Tilikum Crossing Transit Bridge. Portland, OR

Similar documents
Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Ironton Russell Bridge Project

Bonner Bridge Replacement Update:

Ironton Russell Bridge Project

John James Audubon Bridge

The Chief Estimator Software. Item Cost Summary Bridge & Overpass Projects

PROJECT UPDATE SOUTH NORFOLK JORDAN BRIDGE CITIES OF PORTSMOUTH AND CHESAPEAKE, VIRGINIA. April 2012

Strengthened Bascule Piers for the Newly Rehabilitated Bridge of Lions

Design and Construction of the SH58 Ramp A Flyover Bridge over IH70. Gregg A. Reese, PE, CE, Summit Engineering Group, Inc.

Willamette River Transit Bridge. Portland - Milwaukie Light Rail Willamette River Bridge WRBAC

John James Audubon Bridge. Introduction

IMUA ANNUAL PRESENTATION 2013

AREMA 2008 Annual Conference. LOW PROFILE RAILROAD BRIDGE Steve K. Jacobsen, PE NNW, Inc. Rochester, Minnesota

Sweet Creek Road Retaining Wall Replacement. Mapleton, OR

Modjeski and Masters, Inc. Consulting Engineers 04/18/06 St. Croix River Bridge 3D Analysis Report Introduction

2. Outline of the bridge 3-span continuous deck extradosed bridge Bridge length

Presented by: Taya Retterer BRG Webinar July 30, 2012

PHASING CONSIDERATIONS FOR BRIDGES

ABRAHAM LINCOLN BRIDGE

Long Railway Viaducts with Special Spans: Part-1. Arch Construction by Balanced Cantilever with Auxiliary Cables

Lesner Bridge Replacement

2016 ACEC/PA ANNUAL MEETING

City of Mesquite General Design Standards Revision Date:

Sandy High School. Sandy, OR

APPENDIX G WHITTIER BRIDGE TYPE STUDY EVALUATION OF BRIDGE ALTERNATIVES

Introduction.» Demolition Concepts» Concept Design» Final Design» Construction» Health Monitoring

Dan Carrier Parsons Brinckerhoff Project Manager Cooper River Bridge Charleston, South Carolina

Progressive Erection Applied to Box Girder with Strutted Wing Slab

BUILDING THE MERSEY GATEWAY a step by step guide

VIADUCTS BY PUSHING: INCREMENTALLY LAUNCHED BRIDGES

St. Anthony Falls I-35W Bridge Replacement. ASHE National Conference June 13, Dustin Thomas, P.E. I-35W Bridge Construction Engineer

Construction of the Nhat Tan Bridge (Vietnam-Japan Friendship Bridge)

GEOMETRY CONTROL OF PRECAST SEGMENTAL BALANCED CANTILEVER BRIDGES ON THE HUNTER EXPRESSWAY

Special Considerations for Maintenance of the Sunshine Skyway Bridge

COMMONWEALTH OF PENNSYLVANIA DEPARTMENT OF TRANSPORTATION BUREAU OF DESIGN

Rt. 15/29 (SBL) Bridge Superstructure Replacement and Roadway Widening

Pueblo's New 4th street

Construction and design features of the Bridge over the Danube River. Bulgaria

AESTHETIC AND TECHNOLOGICAL CONCEPTS FOR THE NEW ROUTE 9 SOUTHBOUND BRIDGE AND THE REHABILITATION OF THE EDISON BRIDGE

Design of Izmir Bay Crossing Bridge

ESTABLISHING A SOLID FOUNDATION FOR NEW BRIDGE CONSTRUCTION REPLACEMENT OF BRIDGE OVER THE SOUTH CANADIAN RIVER NEAR PURCELL, OKLAHOMA

STANDARDIZED CONCRETE BRIDGES IN TEXAS. John Holt, PE, Texas Department of Transportation Ronald Medlock, PE, Texas Department of Transportation

STRUCTURES INSPECTION SELF STUDY TRAINING COURSE PART ONE

Concrete Filled, Fiber Reinforced Polymer (FRP) Composite Tubes Bridge-in-a-Backpack A collaborative innovation together with:

DESIGN AND ANALYSIS OF PRECAST CONCRETE BRIDGES IN AREAS OF HIGH OR MODERATE SEISMICITY

SOUTH MEDFORD INTERCHANGE BRIDGES

TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

Final Estimates Level 2

Critical Structures Construction Issues

Gilmerton Bridge Replacement Project Virginia Society of Professional Engineers (VSPE) March 27, 2013

Maritime Work Plan for the High Rise Bridge Construction

Temecula Medical Center Temecula, CA

DESIGN OF CAMPBELL ROAD OVERPASS IN KELOWNA. Yulin Gao, M.A.Sc., P.Eng., SNC-Lavalin Inc. Samson Chan, M.Eng., P. Eng., SNC-Lavalin Inc.

