OFFSHORE wind farms are gradually being planned and. Impact of system power losses on the value of an offshore grid for North Sea offshore wind

Similar documents
Abstract Offshore wind farms are gradually being planned and built farther from the shore. The increased integration

Further research (Part II)

Impact of large scale wind integration on power system balancing

Electricity sector transformation in Europe Taking local idiosyncrasies into account

Innovative grid-impacting technologies for pan-european system analyses: key GridTech results on Demand Response application

An Offshore Grid in Northern Europe: Techno-economic Design Considerations

Costs and benefits of offshore grids

ENTSO-E scenarios- general overview. Daniel Huertas Hernando ENTSO-E System Planning Adviser

Frequency Quality in the Nordic Power System: Wind Variability, Hydro Power Pump Storage and Usage of HVDC Links

Integrated modelling of the future energy system results and challenges

D6.1. Report describing the power market model, data requirements and results from analysis of initial grid designs

What can transmission do for a renewable Europe?

European Transmission System Operators. Users Group Belgian Grid. June 10th 2010

Winter Outlook Report 2012/2013 and Summer Review 2012

North Sea Offshore Grid Design

TradeWind Favourable distribution Reinforcing interconnections

Session 2: Grids: the gateway to power

Christian Skar Department of Industrial Economics and Technology Management Norwegian University of Science and Technology (NTNU)

Conditions for accelerating the deployment of offshore wind power in the BSR - Seminar 27 April 2012, Wind Power in the Nordic and Baltic Region

OFFSHORE WIND ENERGY RENEWABLE BULK POWER BUT NO TRANSMISSION? 5 TH CONFERENCE ON APPLIED INFRASTRUCTURE RESEARCH

SCENARIO OUTLOOK AND ADEQUACY FORECAST 2014

Balancing New Renewables in Europe - Norwegian Contributions and Research Challenges

Capacity reserves until 2025: declining, but sufficient

Focus on the Nordic and Baltic Sea

Transmission Planning for Wind Energy: Status and Prospects

Wind Energy The Facts

New power bridges between Germany and Scandinavia

Regional Reports. TYNDP 2018 Regional Insight Report. North-South Interconnections. West

Large-scale balancing and energy storage from Norwegian hydropower

Investment Analyses. - A new functionality for EMPS * *) no: Samkjøringsmodellen Brukermøtet 2013, Trondheim mai 2013.

Adding value to IRENA s REmap 2030 project using a European Electricity Model

European Commission. Communication on Support Schemes for electricity from renewable energy sources

Regional Investment Plan 2017 Regional Group North Sea

Power System Integration of Offshore Wind Farms:

Table of Contents 1 Introduction What do we mean by flexibility and balancing? Scope The Norwegian power and natural gas system

NORDIC AND BALTIC HVDC UTILI- SATION AND UNAVAILABILITY STATISTICS 2014

Developing Infrastructure and Operating Models for Intermodal Shift - DIOMIS Intermodal Rail/Road Transport In Europe 2007

Publishing date: 07/02/2018. We appreciate your feedback. Share this document

Scenarios for Decarbonizing the European Electricity Sector With Particular Consideration to Norway

Norway s role as a flexibility provider in a renewable Europe

2017/ November summer outlook. winter outlook summer review. winter review. 1st June

An SDP/SDDP Model for Medium-Term Hydropower Scheduling Considering Energy and Reserve Capacity Markets

Wind in power 2014 European statistics. February 2015 THE EUROPEAN WIND ENERGY ASSOCIATION

Long-term Market Analysis Nordics and Europe Executive summary

100% Renewable (Electricity for) Europe

Impacts of wind on the Nordic wholesale market. Therese Gjerde- Vice President Spot Bergen Energi AS

The North Seas Countries Offshore Grid Initiative. - Initial Findings - Final Report Working Group 1 Grid Configuration. 16 th November 2012.

