ISSUES & RISKS Potential timing and coordination with a future system planning process Coordination with jurisdictions and partner transit agencies

C-01c: Downtown Seattle to Ballard (Market Street vicinity) LRT, primarily elevated/tunnel options

Future System Planning (ST4)

FINAL. Sound Transit Long-Range Plan Update Issue Paper S.6: Potential Tacoma Link Extension - East. Prepared for: Sound Transit

Assessment of Current Status, Plans, and Preliminary Alternatives for High Capacity Transportation in the I-5 Corridor

Progress Report Sounder Program

Progress Report Sounder Program

Progress Report Sounder Program

Progress Report Sounder Program

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 945

Progress Report Sounder Program

May 24, 2007 Board Meeting. Making Connections Sound Transit 2 The Regional Transit System Plan For Central Puget Sound

CENTRAL PUGET SOUND REGIONAL TRANSIT AUTHORITY GREEN BONDS

SOUND TRANSIT RESOLUTION NO. R Adoption of 1999 Regional Express Bus Service Plan BACKGROUND AND COMMENTS

Sound Transit Long-Range Plan Update/SEIS Agency Scoping Meeting. November 8, 2013

Making Connections Sound Transit 2 The Regional Transit System Plan For Central Puget Sound

1.1 Purpose of the Project

Environmental Scoping Information Report

APPENDIX N East King County Subarea High Capacity Transit (HCT) Analysis: Approach to Assessing System-Level Alternatives

2004 FEASIBILITY STUDY UPDATE

Central Puget Sound Regional Transit Authority

Tacoma Link Stakeholder Group

12 Evaluation of Alternatives

Transit Oriented Development Study

Sound Transit is updating its Regional Transit Long-Range Plan, which

Updating Sound Transit s Long-Range Plan. ITE November 12, 2013

A RESOLUTION of the Board of the Central Puget Sound Regional Transit Authority adopting a revised Sound Transit 2 Regional Transit System Plan.

Ann Arbor Station Environmental Review. Public Information Meetings April 2, 2014

MULTI-MODAL TRANSPORTATION SYSTEM

APPENDIX A - PLANS AND POLICY REVIEW FEBRUARY 2017

SOUTHWEST LRT (METRO GREEN LINE EXTENSION)

Lynnwood Link Extension 2013 Draft EIS Comments and Responses. Page 216

Section 7 Environmental Constraints

Appendix A Transportation Technical Analysis Methodology

Transportation and Utilities

Recommend to Board. Final Action

3. STATION SPACING AND SITING GUIDELINES

The Regional Transportation Plan Appendix K. System Performance Report. Puget Sound Regional Council. May 2018

RURAL CENTER COMMUNITY ROLE COUNCIL ROLE RURAL CENTER ALL COMMUNITIES

Lynnwood Link Extension 2013 Draft EIS Comments and Responses

Chapter 5 Transportation Draft

Sound Transit Transit-Oriented Development (TOD) Policy

PSRC Funding Application

Priorities are for AG comment at today's meeting. Four time frames proposed for implementation

REPORT TO THE CITY COUNCIL rd Avenue NE, Woodinville, WA

King of Prussia Rail Project Frequently Asked Questions - Archive Version: Summer 2018

Summary of transportation-related goals and objectives from existing regional plans

SUBURBAN EDGE COMMUNITY ROLE COUNCIL ROLE ALL COMMUNITIES SUBURBAN EDGE

CENTRAL AND EAST CORRIDORS

Metro Blue Line Improvements & Project Update

The Policies section will also provide guidance and short range policies in order to accomplish the goals and objectives.

Midtown Corridor Alternatives Analysis. Technical Advisory Committee Meeting November 15, 2012

West Seattle and Ballard Link Extensions. Stakeholder Advisory Group March 14, 2018

Site Criteria Evaluation Matrix

Chicago Transit Authority Orange Line Alternatives Analysis Study

High-Speed Rail - Chicago to St. Louis Alton Regional Multimodal Transportation Center Project

Phoenixville Passenger Rail Demonstration Project

3 Documentation of Alternatives

Offering Memorandum SUMNER OFFICE AND WAREHOUSE Fryar Ave Sumner, WA. Exclusively offered by Paragon Real Estate Advisors

TRANSIT ACCESS CHECKLIST 1

Revenues and expenditures increase based on the tax district increase due to increases in real estate assessments in CY 2016 compared to CY 2015.

