Integrated Concurrent Engineering. John Kunz

Similar documents
Integrated Concurrent Engineering

Project Definition and evaluation -- using VDC

Integrated Product, Organization and Process design. John Kunz

Integrated Product, Organization and Process design. John Kunz

This week overview. Take-homes. Theory: Design organizations as we design bridges: predict, measure and manage hidden work; ICE. Tuesday and Wednesday

Integrated Product, Organization and Click to edit Process Master design title style

John Kunz CIFE, Stanford University

Project Delivery Process Mapping Exercise: Directions for Implementation

Passit4Sure.OG Questions. TOGAF 9 Combined Part 1 and Part 2

CIFE welcome CIFE Copyright 2013

Virtual Design and Construction: Themes, Case Studies and Implementation Suggestions

BIM Checklist. Introduction

Project Management Session 6.2. Project Initiation Phase Integration Management

PART THREE: Work Plan and IV&V Methodology (RFP 5.3.3)

How To Manage a Troubled Project GTC Center for Project Management, All Rights Reserved

HEALTHCARE OF THE FUTURE INTEGRATED CARE + FACILITY DESIGN

CIFECENTER FOR INTEGRATED FACILITY ENGINEERING

CONSTRUCTION PROGRESS DOCUMENTATION (SCHEDULING)

6 BIM FAILURES. The design is complete, contracts are written, the project team is assembled and ready to build. Optimism is at its peak!

Metrics for Management and VDC Methods to Predict and Manage them

- DATA REQUIREMENTS BIM

LIFE CYCLE FACILITY ASSET MANAGEMENT. Presented by Pedro Dominguez Managing Principal, The Invenio Group

AIA 2009 BIM AWARDS. Category B: Design/Delivery Process Innovation Using BIM

CHAPTER 7 Building Information Modeling

Making the Integrated Big Room Better

CHAPTER 4 INTEGRATION OF CONSTRUCTION PROJECT MANAGEMENT AND SUSTAINABILITY

Construction coordination

Essential Duties (Roles and Responsibilities)

Project Manager s Roadmap We re all smarter together

Workflow Management Business Engineering

BIM in Singapore. Sonny Andalis. Sinduscson 5 th BIM Conference. Presented by : Building and Construction Authority 22 Oct 2015

General Contractor Regulatory Agency. [Info] Construction budget is defined as all hard costs including overhead and profit

A PERFORMANCE STUDY OF PROJECT SUSTAINABILITY: REDUCING CONSTRUCTION WASTE THROUGH BIM

Centerwide System Level Procedure

International Diploma in Project Management. (Level 4) Course Structure & Contents

Chapter Two. Project Management Growth: Concepts and Definitions. When to Use Project Management

PROJECT SCHEDULING & CONTROL

Environmental Studies Lab: Expansion. East Coast, USA

BIM Standard and Specifications for San Mateo County. Project Development Unit

BIM EXECUTION PLAN PROJECT INFORMATION PROJECT NUMBER

Building Information Modeling (BIM) Execution Plan

Promoting better business outcomes through the use of BIM and digital technologies.

The St. Jerome s University team in Waterloo are delivering lean IPD, scaled to suit the size and complexity of their project

Bringing Order out of Chaos

1.0 ABOUT THE NU GUIDELINES

Job Family Matrix. Core Duties Core Duties Core Duties

LCI Israel s Launch Tel Aviv, 20 th May, Lean Construction Institute Israel

Kanban Cadences and Information Flow

Design Reviews / Highlights DIA Specifications. Dave Mashburn Director of Facilities Services January 28 th, 2015

QUALITY ASSURANCE PLAN OKLAHOMA DEPARTMENT OF HUMAN SERVICES ENTERPRISE SYSTEM (MOSAIC PROJECT)

Project Management Advisory Board Deep Dive Study of Program Management

Project Problem Avoidance

The ParknPayApp. Business Plan Submission-3. Anna Forshufvud Therese Tellstedt Camilla Vachet Viktor Widerberg

PROJECT NAME. Duke University. Architect (Specify Design Vs. AOR If Multiple) Construction Manager. Civil Engineer. Structural Engineer

PSA TEC 2016: Stakeholder Management - Strategies for Project Success

CMMI V2.0 MODEL AT-A-GLANCE. Including the following views: Development Services Supplier Management. CMMI V2.0 outline BOOKLET FOR print.

