SIX MONTHLY COMPLIANCE REPORT JUNE 2015

Similar documents
SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

SIX MONTHLY COMPLIANCE REPORT JUNE- 2015

Health and safety norms of CPWD should be followed during construction.

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests

GENERAL CONDITIONS. 7. The Applicant will adopt the prescribed norms, and standards provided in the national Building Code of India 2005.

Sr. No. Date of starting the project and completion schedule. January 2012 January 2017 (Tentative)

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF OCTOBER TO MARCH-2017

TATA STEEL LIMITED. Environment Compliance Report (Oct 2017 to Mar 2018)

COMPLIANCE TO THE CONDITIONS LAID BY MoEF VIDE CRZ CLEARANCE No.11/32/2009-IA.III dated

State Level Environment Impact Assessment Authority, Punjab Government of India Ministry of Environment and Forests

State Level Environment Impact Assessment Authority, Punjab Government of India Ministry of Environment and Forests

Environment Compliance Report (Apr 2017 to Sep 2017)

M.S.SEIAA Panchkula, Haryana

State Level Environment Impact Assessment Authority, Punjab Government of India Ministry of Environment and Forests

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL 2013 TO SEPTEMBER M/s. Subham Planners Ltd.

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF MARCH TO AUGUST -2013

State Level Environment Impact Assessment Authority, Punjab Government of India Ministry of Environment and Forests Telefax:

State Level Environment Impact Assessment Authority, Punjab Government of India Ministry of Environment and Forests

Department of Ecology and Environment Room No.709, 7 th Floor, IV-Gate, M.S. Building, Bangalore ,

J-11011/45/2009- IA II (I)

4. The ambient air quality monitoring stations We are monitoring the ambient air quality

The SEAC has examined the proposal in the light of amended Notification dated

Check list for construction Project of EC [Category 8(a)]:

SIA/PB/NCP/53462/2016)

SEIAA: 42 (B): CON: 2007 STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, KARNATAKA

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India. Registered

HALF YEARLY COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE CONDITIONS

ENVIRONMENT MANAGEMENT PLAN CONSTRUCTION PHASE. suppression instead of water wherever possible. Cell)

SIX MONTHLY COMPLIANCE REPORT DECEMBER- 2016

State Level Environment Impact Assessment Authority Madhya Pradesh Government of India Ministry of Environment & Forests

Rajasthan State Pollution Control Board

ENVIRONMENTAL MANAGEMENT PLAN. CONSTRUCTION PHASE 1.Construction Contractors

Report on Damage Assessment and. Remediation Plan and Natural & Community Augmentation Plan

Shriram Vinyl & Chemical Industries, : Kota Compliance Report of Environmental Clearance dated 12 th July 2017 and amended on 23 rd November 2017

meeting held on meeting held on The SEAC observed that:

Overburden dumps are stacked separately as per the guidelines and the same will be used for backfilling in mined out area.

2. The expected cost of the project is Rs.50 crores.

V.S LIGNITE POWER Pvt. Ltd AT VILLAGE-GURHA, KOLAYAT, BIKANER, RAJASTHAN

No. SEIAA/3225 Dated: To M/s The Greater Mohali Municipal Officers & Other Welfare Co-Operative House Building Society Ltd.

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT

No. SEIAA/2018/329 REGISTERED Dated:

COMPLIANCE REPORT OF ENVIRONMENTAL CLEARANCE FOR THE PERIOD OF APRIL-2016 TO SEPTEMBER F. No. J-11011/309/2011-IA-ll (I)

Chambal Fertilisers and Chemicals Limited CFG3 Project Environment Clearance_ Compliance Report (Feb 28, 2018)

Construction of Residential Group Housing Project

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB Ministry of Environment and Forests, Government of India. Registered

Environmental Clearance; Letter No J / 152 / 2006-IA-II (I) Dt and corrigendum dated

Environmental Clearance; Letter No J / 152 / 2006-IA-II (I) Dt and corrigendum dated

After detailed discussions, the following shortcomings were concluded:

The Proposed Expansion of Existing ARTEMIS HOSPITAL at Sector-51, Gurgaon (Haryana). In CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT

No. SEIAA/2016/2161 Dated Sh. Rakesh Gupta, M/s GGP Buildtech (P) Ltd., Kharar Landran Road, Sector-115, Kharar.

