DOCUMENTATION WORKBOOK FY 2014

Similar documents
Hosted by: M Squared Engineering on behalf of the Illinois Department of Transportation Thursday, February 9, 2012 Eiger Lab, Rockford, IL

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

SECTION 14 - RESTORATION OF SURFACES TABLE OF CONTENTS

February 22, 2018 BIDDERS WILL ACKNOWLEDGE RECEIPT OF THIS ADDENDUM IN THE SPACE PROVIDED ON THE PROPOSAL PAGE

STANDARD SPECIFICATIONS SECTION PAVEMENT REQUIREMENTS

Warm Mix Asphalt (WMA) Guide Specification for Highway Construction

SPECIFICATIONS FOR STREET CONSTRUCTION WITHIN THE TOWN OF PLAINVILLE

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION 39 - MANHOLES TABLE OF CONTENTS 39-1 GENERAL PRECAST CONCRETE MANHOLES

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Regional Engineers. Jack A. Elston

SECTION FLEXIBLE PAVING

SPECIAL PROVISIONS - SP2014 BOOK Page 1 October 8, 2013

HOT MIX ASPHALT PAVEMENT

Documentation of Contract Quantities

ITEM 6 CONCRETE CURBS, GUTTERS, AND SIDEWALKS

Drainage structure refers to manholes, catch basins, leaching basins, inlets and drop inlets. Drainage structures are designated as follows.

Puerto Rico. Pavement Preservation Conference and Technology Implementation. US. Department of Transportation Federal Highway Administration

SECTION TRENCHING & BACKFILLING

SECTION 26 - COLD PLANE ASPHALT CONCRETE PAVEMENT TABLE OF CONTENTS

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

SECTION IV. PIPELINE EXCAVATION AND BACKFILL

TOWN OF MOUNT PLEASANT WESTCHESTER COUNTY, NEW YORK

February Page 1

SECTION BITUMINOUS CONCRETE PAVEMENT

January 2008 No. 700

SECTION 19 - TRENCH EXCAVATION, BEDDING AND BACKFILL TABLE OF CONTENTS

Contact the Jurisdictional Engineer for materials allowed by each jurisdiction.

Eastern Sewershed Package IV Project Solicitation Number: CO Job No.: ADDENDUM 1 April 20, 2018

M I N N E S O T A D O T BID TABULATION SUMMARY JOB PAGE 1 ON 03/16/94 MINNESOTA PROJECT NO.S: STP 5822(002)

East Manawa Porous Paving Project Council Bluffs, Iowa. Project Location. Phase 1 Project Location 9/2/2011

ENLOE CAMPUS STORM DRAIN AND STREET IMPROVEMENTS (Project Title) PROJECT NO. MAJGC / (Budget Account Number)

PERMIT TO EXCAVATE IN HIGHWAY CHESHIRE, CONNECTICUT

CHAPTER 10: PAVING. Refer to page 548 of the 2016 Spec book or page 573 of the 2018 Spec book for material specifications under G.

DIVISION 31 EARTHWORK 2006 Edition, Published January 1, 2006; Division Revision Date: January 31, 2012

ONE PIPE LENGTH MAX (REFER TO 1/4"/FT SLOPE (MIN) 5'-0" (MIN) OR 4" LATERAL NOTE #1) INCREASER RIGHT-OF-WAY/ 4"x6" REFER TO TYPICAL EXCAVATION,

Perpetual Pavement Demonstration

PERMEABLE INTERLOCKING PAVERS

Special Provision for Hot-Mix Asphalt Prime Coat

PARKING LOT AND ROADWAY MAINTENANCE

Municipal Inspection and Construction Guidelines Section I Roadworks SECTION I ROADWORKS I-1 GENERAL

Part IV - Pavements. Iss. 01/16/2018-Part4.doc

SECTION 7 STREET DESIGN

Adopted October 1, 2001 Page 1 of 20

ITEM D-701 PIPE FOR STORM DRAINS AND CULVERTS

CHAPTER 12: DRAINAGE

BID FORM (LUMP SUM CONTRACT)

1301 SCOPE. This section covers asphaltic concrete (AC) pavement for roadways and parking areas.

Fox Avenue Improvements From Gamebird Road to Dalton Street Bid # PROJECT SPECIFICATIONS TABLE OF CONTENTS

B. Subsurface data is available from the Owner. Contractor is urged to carefully analyze the site conditions.

Construction Documentation Track B LAP Advanced Thursday, September 25,2013 3:00 PM- 4:30 PM

