Balancing Timeline, Budget, and the Unknown on K-12 Renovation Projects KIPP DELTA PROJECT STUDY

Similar documents
(Continued on next page)

Meeting the Challenge of a Difficult Job GC The Beck Group Colorado Mills Mall Restoration 1

Upper Adams School District Facility Study Presentation Part 2 November 17, 2016

Understanding Consultants Needed for Your Building Project By Amy Green, Owner, Architect, Interior Designer & LEED AP of amy green design 579 W

Health Life Safety Survey and Master Facilities Plan

Coos Bay Best Bond Cost Breakdowns

Project Scope & Budget Breakdown. Mandatory Scope Recommended Additional Scope Wish List Scope

LLANO ISD SCHOOL BOARD MEETING. January 2016

St. Helens Middle School Facts

FACILITY ASSESSMENT PRESENTATION 11 October SCHRADERGROUP architecture

BOND CONSTRUCTION UPDATE

Biddeford School Department

CENTENNIAL SCHOOL DISTRICT

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

Volume 7 November Additions and Alterations to: Tinicum Elementary School Palisades School District. T&W Project 0737

HILLSIDE MANOR RENOVATION PROJECT FINDINGS IN SUPPORT OF USE OF REQUEST FOR PROPOSALS AND ALTERNATIVE CONTRACTING METHODS

BOARD OF TRUSTEES OCTOBER 13, 2014

Basic renewal/restoration and safety projects

NEW MIDDLE SCHOOL PROJECT

DENNIS TOWNSHIP FEASIBILITY STUDY

Guam Adequate Education Act Trust Account - CIP/STEM: Formerly SFSF Federal ARRA Grant Year End Report FY

Please comply with the Lean Construction Institute s Usage Policies and Attribution Guidelines at

Introduction & Project Background

10 Year Plan. Facilities Planning Guide. December 15, 2014

RENOVATING AN AGING HOME: Answers to Frequently Asked Questions

ADDENDUM NO. 1. TO SCOPE OF WORK: Section 0220, Form 01004/5

Adolfson & Peterson Construction, Megan Bond; ; CATEGORY 3: Meeting the Challenge of a Difficult Job General Contractor

MIAMI DADE COLLEGE WOLFSON CAMPUS REMODEL & RENOVATION PROJECT FOR THE DAVID W. DYER FEDERAL BUILDING AND UNITED STATES COURTHOUSE MIAMI, FLORIDA

Measure T Project List 2014 Santa Maria-Bonita School District Prop 39 School Bond November 4, 2014

Amendment 01. Issued: August 18, For. RFP 18-KG-0725(BF): Professional Design Services for Douglass Valley Elementary School

Edmonton Public School District No. 7

DESIGN. Challenges of Aging Infrastructure 6/24/2014. Al Tursi, Property Development Specialist / YMCA of the USA

40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT

Report No. 419-F Meeting Date: November 22, 2011 BOARD OF EDUCATION PASADENA UNIFIED SCHOOL DISTRICT PASADENA, CALIFORNIA

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

WAUSeON MACHINe. AND MANUf ACTURING. Robotic Automation. 995 Enterprise Avenue Wauseon, Ohio USA

Revised Central Scheme 1 Existing Building Exterior Upgrades Interior Renovation Areas: Scope of Interior Renovation: 100% Three Story Academic Additi

Hartsville Area Schools - Building Evaluations

REQUEST FOR PROPOSAL COMMISSIONING AGENT SERVICES GARRISON ELEMENTARY SCHOOL RENOVATIONS PHASE I

MCER Study for Little Powder K-8

Crockett Elementary School Renovations

LESSONS LEARNED IN CONTAMINATION CONTROL, SIZE REDUCTION OF OVERSIZED ITEMS, AND WASTE PACKAGING AT THE ROCKY FLATS ENVIRONMENTAL TECHNOLOGY SITE

Change Order Causation; Who is the Guilty Party?

