Chino Valley Unified School District Monthly Construction Update

Similar documents
G703 Continuation Sheet Minimum Schedule of Values Please use the breakdown listed below when submitting your billing for the project

Update on FCPS Construction/Renovation Projects. June 2016

Building Excellence IV Capital Levy Projects Under Construction

Building Excellence IV Capital Levy Projects Under Construction

PAULDING COLLEGE & CAREER ACADEMY

Update on FCPS Construction/Renovation Projects. December 2015

Completed. Project. Melbourne High School. Comprehensive Additions and Renovations

FACILITY COMPONENTS - MIDDLE SCHOOL


RAYMOND EDUCATION CAMPUS

4.1.3 Project Manual

FACILITIES PROJECTS UPDATE BOARD OF EDUCATION. August 11, 2015

Oconomowoc Area School District Facility Construction Update July 27, 2018

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

MONTHLY PROJECT CONSTRUCTION PROGRESS REPORT #07. Latrobe Elementary School. Greater Latrobe School District

HIDDEN VALLEY ELEMENTARY SCHOOL

Boynton High School & Blackford Site

Oconomowoc Area School District Facility Construction Update June 29, 2018

Update on FCPS Construction/Renovation Projects. July 2016

Program Update. Chino Health Science Parking Lot

Cupertino Union School District

New Ringgold Middle School. Project Slideshow August 26, 2017

AZUSA UNIFIED SCHOOL DISTRICT

Seattle Public Schools Building Excellence IV Projects Under Construction

CESAR CHAVEZ LANGUAGE ACADEMY


PROJECT COMPLETED. Bayside High School. Comprehensive Additions and Renovations

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

DOCUMENT B. 2. The low bidder shall submit this Expanded Subcontractors Listing to the Owner within 24 hours after the bid opening.

LLANO ISD SCHOOL BOARD MEETING. January 2016

Independence Adult Center

Capital Projects Update

Invitation to Bid. RLS Construction Group requests your firm to submit a quotation on the following project:

Facility Improvements

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised

2006 FUSD Bond Information Guide

TABLE OF CONTENTS. (Δ = Rev 06/08)

SYLVAN. inspire MIDDLE SCHOOL. which is to. instruction and programs. in a safe, caring, and. collaborative learning community.

Santa Teresa High School

APPLICATION AND CERTIFICATE FOR PAYMENT

Nevada Joint Union HSD Facilities Improvement Plan - DRAFT ITEM NO. ITEM DESCRIPTION AREA (SF) PROJECT COST $/SF

M-DCPS MASTER SPECIFICATION GUIDELINES TABLE OF CONTENTS (TOC) Division 2 SITEWORK Last Revised

FACILITY COMPONENTS - ELEMENTARY SCHOOL

Update on FCPS Construction/Renovation Projects. August 2015

James Lick High School

Chenango Valley Central School District Potential Capital Project BCK-IBI Group Project No October 23, 2017

DOCUMENT BID DOCUMENT

Update on FCPS Construction/Renovation Projects. September 2015

Facility Improvements

Watercrest - Sand Hill - Columbia, SC TABLE OF CONTENTS PROCUREMENT AND CONTRACTING REQUIREMENTS

Lincoln Akerman School Hampton Falls, NH

Yardmen Arena Expansion & Renovation Project Update

Town of Falmouth FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage COSTS FOR SUBSTANTIAL IMPROVEMENTS / REPAIR OF SUBSTANTIAL DAMAGE:

Collins Middle School

TABLE OF CONTENTS. (Δ = Rev 11/15) Update #7

Heritage High School

CEFPI Monthly Meeting

TABLE OF CONTENTS. (Δ = Rev 04/17) Update #8

Capital Projects Update

Building Excellence IV Capital Levy Projects Under Construction

GEORGETOWN ISD 2010 BOND PROGRAM UPDATE. Huckabee APRIL 2012

HILLSIDE ELEMENTARY SCHOOL. Overview: Livingston School District Hillside Elementary School

MCER Study for Little Powder K-8

NALLE ELEMENTARY SCHOOL

FACILITIES LIFE CYCLE ANALYSIS

ADDENDUM 2 - JULY 14, 2015

Update on FCPS Construction/Renovation Projects. November 2015

Project Manual Index of Specifications Shenandoah Schools Concession Building

Facilities Construction

SHEPHERD ELEMENTARY SCHOOL

PRESENTATION JANUARY 24, 2017

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

FACILITY COMPONENTS - ELEMENTARY SCHOOL

Darlington Area Schools - Building Evaluations

Program Update. Michael Alexander Campus Center

Program Update. Data and Telecom Cabling-VPA, New Gym, & Physical Science. Physical Science Complex-Roof Replacement


