HOT, CHILLED, AND CONDENSING WATER PIPING SPECIALTIES (HVAC)

Similar documents
September 6, 2016 Page 1 of 5

SECTION VALVES, HANGERS, AND SPECIALTIES

SECTION STANDPIPE AND HOSE SYSTEMS

SECTION COMMON WORK RESULTS FOR FIRE SUPPRESSION

Design and Construction Standards SECTION HYDRONIC PIPING

SECTION HYDRONIC PIPING

SECTION HYDRONIC PIPING

Bid Opportunity PLUMBING SYSTEMS Section Installation of Boiler Heating Systems Page 1 of 7 Centennial Pool, 90 Sinclair

BASIC MATERIALS & METHODS

SECTION HYDRONIC PIPING

1.2 REFERENCES.1 American National Standards Institute (ANSI)/American Society of Mechanical Engineers (ASME)

This specification describes the minimum requirements for piping systems for the following service: Plant air systems operating up to 125 PSIG.

Iron Check Valves & Y-Strainers Illustrated Index

RESEARCH AND TECHNOLOGY BUILDING RENOVATION 05/18/09 SECTION DOMESTIC WATER PIPING SYSTEM

SECTION BASIC FIRE SUPPRESSION MATERIALS AND METHODS. A. Section includes pipe, fittings, valves, and connections for sprinkler systems.

1.2 REFERENCES.1 American National Standards Institute (ANSI)/American Society of Mechanical Engineers (ASME).

SECTION (15194) - FACILITY NATURAL-GAS PIPING

P A C K A G E R. Oil & Gas

ADDENDUM NUMBER 1 PARTICULARS 1.01 DATE: APRIL 6, 2018

SECTION (15194) - FACILITY NATURAL-GAS PIPING

SECTION PIPING SPECIALTIES FOR STEAM UTILITY DISTRIBUTION

PLUMBING. 1. New kitchen sinks and vanity sinks in residential units; new accessible showers and tubs in residential units and public showers.

SECTION of GENERAL. A. Description

SECTION PLUMBING PIPING

A. This Section includes the following general-duty valves: 1. Division 15 Section "Mechanical Identification" for valve tags and charts.

SECTION PLUMBING PIPING SYSTEM

SECTION CROSS CONNECTION CONTROL AND BACKFLOW PREVENTION

SECTION FACILITY POTABLE WATER DISTIBUTION

Design and Construction Standards SECTION POTABLE WATER SYSTEMS

PIPING SPECIALTIES (PLUMBING) A. American Society for Testing and Materials (ASTM):

Class 125S/200WOG Bronze Gate Valve Non-Rising Stem, Threaded Ends Testing: BS EN 12288, BS 5154, BS EN Working Pressure: PN16

Student Services & Classroom Addition. A. This Section includes the following domestic water piping specialties:

Code. 1) Code. Standard or Specification. Bolting

SECTION STEAM AND CONDENSATE HEATING PIPING

Combination Air Valves - Stainless Steel/ Sanitary Sewer/ For 2 Thru 12 Mains

A.Z.E. SUPPLY COMPANY

This specification, applies at any Vale locations indicated with approval on the cover page, with the following exceptions:

1071 Cast Steel Globe Steam Stop Valve (Flanged)

COMMERCIAL VALVES. When QUALITY, SERVICE and PRICE MATTER MOST! GATE VALVES GLOBE VALVES CHECK VALVES BUTTERFLY VALVES

University of Delaware

INDUSTRIAL VALVES PIPING PACKAGES VARIOUS EQUIPMENT

CATALOG C-IRR-0805 AHEAD OF THE FLOW. Irrigation Valves

CATALOG C-IRR-0805 AHEAD OF THE FLOW. Irrigation Valves

º to 150º F In accordance with this specification and

SPECIFICATIONS FOR PIPE FITTINGS VALVES FIRE HYDRANTS CITY OF ALLIANCE, OHIO. Alan Andreani, Ed. D. Mayor of Alliance

REVISIONS. App Thom. App Sud. App PC 2011/12/01 BM 2011/12/01 GS 2012/10/01. Pending BM 2011/12/01 GS 2012/10/01. Pending BN 2015/02/25

SECTION PLUMBING SYSTEMS

Gas Station & C Store SECTION CWM Job No

Brown University Revised August 3, 2012 Facilities Design & Construction Standards SECTION HVAC PIPES AND TUBES

East Central College

SECTION PLUMBING PIPING SYSTEMS

SECTION VALVES. This section includes materials, testing, and installation of manually operated valves.