SECTION MEASUREMENT AND PAYMENT

PUBLIC WORKS DEPARTMENT GENERAL NOTES

PROPOSAL PACKET CITY OF MASCOUTAH HUNTERS TRAIL PAVING. BID DATE: 9:00 a.m., August 31, 2017

SPECIAL NOTES FOR CONTRACT. Bidding Requirements and Conditions. Specifications Governing this Project

SECTION A1 EXCAVATION AND BACKFILL GENERAL

12/11/ th Annual Illinois Bituminous Paving Conference December 11, 2013

E. GILMAN STREET, N. PINCKNEY STREET, AND N. BUTLER STREET RESURFACING WITH UTILITIES ASSESSMENT DISTRICT CONTRACT NO DATE: 9/22/17

VILLAGE OF LOMBARD CONTRACT DOCUMENT NUMBER SS BID PROPOSAL

SEGMENTAL BLOCK RETAINING WALLS. Comply with Division 1 - General Provisions and Covenants, as well as the following:

SUBJECT: ITB , Oxford Road Complete Street Improvements Project ADDENDUM #1

BASE CONSTRUCTION MATERIALS A Aggregate

CONSTRUCTION SPECIFICATION FOR KEYHOLE EXCAVATION AND PERMANENT REINSTATEMENT OF KEYHOLE CORES TABLE OF CONTENTS

603 - ASPHALT PAVEMENT SMOOTHNESS SECTION 603 ASPHALT PAVEMENT SMOOTHNESS

Section Storm Sewers STORM SEWERS PART 1 - GENERAL 1.01 SECTION INCLUDES. A. Storm Sewers. B. Abandonment of Storm Sewers

CHAPTER 500 STREET PAVEMENTS, CURB, GUTTER AND SIDEWALK CONSTRUCTION SPECIFICATIONS

GENERAL CONSTRUCTION SPECIFICATIONS

Index. Composition and Order of Plan Set. Utility Plan... 5

SECTION STORM DRAIN

REQUEST FOR PROPOSAL Asphalt & Concrete Repair

SECTION 806 MANHOLE REHABILITATION

LANDSCAPE RETAINING WALLS

***************************************************************************************************************

SECTION 11 UTILITY EXCAVATION AND BACKFILL

CONSTRUCTION SURVEY. Construction survey includes personnel, equipment, and supplies required for, but not limited to, the following:

ADDENDUM NO. 1. for the VETERANS PARK RENOVATIONS CITY OF TALLADEGA, ALABAMA. Posting Date: June 20, 2013

CITY OF DES PLAINES-CONCRETE PROGRAM SIDEWALK, CURB AND DRIVEWAY GUIDELINES

Design and Construction of Concrete Overlays. By: James K. Cable, P.E. Cable Concrete Consultation

ITEM 275 PORTLAND CEMENT TREATED MATERIALS (ROAD MIXED)

SECTION 1100 GRADING 1102 MATERIALS AND DEFINITIONS.

2010 IDC WATER AND SEWER CONSTRUCTION PACKAGE III 12/11/2009 SAWS WATER JOB. NO /SAWS SEWER JOB NO SOLICITATION #B RA

ITEM 460 REINFORCED CONCRETE PIPE Description. This Item shall govern for the furnishing of reinforced concrete pipe.

Construction operations shall be conducted in a manner to provide DOT forces access to the Maintenance Yard on a continuous basis.

Addendum No. 1 Page 1 of 2

North Harris County Regional Water Authority TABLE OF CONTENTS. CONTRACT DOCUMENTS Section No. Title

HAWTHORNE AND THAD WATER & WASTEWATER IMPROVEMENTS ITB #124D 16F CITY OF IRVING ADDENDUM # 1 MAY 10, 2016

Bituminous Concrete Base Course (Type HB, Black Base, B-25.0, and B-37.5)

DOCUMENT ADDENDUM No. 2

Section 25 Aggregate Subbase

City of Duluth Development Regulations

MATERIAL ALLOWANCES AND UNIT PRICES

INDEX FOR SPECIFICATIONS FOR REMOVING CULVERTS AND PLACING CULVERTS SCOPE... 1

Special Research Study. Comparison of Stormwater Pipe Installation Lengths and Costs in Texas: Frisco, Arlington, Austin, Victoria and Hidalgo County

Utility Cut Restoration

610 - DOUBLE ASPHALT SURFACE TREATMENT SECTION 610 DOUBLE ASPHALT SURFACE TREATMENT

Request for Proposal: Due October 11, :00 pm

CHAPTER 12: DRAINAGE

SECTION 2200 PAVING CITY OF BLUE SPRINGS, MISSOURI CONSTRUCTION SPECIFICATIONS

INVITATION TO BID ON TOWN PAVING PROJECTS

If you need any additional information concerning this requirement, please contact Superintendent of Public Works John Batchelder.

