Tri-County Aggregates Ltd. 92 Kenhar Drive North York, Ontario, Canada M9L 1N2

Similar documents
ENVIRONMENTAL NOISE ASSESSMENT

Appendix K. Environmental Noise Assessment

Noise Assessment Report

Guelph Curling Club Development Traffic Noise Impact Study

Noise Assessment Report Riverside Drive Phase I

Noise Feasibility Study EMGO (North Oakville I) Ltd., Town of Oakville, Ontario

Noise Assessment Report Main Street, Residential Site Cambridge, ON

TABLE OF CONTENTS LIST OF TABLES

Stationary Noise Assessment. 70 Richmond Road. Ottawa, Ontario

Place Vanier Édifice AEFO

REP Fotenn Bank Phase 1 Feasibility Noise Study with Building Component AmendmentPage 1 of 21

Noise Feasibility Study, McGibbon Condominium 71 Main Street South Georgetown, Ontario

Noise Feasibility Study Proposed Residential Building 103 Dundas Street West Oakville, Ontario

ACOUSTIC ASSESSMENT OF THE PROPOSED PLANTAGENET ASPHALT PLANT

Noise Feasibility Study Proposed Residential Development, 361 Tanbark Road Niagara-on-the-Lake, Ontario

DCR Phoenix. Type of Document 1st Submission. Project Name 256 Rideau Street Ottawa, Ontario. Project Number OTT A0. Prepared By: Nicole Ruyf

Noise Assessment & Control Transportation Noise Assessment 303 Lebreton Street South, 460 St. Laurent Boulevard Ottawa, Ontario Ottawa, Ontario

Noise Control Study. for. Avalon Public School Portobello Boulevard at Stormwind Avenue in Ottawa, Ontario. Revision 1

Traffic Noise Assessment Baseline Road Ottawa, Ontario

Noise Feasibility Study Proposed Hospice 2050 University Avenue East, Waterloo, Ontario

Noise Feasibility Study Proposed Residential Development Old Barber House 5155 Mississauga Road City of Mississauga, Ontario

Attachment A: Background Noise Assessment for Brandon Thermal Generating Station

Noise Feasibility Study Stacked Townhouse Development Glenashton Drive (Block 55) Oakville, Ontario

Noise Feasibility Study Proposed Residential Development Brock Road Pickering, Ontario

NOISE IMPACT ASSESSMENT RIVERSIDE SOUTH PHASE 9-4 CITY OF OTTAWA

Table of Contents. 174 Forward Avenue SACL Project #B7-170 Feb 22, Page ii

NOISE CONTROL STUDY FOR PHOENIX HOMES 3654 & 3658 JOCKVALE ROAD APRIL 28, 2011 REV 1 TABLE OF CONTENTS 1.0 INTRODUCTION BACKGROUND...

Noise Assessment Report

Fayez & Patrizia Ghadban

Roadway Traffic Noise and Vibration Assessment. The Bridge Wesleyan Church Addition. Ottawa, Ontario

671 Victoria Road North City of Guelph Traffic Noise Study. Paradigm Transportation Solutions Limited

NOISE IMPACT ASSESSMENT FOR SITE PLAN APPROVAL 12 HAMILTON AVENUE NORTH OTTAWA, ON.

noise impact study project number: 03117

Noise Feasibility Study Proposed 4 Storey Apartment Building 226 Woolwich Street South Breslau, Regional Municipality of Waterloo

Noise Control Feasibility Study 173 / 175 / 177 Preston Street Ottawa, Ontario

Table of Contents... ii 1. Introduction... 1

DETAILED NOISE CONTROL STUDY OF PROPOSED PHASE 2 CONDOMINIUMS AT 655 & 755 ANAND PRIVATE OTTAWA Ontario Inc.