CATALOG C-IRR-0805 AHEAD OF THE FLOW. Irrigation Valves

CATALOG C-IRR-0805 AHEAD OF THE FLOW. Irrigation Valves

1. Required Minimum Flow:

Copyright 2015 AIA MasterSpec Premium 09/15 PRODUCT MASTERSPEC LICENSED BY ARCOM TO CONBRACO, INC.

YARWAY HANCOCK CONTINUOUS BLOWDOWN GLOBE VALVE SERIES 5505

SECTION HYDRONIC PIPING

Mueller Steam Specialty started in the early 1900's in New

Table of Contents Scope of Design. Scope of Design Materials Dimensions & Weights Orifice Capacities

Specification for: Merck. Project: Caustic Tank. Elkton, VA. Title PIPING SPECIFICATIONS. Jacobs Project No. 63PZ0234. Client Number.

MUSC State Project Number H MUSC Thurmond Gazes Bldg Animal Area Chiller Replacement RMF Project Number B0 Addendum No.

SECTION PLUMBING FIXTURES

The City of Winnipeg Section Replacement of Boilers and Pool Water Heat Exchangers at Pan Am Pool Page 1

SECTION HYDRONIC PIPING

REVISIONS App PC. App Sud. App Thom 2011/10/26 GS 2012/10/01 BL 2011/10/26. Pending GS 2012/10/01 BL 2012/10/23. Pending MDF 2011/10/26 GS 2013/04/22

DIVISION 22 PLUMBING

The Master of Master Distribution

A. Pipe, pipe fittings, valves, and connections for piping systems. 1. Sanitary sewer. 2. Domestic water. 3. Storm water. 4. Gas.

Essex County College - West Essex Campus Addition And Renovations Dib # / SECTION DOMESTIC WATER PIPING SPECIALTIES

TARRANT COUNTY PURCHASING DEPARTMENT

SECTION PLUMBING SPECIALTIES

SECTION HYDRONIC PIPING

NORTHWESTERN UNIVERSITY PROJECT NAME JOB # ISSUED: 03/29/2017

SECTION HANDRAILS AND RAILINGS. A. Section Metal Fabrications: Associated metal supports.

C. ASSE 1013 Performance Requirements for Reduced Pressure Principle Backflow Preventers.

CW 3530 MANUAL IRRIGATION SYSTEM TABLE OF CONTENTS

ADDENDUM. Project: BYU-I Smith Building Chiller Replacement Project No.: Addendum No.: 1

SECTION PLUMBING PART 1 - GENERAL 1.01 RELATED DOCUMENTS

D-1 FIRE PROTECTION PRODUCTS TAPPING VALVE. MUELLER Tapping Valves. MUELLER Tapping Sleeves and Crosses. MUELLER Stainless Steel Tapping Sleeves

SECTION FIRE HYDRANTS

This specification describes the minimum requirements for piping systems for the following service:

SECTION NATURAL GAS DISTRIBUTION

Valves that bear the Hallmark of Quality

All our products Quality Assurance QUALITY Ensure quality control and it strive for the following:

General Service Butterfly Valves. Series 120, 140, 160, 300

SPECIFICATIONS FOR THE INSTALLATION OF REDUCED PRESSURE BACKFLOW PREVENTERS AND CONCRETE VAULTS FOR METERS 4 AND LARGER

CATALOG C-BFV-0518 AHEAD OF THE FLOW. Butterfly Valves

CHINO VALLEY FIRE DISTRICT FIRE PROTECTION STANDARD

NAVSEA STANDARD ITEM. 2.1 S9086-RJ-STM-010/CH-504, Pressure, Temperature and Other Mechanical and Electromechanical Measuring Instruments

SECTION PLUMBING EQUIPMENT AND SPECIALTIES

SUGGESTED SPECIFICATIONS Pump Frames through 64132

CHAPTER 4 PIPES. Prof. Dr. Uğur Atikol

SECTION GENERAL-DUTY VALVES FOR WATER-BASED FIRE-SUPPRESSION PIPING

Transcription:

SECTION 15432 HOT, CHILLED, AND CONDENSING WATER PIPING SPECIALTIES (HVAC) PART 1 GENERAL 1.01 SUMMARY A. Related Sections: 1. 15047 - Identification. 2. 15433 - HVAC Pumps. 3. 15555 - Horizontal Fire Tube Boilers. 4. 15835 - Unit Heaters. 1.02 SUBMITTALS A. Submit properly identified manufacturer's catalog cuts and technical data before starting work. 1.03 QUALITY ASSURANCE A. Testing: 1. Furnish pumps, gages, instruments, test equipment, and personnel required for performance of tests. Perform drainage of pipe systems and remove test equipment after testing has been successfully completed. a. Tests may be made of isolated portions of any piping system to facilitate general progress of the installation. b. Revisions made in a piping system after completion of a successful test shall require retesting of the affected portion of the piping system. c. Notification: As portions of the mechanical work are completed and readied for testing provide A/E at least 48 hours notice and perform the required tests under Contractor's supervision and in A/E's presence. d. Test piping systems, including piping fittings, accessories, and connections to hydrostatic or pneumatic pressure tests before performing painting, application of insulation, or concealment within the building. e. Test Description: 1) Subject systems to a hydrostatic or Project No. SPECIFICATION GUIDELINES 15432-1

pneumatic test pressure of not less than 1-1/2 times operating pressure, but not less than 150 psi, for not less than 2 hours, with no fluctuation in pressure. PART 2 PRODUCTS 2.01 EQUIPMENT 1. Valves: a. Gate Valves, 2 Inches or Less: 200 pound WSP, bronze, rising stem, solid wedge disc union bonnet renewable seats, hardened seat ring, screwed. 1) Manufacturers: Crane 428, Stockham B-107, or Kennedy 425. b. Gate Valves, 2-1/2" and 3 Inches: 125 pound WSP, bronze, bolted bonnet, flanges, ANSI B16.1. 1) Manufacturers: Crane 4437 or accepted c. Butterfly Valves, 4 Inches and Larger: 1) Type: Lug-wafer with the body circumference provided with lugs having tapped holes to accommodate cap-screw pipe flange bolting. 2) Body Construction Through 16 inches; Ferrosteel. 3) Lining: Rubber lined suitable for flow regulation and bubble tight shut-off service. 4) Wafer Valve: Buna-n line, or accepted 5) Operator: a) Screw type with hand wheel where valve is located less than 6 feet above finished floor. b) Chain operator assembly with indicating dial (cast-in marks on face) where valve is located six feet or more above finished floor. Crane or accepted d. Globe and Angle Valves, 2 Inches or less: 125 Project No. SPECIFICATION GUIDELINES 15432-2

pound WSP, bronze, rising stem, plug type disc renewable seats, screwed. Manufacturers Globe Angle Crane 14-1/2P 16-1/2P Stockham B-29 B-261 Kennedy 138PS 139S e. Check Valves: 1) 2 Inches or Less: 200 psi WOG, swing type, screwed, bronze construction, Y-Pattern Crane 37, Stockham B-319, or Kennedy 440. 2) 2-1/2" and 3 Inches: 200 psi WOG, swing type, iron body, flanges, bronze trim; Crane 373, Stockham G-931, or Kennedy 106. 3) 4 Inches and Larger: 175 psi WOG, quick closing globe type with completely guided disc top and bottom to insure against cocking out of position regardless of valve position when installed, Class "B" iron body, composition bronze seats and discs, silicon bronze guide pins and bushings, stainless steel springs. 4) Manufacturer: Mueller #105AP or accepted f. Balancing Valves: B. Piping Accessories: 1. Strainers: 1) Semi-steel, non-lubricated, eccentric type bodies with resilient faced plugs suitable for operation to 250 degrees F., complete with levers. 2) Bushings: Permanently lubricated top and bottom. 3) 2 Inches or Less: Threaded ends. 4) 2-1/2" and Larger: Flanged ends. 5) Manufacturers: Desurik Series 100 and 400 or Homestead. a. Construction: Iron body, Y-type, designed for not less than 125 psi WSP, with 20 mesh monel screen with a free area not less than 2-1/2 times the cross-sectional area of the connected piping. b. Design Flow Rate: Clean strainer shall not exceed 2 psi at the design flow rate. Project No. SPECIFICATION GUIDELINES 15432-3