Economic and Social Council

Outlook for Generation and Trade in the Nordic and German Power System

The potential role of power-to-gas. in the e-highway2050 study. Public Version OIL & GAS DNV GL 2017

Integration of Renewable Energy Sources in the Electricity System - Grid Issues -

EWEA Response to the European Wind Integration Study (EWIS) Report Main Conclusions in a Nutshell

NORDIC AND BALTIC HVDC UTILI- SATION AND UNAVAILABILITY STATISTICS 2015

Conclusion Power Grid Development Plan 2025, Version 2015, 2 ND Draft

Core projects and scientific studies as background for the NREAPs. 9th Inter-Parliamentary Meeting on Renewable Energy and Energy Efficiency

How government subsidies influence the onshore wind energy market. Max ten Cate 27 September 2017

Transmission and Interconnectors

European Power System Completing the map. Technical Appendix

Modelling of Smart Low-Carbon Electricity Systems

European Electricity Market Model

Winter Supply Outlook 2017/2018

Electricity Market Design : Experience from the Nordic electricity market NORDPOOL

Transmission Needs In A Fully Renewable Pan-European Electricity System

An Analysis of Offshore Grid Connection at Kriegers Flak in the Baltic Sea

Climate friendly, reliable, affordable: 100% renewable electricity supply by 2050

Centre for environmental design of renewable energy - CEDREN. Atle Harby, Director

Analyses on the effects of implementing implicit grid losses in the Nordic CCR

PRICE FORECASTS FOR POWER AND CERTIFICATE MARKETS

The Renewable Energy Directive the role of National Renewable Energy Action Plans in reaching the 2020 targets

The European offshore wind industry. Anne-Bénédicte Genachte Regulatory Affairs Advisor Offshore Wind Power The European Wind Energy Association

RES - causa di maggior flessibilità o possibile soluzione?

Overview Balance Management project

Solid biofuel markets in Europe

FB external report for w1, 2017

Simulatie van het EU-wijde elektriciteitsysteem. Modellering van de elektriciteitsmarkt en de hierin gebruikte elektriciteitsinfrastructuur

Renewable energy sources in Slovakia a quantitative assessment and policy conclusion towards, and beyond, 2020

Calculation of transmission capacities between partner-grids

Large scale balancing and storage from Norwegian hydropower

Opportunity-cost-pricing of reserves for a simple hydropower system

Merit Order Effect of Wind Power Impact on EU 2020 Electricity Prices

Delivering the Paris Agreement?

Developments and achievements of Feed-In. evaluation conducted for the IFIC. Cooperation (IFIC) 18th/19th November 2010, Berlin

Model-based Analysis of Infrastructure Projects and Market Integration in Europe with Special Focus on Security of Supply Scenarios

IS BALANCING FROM HYDROPOWER A FEASIBLE IDEA

Simulation and Optimization of Systems with Multiple Energy Carriers

Prepared for: IGD 2014

Phosphorus Regulations in Europe

Network Options Assessment for Interconnectors

Pan European TIMES Model General Description

Effects of Pumped Storage Hydro on Power Systems with Large Amount of Wind Power: A European Perspective

Energy balances 2011 Power balances 2011/2012

Application of ENTSO-E CBA methodology for capital expenditures assessment

Page 2 of 68. ENTSOG Union-wide SoS simulation report

CIGRE Working Group (WG) C4.603: Analytical techniques and tools for power balancing assessments

Features of intermittend electricity supply

EWEA response on the CEER consultation on regulatory aspects of the integration of wind generation in European electricity markets

Practical examples on how Norwegian Hydro could be an enabler of increased RES in North West Europe

Regional Investment Plan Baltic Sea region

PowrSym4. A Presentation by. Operation Simulation Associates, Inc. February, 2012

Wir schaffen Wissen heute für morgen

Transcription:

Paper accepted for presentation at the 2 IEEE Trondheim PowerTech Impact of system power losses on the value of an offshore grid for North Sea offshore wind Hossein Farahmand, Daniel Huertas-Hernando, Leif Warland, Magnus Korpås and Harald G. Svendsen Abstract Grid connection is a critical factor for the integration of large scale wind power. This factor is even more important in the framework of transnational power exchange which is a way to improve power system operation. In this paper a comparison study has been carried out between two different grid building strategies for offshore wind farms in the North Sea using the 23 medium wind scenario from the TradeWind project []. These strategies are i) radial and ii) meshed grid configuration. The paper has considered active power losses for both strategies and capture the effect of losses on different power system aspects, such as the total soci-economic benefit associated with each strategy, offshore wind power utilization, power exchange between the grid points, grid bottlenecks and utilization of HVDC connections. Using a meshed grid compared to radial there will be a total benefit of 2.7 billion Euro over the economic life time of the grid. However this benefit will be increased by.3 billion Euro by taking into account the grid losses for both cases. The results shows the benefit of using meshed offshore grid for future European power system with a large penetration of off- and onshore wind power. Index Terms Offshore wind energy, North Sea super-grid, Grid active power losses, Renewable energy. I. INTRODUCTION OFFSHORE wind farms are gradually being planned and built further from the shore. Grid connection is a critical factor for successful large scale integration of offshore wind power. The increased integration of wind power, both onshore and offshore, and the demand for improved power system operation give rise to a growing need for transnational power exchanges. The flow-based market model Power System Simulation Tool (PSST), developed by SINTEF Energy Research and used in projects such as TradeWind [] and OffshoreGrid [2], is a tool for studying the effect of large scale penetration of wind power in the European power system, that accounts for wind variations and network bottlenecks on production, demand and prices. PSST is a market model that includes linear DC power flow [3] as constraints to the optimization problem. PSST finds the optimal generation dispatch for each of the year, taking into account a detailed grid description. One of the assumptions of a DC power flow is that the resistances in transmission lines are negligible, thus ignoring with Department of Electric Power Engineering, Norwegian University of Science and Technology (NTNU), Trondheim NO-749, Norway Email: Hossein.Farahmand@elkraft.ntnu.no with SINTEF Energy Research, Trondheim NO-7465, Norway Email: daniel.h.hernando@sintef.no, Leif.Warland@sintef.no, Magnus.Korpas@sintef.no, Harald.Svendsen@sintef.no all active power losses. However, the total power loss in the transmission system can be as much as 4 to 7 % of the total power consumption, and it is therefore important to include it when studying large systems. The inclusion of losses effectively puts a cost on power transmission that changes both the total generation cost and the optimal generation dispatch as compared to the lossless situation. It is the influence on generation dispatch and thereby on the power flow which is the main motivation for including losses in this study. Several approaches for including losses in the PSST model have been implemented and assessed for the study in this paper. In paper [4] a comparison study between radial and offshore meshed grid was done for the 23 medium wind scenario of TradeWind (32 GW of installed wind in continental Europe []). The optimal grid design for each strategy is found by the Net-Op grid optimization tool [5]. The offshore grid gave an annual total benefit for the European interconnected power system of 2.6 billion Euro as compared with the radial grid. These results were however obtained neglecting losses in the power system. This paper aims to study how inclusion of power losses affects the results from the previous study [4]. II. POWER SYSTEM SIMULATION TOOL (PSST) In the European project TradeWind [], a model of the European power system was established and by simulations were run for different scenarios up to year 23. The main focus of the TradeWind project was to investigate how large amounts of wind power may affect the power system operation, and emphasis was put on market design and need for new transmission capacity. For this purpose a flow based market model, referred to as the PSST, was developed. The PSST tool and how transmission power losses can be included in the marked model, is briefly described in the next two subsections. A. PSST description PSST is a simulation tool based on a market model with simplified grid representation, assuming aggregated capacities and marginal costs of each generator type within specified grid zones. PSST assumes a perfect market (nodal pricing) and runs an optimal DC power flow that minimizes the total generation costs in the system for each of the year. The optimization takes into account the high voltage (HV) network topology, capacity limitations on generators and interconnectors, wind power variations, hydro power characteristics and fuel price scenarios. 978--4244-847-//$26. 2