Noise Feasibility Study 2120 Hurontario Street and Grange Drive City of Mississauga, Ontario

Roadway Traffic Noise Assessment Montreal Road. Ottawa, Ontario

Transportation Noise & Vibration Assessment Scott Street. Ottawa, Ontario

ENVIRONMENTAL NOISE ASSESSMENT

Proposed Residential/Institutional Development Independent and Assisted Care Senior s Residence 190 Richmond Road Ottawa, ON K1Z 6W6

Mann Avenue Development 87 Mann Avenue Noise Control Study

Roadway Traffic Noise Feasibility Assessment. Ironwood Subdivision. Ottawa, Ontario

1. Introduction Site Noise Impact... 1

Traffic Noise Assessment. 5 Orchard Drive. Stittsville, Ontario

Noise Assessment Report

Noise Feasibility Study Framgard Apartments (South Block) NW corner of Britannia Road and Regional Road 25 Town of Milton, Ontario

Roadway Traffic Noise Assessment Chapel Street. Ottawa, Ontario

Environmental Noise Assessment Montreal Road. Ottawa, Ontario

Brigil Homes. Noise Impact Assessment. Type of Document Site Plan Submission. Project Name Petrie s Landing, Phase 2. Project Number OTT A0

Environmental Noise Assessment Feasibility Assessment 92 Plains Road East

NOISE IMPACT ASSESSMENT FOR SITE PLAN APPROVAL 47 HAVELOCK STREET OTTAWA, ON. REVISED with ADDENDUM for ROOFTOP OUTDOOR LIVING AREA

Noise Feasibility Study 2480 Old Bronte Road, Oakville, Ontario

The anticipated critical noise receptors and their locations are identified as follows and are shown on Figure 3:

NOISE IMPACT ASSESSMENT FOR SITE PLAN APPROVAL 47 HAVELOCK STREET OTTAWA, ON.

ACOUSTIC ASSESSMENT OF TRAFFIC NOISE IMPACTS ON THE PROPOSED AVALON CATHOLIC ELEMENTARY SCHOOL

Avalon Encore Stage Tenth Line Road Infusion Terrace, Block 233 City of Ottawa Environmental Noise Impact Assessment

Prepared for: Gapatas Inc Sherwoodtowne Boulevard, Unit 106 Mississauga, ON L4Z 1Y5. Our File No:

Noise Feasibility Study Proposed Stacked Townhouse Development, 3060 and 3072 Sixth Line, Town of Oakville, Ontario

Road and Rail and Vibration Noise Impact Study Valeriote Subdivision, Guelph, Ontario

R. BOUWMEESTER & ASSOCIATES

18 McArthur Avenue, Ottawa, Ontario Proposed Development Noise Study Report. Prepared for: Takyan Consulting By: ARCH-Nova Design Inc.

Traffic Noise Assessment. 333 Montreal Road. Ottawa, Ontario

NOISE IMPACT ASSESSMENT RIVERSIDE SOUTH PHASE 13 CITY OF OTTAWA

MINTO COMMUNITIES INC GREENBANK ROAD NOISE CONTROL FEASIBILITY STUDY

23, 33 & 39 DEERFOX DRIVE NOISE CONTROL FEASIBILITY STUDY

NOISE IMPACT ASSESSMENT STUDY

MEMORANDUM. Peer Review of Acoustic Assessment Report Freymond Quarry Township of Faraday

UAL URBAN AERODYNAMICS LTD

NOISE CONTROL FEASIBILITY STUDY. MINTO COMMUNITIES INC. Clarke Lands CITY OF OTTAWA

Appendix M. Noise Assessment

Noise Feasibility Study Proposed Residential Development Kemsley Farm St. Thomas, Ontario

Noise Feasibility Study Proposed 6-storey Seniors Condominium 7480 Derry Road West Milton, Ontario

Noise Feasibility Study, Proposed Hotel Development, Living Waters Resort Collingwood, Ontario

TRAFFIC NOISE IMPACT ASSESSMENT FOR THE PROPOSED MULTI-UNIT RESIDENTIAL DEVELOPMENT AT 20 MARK AVENUE

ENVIRONMENTAL NOISE ASSESSMENT

Executive Summary. An inspection of the GCP windows indicates that the operable window seals and operable window closure mechanism should be upgraded.