c. Size: 1) 2-1/2" and Larger: Flanges. 2) 2 Inches or Less: Screwed ends. d. Drain Valve and Reducer: Furnish each strainer for use in equipment rooms and at each AHU with a drain valve and reducer to 3/4" hose thread, capped. e. Manufacturers: Crane or Mueller. 2. Air Vents: Provide accepted air vents at high points in chilled water systems, manual type unless otherwise indicated. 3. Gage Cocks: a. Screwed, bronze, tee handle. b. Manufacturers: Crane Company or Jenkins. 4. Pressure Reducing Valves: a. Brass body and brass working parts with built-in strainer, 125# S.W.P. b. Manufacturers: Bell and Gossett or Taco. 5. Water Gages: a. Polished, brass, designed for 175 pounds working pressure, with angle valves, guide rods, and drain cocks. b. Manufacturers: Crane Company #610 or Jenkins. 6. Straight Thermometers: a. Mercury filled, 9 inch scale "V" shaped, adjustable angle, separable socket well thermometers. b. Select thermometer range with operating temperature at midpoint of range. c. Manufacturers: American Instrument Company or Taylor Instrument Company. 7. Gages: a. Standard depth, cast aluminum alloy case, not less than 3-1/2" faces, with operating pressure at midpoint of range. b. Manufacturers: Ashcroft or Marshall Town. Project No. SPECIFICATION GUIDELINES 15432-4

8. Thermometer Wells: Provide thermometer wells at thermometer locations. a. Construction: Brass, with 2 inch insulation extension neck and with cap and chain. b. Provide tees in lines 3 inches or less for thermometer wells. c. Manufacturers: Marshall Town or Ashcroft. 9. Venturi Flow Meters: a. Provide with quick disconnect valves, safety shut-off valves, and metal identification tags on chain giving pipe size, Venturi series, station identification, and meter reading at specified flow rate at locations where shown on Construction Documents. b. Sizes: 1) 2-1/2" Through 8 Inches: Plated cast iron with slip on flanges. 2) 10 Inches and Above: Fabricated steel plate with welding ends. c. Venturi Size: Same as pipe size manufacturer. d. Manufacturers: Aeroquip-Barco or accepted 10. Prohibited Fittings: Bushings, elbows, tees, and reducers fabricated from pipe and tees and elbows fabricated by butt welding branch line to main. 11. Prohibited Connections: Threaded. PART 3 EXECUTION 3.01 INSPECTION A. Do not proceed with the work of this section until conditions detrimental to the proper and timely completion of the work have been corrected in an acceptable manner. 3.02 INSTALLATION A. Run horizontal piping level or pitch up toward the air vent connections. Make size reduction in horizontal piping with concentric or eccentric reducing fittings, except where specifically shown or noted. Project No. SPECIFICATION GUIDELINES 15432-5

3.03 FIELD QUALITY CONTROL A. Testing: 1. Furnish pumps, gages, instruments, test equipment, and personnel required for performance of tests, to perform drainage of pipe systems and remove test equipment after testing has been successfully been completed. a. Tests: Tests may be made of isolated portions of piping system to facilitate general progress of the installation. b. Revisions: Revisions made in the piping system after completion of a successful test shall require retesting of the affected portion of the piping system. c. Notification: As portions of the mechanical work are completed and readied for testing give the A/E at least 48 hours notice and perform the required tests in the A/E's presence and under Contractor's supervision. d. When to Perform Tests: Subject piping systems, including piping fittings and accessories, and connections to hydrostatic or pneumatic pressure tests before performing the work of painting, application of insulation or concealment within the building. e. Test Description: Subject systems to a hydrostatic or pneumatic test pressure of not less than 1-1/2 times operating pressure, but not less than 150 psi, for not less than 2 hours, with no fluctuation in the pressure. 3.04 ADJUSTING AND CLEANING A. Thoroughly clean hot water piping system with a solution of 1 of the following: 1. Trisodium Phosphate: 1 pound for each 50 gallons in the system. 2. Sodium Carbonate: 1 pound for each 30 gallons in the system. 3. Sodium Hydroxide: 1 pound for each 50 gallons in the system. B. Cleaning Requirements: 1. Obtain approval by A/E of proposed sampling and testing procedures before proceeding with tests. Project No. SPECIFICATION GUIDELINES 15432-6

a. Fill and circulate each piping system tested for a period of eight hours, allowing temperatures to reach the design level for a minimum of 4 hours and then test a sample of water from the system with Hydrion paper, indicating a PH of 7 or higher. b. Add additional cleaning solution, if necessary, to obtain a PH reading of between 7 and 8. END OF SECTION Project No. SPECIFICATION GUIDELINES 15432-7