No. SEIAA: 71: CON: 2011 STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, KARNATAKA (Constituted by Ministry of Environment & Forests, Government

Environmental Clearance Compliance Half Yearly Report

Environment protection measures / technology

BRIEF SUMMARY OF THE PROJECT

THE RAMCO CEMENTS LIMITED, KSR NAGAR COMPLIANCE REPORT - ENVIRONMENTAL CLEARANCE CEMENT PLANT 2.5 MILLION TPA CLINKER, 2

Registered. M/s Simmro Infrastructure & Developers Pvt. Ltd., B-3, Greater Kailash Enclave-2, New Delhi.

Max. building height (m)

Registered. M/s Baba Jiwan Singh Baba Dalip Singh Educational Trust, Goindwal Sahib Road, Tarn Taran.

Rajasthan State Pollution Control Board

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB

SEIAA: 6: CON: 2013 STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, KARNATAKA

Registered. M/s N.H. Matcon Pvt. Ltd., S.C.O-3, Royal Estate, Chandigarh-Ambala Highway, Zirakpur, District SAS Nagar

Hind Energy & Coal Beneficiation (India) Ltd.

Environment Impact Assessment (EIA) The proposed project falls in category 8 (a) B2 as per schedule of EIA Notification, 2006.

STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY PUNJAB

DESCRIPTIVE REPORT ON STATUS OF COMPLIANCE TO THE CONDITIONS OF ENVIRONMENTAL CLEARANCE AND ENVIRONMENTAL MANAGEMENT

COMPLIANCE STATUS REPORT

No. SEIAA/M.S./2014/2634 Dated Registered

Shri Gurudatt Sugars Ltd., Gat No. 61/A, Akiwat - Takaliwadi Road, Takaliwadi , Taluka - Shirol, Dist Kolhapur, Maharashtra

Calcom Cement India Limited

Department of Ecology and Environment Room No.709, 7th Floor, IV-Gate, MS. Building, Bangalore , Date: 29th June To,

From : April 2015 To : October 2015 Status of conditions stipulated in Environmental and CRZ clearance. Adani Vizag Coal Terminal Private Limited

Municipal solid / hazardous waste

No. SEIAA/M.S./2016/1525 Dated To M/s Janta Land Promoters Ltd., SCO , Sector-82, Mohali.

CONCEPTUAL PLAN PROJECT LAYOUT AND DEVELOPMENT CONTEXT

M/s Hind Energy & Coal Beneficiation Pvt. Ltd. is presently operating a 2 x 1.2 MTPA

SEIAA KARNATAKA CHECK LIST FOR BUILDING & CONSTRUCTION PROJECTS

Dated: 22 nd June, To The Director, Mjs Vulcan Waste Management Pvt. Ltd., 1046, Sector-31, Gurgaon, Haryana

CORPORATE OFFICE BUILDING, C-11, URBAN ESTATE-II CITY CENTRE SECTOR 29, GURUGRAM, HARYANA

Subject: Environmental and CRZ clearance for expansion of Karaikal Port (Phase-II) at Puducherry by MIs. Karaikal Port Pvt. Ltd. - Reg.

ENVIRONMENTAL MANAGEMENT PLAN

CRZ Clearance for Proposed construction of Ghodbundar Jetty, Thane by MMB

Subject: Half yearly Report for the period of 1 st April 2013 to 30 th Sept., 2013 for Indmax Project

EIA NOTIFICATION

Ref: Environment Department, MS, SEIAA Letter SEAC 2010/CR.824/TC-2 Dated 2 nd Nov 2011

NMDC Limited Arki Limestone Project, Post: Arki, Tehsil: Arki, District: Solan, H.P.

FORM - I-A CHECK LIST OF ENVIRONMENTAL IMPACTS

Indicative Checklist for construction projects of EC [Category 8(a)]:

Minutes of 292 nd SEAC Meeting Date 20/09/2016

Point wise reply. There is no change in water requirement and wastewater generation. However, water balance enclosed as Annexure-I.