Assessment Report Burgess Park Gymnasium. Summary

CONCURRENT ADVERTISEMENT FOR SUBCONTRACTOR PREQUALIFICATION AND BIDS

B. RESIDENTIAL MASTER PLUMBER $ $ $

PHASE I ACADEMIC BUILDING CORE RENOVATIONS RCNJ Project No C

Facilities Feasibility Study Matthew A. Henson ES Condition Assessment

Existing Site Aerial Frederick High School Feasibility Study September 5, 2012

EXHIBIT "A" WILLIAM S. HART UNIFIED HIGH SCHOOL DISTRICT HART HIGH SCHOOL; NEW 2-STORY DSA MODULAR CLASSROOM BUILDING

BOND CONSTRUCTION UPDATE

City of Treasure Island FEMA Cost Breakdown Worksheet For Substantial Improvement / Damage

J~e~~r Senior Director of Construction Services Facilities Design and Construction UNIVERSITY OF CALIFORNIA, SAN DIEGO.

DIVISION 0 - BIDDING REQUIREMENTS, CONTRACTOR FORMS AND CONDITIONS OF THE CONTRACT

SERIES 0 BIDDING REQUIREMENTS AND CONTRACT FORMS

Perimeter Site Improvements

Montgomery County Public Schools Facilities Guide DIVISION 0 - CONDITIONS OF THE CONTRACT

June 07, City of Fairfax Police Firing Range Expansion And Renovation Design City Council Work Session

Darlington Area Schools - Building Evaluations

Field House Proposal

ADDENDUM NO Refer to Specifications Section Alternates. Clarifications to alternate descriptions are as follows:

ELMIRA HIGH SCHOOL GYMNASIUM ANNEX NOVEMBER 19, 2015

Kaysville Parks and Recreation Department Request For Bids Pioneer Park Phase I RFB 10-17

CAPITAL PROJECTS UPDATE

Transcription:

h Construction of One Classroom Wing Cattle Elementary School Architect: WLC Architects, Inc. Contractor: Pacwest Corporation Construction Manager: Bernards Contract Amount: $2,974,000 Contract Start: August 8, 2011 Change Orders: $88,974 Contract Completion: August 6, 2012 Change Order Percent: 3.02% Scope: Construction of one new classroom wing consisting of seven (7) classrooms, staff and student restrooms, offices, work rooms with a lunch shelter addition and playground extension/reconfiguration and two (2) fire hydrant installations. New site work and courtyard with landscaping. Status: Pacwest Corporation has completed the project, including all punchlist items. The O&M manuals, warranties and asbuilts have been delivered by Pacwest and attic stock has been turned over to the District. The Project s Notice of Completion was approved by the Board on 11/1/12. 1. Courtyard hardscape and buildings complete 2. Asphalt paving and slurry seal complete 3.Shade shelter extensions complete 4. Landscaping complete Page 1 of 7

Swimming Pool Chino Hills High School Architect: WLC Architects, Inc. Contractor: Construct One Construction Manager: Bernards Contract Amount: $5,291,462 Contract Start: March 26, 2012 Change Orders in Process: $129,238 Contract Completion: January 31, 2013 Change Order Percent: 2.4% Scope: Construction of a 25yd X 35m swimming pool, related facilities, boys and girls shower/locker building, restrooms, mechanical room, office, storage, snack bar, ticket booths and bleachers shade structure. Status: Construct One Corporation has now completed all rough carpentry, metal stud framing, structural steel erection and building decking. Building MEP rough-in is in progress. HVAC Rooftop Units are set. Densglass installation is complete and drywall installation has started. Painting of the building CMU is in progress. PVC roofing is complete and the high roofs have been insulated and dried-in with standing seam roofing to start shortly. Louvers and exterior doors are installed. Pool mechanical equipment is onsite and being installed/piped-up. The inner pool deck and first bleacher section have been poured. Bleacher canopy structural steel erection is complete with decking to follow shortly. Lathing is being installed and plastering is expected to start in the next couple of weeks. The structural steel framework for the scoreboard is erected and the scoreboard will be put together over the course of this next month and partly into December. The tie-in of the gas line to the main school line is planned for Thanksgiving week to minimize the impact to the School. 1. Pool inner deck is poured 2. PVC roofing is complete and the building is dried-in 3. First bleacher section is poured 4. Louvers and exterior doors are installed Page 2 of 7