Chapter 4. Recommendations

Progress Report Regional Express & Bus Rapid Transit Program

3.0 REVIEW OF PREVIOUS STUDIES

Sound Transit 3: The Regional Transit System Plan

Pierce Transit / DKS. 10 Years of TSP Evolution and Lessons Learned

AIR QUALITY AND CLIMATE CHANGE EVALUATION GUIDANCE

Columbia Pike Transit Initiative

VRE Gainesville-Haymarket Alternatives Analysis Report

Transportation 2040 Toward a Sustainable Transportation System. Toward a Sustainable Transportation System. Sultan Planning Board.

Peninsula Corridor Electrification Project. Draft Environmental Impact Report

DRAFT ENVIRONMENTAL IMPACT STATEMENT FOR HOUSTON DALLAS HIGH SPEED RAIL (TEXAS CENTRAL)

GULF COAST RAIL DISTRICT VISION FOR REGIONAL RAIL

CHAPTER 3.0 CIRCULATION ELEMENT

Neal Campbell (WSDOT) Mike Dahlem (City of Sumner) Kirk Wilcox (Parametrix)

Texas A&M Transportation Short Course

FEDERAL HIGHWAY ADMINISTRATION RECORD OF DECISION FOR THE LYNNWOOD LINK EXTENSION

1. Evaluation of route and service alternatives; 2. Tier 1 Environmental Impact Analysis; and 3. Service Development Plan.

Chapter 5 - Transportation

MEETING: DATE: TYPE OF ACTION: STAFF CONTACT: PHONE: Recommend to Board. Final Action

CHAPTER 5: TRANSPORTATION

Table of Contents. Green Line Extension Project. Draft Environmental Impact Report/Environmental Assessment and Draft Section 4(f) Evaluation

Stockton Freight & Passenger Rail Mobility Enhancement

Vanasse Hangen Brustlin, Inc. DRAFT. Appendices. MIS Appendices

METRA UP-W LINE. Locally Preferred Alternative Report

GMA Periodic Update Policy/Text Requirements

AREAWIDE BRIDGE REPLACEMENT AND REHABILITATION

MEMORANDUM #4. DATE: November 4, Warrenton TSP Project Management Team. Ray Delahanty, AICP, DKS Associates Kate Petak, EIT, DKS Associates

Issue Paper on Regional Land Use and Transit Planning (Draft)

Corridor Advisory Group and Task Force Meeting #2

CHAPTER 8 TRANSPORTATION ELEMENT

Executive Summary and Staff Recommendation

MONITORING IMPLEMENTATION AND PERFORMANCE

Transcription:

Subarea South King/Pierce Primary Mode Commuter Rail Facility Type Infrastructure Improvement Length Date Last Modified July 1, 2016 PROJECT AREA AND REP RESENTATIVE ALIGNMENT SHORT PROJECT DESCRIPTION This project would establish a program of capital elements that would be used to improve South Sounder access, capacity, and services in response to increases in demand. Program elements could include platform extensions, track and signal upgrades and other related infrastructure to facilitate additional capacity, and access elements such as improvements for pedestrians, bicyclists, buses, and private vehicles, prioritized per Sound Transit s System Access Policy. Note: The elements included in this representative project will be refined during future phases of project development and are subject to change. REGIONAL LIGHT RAIL SPINE Does this project help complete the light rail spine? CAPITAL COST Cost in Millions of 2014 $ RIDERSHIP 2040 daily project riders PROJECT ELEMENTS KEY ATTRIBUTES No $934 TBD subject to further analysis Capital investments to improve South Sounder access, capacity, and services may include, but are not limited to: Platform extensions to accommodate 10-car train sets which include: o Extend boarding platforms at existing Sounder stations to accommodate 10-car train lengths o Platforms will be extended by up to 255 feet at all stations, where necessary o Relocate Kent Station platform features to prevent blockage of nearby street(s) during boarding/deboarding o Extension of the Auburn platform to accommodate 10-car train sets only on the west side. East side platform will be extended to accommodate 8-car train sets only. o Modifications, where needed, to allow platform extensions such as signals, sidewalks, relocation of existing platform elements, signage, and illumination o Raise existing platforms to height closer to level boarding o Special traffic control to address confined site and working near active railroad Acquisition of additional fleet System access improvements such as: o Pedestrian improvements within one-quarter mile of the stations o Bicycle storage infrastructure for station users, and bicycle access improvements within one-half mile of the stations o Transit speed and reliability improvements on routes connecting to the stations Page 1 of 6