CRZ Clearance for Proposed Construction of RO RO Jetties at Narangi-Kharawadashri, Tal. & Dist. palghar by MMB

Cement Manufacturing Company Ltd. Page 1

ANNEXURE-II CONSENT TO OPERATE AND ITS COMPLIANCE

SEIAA: 25: CON: 2012 STATE LEVEL ENVIRONMENT IMPACT ASSESSMENT AUTHORITY, KARNATAKA

(1) LAND ENVIRONMENT (Attach panoramic view of the project site and the vicinity)

Chemplast Sanmar Limited Marine Terminal Facility, Chitrapettai Village Cuddalore District, Tamil Nadu

STATE EXPERT APPRAISAL COMMITTEE, PUNJAB MINISTRY OF ENVIRONMENT AND FORESTS, GOVERNMENT OF INDIA

NOC GRANTED FOR THE EXPANSION OF KASHLOG LIMESTONE MINES OF AMBUJA CEMENTS TIMITED

Clearance Letter no. : MoEF Vide Letter no. J-11011/79/2003-IA-II (I) dated April 21, 2004

Transcription:

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 SIX MONTHLY COMPLIANCE REPORT JUNE 2015 (GROUP HOUSING COMPLEX) At Sector-86, Gurgaon, Haryana Being developed by M/s Deepanshu Projects Pvt. Ltd. D-5, Udyog Nagar, Main Rohtak Road, New Delhi Prepared by: M/s Perfact Enviro Solutions Pvt. Ltd (A NABET Accredited Environmental Consultant) (ISO9001:2008& ISO14001:2004 Certified) 502-507, 5th Floor, NNMall, Mangalam Palace, Sector 3 Rohini, New Delhi Ph No. 47528467, Fax No. 47528434

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 Table of Contents: Chapters Chapter -1 Chapter -2 Chapter -3 Chapter - 4 Chapter 5 Particulars Purpose of the Report Introduction of Project Current Construction Status & Site Photographs Point wise Compliance Report as per EC conditions List of Annexure Annexure -I Annexure II Annexure - III Annexure IV Annexure V Annexure VI Annexure -VII Annexure-VIII Annexure-IX Copy of Granted Environmental Clearance Copy of Consent To Establish NABL Accreditation Certificate & Monitoring reports of Air, Water, Soil, Noise & Stack Health Certificates of few workers engaged during construction work PUC certificates of few Vehicles Hired for Construction Authorization letter for Authorized Signatory Authorization letter for NABET/QCI accredited consultancy organization for preparation of compliance report Copy of Water Supply Assurance from HSIIDC Copy of AAI Approval

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 CHAPTER-1 Purpose of the Report As per the Sub Para (ii) of Para 10 of EIA Notification 2006, it is stated that It shall be mandatory for the project management to submit half-yearly compliance reports in respect of the stipulated prior environmental clearance conditions/safeguards in hard and soft copies to the regulatory authority concerned, on 1st June and 1st December of each calendar year and as per compliance of condition mentioned in Environment Clearance Letter (i.e. Part B General Condition, point number II), Six monthly compliance reports should be submitted to the Haryana State Pollution Control Board and Regional Office, MOEF, GOI, Northern Region, Chandigarh and a copy to the Regulatory Authority of Haryana. It is mandatory to submit a Six Monthly Compliance Report to show the status & compliance of all the Conditions mentioned in Environment clearance Letter, along with monitoring of various Environmental Parameters (as per CPCB Norms). The regulatory authorities in this case are Haryana State Pollution Control Board, Regional Office- MoEFCC (Chandigarh) and Haryana SEIAA. Based on the Specific and General Conditions mentioned in the EC Letter, a Compliance Report was prepared by the Team on behalf of Project Proponent; details of which are present in Chapter Compliance Report. Methodology for Preparation of Report is as follows: 1. Study of EC Letter & Related Documents, 2. Site Visits by a Team of Experts, 3. Monitoring of Environment Parameters, viz. Ambient Air, Water, Noise, Soil & DG Sets, 4. Analysis of Samples collected during Monitoring, 5. Interpretation of Monitoring Results, 6. Compliance Report, explaining the entire General & specific conditions in the EC Letter and providing details w.r.t. each condition/ guideline.

