EDS MULTI-OCCUPIED BUILDING SUPPLIES

Similar documents
Specification for the Installation of Low Voltage Internal Mains and Services

Engineering Recommendation G81 - Part 4: Design and Planning

Statement of Methodology and Charges for Connection to the Electricity Distribution Systems of: The Electricity Network Company Limited.

Engineering Recommendation G81 Part 3 Issue Framework for new low voltage housing development installations Part 3 Installation and records

ECS INSTALLATION OF POWER CABLES AND JOINTS IN AIR

AGREEMENT FOR CONNECTION TO [EASTERN /LONDON / SOUTH EASTERN] POWER NETWORKS PLC S DISTRIBUTION SYSTEM

Site Quality Assurance Inspection Regime for Connections Extension Assets

Engineering Recommendation G81 Part 1 Issue Framework for new low voltage housing development installations Part 1 Design and planning

Technical Guideline for. Section 8. Inspection and Approval of Construction

Pre-commissioning Requirements for Independent Connection Providers Requiring New Assets to be Connected to the 11/6.6kV Network

CHAPTER 5 METERING REQUIREMENTS

STATEMENT OF CHARGES FOR CONNECTION TO NORTHERN IRELAND ELECTRICITY NETWORKS DISTRIBUTION SYSTEM. Effective from 1 st October 2017 Version 1.

Distribution System Design General Requirements

STATEMENT OF METHODOLOGY AND CHARGES FOR CONNECTION TO SP DISTRIBUTION LTD AND SP MANWEB PLC S ELECTRICITY DISTRIBUTION SYSTEMS

Hazardous. Scheme. the power behind your business

EI INSTALLATION OF UNDERGROUND CABLES - LV TO 132KV

HAS/042/001 Code of Practice for Work on Street Lighting and Street Furniture including Installation, Repairs and Maintenance

How to Apply For Electricity Connection

Installation Address. Postcode. Purpose of the report This form to be used only for reporting on the condition of an existing installation.

Engineering Recommendation G81 Part 7 Issue

DOMESTIC ELECTRICAL INSTALLATION PERIODIC INSPECTION REPORT (FOR A SINGLE DWELLING) B ADDRESS AND DETAILS OF THE INSTALLATION Address: SPECIMEN

METERING GUIDE PART 1 METERING GENERAL

Open Networks Project

UPS Electrical Design and. Installation. critica POWER SUPPLIES

Safe System of Work Policy

SERVICE LEVEL PROCEDURE

11.1 INTRODUCTION Objectives Key References Interpretation GENERAL CONDITIONS DESIGN...

National Supervision Guideline for Electrotechnology Apprentices

Electrical safety Dwellings

Access to ICP emaps Portal Procedure

Installation and Records Framework for underground networks in UK Power Networks

Guide to making service alterations. when moving your electricity service

Supervision Guideline for Electrician to Lineworker Apprentices

Version: 1.1 Date of Issue: March 2017 Page: 1 of 23

Distribution System Operating Code

Guidelines for Best Practice in relation to Electric and Magnetic Fields (EMFs) in the Design and Management of Low Voltage Distribution Networks

4. GENERAL REQUIREMENTS

Electricity Supply Agreement

PUBLIC WIFI FROM EE SOLUTION TERMS

Fixed Electrical Testing

TESTING PTE EARTHING

The Legal Obligations of Employers to Maintain all Portable Electric Equipment in a Safe Condition

Guidance for Service Termination Issue Reporting

Design Governance Rules BOP325.23

NEW CONNECTION SMALL WORKS 1-4 PREMISES APPLICATION FORM

Guide to Moving Your Electricity Service

Supervision of Trainees Holding a Limited Certificate

Article 10 - ADMINISTRATIVE SECTION

RIIO-ED1 BUSINESS PLAN Business Plan Commitments Report Glossary. 31 October 2016

ELECTRICAL INSPECTION BULLETIN (Effective )

GUIDELINES ON ELECTRICITY RESALE

Underground commercial and industrial or rural subdivisions (vacant lots - no development)

Performance Reporting Criteria

Guide to applying online

7. For items classified in Section K as C1 ( Danger

RIS RIS-1800-ENE. Rail Industry Standard for Network and Depot Interface Management Isolation Documentation. Rail Industry Standard

IMP/001/914 Code of Practice for the Economic Development of the 132kV System

NPS/002/023 Technical Specification for 132kV Power Cables.