KEY ATTRIBUTES PROJECT ELEMENTS o Off-site parking along bus routes with frequent connections to South Sounder stations during peak periods o Expanded or new drop off/pick up areas at the stations o Additional bus/transfer facilities at the stations o Expanded parking capacity o Non-motorized access facilities (bicycle/pedestrian, including bicycle storage) (See separate document titled Common Project Elements ) Elements to support potential expanded service levels, which would be determined by the ST Board in collaboration with partner agencies and organizations, could include, but not be limited to: o Acquisition of operating rights and real property rights o Related track and signal improvements between Tacoma and Seattle o Up to 3 Sounder stations modified at platforms to accommodate additional train volumes o Replacement of gated signal crossings as needed o Roadway improvements associated with track 1 percent for art per Sound Transit policy NOT INCLUDED Extensions to Tacoma Dome Station platforms Stormwater requirements for leased temporary stalls Payments to jurisdictions for use of existing jurisdiction-owned parking stalls for temporary parking during construction Retail uses in new structures; transit-oriented development Track improvements funded by ST2 See separate document titled Common Project Elements ISSUES & RISKS Determination by FRA, FTA, and BNSF (for platforms on BNSF ROW) regarding retrofit of existing platforms to height closer to level boarding for ADA access Auburn Station may have significant challenges to construct platform extension due to the Stampede Pass rail junction immediately south of the existing station The extension to 10 car platforms may not be possible at all stations, requiring passengers to de-board through adjoining rail cars (Auburn, and potentially new stations in Tillicum and DuPont) The overall station area development agreements with jurisdictions, King County Metro, and/or BNSF may need to be amended Poor soil conditions are present in the study area and hazardous materials remediation may be required Special traffic control to address confined site and working near an active rail line Future freight and other passenger rail trains on the BNSF corridor between Tacoma and Seattle Agreement(s) with BNSF to operate Sounder service at certain levels would be necessary and could be affected by expectations of future freight markets and operations BNSF agreement will be needed to construct necessary improvements or to purchase necessary real property and operating rights Page 2 of 6

Sound Transit developed a conceptual scope of work for this project for the purpose of generating a representative range of costs, both capital and operating; and benefits, including ridership forecasts, TOD potential, multi-modal access and others. This information was developed to assist the Sound Transit Board as it developed the ST3 system plan, including phasing of investments and financial plan, for voter consideration. Final decisions on project elements (e.g., alignment, profile, station locations, and number of parking stalls) will be determined after completion of system planning, project level environmental review, and preliminary engineering during which additional opportunities for public participation will be provided. Therefore, this scope definition should not be construed as a commitment that all representative features will be included in the final developed project. Long Description: This project will establish a program of capital elements that would be used to improve South Sounder access, capacity, and services. Elements of the project may include, but are not limited to, expanding existing south Sounder station platforms to accommodate 10-car train sets, planning and implementation of investments to improve access to the South Sounder train stations, including improvements for pedestrians, bicyclists, buses, and private vehicles, expanding Seattle-Tacoma-Lakewood Sounder service beyond current service levels. Funds included for system access improvements would be prioritized per Sound Transit s System Access Policy. Track improvements for the purpose of accommodating additional service will also be implemented. Track improvements may include elements such as additional main line track, turnouts, gated signals, station platform rebuilds, and associated roadway improvements. Assumptions: Extended platforms at King Street, Tukwila, Kent, Puyallup, Sumner, South Tacoma, and Lakewood to accommodate 10-car train sets Tacoma Dome platform extension would occur as part of the Tacoma Trestle Track and Signal and Amtrak Station relocation projects Costs associated with extending the existing platform one car length and raising it from its current height (8 inches above top of rail) to approximately 15 inches above top of rail and constructing an extension at the same height; platform heights will be determined through coordination with FRA, FTA, and BNSF The Auburn station platform would be extended to accommodate 8-car trains only on the east side due to physical constraints from the Stampede Pass freight rail spur to the west, SR 18 highway columns, and West Main Street intersection. It is anticipated that a 10-car train platform extension would be feasible to construct and operate on the west side. New platforms at the Tillicum and DuPont stations would be constructed to accommodate up to 10-car trains (See separate document titled Sounder Extension to DuPont ). Should this not be feasible at one or both stations, it is anticipated that 10-car trains would still serve them, but operationally, doors on some cars would not open for passenger loading and unloading System operation requires placement of a mini-high for ADA passenger access at the same car location at every station Sounder platform function would remain open during the construction period and users will be protected during construction Additional yard storage to accommodate 10-car train sets Construction of access improvements should be phased to maintain operation of the stations, including alternate routing of Metro, Pierce Transit, and ST buses Special traffic control during construction of access improvements to address confined sites and working near an active railroad Potential track improvements along sections of the corridor from Bay Street/TR Junction in Tacoma to King Street Station in Seattle Track improvements from Ellingson Road in Auburn to S 277 th Street in Kent were included as part of ST2, and are excluded Track improvements from James Street in Kent to Black River in Seattle were included as part of ST2, and are excluded For non-motorized station access allowances, the Tacoma Dome Station is categorized as an Urban station and an Intermodal Transit Center, the Tukwila station is categorized as a Suburban station and an Intermodal Transit Center, the Auburn station is categorized as an Urban station, and all other stations are categorized as Suburban stations Environmental: Sound Transit will complete project-level state and federal environmental reviews as necessary; provide mitigation for significant impacts; obtain and meet the conditions of all required permits and approvals; and strive to exceed compliance and continually improve its environmental performance. Utilities: Utility relocation as needed to complete the project, including fiber optics, sewer, water, overhead electric/communications, etc. Right-of-Way and Property Acquisition: BNSF agreement and possible local jurisdiction agreements for right-of-way use Purchase of nearby properties for new parking facilities and/or other access improvements Costs associated with obtaining waiver(s) of jurisdictions zoning requirements related to height of parking structures and inclusion of other uses in parking structures, such as street-level retail Page 3 of 6

