first few years and then uses top-down approach based on industry growth rates Load considered is dependent on equipment size and redundancy in area substation design A large DG project in the Pennsylvania network is accounted for in 2019 Pennsylvania 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 DG (MW) 1.7 1.7 13.7 13.7 14.2 15.1 15.6 16.7 17.2 18.3 Note: All values incremental in 2017 and then cumulative 13 Confidential CONFIDENTIAL

Final Peak Demand Forecast vs. Capability Pennsylvania Forecasted Load as % of Station Capability 120% 100% 100% of Capability 95% 100% 104% 106% 106% 110% 113% 87% 80% 69% 80% 60% 40% 20% 0% 2017 2018 2019 2020 2021 2022 2023 2024 2025 2026 The 10-Year summer independent electric network and radial forecast is issued in mid-october Distribution Planning uses the forecast as an input to the Load Relief Plan Relief needs for each substation are evaluated by comparing the forecast to the station s capability 14 Confidential CONFIDENTIAL

Orange and Rockland Case Study Draft for Discussion Purposes Only 15

O&R Interconnection History Installed PV Customers and Applications (Incremental #) 16

O&R Interconnection History Installed and Proposed PV Capacity (Incremental MW) 17

O&R Interconnection History Proposed PV Capacity (Incremental MW) Effect of 2015 RNM and CDG Policies 2015 Overall NYSERDA Strategic Zones Oct 26 Start Community Solar Program Opens 18

O&R Interconnection History 2017 DG Proposed Capacity (Total MW) Effect of 2017 Queue Management Plan and Value of DER Jan 25 Queue Management Plan Order released Included new restrictions/hurdles for projects to remain in the queue. Pre- QMP Impacts of QMP on projects Jun 1 Order Delays the QMP activities until 30 business days after Value Stack Order is issued 2017 Overall Value of DER Order How to consider policy in forecasting? 19

DER Uncertainty in Forecasting Proposed PV Effect on a Summer Peak Day Note: Illustrative example of proposed application MW from Slide 6 20

DER Uncertainty in Forecasting Local Area Needs Assumed PV Hourly Output from Historical Meter Data Forecasting drives all planning analysis Requires local levels of study and coordination Integration of high penetration DER adds substantial complexity Technology Type Timing State Policies *Illustrative map 21

Summary Distribution Planning is complex & requires high degree of granular coordination to ensure cost effective solutions are deployed while planning for the future DER uncertainty in forecasting % of queue applications that become operational assets Calibrating hourly coincident factor for energy by service territory and technology Utility forecasting use case is reliable electric service Utility responsible for electric service and SAIDI/SAIFI/CAIDI requirements Risk mitigation actions: outage exposure, mobile transformer, reconfiguring electric infrastructure Granular forecasting becomes more important to drive needs/solutions at local level, but also much more difficult and complex JU welcome stakeholder input to inform forecasting process for evolving forecasting methodology and assumptions 22

Summary of Stakeholder Input from EG Session Draft for Discussion Purposes Only 23

STAKEHOLDER INPUTS AND ENGAGEMENT GROUP DECISION Stakeholder Input Discussion Points Next Steps Stakeholders requested JU to explore and consider probabilistic planning methods Stakeholders suggested probabilistic planning methods as way to address the uncertainty and to evaluate a broader set of possible outcomes Stakeholders stated that opportunities to utilize NWA solutions for small and large projects could be better assessed by using probabilistic methods Stakeholders commented that utilizing probabilistic planning would yield benefits to the forecasting process and capital planning, beyond the assessment of NWA opportunities. Stakeholders presented frameworks to depict cost-effective decision-making while addressing system changes such as adding PV, weather impacts, etc., in a granular manner using probabilistic approaches Stakeholders mentioned that probabilistic planning is utilized widely in multiple industries/sectors with considerable success in assessing risks that are comparable to the electric industry. Closed Feedback solicited from stakeholders on the application of probabilistic methods. Stakeholders are invited to provide further comments in writing Draft for Discussion Purposes Only 24