Same As Client Address SPECIMEN. operational limitations. of the inspection and. agreed with):

How to Become an Accredited Service Provider (ASP) Andrew Loukopoulos

You are also similarly responsible for any part crossing any neighbouring land, including any length of private service pipe in the public highway.

Commercial Plans Application Checklist

WIRING RULES AND REGULATIONS OF TOMBIGBEE ELECTRIC POWER ASSOCIATION

LC19: Construction or Installation of New Plant

METERING INSTALLATION

Guide to Alterations and Work at Premises We Rent Out

The Voice of the Networks Energy Networks Association

Guide to applying online

Level 3 Diploma in Electrical Power Engineering - CT/VT Metering ( )

Route to Authorisation

Southern California Edison Revised Cal. PUC Sheet No E Rosemead, California (U 338-E) Cancelling Revised Cal. PUC Sheet No.

Ofgem Incentive on Connections Engagement 2017/18 Key Performance Indicators

The complete guide to transformers and packaged substations

Inspection Guide for PV Systems in One- and Two- Family Dwellings (For Rooftop Photovoltaic Systems meeting the Standard Plan)

DISCUSSION PAPER ON ACCESS TO SERVICE FACILITIES AND RAIL RELATED SERVICES. Article 1. Subject matter

GUIDE TO SUPPLY AND METERING ARRANGEMENT ON CUSTOMER S INTERNAL DISTRIBUTION SYSTEM

Electrical Safety Management Plan (ESMP)

ELECTRIC METERING GENERAL

ONTARIO ENERGY BOARD

8.1.2 Under no circumstances shall a service entrance be left unmetered. Notify the Company if an unmetered service is encountered.

Distributed Generation (DG) Connection Standard

COST ALLOCATION POLICY FOR VICTORIAN TERMINAL STATIONS NEGOTIATED TRANSMISSION SERVICES

ELECTRICITY DISTRIBUTION NETWORK PLANNING AND CONNECTION

SERVICE ENTRANCES. OPPD S Electrical Service Designer (ESD) shall designate the Point Of Entrance.

terms and conditions for business

CONTENTS INSTRUCTIONS. UK POWER NETWORKS LV JOINTING MANUAL I Version Section Index I Page 1

NEW CONNECTION LARGE WORKS ABOVE 4 PREMISES APPLICATION FORM

PLANNING GUIDE FOR SINGLE CUSTOMER SUBSTATIONS SERVED FROM TRANSMISSION LINES

NPS/002/020 Technical Specification for 11 & 20kV Power Cables

DISTRIBUTION NETWORK OPERATOR CONNECTION CHARGING METHODOLOGY

DOWNTOWN UNDERGROUND NETWORK SECONDARY SERVICES GUIDELINES

Standard connections for water, sewerage and electricity supply

MCS Installer Scheme. Your guide to registration

ISO 9001:2015 ISO 14001:2015 OHSAS

Regarding the compliance of a ground floor landing to a set of stairs in a residential unit at 21 Commercial Street, Takaka

De-Energisation Code of Practice

UNDERGROUND SERVICES (RESIDENTIAL) SINGLE FAMILY RESIDENTIAL, DUPLEXES, OR TOWNHOUSES

Questions & Answers. Amendments to Ontario Electrical Safety Code 23 rd Edition/2002

Achilles UVDB Verify Scheme Rule Book Issue 3 December Services for professional procurement. Be better informed, make better decisions.