CORNERCUBE. Lean Construction and Lean Project Delivery: Implications for Cost and Schedule CORNERCUBE. Optimizing Project Outcomes

4D Modeling: Applications and Benefits

LIFE CYCLE ASSET MANAGEMENT. Project Reviews. Good Practice Guide GPG-FM-015. March 1996

TOGAF Foundation Exam

Trends & Developments. Trends & Developments

VALUE FOCUSED DELIVERY

PMP TRAINING COURSE CONTENT

Decision Analysis Making the Big Decisions

Descriptive Data Sheet

THE PMP EXAM PREP COURSE

SAN FRANCISCO PUBLIC UTILITIES COMMISSION INFRASTRUCTURE CONSTRUCTION MANAGEMENT PROCEDURES

KPMG s Major Projects Advisory Project Leadership Series: Stakeholder Management and Communication

Program/Project Management

GETTING STARTED WITH LEAN CONSTRUCTION. A guide for project teams

Workflow Management Business (Re)Engineering

FMI Construction Professional Survey Job Description

1 Management Responsibility 1 Management Responsibility 1.1 General 1.1 General

COMM 391. Learning Objective 1. Learning Objectives. Introduction to Management Information Systems

Project Management Framework with reference to PMBOK (PMI) July 01, 2009

Lean Project Delivery Operating System

MBA BADM559 Enterprise IT Governance 12/15/2008. Enterprise Architecture is a holistic view of an enterprise s processes, information and

Guidance on project management

BIM Execution Plan. Copyright 2009 Rights Reserved - The Trustees of Indiana University and SHP

PMP Exam Prep Study Group Input-Output-Tools #3a

Volume II- Project Development Processes

CORROSION MANAGEMENT MATURITY MODEL

BUILDING INFORMATION MODELING (BIM) THE WHOLE TRUTH 10:30am 12:00pm. Presenter: Rod Yeoh, Principal, Omicron Architecture Engineering Construction

Project Management Assessment. Apply an In-Depth Approach to Project Management to Achieve Systematic Success

VALUE FOCUSED DELIVERY

Project Management Professionals

Sprint. Innovate via rapid product/service prototyping and market testing.

FDA s Draft Guidance Request for Quality Metrics: What All Drug and Biologics Manufacturers Need to Know June 2017

Well Delivery Process A Proven Method to Improve Value and Performance While Reducing Costs. IADC/SPE

Engaging Staff in Change Management: HR Transformation Process in the School of Medicine and Public Health

The Maryland-National Capital Park and Planning Commission

WM2012 Conference, February 26 March 1, 2012, Phoenix, Arizona, USA. Improving DOE Project Performance Using the DOD Integrated Master Plan 12481

How to Drive Business Value with Capacity Management

Project Process Improvement

Banishing Waste and Delivering Value in Your BCM Program

Metrics for Management and VDC Methods to Predict and Manage them

Benjamin D. Hall Interdisciplinary Research Building

The following Standard reflects employers requirements for the skills, knowledge and behaviours expected from someone to be competent in the job role.