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 CHAPTER-2 1. Introduction Name of the project Group Housing Complex Site address Sector 86, Gurgaon, Haryana. Developed By M/s Deepanshu Projects Pvt. Ltd. Environment Clearance Letter No. SEIAA/HR/2013/643 dated 04.09.2013. Period of Compliance Six Monthly Compliance June 2015 Project Description Construction Status The proposed project involves construction of a Group Housing Complex on a plot area of 59258.11 Sq.m. Proposed Built up area is 148623.86 Sq.m. Construction under Progress. Year of Commencement 2014 Proposed year of completion 2016

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 2. Project Detail Proposed Group Housing project is located at Sector -86, Gurgaon Haryana and being developed by M/s Deepanshu Projects Pvt. Ltd. The proposed Group Housing Complex will have the following salient features: - Particulars Total Area of Plot Built-up Area Details 59258.11 Sq.m 148623.86 Sq.m No. of Basements 2 No. of Blocks 15 No. of Floors GF+ 21 Total Water requirement Fresh water requirement Waste water generation STP capacity 640 KLD 400 KLD 498 KLD 600 KLD RWH pits 10 Power requirement Max. Height of Building Total Cost of Project 5992 KW 76 m Rs. 263 Crores

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 CHAPTER - 3 Component-wise Construction Status: SNo. Component Construction status as on date 1 Civil construction (Structural work, Brick work & Plaster work) 2 Plumbing In Progress 3 Electrical work In Progress 4 Fire Fighting In Progress 5 Sewage Treatment Plant In Progress Structural work 60% completed, Brick Work 30% completed, Plaster work 20% completed 6 Rain Water Harvesting Not started yet 7 Sewerage, Drainage etc. Not started yet 8. D.G Room, In Progress 9. Pollution Control Equipments Not started yet 10. Finishing work In Progress 11. Landscaping Not started yet

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 Site Photographs

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 Medical Facility at site:- Workers wearing safety equipments:

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 CHAPTER 4 4. Current Status of point wise compliance of the stipulated environmental conditions/ safeguards. Construction Phase Sr.No. EC conditions 1 Consent for Establishment shall be obtained from Haryana State Pollution Control Board under Air and Water Act and a copy shall be submitted to the SEIAA, Haryana before the start of any construction work at site. 2 A first Aid Room as proposed in the project report shall be provided in both during construction and operation of the project. 3 Adequate drinking water & sanitary facilities should be provided for construction workers at the site. Provision should be made for mobile toilets. Open defecation by the labourers is strictly prohibited. The safe disposal of wastewater and solid wastes generated during the construction phase should be ensured. 4. All the top soil excavated during construction actives should be stored for use in horticulture /landscape development within the project site. Replies We have obtained Consent to Establish from Haryana State Pollution Control Board under Air & Water Act vide Consent No. 2821213GUSOCTE2990963 Dated 31.10.2013. Copy for the same is enclosed as Annexure II. Well maintained First Aid facility has been provided at site during construction and same will be provided during operation also. Ambulance facility has been provided at site. Site Photographs are attached. Adequate drinking water & sanitary facilities have been provided for Construction workers at site. Safe disposal of wastewater & solid waste is being done. Temporary wash areas have been constructed for laborers and good hygienic conditions are being maintained. 1,39,000/- cubic meter soil has been excavated. Fertile top soil excavated during construction activities has been stored separately under a tarpaulin cover for the future use in horticulture /landscape development within the project site.

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 5. The project proponent shall ensure that the building material required during construction phase is properly stored within the project area and disposal of construction waste should not leach into the ground water and any hazardous waste generated during construction phase, should be disposed off as per applicable rules and norms with necessary approval of the Haryana State Pollution Control Board. 6. Construction spoils including bituminous material and other hazardous material must not be allowed to contaminate water courses and the dump sites for such must be secured so that they should be not leach into the ground water and any hazardous waste generated during construction phase, should be disposed off as per applicable rules and norms with necessary approval of the Haryana State Pollution Control Board. 7. The diesel generator sets to be used during construction phase should be low sulphur diesel type and should conform to Environment (Protection) Rules prescribed for air and noise emission standard. 8. The diesel required for operating DG sets shall be stored in underground tanks and if required, clearance from Chief Controller of Explosive shall be taken. 9. Ambient noise levels should conform to the residential standards both during day and night. Incremental pollution loads on the ambient air Disposal of muck during construction phase is not creating any adverse effects on the neighboring communities and is being disposed off taking the necessary precautions for general safety and health aspects. Construction spoils including bituminous material are being properly stacked to avoid any contamination to the ground water. Only hazardous waste generated during construction phase is used oil from DG sets, which shall be given to approve recycler of CPCB. Acoustically enclosed D.G sets of 250 KVA & 125 KVA has been installed at the project site which conform to the rules made under E (P) A 1986 prescribed for air & noise emissions standards. Diesel required for the DG set has been stored in leak proof containers in an isolated area. If required, permission from Explosive Department shall be taken. To reduce noise level, movement of construction vehicles is being carried during non peak hours and construction machinery