Road and Rail and Vibration Noise Impact Study Valeriote Subdivision, Guelph, Ontario

ASSESSMENT OF THE TRAFFIC NOISE IMPACTS AT THE PROPOSED HOLIDAY INN DEVELOPMENT LOCATED AT 235 KING EDWARD AVENUE

ENVIRONMENTAL NOISE ASSESSMENT

Policy for the Assessment and Mitigation of Traffic Noise on County Roads

January 16, Mr. David Trotman Mono Centre Road Mono, ON L9W 6S3

Noise and Vibration Feasibility Study 1 and 15 Stevenson St & 8 William St Guelph, Ontario

ENVIRONMENTAL NOISE ASSESSMENT

Burnett Lands Greenbank Road. Noise Impact Feasibility Report

Traffic Noise Introduction to Traffic Noise Analysis and Abatement

Ontario County Landfill Proposed Eastern and Wrap-Around Expansions Ontario County, Town of Stanley, New York. Operating Noise Impact Assessment

3.5.1 Outdoor Living Areas (OLAs) Indoor Sound Levels... 8

ACOUSTIC ASSESSMENT REPORT FREYMOND QUARRY

SS WILSON ASSOCIATES Consulting Engineers

APPENDIX D EXISTING ROADWAY NOISE, AIR QUALITY AND GROUND VIBRATION ANALYSIS

ASSESSMENT OF THE TRAFFIC NOISE IMPACTS AT THE PROPOSED RESIDENTIAL DEVELOPMENT 364 ST. PATRICK STREET

NOVATECH ENGINEERING CONSULTANTS LTD. Suite 200, 240 Michael Cowpland Drive Ottawa, Ontario K2M 1P6

Draft Noise Abatement Guidelines

APPENDIX I. Environmental Noise Assessment Reports

Noise Abatement Guidelines. Regional Official Plan Guidelines

TABLE OF CONTENTS. Figure 5: Modelled Concentrations of Suspended Particulate Worst-Case 24-Hour Average

APPENDIX H COMPARISON OF FUTURE NOISE BARRIER OPTIONS

NOISE IMPACT STUDY - HORIZONTAL DIRECTIONAL DRILLING FOR BLUEWATER RIVER CROSSING REPLACEMENT PROJECT

Transcription:

20 October 2016 Tri-County Aggregates Ltd. 92 Kenhar Drive North York, Ontario, Canada M9L 1N2 Attn: CC: Re: Mr. Larry Pevato, Tri-County Aggregates Mr. Bob Long, Long Environmental Noise Impact Study for the Proposed Tri-County Pit Response to Second Valcoustics Peer Review June 17, 2016 Aercoustics Engineering Limited (Aercoustics) has reviewed the second peer review letter prepared by Valcoustics Canada Ltd. (Valcoustics) dated June 17, 2016. We submit the following itemized responses to Valcoustics peer review comments. A summarized version of the comments is presented below along with our responses. The numbering below aligns with the numbering used in the Valcoustics letter. Note that numbers that are missing represent items that have been resolved. 5. Table 2 and Table A should be revised to indicated that Loading and Shipping operations are permitted 06:00-07:00 Monday to Friday and 07:00-12:00 on Saturdays We confirm that both Loading and Shipping operations are indicated to be permitted outside of daytime hours on the site plans. This has already been updated on the Operational Plan dated May 5, 2016. 6. Valcoustics would like to review a copy of the latest site plans to confirm the note about construction activities has been added as described. Aercoustics can confirm that this note has been added in the Operational Plan dated May 5, 2016. We expect that the updated final site plans will be forwarded to Valcoustics for final review & approval. ACTION: Forward final site plans to Valcoustics for review & approval.