Process for Managing Service Transition Efficiently. By Ravinder Singh Zandu

Transcription:

Requirement Relationship Requirement Integrated Concurrent Engineering (ICE) MEP, Teledata room design Task 29 KPFF Task 28 Task 27 SRG Lab Plan SRG Lab Task 37 Furniture Task 44 Project Mgt Task4 AEI Core Task 38 Task 41 Task26 H Block Crew Task 23 Lab Planning Program Meetings with Directors Lab Planning Program Meetings with Pharmacology *05-07-01 Ken Mouchka Lab Planning Program meeting with Bio Organic BMS Controls Meetings (Weekly) 23. *Reprogram B#13 and B#15 Exterior Architecture 26. *Finalize B#13 and B#15 Exiting/architecural H occupancy concept 41. *Reprogram bookends B#13 and B#15 36. *Analyze structural impacts 35. *Finalize Protein Chemistry Program 32. *Finalize Bio-Organic Chemistry Program 33. *Finalize LAR Program 34. *Finalize Pharmacology Program 44. *Complete B#14 Officing Planning 39. *Finalize MEP distribution and section 27. *Finalize B#13, 15 Shaft Size & MEP Room Locations 42. *Develop Execution Strategy 37. *Reprogram B#15 Shafts 19. *Determine vertical utilities 45. *Complete all Basement/LAR Drawings Genentech PM Lab planning Program Meeting with Protein Chemistry 46. *RA Furnture Concept Complete 43. *Changes in Steel Forwarded to Steel Detailers 40. *SRG Reprogram 15/14 interface, exiting, stairs 55. KPFF design stairs for 15/14 38. *SRG Reprogram 13/14 interface, exiting, stairs (3) *AEI design MEP HVAC, Conduit & piping mains B13 Weekly Coordination Meeting Final Program Confirmation with Officing *Lab and vivarium Programming Complete *Exterior Programming Accepted by Genentech 24. *Complete B13,4 H block occupancy requirements on MEP systems Bookend Programming Accepted by Genentech Notice to proceed on structural changes 29. *Document lab plan 48. *Develop exiting plan 1. *Redesign main MEP distribution systems 25. *Do Central Plant design changes 31.* AEI & SRG Determine Design $/Time Impact of Change Review skin changes w/db team 18. *Detailed Lab Program Documentation 47. *Develop lab DD plan 28. *Determine segregation of lab and tech space 50. Designate size, location of 13 MEP, teledata rooms 51. Designate size, location of 14 MEP, teledata rooms 54. KPFF design stairs for 13/14 12. *Complete UG utiliites 30. *Approve Change to Design Contract Review 80% documents Final Program Confirmation with Pharmacology *Package B structural modifications (CCD3A) 5. *Finalize lab & Equipment plans Architect program/mep oncepts Established By Design Team 2. Initial redesign MEP branch lateral distribution 3. Complete Tele Data Design G accept 13/14 Interface *Cal OSHA Recommend Determination of LFFH 4. complete all Interior Architcture *Turnover lab and vivarium DD plan to AEI G accept 15/14 Interface Genentech 80% Detailed Design Review Final Program confirmation with LAR (6) Coord B13 MEP floor section (8) *Revise MEP loads, G accept lab equipment matrix 49. Develop reflected ceiling plan *Notice to proceed with detailed design SRG Management SRG / AEI Technical Steel Detailing Meetings Turnover reflected ceiling plan to AEI 17. *Risick reprogram solvent distribution and waste *Design Budget & Schedule for Changes Approved *City Accept exiting B13 MEP HVAC, conduit, piping mains completed Organization MEP Equipment schedules finalized AEI Management Task22 AEI Core and SRG Lab Meetings 80% Drawing Review Work Process *Package C skin modifications HDCCO Costing Tele Data Coordination Meetings (13,15,16) MEP specs, P&ID's, control sequences 22. *Complete catwalk drawings 20. *Determine Scope of package D including vivarium changes 16. *HDCCO Determine Schedule Impact 21. *Prepare Plan Views for Review of Concept w/city 52. Finalize landscape SRG Technical 14. *HDCCO update Estimate of cost of Program AEI Core and Tech 13. *Code Consultants Review Concept for final city Presentation KPFF Package D and UG addendum issued: underground utilities, vivarium catwalk HDCCO Core *City Approval of H Concept Code Rev Consultant 15. Jeff reprogram HMIS Solvent *Accept project scope:budget by Genentech 10. Draft Alternate means Tarter 8. Review Alternate Means w/impact on LEL and LFFH H Block Crew & Tech SRG Landscape City Approval of Alternate Means for Program Tele Data Design Code Rev Issue 80% MEP CDs Detailed Design 80 PC Complete (19) Genentech review 80% drawings (20) Incorporate 80% MEP review comments 53. Incorporate comments, complete Architectural detail MEP 80% Review comments incorporated (21-4) Finalize MEP Details, update specs and p&id's Finish Integrated Concurrent Engineering Function Product Behavior Qualitative Threshhold values Predicte Observed Object Attribute d value value -2-1 0 1 2 Product Product Scope Product Scope. Building Spaces includes - Project Goals Project Goal. Capacity (people) >= 60 -?o Project Goal. Cost (M$) = 70 -?o Goal. Net Energy Use (K- Building BTU/ft2) <= 250 -?o Goal. Quality conformance Building (%) >= 12 -?o Organization Organization Scope Organization Scope. Actors includes - - Organization Goals Organization Goal. Predicted. Cost (K$) - <= -?o Goal. Observed. Response Organization Latency (days) 3 <= -?o Goal. Predicted. Peak Organization Backlog (days) 3 <= -?o Goal. Predicted. rework Organization (FTE-days) - <= -?o Process Process Goals Process Goal. Peak Quality Risk < 0.50 - - Goal. Schedule Growth Process (months) < -?o Process Goal. Completion Date <= 1/1/09 -?o Process Task. Action: Object Process Task. Design: Actor Actor that designs Process Task. Predict: Actor Actor that predicts Process Task. Assess: Actor Actor that assesses Process Task. Build: Actor Actor that builds John Kunz Baseline Year-1 Rate ($K) Change (K$) Revenue 100,000 2% 102,000 Cost of contracted 85,000-2.0% 84,660 work 85% Cost of self-performed work 10% 10,000 2.0% 12,240 Gross Margin 5,000 5,100 Sales, G&A 2% 2,000 2,040 IT investment 70 Amortized costs of IT/yr 33% 23 Net income 3,000 3,037 Time to payback (years) 1.9 Net Income change (%) 1.2 Big idea: Integrated Concurrent Engineering (ICE) is a social method, helped by technology, to create and evaluate multidiscipline, multi-stakeholder VDC models extremely rapidly.