Transcription:

DOCUMENTATION WORKBOOK SPECIFIC TASK TRAINING PROGRAM Conducted by the ILLINOIS CENTER FOR TRANSPORTATION (ICT) AND IDOT BUREAU OF CONSTRUCTION FY 2014

WORKBOOK TABLE OF CONTENTS Workbook Page 1... Maximum Payment for Tons Example Workbook Page 2... HMA Yield Checks for Binder Course Workbook Page 3... HMA BC Theoretical Tons Daily Yield Check Workbook Page 4... Thickness Determination Problem Workbook Page 5... Aggregate Moisture Correction Problem Workbook Page 6... Traffic Control Surveillance Problem Workbook Page 7... Structure Excavation Problem Workbook Page 8... Trench Backfill Diagram Workbook Pages 9-11... Trench Backfill Example Workbook Page 12... Trench Backfill Problem Workbook Page 13... Complete the IDR Workbook Page 14... Blank IDR Workbook Page 15... Surface Variation Problem Workbook Page 16... Traffic Control Adjustment Problem Workbook Pages 17-18... Pavement Patching Problem Workbook Page 19... HMA Surface Course Example Workbook Page 20... HMA Surface Course Adjusted Plan Quantity Example Workbook Page 21... HMA Surface Daily Yield Problem

MAXIMUM PAYMENT for TONS EXAMPLE Agg Base Cse TY B Plan Quantity = 7783 Tons Revised Plan Quantity = 7850 Tons 7850 x 1.08 = 8478 Tons Contractor t delivered d 8496.0 Tons What is the final payment? Workbook Page 1

HMA Yield Checks Binder Course (sy) (112lb/sy in) (1 ton/2000lb) (inches of thickness) = theoretical tons YIELD = DELIVERED = THEORETICAL X 100 % For HMA Binder, verify unit weight via District Materials Office, Plans or Special Provisions Workbook Page 2

Workbook Page 3

Thickness Determination Problem How many depth checks are required for PCC sidewalk that measures 1000 ft in length by 4 ft wide? Workbook Page 4

Aggregate Moisture Correction Sample Problem: Wet weight = 1623 grams Dry weight = 1496 grams Ticket total = 763.5 tons What s the pay weight? Note: Moisture should be calculated to the nearest TENTH (E.g. 6.8 %) percent. Workbook Page 5

Traffic Control Surveillance Problem The contractor was required to perform Traffic control surveillance on Tuesday and Wednesday, as part of an ongoing operation that required surveillance over several days. The contractor worked from 7:00 a.m. to 4:30 p.m. on those two days. The contractor performed the inspections and completed the BC 2240 s as required. What will the total pay be for these two days of Surveillance based on the Standard Specifications?

Structure Excavation Problem The contractor has excavated for a proposed footing as shown below: 5 ft Avg. Fron nt View Proposed Footing Side View Prop. Ftg. 5 ft Avg. 1.0 32 2.5 3. 10 25 2.5 Determine the correct volume of Structure Excavation that will be used as final payment to the contractor at this location. Workbook Page 7

Storm sewer is paid to the inside wall of the structure Payment for T.B.F. ends 3 from the outside wall of the structure Trench Backfill Diagram (looking down from above) S.S. length T.B.F. length Storm Sewer Workbook Page 8 MH Structure wall 3 T.B.F. included in the cost of the structure

Trench Backfill Example Trench Limits MH Centerline of Pipe Given: MH 5 (for pipe running parallel to the centerline of the road) 29 ft CROSS Back of Curb SECTIONAL VIEW Edge of Pavement Centerline of Roadway 5 ft PLAN VIEW 42 Circular Concrete Pipe Average Depth from subgrade to invert of the pipe = 6.8 Trench Length = 75 from outside face of manhole to outside face of manhole Contractor s Excavated Trench Width = 7 4 Centerline of Pipe Run is 5 behind the back of curb Determine: Allowable Pay Quantity for Trench Backfill Workbook Page 9 D