Long Environmental / Tri-County Pit Peer Review Responses 2 Page 2 7. Aercoustics used a 50% duty cycle for shipment loader operation, a 100% duty cycle should be used to reflect a worst case predictable condition of a busy operation A 100 % duty cycle was modelled at Valcoustics request and there was no effect on the reported maximum predicted sound levels. For example, the sound level at Receptor R02 increased from 41 dba to 42 dba for one scenario, but the maximum level of 45 dba experienced by R02 at the worst case scenario did not change. All predicted sound levels remained below the sound level limits. 8. Valcoustics requests specific details of the processing plant noise enclosure to be provided on the site plans In Tables 3 and B, the report provides the required noise emission levels to be satisfied for the enclosed processing plant; 83 dba and 72 dba in the loud side and quiet side respectively. In the recommended noise controls, the orientation of the enclosure, with the quiet side facing R02, is provided. This is also reflected in the Operational Plan notes and clearly shown on the drawing. These form the noise performance requirements and are independent of construction details. Valcoustics has requested a post-construction performance verification by an acoustical consultant. Aercoustics agrees that a one-time acoustical audit to confirm the sound power of the ISO enclosure is appropriate. ACTION: The requirement for this one-time audit shall be added to the site plans and should be conducted as soon as possible after the enclosed plant becomes operational. 9. Valcoustics requests that the boundary of the pit Stages be clearly shown. The Operational Plan drawing correctly illustrates the Stages with directions of extraction. Valcoustics requests that the boundary between each Stage be clearly marked, since certain noise controls are tied to these areas. ACTION: The Stage boundaries on the Operational Plan should be clearly marked. 11. Valcoustics requests additional detail on how the shipment truck 3 m deep cut out for Stage 1 will be created and noise impacts mitigated The following details were confirmed with the planner and the proponent: They will initially strip and built the berms. Then any haul road aggregate could be stockpiled, unprocessed, near the Stage 1 plant location. Processing would be

Long Environmental / Tri-County Pit Peer Review Responses 2 Page 3 done after all of the site preparation, including the haul road cut, has been completed. 13. Clarification is requested for Stage 3 operation. The recommended extraction direction is towards R02 but the figures appear to show extraction progressing towards R07. As discussed with Valcoustics, the direction of extraction during the first lift of Stage 3 can be in any direction. The noise controls restrict all of Stage 3 to a northeast direction for simplicity, but if an operational issue arises during the small first lift, a direction change will not affect the noise controls. ACTION: The Operational Plan dated May 5, 2016 has incorrect directions indicated in the Stage 3 and Stage 4 noise controls. These should be revised so notes N11 and N12 read: NORTHEAST and SOUTHWEST, respectively. 14. Stage 3 and Stage 4 require that the extraction loaders are to operate no more than 30 m from the working face. The direction of this requirement should be provided. As per the above note, this is resolved. 15. Additional detail on concrete recycling is needed. As noted in the report, Concrete Recycling may occur on this site. Aercoustics clarified that the Processing Plant operations include crushing of either native material or recycled material, or a blend. All of the noise control measures required of the portable processing operations apply to the concrete recycling operations, and only one may operate at a time. Valcoustics would prefer to see the recycling operations called out specifically in the Table in Note N3. ACTION: The first two rows of the Table in Note N3 should be updated to include CONCRETE RECYCLING PLANT. Specifically, Portable Processing Plant and Concrete Recycling Plant for the first row, and Enclosed Portable Processing Plant and Enclosed Concrete Recycling Plant for the second row. ACTION: Note N4 should include the word PORTABLE before PROCESSING PLANT, as in Only one portable processing plant