Overview Session Integrated Concurrent Engineering (ICE): Objectives Develop, show and explain the product, organization, process, POP and 4D models as well as analyses of each and recommendations for management based on the design exercise collaboratively and quickly 2

XC Good traditional Integrated Concurrent Engineering (ICE) Background Given Objective = Rapid, effective design extreme collaboration (~1 week) Excellent POP software Collocated team iroom Good generic POP model SD (DD) phase focus Performance change 60000 40000 20000 0 Latency (secs) Duration Latency (secs) 300 250 200 150 100 50 0 XC Good traditional Duration (days) 3

The big ideas of ICE The Big Ideas: Exceptional performance, e.g., Team-X at NASA-JPL It works because it achieves exceptionally short information latency and short task durations, reliably. Multiple factors enable ICE to work. 4

Define: Goals of this design session: Project Definition (v) What each of the teams expects to deliver What they expect from the other team members How can individuals coordinate their respective and collective scopes How team members know how work is progressing How team members know when (pre)construction is completed What work resources and methods can be used for (pre)construction work What resources and work methods will be used for the (pre)construction 5

Define: Goals of this design session: Project Definition (v) What each of the teams expects to deliver (plans, commitments) What they expect from the other team members (commitments) How can individuals coordinate their respective and collective scopes (coordination commitments) How team members know how work is progressing (risks; measurable process performance metrics) How team members know when (pre)construction is completed (measurable outcomes) What work resources and methods can be used for (pre)construction work (controllable factors) What resources and work methods will be used for the (pre)construction (commitments) 6