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 and noise quality should be closely monitored during construction phase. Adequate measure should be taken to reduce ambient air and noise level during construction phase, so as to confirm to the stipulated residential standards. with lesser noise and vibration parameters is being used. Incremental pollution loads on the ambient air quality is being closely monitored. Test results are enclosed as Annexure III. 10 Fly ash should be used as building material in the construction as per the provisions of Fly Ash Notification of September, 1999 and amended as on 27 th August, 2003. 11. Storm water control and its reuse as per CGWB and BIS standards for various applications should be ensured. 12. Water demand during construction should be reduce by use of pre mixed concrete, curing and other best practices. 13. In view of the severe constrains in water supply augmentation in the region and sustainability of water resources, the developer will submit the NOC from CGWA specifying water extraction quantities and assurance from HUDA/ utility provider indicating source of water supply and quantity of water with details of intended use of water potable and non-potable. Assurance is required for both construction and operation stages separately. It shall be submitted to the SEIAA and RO MOEF, Chandigarh before the start of construction. 14. Roof should meet prescribed requirement as per Energy Conservation Building Code by using appropriate thermal insulation material to fulfill requirement. We are using fly ash based material as per the provisions of Fly Ash Notification of September, 1999 and amended as on 27 th August,2003. We shall have the provision for Storm water control and its reuse inside our project site after the completion of structural work. We are using pre mixed concrete curing agent and other best practices to reduce the water demand during construction phase. During construction phase, water requirement is meeting through the HSIIDC tanker STP treated effluent supply. Since we are not extracting ground water, permission from CGWA is not required. Permission from HSIIDC has been obtained and copy is enclosed as Annexure-IX. Roofs shall be constructed by using thermal insulation material.

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 15. Opaque wall should meet prescribed requirement as per Energy Conservation Building Code which is proposed to be mandatory for all air conditioned spaces while it is aspirational for non-air-conditioned spaces by use of appropriate thermal insulation material to fulfill requirement. 16. The approval of the competent authority shall be obtained for structural safety of the building due to earthquake, adequacy of fire fighting equipments, etc. as per National Building Code including protection measures from lighting etc. If any forest land is involved in the proposed site, clearance under Forest Conservation Act shall be taken from the competent Authority. 17. Overexploited groundwater and impending severe shortage of water supply in the region requires the developer to redraw the water and energy conservation plan. Developer shall reduce the overall footprint of the proposed development. Project proponent shall incorporate water efficiency/savings measures as well as water reuse/recycling within 3 months and before start of construction to the SEIAA, Haryana and R.O, MOEF, GOI, Chandigarh. 18. The project proponent shall construct 10 nos. rain water harvesting pits for recharging the ground water within the project premises. Rain water harvesting pits shall be designed to make provisions for silting chamber and removal of Opaque walls will be made as per Energy Conservation Building Code, as required. The approval of the competent authority shall be obtained for the structural safety of the building due to earthquake, adequacy of the firefighting. NOC from Forest Department has been obtained & submitted. We are not using ground water for construction. During construction. STP treated water from HSIIDC Manesar Plant is being used. Permission in this regard has been obtained and copy is enclosed as Annexure-IX. As far as water requirement during operational phase is concerned, water balance has already been submitted. Water saving techniques shall be adopted. 10 nos. of rain water harvesting pits for recharging the ground water within the project premises shall be installed. De-silting chamber, bar screens etc shall be provided to prevent contaminated water from entering