Long Environmental / Tri-County Pit Peer Review Responses 2 Page 4 16. Additional detail of potential noise impacts of off-site haul route noise is required. Valcoustics has requested road traffic noise calculations to determine the worst case change in hourly equivalent sound level, based on the draft MOE Noise Guidelines for Landfill Sites. As noted in the report, the proposed haul route is an existing tuck haul route that is used by the existing pits in the area. There is a single haul route option: exiting the site north on 17 th Line to County Road 3 and County Road 3 easterly. Refer to the attached excerpt from the Site Planning Report dated February 15, 2015 which describes the route and also the potential traffic impacts. Traffic data from the final Traffic Impact Study (TIS), dated March 2014 and prepared by C. F. Crozier & Associates Inc., was used. The TIS for the subject site predicts a total of 36 truck passes (18 in and 18 out) in a regular peak hour, averaged from a peak month. The noise impact study conservatively assumed 60 truck passes (30 in and 30 out) in a single peak hour, which addresses a rarer predictable worst case hour. The haul route noise analysis that follows assumed the more conservative number of 60 truck passes in a peak hour for the subject site (Tri-County Aggregates). A summary of the haul route road traffic noise calculations is provided in Table 1 which outlines the hourly traffic noise impact for the existing conditions and the Tri- County pit generated traffic. The predicted hourly sound levels used a reference distance of 30 m from the road. Table 1: Summary of Haul Route Traffic Noise Analysis 17 th Line Country Road 3 Noise from existing traffic 59 dba 66 dba Tri-County Pit new trucks per hour 60 60 Noise including Tri-County Pit traffic 66 dba 68 dba Difference in sound level 7 db 2 db MOE qualitative description Significant Insignificant The STAMSON calculation sheets are attached. The qualitative descriptions for change in sound level were adapted from the draft MOE Noise Guidelines for Landfill Sites (1998). The existing background traffic was determined by traffic counts conducted on October 30, 2013, which is at the end of the production season and likely did not include much or any truck traffic from the existing aggregate operations. It is likely that the background traffic during summer months is higher, which would result in a smaller change in sound level. It should therefore be emphasized that the above

Long Environmental / Tri-County Pit Peer Review Responses 2 Page 5 predicted changes in sound level are conservative and are comparing very quiet road traffic conditions to an assumed peak hour from the proposed operation. To conclude, the haul route road traffic noise predictions indicate that, at times, the maximum change in sound level on 17 th Line may be perceived as significant and the maximum change in sound level on Country Road 3 is insignificant. The proposed haul route remains the preferred route. 17. To address the Official Plan for the Township of East Garafraxa, a cumulative noise assessment of the haul route noise is needed. To address the cumulative noise concerns relating to the proposed haul route, road traffic from the adjacent proposed licence by Greenwood Construction has been assessed. The traffic study for this proposed site, dated February 2014 and prepared by Paradigm, was provided by the planner for the proposed Tri-County Pit. This traffic study indicated a maximum of 94 truck passes (47 in and 47 out) in an hour. This results in a cumulative change in sound level of 4 db relative to the proposed Tri-County Pit peak truck traffic. 18. Valcoustics recommends a noise monitoring program. Aercoustics does not agree that a regular periodic noise monitoring program is required for this site. In our opinion, a noise complaint response procedure can be more effective in addressing concerns or complaints of neighbours. Valcoustics considers this resolved subject to the inclusion of the one-time plant enclosure audit on the Operational Plan, as described in Item 8 above. 19. Valcoustics recommends a noise complaint procedure. Aercoustics can confirm that this note has been added in the Operational Plan dated May 5, 2016. We expect that the updated final site plans will be forwarded to Valcoustics for final review & approval. Please do not hesitate to contact us if any further clarifications are required. Yours Truly, AERCOUSTICS ENGINEERING LIMITED Derek Flake, M.Sc., P.Eng. Bob Rimrott, M.A.Sc., P.Eng.

Long Environmental / Tri-County Pit Peer Review Responses 2 Page 6 STAMSON 5.0 NORMAL REPORT Date: 20-10-2016 14:19:13 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: 17_line.te Time Period: 1 hours Description: 17th Line - Existing Road data, segment # 1: 17 Line ------------------------------- Car traffic volume : 87 veh/timeperiod Medium truck volume : 0 veh/timeperiod Heavy truck volume : 15 veh/timeperiod Posted speed limit : 80 km/h Road gradient : 0 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 1: 17 Line ----------------------------- Angle1 Angle2 : -90.00 deg 90.00 deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 1 (Absorptive ground surface) Receiver source distance : 30.00 m Receiver height : 1.50 m Topography : 1 (Flat/gentle slope; no barrier) Reference angle : 0.00 Results segment # 1: 17 Line ---------------------------- Source height = 1.96 m ROAD (0.00 + 59.12 + 0.00) = 59.12 dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq ---------------------------------------------------------------------------- -90 90 0.65 65.51 0.00-4.96-1.43 0.00 0.00 0.00 59.12 ---------------------------------------------------------------------------- Segment Leq : 59.12 dba Total Leq All Segments: 59.12 dba