2 The free (controllable) variables in the optimal power flow problem are the power output of all generators and the flow on HVDC interconnections. The power outputs of the generators depend on the maximum and minimum capacity, marginal cost relative to other generators and limitations of power flow on the physical lines. Aggregated wind farms are modelled as generators with maximum power equal to the available wind power for the specific. The marginal cost of wind production is set to zero, so that wind power plants will always produce if not limited by grid constraints. Marginal costs of hydro power are determined by the so-called water values [6], deduced from the EMPS model [7], and the current reservoire level for the simulated. The European grid model used in the simulations consists of separate DC power flow data files covering the Continental [8], Nordic, UK and Ireland regions as defined by the European Network of Transmission System Operators for Electricity (ENTSO-E). The entire model consist of 4 nodes, 2222 branches, 56 HVDC connections, 54 generators and 52 wind farm clusters []. In order to study the main power flows in the system, each country has been divided into one or more zones. Due to limited data available, all branches within a country have been modelled with unlimited capacity except the Nordic countries and parts of Germany. Net transfer capacities (NTC) between countries, as given by ENTSO-E, are used as constraints in the power flow optimization. B. Power losses in DC Power Flow The PSST marked model uses a DC optimal power flow. One of the assumptions of the DC power flow description [3] is that all active power losses can be ignored. The resulting dispatch of power production given by the optimization will then be significantly less than the actual value, and the problem of transporting power over great distances is not reflected by the model as long as the losses are not included in the optimization. Active power losses can be included in a DC optimal power flow analysis in several ways. Two different approaches have been considered in this study, where both involve iterations: ) Simply account for losses, where computed losses P loss = RI 2 (constant values) are injected on transmission lines before the next iteration; and 2) Include losses in the optimization through a linearization of the quadratic power losses around values computed from the previous iteration P loss = A + B I.HereA is the "constant" value of the losses at the working point computed in the previous iteration and B is the value of the slope for the first order linear expansion term around this point. Both approaches require an iterative method, where the parameters of the loss description is updated between each LP solution within one optimal power flow. In the linearization approach, both the constant value A and the slope of the losses B are calculated for each iteration. In principle both values must be updated between each iteration, but keeping the slope B fixed has the distinct advantage of allowing warm start of the LP problem (i.e. using the previous solution as a start point for the next iteration) giving a significant improvement in calculation time, especially for cases where the DC optimal power flow has to be solved many times, as is the case in PSST studies that typically run for each of a whole year. In this paper the transmission power losses are included in the optimization problem using the method of iteratively upgrading the constant part of the linearization only. HVDC power losses are assumed to be linear with the flow, and are handled by using two state variables for every HVDC connection, one for each direction where both have to be greater than zero. The HVDC active power losses is consider as the constant percent of the exchange power at HVDC cable. Two different cable technologies are considered for HVDC connections, LCC or VSC. LCC HVDC technology is used for point-to-point connection between mainland converter substation (CVST) and offshore wind farm while VSC HVDC technology is mainly used for connecting two offshore wind farms. Table I shows the percentage of losses for different cable technologies [9]. TABLE I PERCENTAGE OF LOSSES FOR DIFFERENT HVDC CABLE TECHNOLOGIES HVDC cable Technology Losses typical system [%] LCC HVDC 3.5 VSC HVDC 5 III. OFFSHORE GRID STRATEGIES In this paper, the PSST tool is used to investigate two different strategies for the development of the grid connection of offshore wind farms in the North Sea, namely: Radial Grid: Radial connection between each offshore wind farm and the main grid onshore and point to point HVDC connections between countries across the North Sea (see Figure a, c). Offshore Grid: A strategy based on the use of offshore nodes to build a meshed HVDC offshore grid (see Figure b, d). The scenarios used are the medium wind 23 from TradeWind [], except for the load forecast data for which the Combined high renewables and efficiency load demand scenario from EWEA [] has been used instead. The grid design used in PSST for each strategy is shown in Figure a, b). These offshore grid designs have been determined by the Net-Op grid optimization tool [5]. Net-Op is a transmission expansion planning tool for power systems with large shares of renewable energy sources like e.g. wind. Figures c, d), show the labels used for each country, the offshore wind farm clusters (O) considered in the Net- Op optimization and the corresponding CVST connecting the offshore HVDC cable to the main AC grid. Table II lists all the labels further used in the text. Several important differences between Net-Op and PSST should be mentioned: i) PSST includes detailed onshore grid topology (see Red lines and nodes in Figures a, b) whereas in Net-Op, countries are modeled as single nodes (see Figures c, d). Net-Op only includes net transfer capacity limits