Trench Backfill Solution 1. Need to determine if any part of allowable trench width falls within 2 ft. of the back of curb. Allowable trench width Since D>5.0 ft., Width = 18 + 4.5 + 42 + 4.5 + 18 = 87 Half trench width = 87 /2 = 43.5 Centerline of pipe pp is given as 60 from the back of curb. 60-43.5 = 16.5 which is the dimension from the inside of the trench to the back of the curb. Since 16.5 < 24 24, must use trench backfill. 2. Determine allowable pay length Length given is 75 ft. from outside face of manhole to outside face of manhole. Workbook Page 10

According to Article 602.12, 6 greater than the diameter of the structure will be backfilled and incidental to the installation of the structure. Therefore 3 on each manhole location is incidental backfill, and allowable pay length is 75-3 - 3 = 74.5 3. Check excavated width against allowable trench width. Excavated width = 7 4 = 88 Since excavated width > allowable trench width, we can use backfill tables. 4. From table, cu. yd./lin ft. x Allowable Pay Length = Trench Backfill Volume 1.093 x 74.5 = 81.4 cu yds. Workbook Page 11

Trench Backfill Problem Sidewalk MH Given: (For pipe running perpendicular to the centerline of the road) 4 5 53 18 50 Back of Curb 102 24 SS MH 3.8 24 Circular Concrete Pipe Average Depth from subgrade to invert = 3.8 Contractor s Excavated Trench Width = 50 Determine: Show your calculation on the IDR on Workbook Page 14 Allowable Pay Length for the Trench Backfill Maximum allowable trench width Allowable Pay Quantity for Trench Backfill Workbook Page 12

Complete the IDR provided on Workbook Page 14 Todays Date, Contract #96345 United Construction (Prime) Weather is clear, 67 degrees Pay item number for Trench Backfill is 20800150 Location station 100+00 Show calculation on the IDR since it is your primary source of Documentation Workbook Page 13

Workbook Page 14

Surface Variation Problem You are working on a 2 lane milling and bituminous resurfacing project that is 15,000 feet long. The contractor s bid price is $87.00 per ton for the surface mix. As per plan, the contractor mills 1.5 inch of existing surface and then places a 1.5 inch lift of binder and a 1.5 inch lift of surface. Upon the completion of the work you recorded in both lanes a total of 17 surface variations. How much money will be deducted from the contract for the surface variations? Workbook Page 15

Traffic Control Price Adjustment Problem Art.701.20 Your contractor was performing contract work under Traffic Control Standard 701411. The original value of this work completed is $214,305.00. The final value of the completed work under this standard is $248,593.00. The unit price for this pay item is $27,500.00. What is the adjusted unit price for Traffic Control Standard 701411? Also, what is the pay item number for the additional adjustment? Workbook Page 16

Pavement Patching Problem You are the inspector on a section of two-lane road in Madison County. The contractor is performing pavement patching operations today and the pay items used for the patching are as follows: 44200108 Pavement Patching, Type II, 9 44200112 Pavement Patching, Type III, 9 Yesterday you laid out 3 patches in the northbound lane. The patch at Station 1246+52 is 12 wide by 8.0 long. The patch at Station 1247+23 is 12.0 wide by 9.0 long. The patch at Station 1247+79 is 12 wide by 11.0 long. After the patching operations for these 3 patches are complete, you measure the patches. The in-place dimensions are as follows: Station Width Length Depth 1246+52 12.0 8.0 9 1247+23 12.0 10.0 9.2 1247+79 12.0 11.0 11 You have received the required material inspection documentation. 1247+79 12 0 11 0 11 Workbook Page 17 Complete the attached field book entries and total the page for these items.

Workbook Page 18 & Tests

HMA SC Example (as specified by Engineer) Quantity Awarded = 229 Tons Plan Length = 1,022 FT Plan Width = 24 FT Plan Thickness = 1.5 inches Measured in field Length = 1,027.5 FT Width = 24 FT Thick = 1.5 inches 112 lbs/sy/in x 1027.5 x 24 x 1.5 = 230.2 2 tons 9 (2000) Workbook Page 19

HMA SC Example Adjusted Plan Quantity (Article 406.13) Gmb = 2.37 U = 112lbs/sy/in Constant = 46.8 C = 2.37 x 46.8 = 0.99 112 Adjusted Qty: 0.99 x 230.22 = 227.9 tons Max Pay: 227.9 x 1.03 = 234.7 tons Workbook Page 20

HMA Surface Daily Yield Check G mb = 2.360 Length = 10,110.0 ft Width = 24.0 ft Thickness = 1.5 inch Delivered tonnage 2310 Is the contractor exceeding the maximum specified amounts of quantity? Workbook Page 21