Long Environmental / Tri-County Pit Peer Review Responses 2 Page 7 STAMSON 5.0 NORMAL REPORT Date: 20-10-2016 14:20:06 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: 17_line.te Time Period: 1 hours Description: 17th Line - Tri-County Trucks Road data, segment # 1: 17 Line ------------------------------- Car traffic volume : 87 veh/timeperiod Medium truck volume : 0 veh/timeperiod Heavy truck volume : 75 veh/timeperiod Posted speed limit : 80 km/h Road gradient : 0 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 1: 17 Line ----------------------------- Angle1 Angle2 : -90.00 deg 90.00 deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 1 (Absorptive ground surface) Receiver source distance : 30.00 m Receiver height : 1.50 m Topography : 1 (Flat/gentle slope; no barrier) Reference angle : 0.00 Results segment # 1: 17 Line ---------------------------- Source height = 2.40 m ROAD (0.00 + 65.62 + 0.00) = 65.62 dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq ---------------------------------------------------------------------------- -90 90 0.63 71.95 0.00-4.92-1.41 0.00 0.00 0.00 65.62 ---------------------------------------------------------------------------- Segment Leq : 65.62 dba Total Leq All Segments: 65.62 dba

Long Environmental / Tri-County Pit Peer Review Responses 2 Page 8 STAMSON 5.0 NORMAL REPORT Date: 20-10-2016 14:20:59 MINISTRY OF ENVIRONMENT AND ENERGY / NOISE ASSESSMENT Filename: 17_line.te Time Period: 1 hours Description: 17th Line - Tri-County and Greenwood Trucks Road data, segment # 1: 17 Line ------------------------------- Car traffic volume : 87 veh/timeperiod Medium truck volume : 0 veh/timeperiod Heavy truck volume : 169 veh/timeperiod Posted speed limit : 80 km/h Road gradient : 0 % Road pavement : 1 (Typical asphalt or concrete) Data for Segment # 1: 17 Line ----------------------------- Angle1 Angle2 : -90.00 deg 90.00 deg Wood depth : 0 (No woods.) No of house rows : 0 Surface : 1 (Absorptive ground surface) Receiver source distance : 30.00 m Receiver height : 1.50 m Topography : 1 (Flat/gentle slope; no barrier) Reference angle : 0.00 Results segment # 1: 17 Line ---------------------------- Source height = 2.40 m ROAD (0.00 + 69.06 + 0.00) = 69.06 dba Angle1 Angle2 Alpha RefLeq P.Adj D.Adj F.Adj W.Adj H.Adj B.Adj SubLeq ---------------------------------------------------------------------------- -90 90 0.63 75.39 0.00-4.92-1.41 0.00 0.00 0.00 69.06 ---------------------------------------------------------------------------- Segment Leq : 69.06 dba Total Leq All Segments: 69.06 dba

11. TRAFFIC Crozier & Associates was retained to conduct a traffic study in October 2013. Crozier s scope and a draft of its report were reviewed by the County, the Township and its Consulting Engineer. It was confirmed, during a traffic review meeting on January 28, 2014 that the total annual aggregate production, to be transported on the 17 th Line haul road, will be 2 million tonnes: 1 million from the existing Greenwood pits and 1 million from the proposed Tri-County Pit. It was recognised, during meetings with the County and the Township, that structural improvements to the 17 th Line will be required. The Township s will retain it's Consulting Engineer for any necessary design and construction coordination. Crozier s Traffic Impact Study is bound in Appendix 7. It includes a complete traffic assessment, with plan and profile drawings of the 17 th Line and County Road 3. It is concluded that there is sufficient road capacity, mainline stopping sight distance and turning sight distances available for the proposed pit entrance and the intersection of the 17 th Line with County Road 3. Levels of service will be unchanged. The currently configured intersection of the 17 th Line with Dufferin County Road 3 will continue to operate at a Level Of Service B during peak hours under future total traffic conditions. Crozier s report was circulated to the County and the Township in April 2014. Comments have not yet been received. Tri-County's 2 - lane internal haul road extends 700 m from the 17th line to the stockpile and loading area. The incoming, south lane will be used for internal truck queuing. Parking on the 17th line will be prohibited. Since circulation of our TIS, consultants for Greenwood have advised that it intends to increase its total annual production to 2 million tonnes/year. Including the Tri-County production, up to 3 million to/year will be transported on the 17 th Line haul road. In its February 2014 Traffic Study, Greenwood s consultant advised that this total production can be supported on the 17 th Line and at County Road 3,with construction of a 25 m westbound left turn storage lane for the latter. In a 17 th Line Geotechnical Investigation, SPL Consultants reported that the majority of the existing granular base materials do not meet Provincial specifications. Complete reconstruction, with a 240 mm raise in pavement elevation, is recommended for long term haul road operation. C. F. Crozier & Associates Inc.: Traffic Impact Study, March 2014 Paradigm Transportation Solutions: Greenwood Construction Traffic Study, February 2014 SPL Consultants Limited: Geotechnical Investigation For 17 th Line, June 2014 EcoVue Consulting Services Inc.: Letter Re: Greenwood Pits Production, October 2014 Tri-County Aggregates Ltd., February 2015 TRI-COUNTY PIT - SITE PLANNING REPORT Page 48