PLUMMER ELEMENTARY SCHOOL

Architectural Services

B. Sections and all references contained therein form a part of this Section of the Specifications.

Frost Technical Center

HMS HIM 4th Floor Renovation LEED-CI v3 4 Blackfan Circle, Boston, MA LEED GOLD Project Profile 2016 LEED Facts Harvard University HIM 4th Floor 36%

NEW MIDDLE SCHOOL PROJECT

Belmont Mill Renovation Project. February 23, :30 P.M. Informational Session

TECHNICAL QUESTIONS FOR ITB-DOT-17/ LV DEMOLITION AND CONSTRUCTION OF DISTRICT SEVEN OFFICE SPACE

AZUSA UNIFIED SCHOOL DISTRICT

COMPANY. Critical Facility Upgrades 2018 Progress Update GREATER ALBANY PUBLIC SCHOOLS. Investments in Existing Capital Assets: Safe Warm - Dry

La Conner School District

San Leandro High School Pools Project

11 Tips for Breathing New Life into Old Office Spaces

Cold Spring School District

Energy and Utility Management Plan and Procedures. Updated September 7, 2018 by: Danny Helm Energy Manager

Cupertino Union School District

Completed projects. Projects in progress. Program developments

Professional Engineers (PE) Experienced Teamwork Ability to meet Short Timelines Consistency of Performance

ADDENDUM NO. 3, February 8, Renovations to the Existing Shelby County Center Architect s job no. 2598/BN

Hingham Public Schools Foster Elementary School

Labor Efficiencies & Base Service Charges New Features Introduced in Xactimate version 2002

40 CFR 763 THREE-YEAR AHERA ASBESTOS RE-INSPECTION SUMMARY REPORT INDIAN HEAD ELEMENTARY SCHOOL

BOYERTOWN AREA SCHOOL DISTRICT February 28, Boyertown West Middle School Renovation Project

Horse Farm, Livestock Office, and Horticulture Shed Cost Evaluation Report, Revised to address comments

/ Policy Number: Policy Name: Capital Planning and Development Processes Definitions

City High Middle School pre-design recommendations. March 29, 2017

: I EJM /~. / $ 20, $ 1,183, $ 373, $ 373, Janua!Y 3, 2012 Page 1 of 4 SUMMER 2012 PROJECTS ALSIP SCHOOL DISTRICT NO.

Commercial Portfolio

COMMITMENT. U.S. ARMY CORP OF ENGINEERS Richardson Pool Schofield Barracks Renovation

Case Study The Polyclinic Northgate Plaza, Seattle, WA

December 18, Michael Otavka William S. Hart Union High School District Centre Pointe Pkwy Santa Clarita, CA 91350

City of Roanoke. Commercial Permit Submittal Guidelines

Edmonton Public School District No. 7

COMMERCIAL PLAN SUBMITTAL GUIDELINES JAN 2018

Pigeon Lake Regional High School Falun, Alberta

Facility Study Update

WELD COUNTY SCHOOL DISTRICT RE-1 04/12/2016 BUILDING ASSESSMENT INTRODUCTION

Explain in writing if the address of the building is different than the address on this form:

SOLAR THERMAL COOLING TECHNOLOGY & TECHNOLOGY RISK

Leveraging second-generation space for your new workplace

Minnesota Healthcare Engineers Association, Fall Conference. Bob Dehler, P.E. Engineering Program Manager September 14, 2017

1.4 USE OF EXISTING ELEVATORS FOR CONSTRUCTION PURPOSES (NO ELEVATOR CONTRACTOR IS CONTRACTED FOR THE PROJECT)

School Modernization Overview

Berryessa Union School District Measure L Bond Construction Program

Design Advisory Committee Meeting #5. December 19, 2017

Feasibility Site Report

INSPIRE each student to develop a strong

Madison School District. Strategic Five-Year Facility Maintenance Plan

FACILITY DESIGN PLAN FOR HARDING HALL RENOVATION AND ADDITION SOUTH DAKOTA STATE UNIVERSITY DATE: March 29, 2017

HOMEBUILDING PROCESS TIMELINE. 13 Steps from Start to Finish HOMEBUILDING RESOURCE GUIDE

Hazardous Materials G

NORTHEAST IOWA COMMUNITY COLLEGE 2018 FACILITY ASSESSMENT MAY 15, 2018

Project Status Update & Progress Report

Deferred Maintenance Plan

WATKINS ELEMENTARY SCHOOL

EXHIBIT NO. 1 BUILDING REMEDIATION AND REDEVELOPMENT PLAN. Category #1: Work that must be done to cure dangerous and hazardous conditions

PROPOSAL FOR CONSTRUCTION MANAGEMENT SERVICES. April 13, 2016

Transcription:

Balancing Timeline, Budget, and the Unknown on K-12 Renovation Projects KIPP DELTA PROJECT STUDY