Goals of this design session: Project Definition (v) For the product, organization and process, project definition clarifies and aligns: Functional objectives what project stakeholders want Specific deliverables, e.g., spaces, systems Conforming and highly reliable safety, schedule, quality and cost Scope forms you create -- periodic design and construction deliverables, including: designs of the Product (~weekly or daily) to update objectives, designed scope, predicted and measured behaviors Organization groups of people to do tasks that work on the design Process (daily work) tasks to design and manage, procure, fabricate, deliver, construct and inspect Behaviors what you predict and what you did predict and measure performance of designed scope With respect to specific stakeholder objectives Using methods of VDC, Integrated Project Delivery, Lean and Sustainable development 7

Potential value of VDC Better project or corporate performance (measurably) Suggests need for ~weekly performance data: specify >3 metrics Better clarity of decision processes, for Decision-makers Execution team Executive team Better plans and clear commitments for working team Increased profitability: rework; work effort; business VDC methods: Models: Product (3/4D), organization (commitments), process (plan, schedule) Collaboration methods: ICE Analyses (model-based): Clash, Structure, QTO, cost, energy, Metrics: Outcome, process, controllable factors 8

Product Organization Process (POP) Model format: 9

Process of Project Definition Build POP model as a stakeholder team Set functions (objectives) of Product, Organization, Process Design form or scope of Product, Organization, Process Identify project behaviors and define methods to predict, assess and observe them 10

Virtual Design and Construction (VDC) vs. Building Information Modeling (BIM) VDC BIM 11

Integrated Concurrent Engineering at JPL (ICE) Properties Collocated Organization (Closed Knowledge Network) Excellent Technical Infrastructure Formal Objective Metrics Informal Process and Culture Photo thanks to JPL 12

Integrated Concurrent Engineering at CIFE Integrated Collaborative Engineering (ICE) at CIFE Collocated Organization (Closed Knowledge Network) Excellent Technical Infrastructure Formal Objective Metrics Informal Process and Culture 13

Without Integrated Concurrent Engineering Source: @ammunition group: http://twitpic.com/5xs1vy 14

Observations ICE at NASA-JPL characteristics Organization: Multiple stations (~18) Process: careful design Technology: Multiple shared display screens Shared database (Icemaker) 15

Coordination Latency is the fundamental performance metric for knowledge work Response latency = Time from a designer posing a question to receipt of a useful answer Decision latency = Time from receiving useful information to making a decision with it Good engineering practice for both: 2 days weeks typical Measurable ICE Objective for latency: minutes, reliably For and as assessed by all intended stakeholders 16

Simple analysis of Latency Traditional Project requires 100 queries per engineer @ Latency = 2 days (good!) 100 modeling, analysis, meeting tasks @ task durations < 2 days Project duration ~ 200 calendar days (typical) Latency paces schedule (typical) Not direct work ICE (Team-X) Project requires 100 queries per engineer @ Latency = 1 minute 100 modeling, analysis, sidebar tasks @ task durations ~8 minutes Project duration ~ 2 calendar days (Team-X) Direct work (modeling + analysis + documentation) paces schedule (Team-X), Not coordination latency 17

ICE requires latency management Latency extends schedules Interdependent tasks have incessant information requests Requests have response delays (latency) Latency adds no value, measures collaborative waste Integrated Concurrent Engineering dramatically cuts time and latency Reduces latency from days to minutes Direct work tasks must run in minutes Enables radically decreased project duration Researchers, practitioners report improved cost, quality Requires high reliability (> 99%) latency: one major latency source jeopardizes project success New organizational form 18