Regulations on Work Permits for Contractors Performing Assembly, Dismantling, and Maintenance of Temporary Facilities in Buildings and at Outdoor

Transcription:

Document Number: EDS 08-1103 Network(s): Summary: ENGINEERING DESIGN STANDARD EDS 08-1103 MULTI-OCCUPIED BUILDING SUPPLIES EPN, LPN, SPN This standard provides guidance on the provision of supplies to multi-occupied buildings. Author: Stephen Cuddihey Approved By: Paul Williams Approved Date: 20/12/2017 This document forms part of the Company s Integrated Business System and its requirements are mandatory throughout UK Power Networks. Departure from these requirements may only be taken with the written approval of the Director of Asset Management. If you have any queries about this document please contact the author or owner of the current issue. Circulation UK Power Networks External Asset Management G81 Website Capital Programme UK Power Networks Services Connections Contractors Health & Safety ICPs/IDNOs Legal Meter Operators Network Operations Procurement Strategy & Regulation Technical Training THIS IS AN UNCONTROLLED DOCUMENT, THE READER MUST CONFIRM ITS VALIDITY BEFORE USE

Revision Record Version 4.0 Review Date 20/12/2022 Date 13/11/2017 Author Stephen Cuddihey Reason for update: Re-alignment of LV design standards. What has changed: Introduction of supporting document (EDS 08-01103a) for 100A LV supplies (Section 4.1). Requirement not permitting the installation of risers and laterals removed (Section 4.2). Reference to the LV supplies flowchart (Section 6.2). References to LV design standards updated throughout. Document renumbered from EDS 08-0118 to EDS 08-1103 Document reviewed and review date extended Version 3.0 Review Date 01/04/2020 Date 22/04/2016 Author Stephen Cuddihey Reason for update: Document updated following internal and external engagement. What has changed: Previous EDS 08-0118 addendum incorporated in EDS 08-0143 ESQCR responsibilities updated in Section 4.4. No BNO criteria and function updated in Section 5. Simplified approach to existing multi-occupied building supplies in Section 6. All equipment references moved to EDS 08-0143. Document title amended. Version 2.0 Review Date 01/12/2017 Date 14/02/2014 Author Stephen Cuddihey Structure changed for ease of use, supply arrangements moved to appropriate standards, firefighting supplies, multiple supplies, BNO definition and requirements point of isolation all clarified. Version 1.3 Review Date 14/02/2014 Date 19/12/2012 Author Stephen Cuddihey Effective from date changed Version 1.2 Review Date 19/12/2012 Date 20/09/2012 Author Stephen Cuddihey Layout revisions Version 1.1 Review Date 20/09/2012 Date 01/08/2012 Author Stephen Cuddihey G81 review, effective from date, minor revisions Version 1.0 Review Date 01/08/2012 Date 15/03/2012 Author Pete Lawson Initial issue UK Power Networks 2018 All rights reserved 2 of 15

Contents 1 Introduction... 4 2 Scope... 4 3 Definitions, Abbreviations and Terminology... 5 4 New Supply Arrangements... 6 4.1 Overview... 6 4.2 Ownership of Risers and Laterals within the Building... 6 4.3 What is a BNO?... 7 4.4 Regulations... 7 4.5 Intake Position... 8 4.6 Point of Isolation... 8 4.7 Building Network Design... 9 4.8 Demand... 9 4.9 Metering... 9 4.10 MPANs... 10 4.11 Security... 10 5 New Supply Arrangements without a BNO... 11 6 Existing Supply Arrangements Modifications and Additions... 12 6.1 Ownership... 12 6.2 LV Supplies... 12 6.3 HV Supplies... 13 7 References... 14 7.1 UK Power Networks Standards... 14 7.2 National and International Standards... 14 8 Dependent Documents... 15 UK Power Networks 2018 All rights reserved 3 of 15

1 Introduction This standard provides guidance on the provision of supplies to multi-occupied buildings. A multi-occupied building is defined by UK Power Networks as a building occupied by more than one customer. Supplies to multi-occupied buildings have been provided by various methods and arrangements across UK Power Networks and the UK. Engineering Recommendation G87 was issued in January 2010 by the Energy Networks Associations (ENA) to provide industry guidelines for the provision of low voltage supplies to multi-occupancy buildings. UK Power Networks has inherited different standards and practices relating to the adoption of rising and lateral mains. This standard provides a consistent approach across UK Power Networks and became effective from 01 June 2013. This document provides guidance to ensure: There are clear ownership boundaries and responsibilities within a customer property. A safe system of earthing is provided. Points of isolation are provided where required. 2 Scope This standard applies to the provision of supplies to multi-occupied buildings in EPN, LPN and SPN. The specific supply arrangements are detailed in EDS 08-2100 and EDS 08-3100. UK Power Networks 2018 All rights reserved 4 of 15