3 TABLE III OPERATIONAL SAVINGS Cases Mill e Without grid Loss 4.6 With grid Loss 29. PSST radial grid PSST offshore grid TABLE IV INVESTMENT COST [4] o 6 N NO o 6 N 58 o N 56 o N GB O NO O DE O DK CVST DK NO Grid topologies Mill e 58 o N 56 o N GB O NO O NO O DE O DK CVST DK Radial grid 8283.2 Meshed grid 7279.4 Difference 3.8 54 o N 52 o N 5 o N GB B O B CVST N O N CVST B o 3 o E 6 o E 9 o E N DE Net-Op radial grid 54 o N 52 o N 5 o N GB B O N O B CVST N CVST B o 3 o E 6 o E 9 o E N DE Net-Op offshore grid Fig.. Grid configurations:red lines: AC grid; Blue lines (in c and d): Connection between AC node and CVST; White lines (in a, b) and green lines (in c, d): HVDC connections; Google Earth maps in (a,b) under c 29 Google, c 29 Europa Technologies, Image c 2 GeoContent, c 29 Tele Atlas TABLE II COUNTRY, LABEL, CONVERTER SUBSTATION (CVST) AND OFFSHORE WIND FARM (O) Germany Denmark Norway Netherlands Belgium UK DE DK NO NL BE GB DK CVST NL CVST BE CVST DE O NO O NL O BE O GB O TABLE V TOTAL BENEFITS Cases Mill e Without grid loss 2765.5 With grid losses 2986.8 IV. RESULTS In this paper the impact of losses on the results presented in [4] have been addressed. Losses influence the operating costs and thereby also the difference in costs between radial and meshed offshore grid. Different cases will be present, addressing the impact that power losses have on different power system aspects, e.g. power exchanges between countries, offshore wind power utilization, grid congestions and utilization of HVDC cable capacity. between countries but no internal grid constraints for each country; ii) Only the farthest offshore wind farms to shore have been considered in the Net-Op optimization for the radial and offshore grids. Additional wind farms closer to shore have only been considered in PSST as radially connected to land (see Figures a, b). iii) In PSST the future connects between Norway and Germany (NorGer) as well as second NorNed cable between Norway and the Netherlands have been considered. In the TradeWind medium wind scenario used [] there is 32 GW of installed wind power, of which 9 GW is offshore wind. These numbers are in agreement with EWEA s [] targets for the 23 medium scenario: 3 GW (8 GW onshore and 2 GW offshore). Note that EWEA s offshore wind target of 2 GW is higher than the 9 GW offshore wind used in this study. The case study thus presents a relevant wind scenario study case in line with EU targets, with a more conservative offshore wind installed capacity. The next section presents results addressing aspects such as the total socio-economic benefit associated with each offshore grid strategy, the export/import power exchanges, offshore wind power generation, grid congestions and utilization of HVDC cable capacity. A. Total benefit The operational savings calculated using PSST with and without losses are presented in Table III. The operational saving is defined as the annual operation cost difference between radial and meshed offshore grid. For both cases, with and without active transmission power losses, the savings are found to be positive. The largest difference is seen when including active power losses. It is 4.4 e/year greater than the case without losses. The total benefit is define as in [4]: Total Benefit= the operational saving Lifetime Factor + Investment Cost Difference. Difference is defined as Radial Meshed grid. The Life Time Factor for a lifetime of 3 years and 5% discount rate is 3 n= / ( +.5)n =5.3725 and it allows a comparison of the operational savings accumulated throughout the lifetime of grid project. The results are presented in Tables IV and V, and reflect the fact that the meshed grid configuration provides a flexible infrastructure to exchange potential wind energy across the North Sea area. However grid losses introduce more constraints for energy exchange and is translated into larger benefit associated with the meshed grid compared to the radial grid configuration. More detailed power flow results are presented in the next sections.