How ICE (Team-X) works Manages: 1. Duration of direct work tasks Model, describe, predict, explain, evaluate, generate alternatives, decide Requires highly skilled engineers with excellent tools that they know well and culture that provides good enough answers 2. Coordination Latency Time for a designer to obtain usable information Requires many enabling factors Supports both: 1. Associative (divergent) thinking Many options, intuitive, including unique idea Fluency (lots of options), Flexibility (different kinds), Original (at least one) 2. Analytical (convergent) thinking data, prediction, analysis, evaluation and recommendations that believably support decisionmaking Actionable 19

Use ICE for Target value design for cost, schedule, energy, Generate and evaluate many design options w/ice Select target cost Rapid design method: PIDO http://network.mod efrontier.eu/docum entation/pido.html + - Value Assessed project value and predicted cost of many options Linear value curve Low Cost High 20

Use ICE for Target value design for cost, schedule, energy, Generate and evaluate many design options w/ice Select target cost + Value Assessed project value and predicted cost of many options Non-Linear value curve - Low Cost High 21

Use ICE for Target value design for cost, schedule, energy, Generate and evaluate many design options w/ice Select target schedule Assessed project value and predicted schedule of many options Value + - Low Schedule High 22

Use ICE for multi-discipline target value design: When a change affects two measures of project success, Choose when upside value exceeds downside risk E.g., - cost risk < + upside schedule compression value 23

ICE Methods Normal Stations Owner Product: model functions, scope, behaviors Organization: model functions, scope, behaviors Process: model functions, scope, behaviors Integrated project: POP model Facilitator (session leader) Project manager Process All stations simultaneously develop model inputs Coordinate continuously Assess and evaluate first design option Deliver project: Definition Objective assessment Option evaluation 24

Steps to perform ICE sessions Pre-planning: a few days immediately prior to ICE sessions Invite a very small set of project principals (2-4) Do project definition and identify POP model at Level-B with ~10 each of P, O, P elements Determine the design space to explore in ICE session: Invite participants of actors in POP model to ICE session Select modeling and analysis tools and methods Assure that facility and intended tools are available ICE session: ~3 sessions within one week Post-session: a few days immediately following ICE sessions to create formal deliverables 25

When to hold ICE sessions For each major project phase at least early (concept and schematic), detailed (DD, CD) and to plan construction Collaborating with your other stakeholders Hold a set of about 3 ICE sessions Build and analyze a project model for the next phase in enough detail to identify objectives, scope and predicted performance believably 26

Why to hold an ICE session Do project definition rapidly and believably Define functional objectives, scope, behaviors of Project, i.e., Product, Organization, Process Clearly identify tasks and deliverables for next period (week or month) Focus: product element and system(s) served Who: responsible group, individuals What: tasks to perform When: according to broadly reviewed and accepted schedule How: methods and resources to be used by responsible team(s) to coordinate, do work and verify work Context: specific risks and uncertainties to address based on broad project review coordination tasks to assure success given risks 27

To plan a set of ICE sessions Enable effective use of ICE methods Professional development of potential team members - create culture, methods, incentives Implement enabling tools: P, O, P modeling and analysis applications, display technology, shared database Plan each set of ICE sessions: Identify Objectives and intended deliverables: models, analyses, reports, recommendations, Number of sessions and calendar schedule: typically 2-4 over ~ 1 week Intended participants, tasks for each session Effort and time budgets for use of ICE sessions Process performance metrics and methods: measured and assessed quality, schedule, cost 28

ICE deliverables Functions: statement of project objectives for P, O, P Scope: Design of multiple P, O, P options in large design space P, O, P models for use by next phase Behaviors: predicted P, O, P performance Evaluation of acceptability of options given objectives Risk assessment and mitigation strategy Recommendation for new P, O, P design option(s) Proposed product design, team, schedule and responsibilities for next phase 29

ICE vs. traditional meetings in construction Issue Outcome re issue at hand Resolution ICE Agenda management Focused on clear, shared agenda Description of problem and context Number of options considered Supporting technologies Shared and clear Multiple; consider whatifs Interactive visual models and analyses Traditional meetings Tracking of status Tangents, pursuit of personal agendas Individual perceptions Focused on agenda of one individual Paper and appeal to understanding of others 30