February 28, 2014 Greenwood Construction Company Limited Future Expansion Volumes The expansion plan to 3,000,000 tonnes annually would result in a maximum truck volume of 47 trucks/hour exiting and 47 trucks/hour entering at the intersection of County Road 3 and 17 th Line during the peak month. TABLE 1: EXISTING AND FUTURE TRUCK TRAFFIC PEAK MONTH 1,000,000 Tonnes per Annum 3,000,000 Tonnes per Annum Days of Operation/Month 23 Days Days of Operation/Month 23 Days Peak Month % of Annual Volume 15% Percent Peak Month % of Annual Volume 15% Percent Average Day of Peak Month 6520 Tonnes Average Day of Peak Month 19563 Tonnes Tractor Trailer Use 85% Percent Tractor Trailer Use 85% Percent Tractor Trailer Total 5,540 Tonnes/Day Tractor Trailer Total 16,627 Tonnes/Day Tractor Trailer Capacity 38 Tonnes/Load Tractor Trailer Capacity 38 Tonnes/Load Number of Tractor Trailer Loads 146 Trucks/Day Number of Tractor Trailer Loads 438 Trucks/Day Tri axle Vehicles Use 15% Percent Tri axle Vehicles Use 15% Percent Tri axle Vehicle Total 980 Tonnes/Day Tri axle Vehicle Total 2936 Tonnes/Day Tri axle Vehicle Capacity 23 Tonnes/Load Tri axle Vehicle Capacity 23 Tonnes/Load Number of Tri axle Vehicle Loads 43 Trucks/Day Number of Tri axle Vehicle Loads 128 Trucks/Day Total Trucks 189 Trucks/Day Total Trucks 566 Trucks/Day Hours of Operation/Day 12 Hours Hours of Operation/Day 12 Hours Average Trucks Per Hour 16 Outbound Average Trucks Per Hour 47 Outbound Average Trucks Per Hour 32 In + Out Average Trucks Per Hour 94 In + Out The intersection impact at 17 th Line and County Road 3 is evaluated based on a 5 year forecast of traffic on County Road 3 as it is conventional that a future horizon year be examined. Therefore, the existing volumes on County Road 3 were increased by 1.6% per year from 2012 (date of the count) to 2019 based on the historical growth rate noted above. The existing and future projected volume at the intersection with County Road 3 and 17 th Line is shown below with an additional allowance for passenger cars generated by local residents. FIGURE 3: COMPARISON OF PROJECTED 2019 VOLUMES (AVERAGE DAY OF PEAK MONTH) Future 2019 (100,000,000 Tonnes) Future 2019 (300,000,000 Tonnes) 5 5 5 292 292 294 19 316 297 47 0 0 3 0 3 17th Line 3 0 5 3 17th Line 344 County Road 3 County Road 3 299 0 317 302 0 297 297 2 5 2 0 17 21 17th Line 19 52 17th Line 50 5 0 45 345 Page 4