4.8.6.4.2.8.6.4.2 WATER LEVELS -- OPTGRID with Loss 2 3 4 5 6 7 8 9 WATER LEVELS -- RADIAL with Loss 2 3 4 5 6 7 8 9 FI NO SE PSST with grid losses.8.6.4.2 WATER LEVELS -- OPTGRID without Loss 2 3 4 5 6 7 8 9.8.6.4.2 WATER LEVELS -- RADIAL without Loss 2 3 4 5 6 7 8 9 FI NO SE PSST without grid losses 8 6 4 2 8 6 4 2 6 6 62 63 64 65 66 WIND GENERATION -- OPTGRID WIND GENERATION -- RADIAL 6 6 62 63 64 65 66 BE O DE O NO O Fig. 2. Hydro reservoir levels: Blue curve is Finland (Fi), Red curve is Sweden (SE) and Green curve is Norway (NO). All the curve are based on the present of reservoir capacities in each country Fig. 4. Offshore wind production without grid losses a) Wind production for the offshore grid case b) Wind production for the Redial grid POTENTIAL (MW) 5 WIND GENERATION -- OPTGRID 6 6 62 63 64 65 66 WIND GENERATION -- RADIAL 5 6 6 62 63 64 65 66 WIND GENERATION -- POTENTIAL 5 6 6 62 63 64 65 66 BE O DE O NO O Fig. 3. Offshore wind production wit grid losses a) Wind production for the offshore grid case b) Wind production for the Redial grid c) Potential wind production based on installed capacity scenarios B. Nordic hydro production, offshore wind production and energy exchange Figure 2 shows the simulated hydro reservoire filling levels throughout the year for the Nordic area. Figures 2a and 2b show that more hydro power has been used in Norway and Sweden in order to compensate for the transmission losses. However, in general Norwegian hydro level has been slightly increased at the end of the year around 6 which is due to the fact that high wind generation continued in the surrounding countries and the grid congestion in the central Europe, resulting in export of surplus wind power from the North Sea further north. Comparing Figure 3a, 3b and 3c, shows that the actual wind production is constrained. This is reflected by the dips in the wind generation shown in Figure 3a and 3b. Grid bottlenecks in the European continent prevents potential wind power to be utilized in certain periods. This is especially clear in the radial case where there is curtailment of wind production from the German wind farm clusters (Green line in Figure 3a and 3b). Comparing wind simulations ignoring losses (Figure 4) it is clear that transmission losses increase the level of wind power curtailment. This effect is quite pronounced in the German wind farm cluster DE O between s 62-64. Figure 5 illustrates the correlation between the hydro production in Norway (NO) and the total offshore wind production from the North Sea during s 55-85. In general, Figure 5a shows that the Norwegian hydro power follows the wind power fluctuations and ensure the balance between production and consumption. For instance in situation with low wind production around s 55 and 66 the hydro production in Norway follows the Norwegian load profile closely and take over the security of supply. However the surplus production during theses s can be exported to Continental Europe through HVDC links. In the next period (s 7-85), with high wind penetration from the North Sea the hydro production is substantially below the Norwegian demand. Figure 5b presents similar behaviour for the meshed offshore grid with and without grid losses while the hydro production for the case with grid losses is slightly higher than the case without grid losses. The additional power is used for compensating of grid losses. Power (MW) x 4 3 2.5 2.5.5 HYDRO -- LOAD -- WIND NO Hydro -- Meshed Offshore(Loss) NO Hydro -- Radial(Loss) Load Offshore wind 55 6 65 7 75 8 85 x 4 3 2.5 2.5.5 Fig. 5. HYDRO -- LOAD -- WIND NO Hydro -- meshed Offshore (Loss) NO Hydro -- Meshed Offshore (NoLoss) Load Offshore wind 55 6 65 7 75 8 85 Norwegian Hydro and load vs the North Sea offshore wind production Figure 6 illustrates the flow dynamics for the meshed offshore grid connection between the countries across the North Sea. The flow has more or less the same behaviour as discussed in [4] where for the connections : DE O NL O