ICE Enabling Factors (Committed) Organization Stakeholders Present: (Closed knowledge network) Focused design staff: 100% committed in sessions Flat organization structure Egalitarian culture High goal congruence (Dynamic) Process Processes clear: (low equivocality) Processes distinct: High structure independence Resolve problems in small self-formed groups (Pooled communications) (Visual) Technology Excellent disciplinespecific modeling, visualization tools Rich communications media Integrated database 31

Staff survey: Example of how senior management helps 1. I feel that I can challenge people at any level in my organization without fear. 2. I feel I can ask for and receive the resources (time, budget, equipment) I need to solve problems. 3. My Manager/Supervisor makes it easy to speak up when problems arise. 4. My Manager /Supervisor listens to bad news, yet still asks for unrealistic targets. 5. When we present bad news, our Manager/Supervisor repeatedly asks for more information focused on showing that the problem is not as bad as it seems. 6. My Manager/Supervisor encourages us to ask for help outside our organization or the chain of command (e.g., outside our project or work group or next level up) if we need it. 7. I am aware of what to do when a Manager/Supervisor doesn t respond appropriately to bad news and it needs to be escalated to a higher level. 8. My team uses metrics and processes effectively (e.g., trend program, standard metrics, etc.) to analyze, surface & solve problems. 9. In my organization, we live by our corporate values 10. The formal metrics in my organization often do not convey an accurate picture of performance. 32

Organization Enabling factor: Stakeholders Present: (Closed knowledge network) Objective: knowledge and authority always present Meaning: Requisite knowledge, procedures, options, and authority are immediately available in the room (almost always) Risk factors: sidebars; unanswered sidebars Team-X Methods: Heavy reliance on collaborative design sessions Designer collocation during sessions Careful participants selection and training Pre-plan to identify needed participants 33

Organization Enabling factor: Design staff focus Objective: 100% available during meetings Meaning: Design session participants focus exclusively on project work during design sessions Risk factors: Designers have other responsibilities during design sessions, so team waits for expertise Team-X Methods: Management support of focus Short sessions enable managers to free valued staff 34

Organization Enabling factor: Hierarchy structure Objective: Flat Meaning: Minimal required decision-making structure and overhead Risk factors: Soliciting management approval challenges short latency Team-X Methods: No managers Culture of autonomy and respect One facilitator (session leader) 35

Organization Enabling factor: Egalitarian culture Objective: Egalitarian Meaning: Positions assume empowered decisionmaking and low management overhead Risk factors: Soliciting management approval challenges short latency Team-X Methods: Culture of autonomy and respect Careful recruitment Decisions and decision processes highly visible to all 36

Organization Enabling factor: Goal Congruence Objective: Highly congruent Meaning: participants know and aspire to same goals and methods Risk factors: positions debate priorities or methods Team-X Methods: Discuss goals and methods at session start Facilitator (session leader) attention Culture of congruence Analysis and decisions very visible to all 37

Process Enabling factor: Processes clear: (low equivocality) Objective: design, coordination and construction processes clear Meaning: all participants understand and accept procedures, goals and objectives Implies that method applies only to well-understood processes Risk factors: positions ask for and wait for facilitator (session leader) decisions Team-X Methods: Use only for well-understood processes Pre-plan for process clarity Culture of autonomy Analysis and decisions very visible to all Excellent process facilitator (session leader) 38

Process Enabling factor: Processes distinct: (High structure independence) Objective: design processes clearly separated Meaning: Design tasks are distinct, positions all understand their responsibilities and can proceed with minimal management oversight Risk factors: positions solicit or wait for facilitator (session leader) decisions Team-X Methods: Use only for projects that allow independence Pre-plan for independence Staff selection and training Culture of autonomy Analysis and decisions very visible to all 39

