Reducing Hospital Energy Use and Maintaining Savings. Glen Anderson, PE

Similar documents
RETRO-COMMISSIONING: AN OWNER S LOOK AT THE TRUE COSTS AND RETURN ON INVESTMENT. Adam Renzi, PE

Monitoring-Based Commissioning: A Case Study in Higher Education. Janelle H. Griffin, PE, CCP, LEED AP

Strategies for Persistence: Measurement and Verification. Ryan Hughes PE, CEM, LEED AP Eaton Energy Solutions

Building Control Strategies That Work to Improve Your Energy Bottom Line

BUILD. CONNECT. ACHIEVE.

Wireless Pneumatic Thermostats:

Karl Helmink, P.E., CEM Retrocommissioning Manager University of Illinois. Retrocommissioning Saving the Planet One Building at a Time

How LEED & The Retro-Commissioning Credits Produce Energy Savings. James Vallort Vice President Environmental Systems Design, Inc.

Existing Building Cx: Processes & Results A Cultural Journey. Barry Abramson Senior Vice President Servidyne

City of Fort Collins Building Automation Systems Enhances Savings and Commissioning Efficiency Works Training

Retro-Commissioning in Hospitals

Monitoring-Based Commissioning (MBCx) Plan Template

Performance Monitoring for Efficiency

Seminar 4 Energy Performance of Active Chilled Beam Installations

Energy Reduction in Hospitals

George Bourassa, National Director, Commissioning Services Robert Bucey, Program Manager RETRO-COMMISSIONING

NEBBinar: Retro-Commissioning for Comfort and Energy Efficiency. August 21, 2013

9/13/2011. Mark Hanicits, Director of Facilities and Safety, MetroSouth Medical Center. Terry Malloy P.E., Cxa, Project Manager, Teng & Associates

Use of Building Automation Systems for (Retro)Commissioning

Optimizing BAS Information for Operator Effectiveness and Optimal Control

MBCx: The Next Wave of Energy Savings in Utility Incentive Programs

Optimizing Energy Use in a HealthCare Setting. Michael P. Della Barba Environmental Health & Engineering, Director of Commissioning

Retrocommissioning Investigation Report

UCSF Mission Bay Campus Arthur and Toni Rembe Rock Hall th Street San Francisco, California

Retro-Commissioning for Existing Facilities

Converting CAV to VAV in Florida: What does this really mean?

Identify and Quantify Mission-Critical Factors (How to Perform a Critical Audit) Neil Maldeis, Energy Solutions Engineering Leader, Trane

Project Information. Measure Description

Energy Efficiency Opportunities in the OR

Large Campus Chilled Water System RetroCx

Xavier University of Louisiana

The Ed Roberts Campus

Case Study for Fortune 500 Telecom: Retrofitting Pneumatic Controls for Energy Efficiency

Getting Started with Your First Project: Considering Rules

ASHRAE Standard : Ventilation Rate Procedure

SMART HVAC & LIGHTING SYSTEMS. Savings From Two Major C&I End Uses

how to read an energy model

EBCx of the Connecticut Convention Center Complex

Introduction to Building Analytics

Building Operator Certification Level I

Optimizing Chilled Water Systems for Energy Efficiency and Occupant Comfort

Steve Harrell, LEED AP, CEM, CxA SSRCx Dr. David Claridge, P.E. Energy Systems Lab, Texas A&M University

Teague Research Center

Mechanical Technical Report Three Mechanical Systems Existing Conditions Evaluation

Opening a New Hospital: A Case Study Healthcare Commissioning and the Authority Having Jurisdiction

LEED Commissioning and Actual Energy Use. John Kokko, P.Eng. LEED A.P. Vice President Enermodal Engineering

Xavier Energy Initiative

Monitoring-Based Commissioning Best Practices Award Welch Hall

D DAVID PUBLISHING. Optimizing Thermal Energy Storage Systems in the Hospitality Industry. 1. Introduction

PECI s RCx Programs: The Next Generation. Michelle Lichtenfels Program Manager PECI

Management Committee December 3, Johnson County Community College Retrocommissioning Report

CONTINUOUS COMMISSIONING OF SALT LAKE COMMUNITY COLLEGE SOUTH CITY CAMPUS

Retrocommissioning Investigation Study of the Sheraton Chicago Hotel

Air-Water Systems. Chilled Ceilings and Beams TROX USA. Principle of Operation. Radiant Effect on Occupants. Early 1980 s. Chilled Ceiling Panels

Building Commissioning, Energy Efficiency & Building Automation Systems

June 4, 2009 Dave Moser, PE, Senior Engineer Portland Energy Conservation, Inc.