5 (Figure 6a), GB O NL O (Figure 6e), NO O DE O (Figure 6c) and NO O GB O (Figure 6g) the large offshore wind production is re-directed towards the Netherlands and Norway. While in the radial offshore grid as it is shown in Figure 3b this amount of power has been reduced due to internal German system congestion and insufficient exchange capacity between Germany and Norway. The exchanged energy through GB O DE O (Figure 6b) between Germany and UK, the two largest offshore wind farm production during this period, has reduced significantly and in most of the time there is not exchange between these countries showing that the injected power has been absorbed by internal grid losses in these countries. When losses are included, Figure 6d shows that there only a small difference in the usage of the DE O connection between the radial and meshed grid structure. This is a significant difference from the similar result without losses (Figure 5 in [4]), which showed markedly more constraints in the German power system for the radial case. On the other hand, the Dutch wind farm connector to the land (NL O NL CVST (Figure 6h)) has the same as shown in [4] showing a redistribution of the wind power injection into the mainland grid in order to cover load and grid losses. The NL O BE O connection has also the same behaviour as in [4] showing wind penetration shifts more towards Belgium in the meshed offshore grid case (see Figure 6f). 2 5 5-5 - -5 DE O -- -2 6 6 62 63 64 65 66 25 2 -- DE O 5 5-5 - -5-2 6 6 62 63 64 65 66 4 2-2 -4 NO O -- DE O -6 6 6 62 63 64 65 66 4 3 2 - -2-3 NO O -- -4 6 6 62 63 64 65 66 Fig. 7. Example of flow results at the most exploited corridors, Green line represents the case taking into account the active power losses and the Red line without losses: For each connection A-B, positive values mean flow from AtoB:A B and negative values mean flow from B to A: A B in the meshed grid configuration and the results are shown in Figure 7. As the figure shows the exchange capacity between Germany and the Netherlands, Great Britain as well as Norway has significantly decreased showing that this amount of power is used to cover internal grid active power losses within German grid. Therefore introducing losses has highly affected the penetration of wind in countries across the North Sea. 2 - DE O -- -2 6 6 62 63 64 65 66 2 -- DE O - -2 6 6 62 63 64 65 66 4 2 NO O -- DE O -2-4 -6 6 6 62 63 64 65 66-5 - -- DE O -- DE O [Rad] -5 6 6 62 63 64 65 66 4 (e) 3 2 - -- -2 6 6 62 63 64 65 66 2 (f) - -- BE O -2 6 6 62 63 64 65 66 4 (g) NO O -- 2-2 -4 6 6 62 63 64 65 66 6 (h) 4 2-2 -- NL CVST -4 -- NL CVST [Rad] -6 6 6 62 63 64 65 66 Fig. 6. Example of flow results at the most exploited corridors, Green line represents the case taking into account the active power losses and the Red line without losses: For each connection A-B, positive values mean flow from AtoB:A B and negative values mean flow from B to A: A B As it has been mentioned in sections IV-A and IV-B the effects of grid bottlenecks is more pronounced in the case with power losses than without losses. This paper investigate the flow between the most utilized offshore grid HVDC links C. Energy exchange duration Duration curves for annual exchange of energy through the meshed offshore HVDC links are shown in Figure 8. Generally HVDC usage has been reduced in the case with active power losses meaning that all countries could use the available wind power to cover inter area losses. DE O -- - 2 4 6 8 DE O -- - 2 4 6 8 DE O -- NO O 5-5 2 4 6 8 2 -- -2 2 4 6 8 -- BE O (e) - 2 4 6 8 -- NO O 2-2 (f) 2 4 6 8 Fig. 8. Utilization of the meshed offshore HVDC connections: The offshore grid with- (blue curves) and without transmission active power losses (red curves) In the case of radial offshore grid, the point-to-point connection between CVSTs in different countries are represented in Figure 9. As it is shown in this figure the exchange energy has been reduced taking into account the grid losses except the connection between Norway and Germany (Figure 9). The exchanged power from Norway has been increased in order to cover the grid losses in