Process Enabling factor: Resolve problems in small self-formed groups (Pooled communications) Objective: Pooled communications Meaning: Participants resolve problems in small selfformed groups Risk factors: Formal or inflexible coordination requirements Team-X Methods: Collocation Shared project (POP) model Shared projection screens Sidebar culture 40

Objective: Excellent Technology Enabling factor: Modeling, Visualization Tools Meaning: Discipline-specific tools allow all positions to do direct work very fast Risk factors: Manual design activities or poor tools bottleneck schedule; Other designers fail to understand a model Team-X Methods: Modeling, visualization, analysis and decision support tools enable all critical path tasks High team experience Shared project (POP) model 41

Technology Enabling factor: Communications Media Objective: Rich Meaning: Shared and personal, visual, multidisciplinary, showing functional requirements, design choices and predicted behaviors Risk factors: Slow process to describe models, explain rationale, evaluate choices, make predictions, create alternatives Team-X Methods: Mature modeling and analysis tools Personal workstations Shared iroom displays 42

Technology Enabling factor: Shared Project Database Objective: Integrated Meaning: Discipline-specific models all access and store shared data easily Risk factors: data reentry, missing shared data Team-X Methods: Develop good shared generic (POP) model ontology Applications have developed uniform semantics for shared data Designated position assures consistency 43

Assessment of status of ICE Enabling Factors (Committed) Organization Stakeholders Present: Focused design staff: 100% committed in sessions: Flat organization structure: Egalitarian culture High goal congruence: (Dynamic) Process Processes clear: (low equivocality): Processes distinct: Resolve problems in small self-formed groups: (Visual) Technology Excellent disciplinespecific modeling, visualization tools: Rich communications media: Integrated database: 44

ICE Enabling factors: so what? Necessity: excellent ICE performance requires all factors to work well Sufficiency: No one factor suffices Early evidence (Stanford classes) of necessity, sufficiency of these factors (from observations or theoretically-founded simulation) Process and team experience are crucial, so understanding factors may help understand how to change Team-X to Make specific improvements Replicate Team-X (in less than 10 years it to create it) 45

Define: Goals of ICE sessions session: Project Definition (v) What each of the teams expects to deliver (plans, commitments) What they expect from the other team members (commitments) How can individuals coordinate their respective and collective scopes (coordination commitments) How team members know how work is progressing (risks; measurable process performance metrics) How team members know when (pre)construction is completed (measurable outcomes) What work resources and methods can be used for (pre)construction work (controllable factors) What resources and work methods will be used for the (pre)construction (commitments) 46

Deliverable commitment report: responsibility matrix Planned deliverable Responsible team, individuals Receiving team Due date Due date met (y/n)? Expected LOD Comments Commitment conformance Time 47

Coordination commitment report Planned coordination activity Responsible individuals Due date Due date met (y/n)? Expected LOD Comments Commitment conformance Time 48

Metrics Implementation table Name Type [C, P, O] How to use in management Source of data Display Collection frequency M E T R I C S C: Controllable; P: Process; O: Outcome 49

Risk report Identified risk Responsible individuals Earliest analysis/ last responsible moment dates Resolution date met (y/n)? Potential impact ($, time, effort) Comments Risk resolution conformance Time 50

To read more Section Integrated Concurrent Engineering (ICE) supports VDC Pp 34-38 in VDC recommended reading "Virtual Design and Construction: Themes, Case Studies and Implementation Suggestions," CIFE working Paper #97, 2011. 51

ORID: Focused Conversation and Analysis Objective What do you recall seeing? Reflective Positive What do you feel positive about? Reflective Negative What do you find negative? Interpretive What sense do you make of it? Decisional What agreements can be made now? 52

Overview Session Integrated Concurrent Engineering (ICE): Objectives Develop, show and explain the product, organization, process, POP and 4D models as well as analyses of each and recommendations for management based on the design exercise collaboratively and quickly 53