3 Definitions, Abbreviations and Terminology Term BNO Building Network CT DNO EHV EDNO HV IDNO Intake Position LV MOP MOCOPA MPAN Risers and Laterals SNE TN-C-S TT Definition Building network operator the organisation that owns or has been appointed to operate the electricity distribution network within a multi-occupancy building, between the intake position and customer s installation The electrical installation within and servicing an individual building Current transformer The licensed distribution network operator, in this instance UK Power Networks Voltages above 11kV. These may be both transmission and distribution networks depending on location and requirement License Exempt Network Operator, as defined in Electricity (Class Exemptions from the Requirement for a Licence) Order 2001; for example a network operator distributing less than 2.5MW or generating less than 10MW Voltages above 1000V; generally used to describe 11kV or 6.6kV distribution systems but may include higher or other legacy voltages Independent distribution network operator who holds a distribution licence The location within the building, separate intake room or intake pillar where the boundary between the DNO s network and BNO Network or Customers Installations occurs Voltages up to 1000V; generally used to describe 230/400V or 230/460V distribution systems The supplier appointed meter operator, an appointed agent approved for installing and maintaining electricity metering equipment Meter Operation Code of Practice Agreement Metering Point Administration Number A unique number for each metering point, issued by the relevant licensed distributor for use in the settlement system A term for cables within a building installed and owned by the BNO. These cables are also be referred to as BNO mains or services Separate Neutral and Earth Terre Neutral Combined Separated. A single conductor for neutral and earthing functions is utilised and an earth terminal is provided at the customer s installation. The customer s earthing may be connected to this terminal providing the relevant requirements in BS 7671 are satisfied. Terre Terre. Independent local or TT earthing is common in older installations and is also used where PME cannot be provided. An earth terminal is not provided and the customer is responsible for providing the earth electrode system (typically buried earth rods and/or conductor). Where local earthing is employed the installation normally has to be protected by a residual current device (RCD) in order to comply with BS 7671 UK Power Networks 2018 All rights reserved 5 of 15

4 New Supply Arrangements 4.1 Overview This section provides guidance to both BNOs and UK Power Networks with regards to building networks. The provision of supply to a multi-occupied building shall be appropriate to the customer s stated maximum power requirement, therefore this standard shall be considered in addition to either: EDS 08-2100 for LV supplies between 24kVA and 1000kVA or, EDS 08-3100 for all HV supplies. The number of exit points and the diversity factor applied to each property to achieve the maximum power requirement of the building network shall be the responsibility of the customer. Advice regarding the diversity of supply is provided within EDS 08-2000 but, UK Power Networks will defer to the customer requirement for the provision of supplies to a building network. Whilst it is not intended that supplies to multi-occupied buildings will be directly supplied by voltages above HV, this standard shall remain applicable in addition to the appropriate EHV design. Supplies of less than 100A three-phase, as detailed in EDS 08-2101 and EDS 08-2102 shall not be provided to multi-occupied buildings. For additional guidance on 100A LV supplies to multi-occupied buildings, refer to supporting document EDS 08-1103a. 4.2 Ownership of Risers and Laterals within the Building For all new installations UK Power Networks shall not own risers and laterals, emanating from an intake position into the fabric of the building, or any part of a building network and shall not adopt those installed by others. The UK Power Networks ownership boundary shall be at the outgoing terminals of the intake position and shall be indicated on site by the use of the approved boundary label EDS 07-0009.147. Therefore it shall be the responsibility of the BNO to own, inspect, repair, maintain and replace as required the building network and associated risers and laterals. Guidelines for buildings with no reasonable ability to determine a BNO are detailed in Section 5. UK Power Networks 2018 All rights reserved 6 of 15