6 Germany. The internal grid congestion in Germany adds the this energy re-dispatch towards Norway. -- DK CVST - 2 4 6 8 NO -- CVST - 2 4 6 8 NO -- NL CVST CVST - 2 4 6 8 5 -- -5 2 4 6 8 GB -- BE CVST CVST 5-5 (f) 2 4 6 8 Fig. 9. Utilization of the radial offshore HVDC connections: The offshore grid with- (blue curves) and without transmission active power losses (red curves) The annual power exchange between different European countries for both meshed and radial offshore grid strategies is shown in Figure. Due to highly changed flow pattern in the countries surrounding the North Sea all the exchange power to/from neighbouring countries has been substantially altered. This effect also influences exchange between countries further south. The most affected countries are Germany and Norway and the main corridors are NL-DE, FR-DE, No-DE, SE-NO and IT-FR. UA-SK UA-RO RS-RO SK-PL SE-PL SE-NO NO-NL RS-MK SI-IT UA-HU SK-HU RS-HU RO-HU SI-HR RS-HR HU-HR MK-GR IT-GR NO-GB NL-GB IE-GB IT-FR GB-FR SE-FI RU-FI PT-ES FR-ES SE-DK NO-DK SE-DE PL-DE NO-DE NL-DE LU-DE GB-DE FR-DE DK-DE SK-CZ PL-CZ DE-CZ IT-CH FR-CH DE-CH RS-BG RO-BG GR-BG NL-BE LU-BE GB-BE FR-BE RS-BA HR-BA SI-AT IT-AT HU-AT DE-AT CZ-AT CH-AT -4-3 -2-2 Electricity transfer [TWh] Fig.. Annual exchange flow between the countries taking into account the transmission losses: Red bars - Radial grid case; Blue bars - Meshed offshore grid case There is higher benefit associated with the meshed offshore grid as shown in Table V. This is due to a better and more flexible utilization of exchange infrastructures. Therefore more power can be injected into mainland power grid and this is clearly observed in Figure by generally larger bar for meshed offshore power grid. This effect is more significant here, taking into account power losses than observed in [4]. V. CONCLUSIONS A comparison between two different offshore grid expansion strategies in the North Sea has been studied. In the absence of the active power losses the total benefit of meshed offshore grid with respect to the radial grid is estimated to be 2.7 Billion Euro. This shows the effectiveness of meshed grid to relieve the expected grid bottlenecks due to high penetration of wind power from the North Sea. Taking into account the losses makes the power flow more constrained and meshed grid strategies play an even more important role to relieve grid bottlenecks. This is reflected in the total benefit results which is then increased to 3 Billion Euro. Future work will include reserve procurement in each control area across the North Sea and identifying needs for onshore grid reinforcement in order to improved distribution of onshore and offshore wind. VI. ACKNOWLEDGEMENTS This work has been financed by NOWITECH FME centre (www.nowitech.no) and KMB project Balancing Management in Multinational Power Markets. REFERENCES [] EU, Final report. TradeWind EU-IEE project, Tech. Rep, 29. [Online]. Available: www.trade-wind.eu [2] EU s intelligent energy-europ programme, OffshoreGrid. [Online]. Available: www.trade-wind.eu [3] B. Stott, J. Jardim, and O. Alsac, DC power flow revisited, IEEE Transaction on Power Systems, vol. 24, Issue 3, pp. 29 3, Aug. 29. [4] D. Huertas-Hernando, H. G. Svendsen, L. Warland, T. Trötscher, and M. Korpås, Analysis of offshore grid alternatives for north sea offshore wind farms using a flow-based market model, in Proceedings of the European Energy Markets Conference (EEM ), Madrid, SPAIN, 23-25 June 2, pp. 6. [5] T. Trötscher, M. Korpås, and J. O. Tande, Optimal design of a subsea grid for offshore wind farms and transnational power exchange, in Proceedings of the European Wind Energy Conference and Exhibition, Madrid, SPAIN, 23-25 June 29, pp. 63 66. [6] O. B. Fosso, A. Gjelsvik, A. Haugstad, B. Mo, and I. Wangensteen, Generation scheduling in a deregulated system: The norwegian case, IEEE Transaction on Power Systems, vol. 4, Issue, pp. 75 8, Feb. 999. [7] O. Wolfgang, A. Haugstad, B. Mo, A. Gjelsvik, I. Wangensteen, and G. Doorman, Hydro reservoir handling in norway before and after deregulation, Energy, vol. 34, Issue, 29. [8] Q. Zho and J. Bialek, Electricity market integration in europe, IEEE Transaction on Power Systems, vol. 2, Issue, pp. 782 787, May 25. [9] Erik koldby, the power grid. ABB A/S: Symposium Energy and CO2 Emissions /Politics-Global CO2 Economics. [Online]. Available: http://static.sdu.dk [] European wind energy association EWEA, pure power: Wind enery scenarios up to 23, 29. [Online]. Available: www.ewea.org

7 BIOGRAPHIES Hossein Farahmand was born in Iran, on September 6, 979. He received both B.Sc. and M.Sc. in electrical engineering in 22 and 25 respectively. Currently he is pursuing the Ph.D. degree in the area of balance management in multinational power markets at Department of Electric Power Engineering, Norwegian University of Science and Technology (NTNU), Trondheim, Norway. Daniel Huertas-Hernando was born in Spain, on May 6, 975. He received M.Sc. and Ph.D. in Theoretical Solid State Physics in 998 and 22 respectively. Currently he is Research Scientist at SINTEF Energy Research. Research activities focus on modeling of grid connection of large scale offshore wind power, wind forecast uncertainty and balancing of intermittent renewable generation. Leif Warland received his siv.ing (graduate degree in electrical engingeering) and dr.ing (Doctorate in electrical engingeering) from Norwegian University of Science and Technology (NTNU), Trondheim, Norway in 997 and 22 respectively. He is currently working at SINTEF Energy Research in Trondheim. Magnus Korpås received his siv.ing (graduate degree in electrical engingeering) and dr.ing (Doctorate in electrical engingeering) from Norwegian University of Science and Technology (NTNU), Trondheim, Norway in 997 and 22 respectively. He is currently working at SINTEF Energy Research in Trondheim. Harald Svendsen was born in Norway in 975. He received his cand.scient. from the University of Oslo in 999, and his PhD from Durham University in 24, both in the field of theoretical physics. His work experience includes two years at the Max Planck Institute for Gravitational Physics in Germany and two years at Senergy Econnect, a renewable energy consultancy and product development company in the UK, before joining SINTEF Energy Research in 29.