STAKEHOLDER INPUTS AND ENGAGEMENT GROUP DECISION Stakeholder Input Discussion Points Next Steps Stakeholders requested JU to explore and consider probabilistic planning methods Stakeholders acknowledged the complexity in probabilistic planning but stated that increased uncertainty in forecasting arising from growth of DERs, warranted exploring probabilistic planning approaches for forecasting Stakeholders commented on utilizing use-cases to investigate benefit and costs of utilizing probabilistic planning for assessing load and DER forecasts. JU requested stakeholders to specify data that utility could provide to help inform use-cases on probabilistic planning Closed Feedback solicited from stakeholders on the application of probabilistic methods. Stakeholders are invited to provide further comments in writing Draft for Discussion Purposes Only 25

STAKEHOLDER INPUTS AND ENGAGEMENT GROUP DECISION Stakeholder Input Discussion Points Next Steps Stakeholders provided inputs on forecasting use-cases Stakeholder suggested multiple use-cases focused on the forecasting process evolution: Use-case to assess benefits and costs of utilizing probabilistic planning for load and DER forecasting and identifying DER s that can alleviate load Use-case on the process of identifying grid investments on improving system capabilities to accommodate growth of DERs Use-case to identify DERs through NWA procurement to defer T&D investments Use-case to identify regions with large amounts of hosting capacity to accommodate DERs Assessing forecasts and cost-curves to identify the DER penetration level, which would yield the most benefits under the BCA framework. Closed Feedback solicited from stakeholders on use cases and planning process. Stakeholders are invited to provide further comments in writing Draft for Discussion Purposes Only 26

STAKEHOLDER INPUTS AND ENGAGEMENT GROUP DECISION Stakeholder Input Discussion Points Next Steps Stakeholder Inputs with relevance to other JU working groups JU informed stakeholders that aspects discussed during the engagement session, which had touchpoints with other working groups would be conveyed to the respective working groups. Aspects relevant to DER Sourcing: Non-wire alternatives procurement and screening criteria NWA performance assessment Aspects relevant to System Data: Communication on granularity of forecast data for probabilistic planning, Third-party and market data Timeline and Periodicity of data availability 8760 forecast data requirement for stakeholders Aspects relevant to Hosting Capacity: Use-case related to identifying regions that could accommodate DERs Closed The inputs provided by stakeholders have been communicated to the team leads for in the relevant group and will be used to inform further stakeholder engagement by those groups. Draft for Discussion Purposes Only 27

STAKEHOLDER INPUTS AND ENGAGEMENT GROUP DECISION Stakeholder Input Discussion Points Next Steps Stakeholders requested JU to ensure customer interests are not compromised Stakeholders suggested exploring collaboration with academia Participants articulated concern about discussions related to the development of forecasting capabilities and suggested use cases that could incentivize DER deployment and impact the utility customer rates Participants requested JU to explore use-cases, forecasting approaches that accrue DER benefits to customers, commensurate with the costs incurred by them. JU requested stakeholders to specify necessary data which would aid JU in data management and reduce unnecessary costs to customers Explore collaboration with academic institutions to address longer term research questions related to probabilistic approaches and DER supply curves Closed Feedback solicited from stakeholders on the evolution of forecasting tools and methods. Stakeholders are invited to provide further comments in writing. Open Utilities will consider these study concepts as future R&D opportunities become available Draft for Discussion Purposes Only 28

Next Steps The Joint Utilities thank participants for joining the stakeholder engagement session on Long Term Load and DER forecasting, today, 7/14 The Joint Utilities invites all stakeholders to provide written comments on the forecasting process The Joint Utilities will coordinate with stakeholders for participation in the Stakeholder Conference on November 30 th, 2017. More Information can be found online: http://jointutilitiesofny.org/ Draft for Discussion Purposes Only 29

Draft for draft Discussion for discussion Purposes Only 30