Energy Management Journey

South Carolina Society for Hospital Engineers


Building Controls Strategies Conference. Retro-Commissioning with BAS Overview. 10 March Steve Brown, CAP ESD Controls Team Leader

Existing Building Commissioning (or Retro-Commissioning)

Fundamentals of Test & Balance for Engineers, Cx & Energy Providers Course Number: CXENERGY1619

Figure 26.5 Potential fan energy savings using fan speed limiting 16.

Retro-Commissioning for Energy Efficiency

DABO TM : A BEMS ASSISTED ON-GOING COMMISSIONING TOOL

Paul Ehrlich, PE Ira Goldschmidt, PE

MN/CO Xcel Energy Recommissioning Program

Technical Development Program

Retrocommissioning: A Persistence Study

Cost Savings from Operational Energy Efficiency: A Case Study from WCSU. Tom Arnold Vice President, Energy Efficiency & Carbon Solutions

Characteristics of Energy Consumption by building type of a U.S. Navy Installation in Hot and Humid Climate

Comparison of Air Distribution Systems

Energy Modeling Tools Solutions for Creating an Intelligent Building

Practical M&V for Recommissioning Projects

Acutherm was spec d here. Building Automation Guide for Therma-Fuser Systems

AN INNOVATIVE DEDICATED OUTDOOR AIR APPLICATION FOR A GOVERNMENT OFFICE TOWER. MICHAEL HALLENBECK, PE, CEM Southland Industries

Commercial Building Performance Evaluation System for HVAC Diagnostics and Commissioning

Smart Labs: Building Next Generation Labs While Maintaining Safety and Comfort

INCENTIVE ESTIMATOR HVAC USER GUIDE CONTENTS FLORIDA CUSTOM INCENTIVE PROGRAM

Performance of Ductless Heat Pumps in the Northeast

Three Case Studies of the Application of Energy Systems Optimization Best Practices for Automatic Demand Response

B. OPR, BoD, and BoD-HVAC documentation prepared by Owner and Architect contains requirements that apply to this Section.

An Evaluation of ComEd s Retro- Commissioning Program

Coach House: Hunziker Hall:

Incorporating Uncertainty Analysis into a Building Retrofit Analysis Using OpenStudio and EnergyPlus

ANALYSIS OF THE POTENTIAL ENERGY SAVINGS FOR 14 OFFICE BUILDINGS WITH VAV SYSTEMS

WHOLE BUILDING RETROFITS: A CONTRACTOR/SUPPLIER DEMONSTRATION

5/7/2012. Agenda. What is High Performance? Ensuring a Successful Transition to Sustainable, High-Performance Operations

Chilled Beams. The new system of choice?

Level 1 Modules tdp-101 hvac industry overview tdp-103 concepts of air conditioning tdp-102 abcs of comfort

Recommended Methods to Evaluate Performance of Variable Air Volume Fume Hood Systems

Building Retro-Commissioning

Georgetown University New Science Center

Continuous Commissioning Leading Energy Project Process - An Industry Approach

Mission Critical Commissioning for Healthcare Facilities

ORIGINAL YEAR OF CONSTRUCTION NUMBER OF BUILDING STORIES 02/06/2013 BUILDING SURVEY DATE

Implementing Smart Hospital Systems. Adam R. Bare, PE, LEED APBD+C Stanton Stafford, PE, LEED APBD+C Donald L. Walker, PE, RCDD

Energy & Climate Action

Hourly Analysis Program v.4.1 Page 1 of 1

2-Pipe fan coil terminal units were selected as the parallel system to handle the remaining sensible cooling load.

Transcription:

Reducing Hospital Energy Use and Maintaining Savings Glen Anderson, PE

AIA Quality Assurance The Building Commissioning Association is a Registered Provider with The American Institute of Architects Continuing Education Systems (AIA/CES). Credit(s) earned on completion of this program will be reported to AIA/CES for AIA members. Certificates of the Completion for both AIA members and non-aia members are available upon request. This program is registered with AIA/CES for continuing professional education. As such, it does not include content that may be deemed or construed to be an approval or endorsement by the AIA of any material of construction or any method or manner of handling, using, distributing, or dealing in any material or product. Questions related to specific materials, methods, and services will be addressed at the conclusion of this presentation. 2

Learning Objectives 1. Identify the tools required for successful monitoring based commissioning 2. Differentiate between existing BAS capabilities and MBCx 3

Retro-Commissioning Measure Examples Major Equipment AHU economizers AHU valves AHU humidifier controls Chiller plant staging Heating plant staging Low flow cooling towers Terminal Equipment Space scheduling Occupancy sensors Repair dampers, valves, airflow stations Temperature settings Minimum airflow requirements 4