Potential Permits/Approvals Needed: Building permits: Electrical, Mechanical, Plumbing Utility connection permits Construction-related permits (clearing and grading, stormwater management, street use, haul routes, use of city right-of-way) Land use approvals (Conditional use, design review, site plans, Comprehensive Plan or development code consistency, Special Use Permits) BNSF All required local, state, and federal environmental permits NEPA/SEPA and related regulations Project Dependencies: BNSF agreement needed to permit construction Tacoma Trestle project and Point Defiance Bypass project completion Determination by FRA, FTA, and BNSF regarding retrofit of existing platforms Amendments may be required to existing agreements with the jurisdictions, BNSF, King County Metro and/or Pierce Transit to facilitate construction Sound Transit will need to acquire real property and operating rights from BNSF. Potential Project Partners: WSDOT Amtrak BNSF Cities of Lakewood, Tacoma, Puyallup, Sumner, Auburn, Kent, Tukwila, Seattle FTA FRA Transit Partners Also Serving Project: King County Metro, Pierce Transit Page 4 of 6

Cost: Sound Transit developed a conceptual scope of work for this project for the purpose of generating a representative range of costs, both capital and operating; and benefits, including ridership forecasts, TOD potential, multi-modal access and others. This information was developed to assist the Sound Transit Board as it developed the ST3 system plan, including phasing of investments and financial plan, for voter consideration. Final decisions on project elements (e.g., alignment, profile, station locations, and number of parking stalls) will be determined after completion of system planning, project level environmental review, and preliminary engineering during which additional opportunities for public participation will be provided. Therefore, this scope definition should not be construed as a commitment that all representative features will be included in the final developed project. In Millions of 2014$ ITEM COST Agency Administration Preliminary Engineering & Environmental Review Final Design & Specifications Property Acquisition & Permits Construction Construction Management Third Parties* Vehicles Contingency Total $934 Design Basis: Conceptual *Permitting and Startup costs included Page 5 of 6

Evaluation Measures: MEASURE MEASUREMENT/RATING NOTES Regional Light Rail Spine Does project help complete regional light rail spine? No Ridership 2040 daily project riders Capital Cost Cost in Millions of 2014 $ Annual O&M Cost Cost in Millions of 2014 $ Travel Time In-vehicle travel time along the project (segment) Reliability Quantitative/qualitative assessment of alignment/route in exclusive right-of-way System Integration Qualitative assessment of issues and effects related to connections to existing local bus service and potential future integration opportunities Ease of Non-motorized Access Qualitative assessment of issues and effects related to non-motorized modes TBD subject to additional analysis $934 TBD subject to additional analysis TBD subject to additional analysis Medium-High Some at grade crossings Percent of Non-motorized Access Percentage of daily boardings Connections to PSRC-designated Regional Centers Number of PSRC-designated regional growth and manufacturing/industrial centers served Land Use and Development/TOD Potential Quantitative/qualitative assessment of adopted Plans & Policies and zoning compatible with transit-supportive development within 0.5 mile of potential stations Qualitative assessment of real estate market support for development within 1 mile of potential corridor Density of activity units (population and employment for 2014 and 2040) within 0.5 mile of potential stations 10 centers Manufacturing and Industrial Centers: Kent, North Tukwila and Port of Tacoma Regional Growth Centers: Auburn, Kent, Lakewood, Puyallup Downtown, Seattle CBD, Tacoma Downtown and Tukwila Socioeconomic Benefits Existing minority / low-income populations within 0.5 mile of potential stations 2014 and 2040 population within 0.5 mile of potential stations 2014 and 2040 employment within 0.5 mile of potential stations For additional information on evaluation measures, see http://soundtransit3.org/document-library Page 6 of 6