4.3 What is a BNO? A BNO is defined in ENA ER G87 as: The organisation that owns or operates the electricity distribution network within a multiple occupancy building, between the intake position and customers installations The BNO may be the DNO, another licensed distributor or a third party exempt from an electricity distribution license (e.g. a facilities management company). Therefore a BNO may be a building owner, landlord, developer or similar function in control of a building infrastructure at that given moment. A BNO may appoint a third party to act as the network operator on their behalf. An IDNO or an EDNO, as defined in the Electricity Order 2001, may undertake a BNO function. A BNO does not require a distribution license if the BNO fulfils the criteria of an EDNO, i.e. the distribution of less than 2.5MW or generation less than 10MW; amongst other criteria (refer to the Electricity Order 2001). 4.4 Regulations A multi-occupancy building is defined in ENA ER G87 as: Any single building that has been sub-divided into more than one premise, for example flats (including conversions) or factories that have been broken up into smaller industrial units. It includes communal areas (if any). Building networks are governed by BS 7671; therefore UK Power Networks shall not give approval for building network designs as UK Power Networks is not an enforcing or advisory body for BS 7671. Where questions of the adequacy of the customer s installation need to be resolved the electrical contractor should seek advice from the trade body providing their accreditation e.g. Electrical Contractors Association (ECA), National Inspection Council for Electrical Installation Contracting (NICEIC) etc. Prior to energisation the customer shall provide a request for energisation in writing together with a statement of testing/compliance with BS7671 (and any other applicable legislation) for the building network, signed by an appropriately authorised person. The BNO shall consider at the design stage the on-going safety of both the occupants and meter readers from hazards, as listed in ENA ER G87, in accordance with the CDM Regulations 2015. Note: The BNO is responsible for the quality of the customer supply at the customer supply terminals in accordance with the ESQCR. UK Power Networks shall provide all reasonable assistance to the BNO to ensure that the customer has an ESQCR compliant quality of supply. UK Power Networks 2018 All rights reserved 7 of 15

4.5 Intake Position The intake position shall be installed in accordance with EDS 08-2100 or EDS 08-3100 as appropriate. The BNO shall recognise that MOCOPA parties require the installation of metering equipment to be mounted at a height of between 500mm and 1.8m, with a free working space of not less than 1m. A building network supplied in accordance with EDS 08-2100 shall have a single intake position only; multiple intake positions shall not be used for any LV supplies. A building network supplied in accordance with EDS 08-3100 or EDS 08-4100 may have multiple intakes and multiple intake positions as detailed in the respective standards. A building network supplied in accordance with EDS 08-2100, EDS 08-3100 or EDS 08-4100 shall have no additional supplies taken from EDS 08-2101 or EDS 08-2102. 4.6 Point of Isolation As a minimum requirement, with agreement of UK Power Networks, the intake position shall be considered the first point of isolation for the building network. However UK Power Networks strongly recommends that an additional point of isolation is provided by the BNO to accommodate independent operation of the building network without recourse to UK Power Networks. This has the additional benefit that energisation of the intake position may occur before completion of the building network, refer to EDS 08-3100 or EDS 08-2100 as appropriate. If the BNO opts to rely upon the intake position as the first point of isolation, UK Power Networks shall not energise a building network until all electrical works are complete. Should the BNO choose to install a point of isolation it shall be on the first length of BNO cable from the intake position and shall be installed at the shortest cable distance possible that is both safe and easily accessible. The point of isolation may be an isolating switch, a fuse or link in a cut-out, either integral to the intake position, distribution equipment or a standalone device. A point of isolation for the building network is in addition to any metering points of isolation as required by MOCOPA (refer to Section 4.9). For emergency trip arrangements refer to EDS 08-1113. UK Power Networks 2018 All rights reserved 8 of 15