Construction of Bridges

DESIGN OF THE MAIN SPANS OF THE CHONGQING CAIYUANBA BRIDGE

STRUCTURES INSPECTION CERTIFICATION TRAINING COURSE

Use of Grade 80 Reinforcement in Oregon

Table of Contents. ACKNOWLEDGEMENTS...ii LIST OF FIGURES...xii LIST OF TABLES...xv LIST OF SYMBOLS...xvi CHAPTER 1:ABOUT THIS STUDY...

SINGLE STEEL BOX GIRDER BRIDGES FOR THE TERMINAL DEVELOPMENT PROJECT AT TORONTO PEARSON INTERNATIONAL AIRPORT. Srdjan Brasic, M.Sc., P.Eng.

Fiber Reinforced Polymer (FRP) Panels for Rail Station Platforms

Lecture 13 CONCRETE WORKS

SECTION TILT-UP PRECAST CONCRETE SANDWICH PANELS. A. Work includes, but is not limited to, the following:

Chapter 1. General Design Information. Section 1.02 Structure Selection and Geometry. Introduction

1/26/2015 DETAILS CIP DETAIL EXAMPLES WHY SIMPLIFY DETAILS? CIP DETAIL EXAMPLES DETAILING FOR SIMPLICITY

OHIO DEPARTMENT OF TRANSPORTATION CENTRAL OFFICE, 1980 W. BROAD ST., COLUMBUS, OHIO

SIBLEY POND DESIGN-BUILD BRIDGE REPLACEMENT ROUTE 2 CANAAN/PITTSFIELD, MAINE

The New Incremental Launching Construction Technology of Jiubao Bridge Long-span Hybrid Arch-girder Structure

STRUCTURAL CONCRETE - LIGHTWEIGHT

BRIDGE DESIGN MANUAL UPDATES. Jamie F. Farris, P.E.

High Performance Insulating Concrete Form

Basarab Cable Stayed Bridge in Bucharest

Title Page: Modeling & Load Rating of Two Bridges Designed with AASHTO and Florida I-Beam Girders

Well Road Project Accelerated Bridge Construction Using Self-Propelled Modular Transporters (SPMT s) By: Mark Bucci, P.E.

7. Draw an equipment set up for the production of a beam by post tensioning. 10. What are the common concrete structures which are produced by

Recent Major Cable-Stayed Bridges in Shanghai

DEVELOPMENT OF GUIDE FOR SELECTION OF SUBSTRUCTURE FOR ABC PROJECTS

Analysis of the Response Under Live Loads of Two New Cable Stayed Bridges Built in Mexico

Elevated Slab Sequence

The Main Street Bridge - Supporting Transportation Systems

LRFD Bridge Design Manual Changes

SECTION 415 REINFORCING FOR CONCRETE

PC HOUSE FOR INCHEON BRIDGE PILE-CAP

The Aizhai Suspension Bridge is

Public Works Manual. Revised September Concrete & Asphalt

PIER PROTECTION (VEHICLE COLLISION) September 13, 2018

Applications of Ultra High Performance Concrete and Prefabricated Concrete Elements in Accelerated Bridge Construction

Office Building-G. Thesis Proposal. Carl Hubben. Structural Option. Advisor: Dr. Ali Memari

SEGMENTAL CONTRUCTION IN THE INNER CITY: THE BQE CONNECTOR RAMP TO WILLIAMSBURG BRIDGE

Providing Engineered Concrete Solutions. Precast and Mission Critical Facilities A Natural Fit

Construction Innovations / Sustainability

SPECIAL SPECIFICATION 4584 Segmental Concrete Bridge Unit

Economical Design / Case Studies

SECTION US Patent 8,857,130 B1 CAST-IN-PLACE CONCRETE WITH ARDEX CONCRETE MANAGEMENT SYSTEMS (ACMS ) EARLY MC APPLICATION

Construction of Long Key Bridge

Fort (M-85) Street Bascule Bridge

Transcription:

Tilikum Crossing Transit Bridge Portland, OR

Technical Information Size of Project: The Tilikum Crossing Transit Bridge is 1,720 ft. long and required 24,000 cy total concrete Strength Requirements: The contract required concrete strengths for individual elements: 4,000 psi for barriers and curbs, 5,000 psi for foundations and pylons, 8,000 psi for the deck/superstructure, and 4,000 psi for the light-weight light rail track slab Water/Cement Ratios: The contract required specific water-to-cement ratios for individual elements: 0.44 (barriers and curbs), 0.399 (foundations and pylons), 0.326 (superstructure), and 0.44 (light rail track slab) Unique or High Volume Admixtures: Admixtures for the mass concrete mixes included water reducers, stabilizers, and air entraining agents Unique Mix Designs: Because of the bridge length and slender superstructure, Kiewit elected to use a high performance fine aggregate concrete mix. This mix design ensured durability to stand the weight of traffic, structural integrity during seismic events, and longevity. Additionally, the concrete mix used around the light rail track was a concrete with light weight aggregate and fiberglass fibers.