Space Scheduling When the space is unoccupied: Decrease the minimum airflow set point to 0 CFM Increase the cooling set point by 1-2F Decrease the heating set point by 1-2F Airflow will increase, if necessary, to maintain space conditioning When space is occupied, not much warm-up or cool-down will be needed If an occupant enters at night, the room will still be conditioned 5

VAV Scheduling Impact on AHU $5,600 savings just in fan power 6

Changing from CV to VAV Fan Impact 50% fan power savings = 75 kw 7

Occupancy Sensors Conference Room Conference Room VAV Box $7,925 savings per year! Occupied Air Flow Unoccupied Air Flow 8

Unoccupied Zones Overcooled as CV cooling-only box Minimal airflow maintains 72F space temp 9

Drift Following ReCx 10

Gateway MC - Monthly Electric Use Electric Use, kilowatt hours 2,000,000 1,800,000 1,600,000 1,400,000 1,200,000 1,000,000 800,000 600,000 400,000 200,000 0 2011 Energy (kwh) 2012 Energy (kwh) 2013 Energy (kwh) 2014 Energy (kwh) 2015 Energy (kwh) 11

ReCx Begins Drift Begins MBCx Begins Complete Deeper Dive 12

Complete ReCx Drift Begins 13

Complete ReCx Drift Begins 14

ReCx vs MBCx 15

Causes of Drift Operator overrides to address facility issues Balancers overriding AHU dampers during testing Valve and damper failures 16

Chilled Water Plant Override dp raised to 60 psi increases pump power by 100 kw 17

Dual Duct Air Handler Hot duct manual damper closed preventing pressure measurement (damage cold ductwork) 18

Monitoring-based Commissioning (MBCx) Platform Trend Viewer Automated Diagnostics, Fault Detection and Diagnostics many names being used Predictive Maintenance Measurement of Performance Workflow management Service Continuous Engagement Advantages Sustained Savings Identify new opportunities 19

Hospital Example Return on Investment Annual Savings $449,000 4,770,000 kwh 13,600 dtherms ROI: 225% 20

Trend Viewer 21

Hot Water Valve Leak 22

Chiller Cycling 23

Fault Detection / Predictive Maintenance 24

CHW Valve Leak Chilled water valve has failed open, over cooling SA Fault reported 25

MBCx Economizer Fix 26

When to Change Air Filters Looking for the inflection point Balancing filter change costs, energy costs, and occupant air quality 27

Filter Loading Airflow vs speed relationship drops indicating filters loading Filters replaced 28

Terminal Unit Reports Allow priority of maintenance Comfort Ventilation requirements Energy use 29

VAV Boxes not Flowing Properly 30

Notification of Faults - Email 31

Notification of Faults - Email 32

Notification of Faults (Software Interface) 33

Measurement of Performance 34

Model Baseline Energy Use Using Regression Collect historical weather and power consumption data for a period of months or years; best if hourly Use regression to relate weather-related variables to power consumption; for example, to relate temperature and humidity to kw A good regression model will have an R-squared value close to 1; this would mean that for every temperature and humidity you can use the regression equation to reliably predict power consumption Temperature Humidity kw 35

Model Baseline Using Weather Data Chiller Plant Modeled Power Use Power (kw) kw = f(temp, humidity) March Date Nov 36

Actual Performance Relative to Baseline Chiller Plant Modeled (Yellow) vs. Actual (Blue) Power Use Started Started Work Work Saved Power Power (kw) March Date Nov 37

Visualize Monthly kwh Savings Compare actual to baseline power use for each month Show kwh saved each month Show cumulative kwh saved over time 38

Workflow Management 39

Workflow Overview 40

Workflow Discussions 41

Reporting Results 42

KPI Analysis 43

Thunderbird Results Chiller plant project Fault Detection Deployed Energy Projects MBCx $800,000/year delivered (> 20% savings) 44

What Next? Chilled Water System differential pressure driven by elevator room cooling Replace fan coil with water source heat pump Modify outdoor air intakes to not draw in relief air Re-calculate minimum airflows for VAV boxes operating as constant volume boxes Reduce minimum outside air requirements for specific AHUs Standardize temperature settings in hospital 45

Identifying Opportunities and Testing Solutions 46

Controlling VAV Parameters VAV t-stats: Setting ±2F deadbands on temp set points and limiting set point range to 70 to 78F 47

Reduce Outdoor Air When Hot With outside temp = 110F, bringing in 35% to 67% outside air 48

Effective Airside Economizers OA intake draws in relief air, preventing effective economizing Relief air directed away from OA intake. MAT tracks OAT reducing cooling load Tested with cardboard will complete permanent solution on 15 AHUs 49

Questions? 50

Glen Anderson, PE ganderson@etcgrp.com