PROJECT SUMMARY Every project has a budget, but few are stricter than the budget for a K-12 project. The combined pressures of often using both federal and local dollars, as well as the obligation to return every unused dollar back to the school for other improvements, makes finding an experienced K-12 construction firm critical. It also helps to have a relationship with that contractor. When KIPP Delta selected Nabholz to oversee the Blytheville Central project, it was just the latest in an eightyear partnership between our firm and KIPP Delta. Like most K-12 projects, this remodel came with a strict budget and strict timeline. From a design and construction point of view, the Blytheville Central Elementary project stands out because it involved taking an existing 60-year-old structure that students had not occupied in two years and updating it to today s current standards for operations and life safety, while also updating it to facilitate KIPP

Schools Commitment to Excellence. The old building was part of another school district and was shuttered several years back. Our task was to turn the building back over to KIPP Delta as an updated, functioning elementary school with a gymnasium, classrooms, warming kitchen, cafeteria, upgraded plumbing, electrical, fire alarm, cosmetic finishes, millwork, and restroom facilities. Funded by taxpayer dollars, K-12 projects come with some of the strictest budgets.

PROJECT TRENDS This project follows a national trend of renovating facilities for K-12 use. According to an article by Clif Greim, PE, published by FacilitiesNet, communities are renovating instead of building for several reasons: Generally, schools built in the 1950s or earlier have impressive architectural character and often are fixtures in their neighborhoods. They are structurally sound and can accommodate new systems. In addition, there is often strong sentiment to keep them in some form. Newer schools built in the 1960s and 70s often become hand-me-down conversions from high schools to junior highs or from junior highs to elementary schools. The article goes on to state that another reason school administrators would choose to renovate older buildings is because there is no new land available to move the school or the available land is prohibitively expensive. A final factor is whether a renovation can be undertaken while a school is in use. If the goal is to continue to occupy the building, developing a phased construction schedule that separates construction from occupied areas is critical.

THE UNEXPECTED On the KIPP Delta renovation project, neither the budget nor schedule left room for mistakes. Nabholz started work in early April 2016 with a turnover date of July 1, 2016. As luck would have it, existing factors in the building would soon halt the job, shortening the renovation schedule even more. Renovating an existing building means preparing for the unknown, while simultaneously building a budget around what the end-user wants. We balanced these two objectives in the estimating stage. Throughout the estimating process, we kept the school informed of items that we might discover once work began and allowed contingencies for these circumstances in both budgeting and schedule. When the budget was finalized, we again ensured all parties were aware of the possibility of discovering concealed items such as mold, lead paint, asbestos, and HVAC, plumbing, and electrical issues. We made preliminary plans with the owners to handle any anticipated unknowns.

When demolition began in early April, samples of the VCT flooring collected during preconstruction tested positive for asbestos. We immediately submitted this to Arkansas Department of Environmental Quality and utilized our abatement contingency. Nabholz in-house asbestos abatement team quickly removed the asbestos and worked with the project management team to turn over different areas of the project at a time to allow work on the floor to continue. At the same time, the paint samples we gathered came back positive for lead. Again, we immediately utilized our lead-paint encapsulation contingency plan. Discovery of these hazardous materials shut down the entire jobsite for three weeks while we performed remediation and encapsulation. We called in a special lead paint remediation contractor for that scope of work. Even with these challenges, our client could not extend the July 1, 2016 move-in date. School starts when it starts. We resumed demolition activities at the beginning of May, at which point it was determined the building had no existing hotwater capabilities. We performed design, pricing, and inclusion for this scope of work, using funds from the overall project contingency to cover the cost. Renovating an existing building means preparing for the unknown.

As work continued at an accelerated rate, the pace at which we needed owner-supplied color and finish selections picked up rapidly. We worked with KIPP Schools to coordinate our work schedule so owner representatives could review all selections and finishes without hurrying the process and possibly rushing a selection. With a three-month project schedule and possible eight-week lead-times for some materials, we had to impress upon the owner how important it was to make these selections while still being sensitive to their concerns. We were in constant communication with KIPP Schools, the City of Blytheville, and WER (the designer) to ensure the concealed items or finish selections did not delay the final inspection and occupation of the building. As the project came to a close, a last minute decision to include a warming kitchen into the scope of the project was requested and included without extension of the July 1, 2016 completion date. When budgets and timelines are tight, good communication is crucial.

THE RESULT In the end, we competed the new Central Elementary for KIPP Public Schools on time and under budget. We are proud to have played our part however small in creating a place where the staff of KIPP Public Schools can provide the best possible education to their students every day. This job also prepared Nabholz to tackle the ongoing trend of renovating decadesold school facilities. THINKING ABOUT A RENOVATION PROJECT? GIVE US A CALL US AT 1.877.NABHOLZ AND ASK FOR YOUR AREA BUSINESS DEVELOPMENT OFFICER.