4.7 Building Network Design The BNO shall: Ensure that the building network is secured to prevent illegal abstraction of electricity. Use SNE cables throughout which shall be owned and maintained by the BNO. Provide, own and maintain the location for the intake position which shall be approved by UK Power Networks. The approval shall cover the building design, structure and civil works. Provide and maintain any enclosure for an intake position that is separate from the building in a free-standing cabinet or switchroom if such a structure is necessary. Provide the SNE tails from their equipment for UK Power Networks to connect onto the load side terminals of the intake position. Provide and maintain cable routes that are in secure areas of the building to minimise the risk of damage, unauthorised access, illegal abstraction and vandalism. Prevent interference to and inadvertent contact with the intake position or any part of the BNO Network is avoided in accordance with BS 7671. The precautions may involve barriers, a caged area or a designated area. Ensure that all cables and ancillary equipment between the intake position and individual premises are installed in accessible areas within the building and not routed through the property of a third party. Note: The use of cables with low smoke and zero halogen sheathing is recommended for cables where fire might affect publicly accessible areas. 4.8 Demand It is the responsibility of the BNO to determine the electrical requirements and the supply capacity required to meet the customer s needs. The BNO shall: Specify the site to be supplied, the demand, generation and the load characteristics to be satisfied. Provide specific load characteristics for loads such as communal water pumps, refuse pulverisers and CHP which will determine the incoming supply arrangement. 4.9 Metering EDS 08-2100 and EDS 08-3100 both include the metering options applicable to the supply arrangements. A building network shall have no unmetered supplies, therefore metering at the intake position shall be provided if any exit points of the building network are unmetered. If all building network exit points are metered, metering at the intake position is not required. UK Power Networks shall: Only install or own metering at the intake position of a building network. Not install or own any metering CTs, CT chambers or provisions for whole current meters within a building network. The provision of metering within a building network shall be provided by an appointed MOP in coordination with the BNO. This may take the form of whole current or CT metering as appropriate. UK Power Networks 2018 All rights reserved 9 of 15

A point of isolation adjacent to each metering point shall be provided to allow safe installation and operation of the MOP provided meter. A group metering location or the use of metering at each exit point of the network shall be at the discretion of the BNO. 4.10 MPANs The MPANs shall be registered by: UK Power Networks where the building network is owned by an unlicensed BNO. The BNO where building network is owned by a licensed BNO. 4.11 Security Seals, locks or equivalent measures shall be fitted to all accessible equipment (e.g. cut-outs, isolators and meters) between the intake position and the customer s isolator or distribution board in accordance with MOCOPA. The BNO shall consult their appointed MOP to ensure that installed security measures are adequate. The BNO shall be responsible for the security of all equipment after the UK Power Networks intake position equipment; this includes the first point of isolation to a building network and local points of isolation adjacent to metering positions. This BNO may request guidance from their appointed MOP. Labels and circuit identification shall be provided and installed by the BNO to explicitly identify circuit-breakers and/or fuses and relate them to individual premises. UK Power Networks 2018 All rights reserved 10 of 15

5 New Supply Arrangements without a BNO UK Power Networks shall only provide LV supplies directly to each unit of the multi-occupied building if: No landlord, owner or freehold owner of the site exists. Each unit shares no communal services with an adjacent building. Each unit is be supplied at a maximum height of 1.8 metres. Note: Communal services include any function for which a ground rent or an infrastructure maintenance charge is paid to a third party. If these criteria cannot be met, UK Power Networks shall: Require a BNO to be appointed for the multi-occupied building. Provide a supply to the appropriate approved intake position in accordance with EDS 08-2100. Under any circumstances, UK Power Networks shall not: Provide direct LV services to an HV (EDS 08-3100) or EHV (EDS 08-4100) supplied building and shall require that a BNO is appointed. Assume a BNO function. UK Power Networks 2018 All rights reserved 11 of 15

6 Existing Supply Arrangements Modifications and Additions 6.1 Ownership In general, UK Power Networks are unlikely to own risers and laterals in any properties other than purpose-built non-council flats (where there is no other managing body). This means that UK Power Networks will not be responsible for risers and laterals within properties such as houses, properties converted into flats and maisonettes, including those with commercial premises below and a domestic flat above. Historically, the building developer or owner would have paid their own electricians or the contracting branch of the regional electricity company or DNO, to install risers and laterals in a multi-occupancy premise. The regional electricity company or DNO would have then inspected the installation and made the final connections. This does not confirm, or imply, ownership, and in most cases, the DNO is not actually responsible for the internal wiring in any premises. As of 1 st June 2013, UK Power Networks shall not own risers and laterals emanating from the intake position into the fabric of the building and shall not adopt those installed by others. Rising and lateral mains and services associated with new supplies shall not be adopted by UK Power Networks. This applies to all three DNO licensees and the IDNO licensee. If the installation beyond the main intake cut-out bears the name or logo of a pre-1947 electricity company, then UK Power Networks are responsible, unless it has been adopted by others since that time. There may be exceptions, where UK Power Networks would be the custodians if the following conditions are met: In SPN, only riser and lateral systems that are of an adoptable standard, or would have been at the time of construction, if the installation occurred prior to 1st June 2013. In EPN, only riser and lateral systems that are of an adoptable standard, or would have been at the time of construction, and installed post 1972 and before 1st June 2013. Indications of pre-1972 properties will include the existence of metal-clad cut-outs or VIR cables. In LPN, riser and lateral systems are not owned by UK Power Networks and consequently are not included within the inspection programme. Note: There are a number of installations in LPN where UK Power Networks has historically received a payment in respect of the ongoing inspection, but not replacement of customer owned risers and laterals. These installations are recorded in the asset register. 6.2 LV Supplies It is not intended that the provisions of this standard are applied retrospectively to existing installations. Where a building is to be refurbished and a service alteration is required then the opportunity to apply the principles described in this document should be taken. Where adoption of this standard is not reasonable or practical, modifications and additions shall be made on a like-for-like basis. A flowchart providing further guidance is included in EDS 08-2100. UK Power Networks 2018 All rights reserved 12 of 15