Exterior Site Improvements Glenmeade ES Construction Manager: Bernards Contract Amount: $1,058,502 Contract Start: June 11, 2012 Change Orders in Process: $59,188 Contract Completion: August 5, 2012 Change Order Percent: 5.59% Scope: Reconstruction of existing slope with new drainage swale, fence and retaining walls. New playground equipment with surfacing, new turf at the upper level field, new switchback ramp, new parking lot with trash enclosure and new ADA path of travel upgrades. Status: All work in the lower level areas are complete and being used. The sod has been installed at the upper field. The concrete walkways at the upper field have been placed up to the portion along the street for the bus stop. The bus stop and adjacent work is set to begin now that we have City approval. 1. Sod installation at upper field in maintenance period 2. Sod at upper field in maintenance period 3. Slope hydroseed growth in progress at upper field 4. Playground equipment complete Page 3 of 7

Interior Renovations Glenmeade ES Construction Manager: Bernards Contract Amount: $1,155,502 Contract Start: June 11, 2012 Change Orders in Process: $100,110 Contract Completion: August 5, 2012 Change Order Percent: 8.66% Scope: Interior modernization to majority of the Glenmeade ES campus, including casework, paint, tackable walls, acoustical ceiling tile, ENO Boards, learning center casework, MEP, restroom upgrades and upgrades at the stage at the MPR including operable partition. Scope also includes new ramp at the outdoor stage and ADA path of travel upgrades at the landings. Status: All work has been completed and all punchlist items have been completed. The Project s Notice of Completion was approved by the Board on 11/1/12. 1. Classroom furniture moved in 2. Workroom complete 3. New offices and storage rooms complete 4. New office complete Page 4 of 7

Modernization Magnolia Junior High School Construction Manager: Bernards Contract Amount: $1,424,155.00 Contract Start: July 9, 2012 Change Orders in Process: 0 Contract Completion: April 9, 2013 Change Order Percent: 0% Scope: Small expansion to staff lounge in building D and modernization of Library at building C. Scope of work includes, but is not limited to; new finishes (paint, ceiling tile, flooring, wall coverings) casework, low voltage data systems, HVAC units, and concrete site work. Improvements will also be made to the restrooms, lighting, roofing and fire alarm system. Status: Mechanical, electrical, plumbing rough-in at all interior areas is mostly complete in building C. In addition, metalstud wall and soffit framing is in progress. Demolition, removal and over-excavation of the new staff lounge at building D has been completed. Staff lounge expansion footings and slab on grade set to begin. 1. Staff lounge expansion framing in progress 2. Staff lounge expansion in progress 3. Building C framing and drywall in progress 4. Building C library in progress Page 5 of 7

Slope Renovation Alternative Education Center Construction Manager: Bernards Contract Amount: $712,502 Contract Start: September 10, 2012 Change Orders in Process: $0 Contract Completion: January 9, 2013 Change Order Percent: 0% Scope: Reconstruction of existing slope with new drainage swale, fence and curb. Existing field gets new irrigation and hydroseed after demolition of the existing backstops and ballpark lighting. Status: Demolition of the entire site is complete. Soil import is now complete. Earthwork is in progress with the north portion of the field set to begin after Thanksgiving. On the south side, all earthwork is complete, the slopes have been filed and the CMU splash wall has been completed. 1. Slope along backside portables complete 2. South slope and CMU splash wall complete 3. Demo of walkway and picnic tables near play equipment 4. North slope earthwork in progress Page 6 of 7

Modernization/HVAC Replacement Project Briggs Fundamental School Architect: KPI Architects, Inc. Contractor: Harik Construction, Inc. Construction Manager: Bernards Contract Amount: $3,758,000 Contract Start: July 18, 2011 Change Orders in Process: $234,754 Contract Completion: September 26, 2012 Change Order Percent: 6.25% Scope: Site work modifications and modernization to 19 buildings, including new finishes (paint, ceiling tile, vinyl tackboard, flooring) casework, low voltage data systems, HVAC units, accessibility upgrades, and concrete site work. Improvements will also be made to the restrooms, lighting, signage, and new automatic fire alarm system. Status: Punchlist items have all been addressed. Closeout documents have been submitted and are currently under review by the project team for completeness. The Project s Notice of Completion was approved by the Board on 11/1/12. 1. Completed irrigation, landscape, striping, signage, benches, and 2. Installation of new stage curtain, valance, vinyl composite tile, trash receptacles ceiling tile and light fixtures 3. Placement of new ceramic tile, lavatories, mirrors, hand dryer, 4. Shade structure and concrete placement installation complete east soap dispensers and epoxy flooring of blacktop Page 7 of 7