Technical Information Tilikum Crossing Transit Bridge Other Special Technical Aspects: The bridge was designed with a thin deck to maximize both its visual appeal and vertical navigational clearance. Though a visually stunning bridge, its minimal, slender dimensions made every aspect of its construction challenging. For instance, the thin deck required seven to eight tendons per segment, not to the typical three or four tendons per segment, to support the weight of traffic. Additionally, each concrete segment and stay cable pitch was unique so every segment form and cable anchor had to be designed uniquely as well. Finally, cantilever construction had to be planned and performed meticulously to not overstress the deck, or to allow the cables to slip through the saddles while the segments were cast on opposite sides of the towers. Unique Specifications/Requirements : The bridge's unique design was selected by TriMet with input from a citizen's advisory committee. To ensure the final bridge met the conceived vision, the contract specified key geometrical and architectural elements including: a smooth all-white concrete finish, bridge deck width and geometry, tower geometry, joint locations, transit-way geometry, edge beam shape, barriers and handrails, column shapes and dimensions, and stay cable arrangement. In addition the mix for the pylons had to attain a strength of 3,200 psi in less than 18 hours so stressing could take place prior to form jumping.

Technical Information Placement Challenges or Unique Techniques: Several concrete challenges and techniques to overcome those challenges were used on this cast-in-place (CIP) segmental cable-stay bridge. In-water work windows drove foundation construction for the bridge, which were located 130 ft. offshore. Kiewit built trestles and a work platform to support cofferdam construction, shaft drilling, and shaft pours. After oscillating casings and installing rebar, crews poured 1,720 cy of concrete to build the shafts. Next, the footings required two-stage, 2,400-cy concrete pours. Rotating crews poured 1,800 cy continuously for over 24 hours. The pour was a logistical challenge as it required 180 truck loads of concrete arriving every 5 to 10 minutes. Crews then hand-finished the footing exterior from screed rails. Next, a 3-ft. concrete mat was poured on the footings and the 180-ft. tall CIP towers were built in ten 65-cy lifts using a custom-fabricated jump form. The two CIP pier tables were then constructed from the towers, each totaling 1,000 cy and poured in alternating 10-yd. sections to balance the structure. The CIP deck segments were then built using form travelers, one on each side of the tower, in alternating 16-ft. (115 cy) sections. The majority of the placements were considered mass concrete and required an extensive thermal cooling system. In addition, due to the high concentration of reinforcement with minimal clearance, slump and placement vibration was critical to achieving quality segments.

The Tilikum Crossing Transit Bridge is a multi-modal transit, segmental cable-stay bridge across the Willamette River that connects downtown Portland to Milwaukie. The bridge consists of two in-water piers at the towers, two landside piers, 3.5 miles of stay cable, and a 1,720-ft. bridge deck.

Originally round with eight shafts, the in-water footings were redesigned by the project team to be smaller ovals with only six shafts. Smaller footings reduced the foundation footprint, lowered seismic demands, and shortened foundation construction.

Each in-water tower footing required two-stage, 2,400-cy concrete pours. Rotating crews poured 1,800 cy continuously for over 24 hours. Nearly 180 truckloads of concrete were delivered to the site in 5 to 10 minute increments.

The bridge's 180-ft. tall pylons were cast in multiple lifts using jump forms. Saddles for permanent cables were embedded into the rebar cages of the top four lifts.

The pier tables were poured in two lifts using false work supported off the pile cap, eliminating the need for in-water false work piles.

Temporary precast pylon caps and cables were used to support the weight of construction equipment on the bridge deck. Once the deck was complete, permanent slanted pylon caps were poured and permanent cables installed.

Form travelers were used to cast the bridge's 78 deck segments, including closure pours, alternating sides to balance the structure. Deck erection occurred concurrently on the east and west foundations until they reached both landsides, and then closed mid-span over the river.

The roadway contains 1,720 ft. of embedded, direct-fixation light rail track and will carry Portland Streetcar.

The bridge design called for a smooth white concrete finish for the entire bridge, so special concrete mixes and finishing techniques were used. Great care was taken during forming to minimize patchwork so the aesthetic effect of the bridge could be realized.

A stunning "mood" lighting system changes colors based on the Willamette River's speed, height, and water temperature.