Where an existing multi-occupied building has been supplied with two or more single-phase supplies (in accordance with EDS 08-2101) and additional supplies are required, the option to remove these supplies in favour of a three-phase supply (in accordance with EDS 08-2100) should be considered. However where this cannot be reasonably or feasibly achieved, additional single-phase supplies (in accordance with EDS 08-2101) shall be considered to a maximum of four per multi-occupied building. It is imperative that earthing provision remains consistent within a building network, for example TT earthing shall not be provided to a TN-C-S building network. All supplies shall be in accordance with EDS 06-0017. Where a customer within a multi-occupied building requires augmentation of the building supply or an additional building supply the BNO shall be consulted with regards the arrangements and options. 6.3 HV Supplies Refer to EDS 08-3100 for additions and modification to HV supplies. UK Power Networks 2018 All rights reserved 13 of 15

7 References 7.1 UK Power Networks Standards EDS 06-0017 EDS 07-0009 EDS 08-1103a EDS 08-3100 EDS 08-4100 EDS 08-0149 EDS 08-2100 EDS 08-2101 EDS 08-2102 EDS 08-3100 Customer Installation Earthing Design Signs and Labels for Operational Sites Small Service Multi-Occupied Guidance HV Customer Supplies EHV Customer Demand and Generation Supplies Customer Supply Interface LV Customer Supplies Above 100A Single Phase LV Customer Supplies up to 100A Single Phase LV Customer Unmetered Supplies HV Customer Supplies 7.2 National and International Standards ESQCR Electricity Order 2001 BS 7671 BS 9999:2008 The Electricity Safety Quality & Continuity Regulations 2002 (as amended) Electricity (Class Exemptions from the Requirement for a Licence) Order 2001 IET Wiring Regulations 17th Edition (BS 7671:2008 incorporating amendment number 3:2015) Code of Practice for Fire Safety in the Design, Management and Use of Buildings CDM Regulations 2015 Construction (Design and Management) Regulations 2015 ENA ER G87 Engineering Recommendation G87 Guidelines for the Provision of Low Voltage Connections to Multiple Occupancy Buildings UK Power Networks 2018 All rights reserved 14 of 15

8 Dependent Documents This document is referenced in the following documents, any of which may be affected by updates. CON 05 003b CON 08 114 CON 08 116 EDS 05-2004 EDS 06-0017 EDS 08-0123 EDS 08-0148 EDS 08-3100 EDS 08-4100 EDS 08-0150 EDS 08-2000 EDS 08-2100 EDS 08-2101 EOP 09-0090 NOP 50 024 Harmonised Quote Letter ICP Design Fast-Track and Approved Designer Scheme ICP Self Determination of Point of Connection Secondary Protection Planning Policy Customer LV Installation Earthing Design LV Electrical Service Drawings Appendices to ENA ER G81 HV Customer Supplies EHV Customer Demand and Generation Supplies London 33kV Distribution Network Design and Customer Supplies LV Network Design LV Customer Supplies Above 100A Single Phase LV Customer Supplies up to 100A Single Phase Mitigation of Theft in Conveyance Operational Control of Service ACBs UK Power Networks 2018 All rights reserved 15 of 15