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 floating matter before entering harvesting pit. Maintenance budget and persons responsible for maintenance must be provided. Care shall also be taken that contaminated water do not enter any RWH pit. 19. The project proponent shall provide for adequate fire safety measures and equipments as required by Haryana Fire Service Act, 2009 and instructions issued by the local Authority /Directorate of Fire from time to time. Further the project proponent shall take necessary permission regarding fire safety scheme/noc from Competent Authority as required. 20. The Project Proponent shall submit assurance from the HVPNL for supply of 5992 KW of power supply before the start of construction. In no case project will be operational solely on generators without any power supply from any external power utility. Under intimation to SEIAA Haryana before the start of construction. In no case project will be operational solely on generators without any external power utility. 21. Detail calculation of Power load and ultimate power load of the project shall be submitted to HVPNL under intimation to SEIAA Haryana before the start of construction. Provision shall be made for electrical infrastructure in the licensed area. 22. The project proponent shall not raise any construction in the natural land depression/ Nallah/ water Course and shall ensure that the any RWH pit. Regular maintenance of the same shall also be carried to take care of these aspects. Details of maintenance budget and person responsible shall be submitted. Adequate fire safety measures and equipments as required by Haryana Fire Service Act,2009 shall be provided within the complex. Necessary permission regarding fire safety scheme/noc from Competent Authority as required has been obtained. Necessary assurance from the HVPNL for power supply has been obtained. Copy is enclosed as Annexure VIII. Exact Power load can be determined only after operation of the project however, estimated power load details has been submitted. No natural land depression/ nallah/ water course exists within the project. No natural flow will be obstructed.

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 natural flow from the Nallah/water course is not obstructed. 23. The project proponent shall keep the plinth level of the building blocks sufficiently above the level of the approach road to the Project as per prescribed by laws. Levels of the other areas in the Project shall also be kept suitably so as to avoid flooding. 24. Construction shall be carried out so that density of population does not exceed norms as approved by Director General Town and Country Department Haryana. 25. The project proponent shall submit an affidavit with the declaration that ground water will not be used for construction and only treated water should be used for construction. 26. The project proponent shall not cut any existing tree and project landscaping plan should be modified to include those trees in green area. 27. The project proponent shall ensure that ECBC norms for composite climate zone are met. In particular building envelope, HVAC service, water heating, pumping, lighting and electrical infrastructure must meet ECBC norms. 28. The project proponent shall provide 3 meter high barricade around the project area, dust screens for every floor above the ground, proper sprinkling and covering of stored We have kept plinth level of building blocks at least 6 meters above the approach road. Levels of the other areas will also be kept suitably as to avoid flooding. Approval from Town and Country Department has been obtained. Population shall be as per the norms & proposal. We are not using groundwater during construction phase. Affidavit in this regard has already submitted to the SEAC. During construction phase water requirement is meeting through the STP treated water from the HSIIDC Manesar Plant. Copy of water supply permission from HSIIDC is enclosed as Annexure IX. Noted. Group Housing complex is being constructed according to ECBC norms. Barricading around the project area has been provided. Dust screens are being provided for every floor above the ground when construction is in progress in floors. Water

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 material to restrict dust and air pollution during construction. 29. The project proponent shall construct a sedimentation basin in the lower level of the project site to trap pollutant and other wastes during rains. 30. The project proponent shall provide proper Rasta of proper width and proper strength for each project before the start of construction. 31. The project proponent shall ensure that the U- value of the glass is less than 3.177 and maximum solar gain co-efficient is 0.25 for vertical fenestration. 32. The project proponent shall adequately control construction dusts like silica dust, non-silica dust, and wood dust. Such dusts shall not spread outside project premises. The project proponent shall provide respiratory protective equipment to all construction workers. 33. The project proponent shall submit NOC from AAI regarding height clearance before the start of construction. 34. The project proponent shall provide one refuse area till 24 meter, one till 39 meter and one each after 15, meter as per National Building Code. 35. The project proponent shall provide fire control room and fire officer for building above 30 meter as per National Building Code. 36. The project proponent shall obtain permission of Mines and Geology Department for sprinkling is being done to avoid dust emission. Covered transportation of construction vehicles is being practiced. Sedimentation basin shall be provided to trap pollutant and other wastes during rains. Rasta as per the requirement shall be provided. Group Housing Complex is being constructed as per the ECBC norms of residential complex rules & regulations. Dust emission during the construction is being controlled by adequate water sprinkling. Personal Protection equipments have been provided to the construction workers. Photographs are enclosed. NOC from AAI has been obtained for building height. Copy for the same is enclosed as Annexure X. Refuge area as per norms shall be provided. Necessary arrangements as per National Building Code shall be done. Permission from Geology Department for excavation have been obtained.

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 excavation of soil before the start of construction. 37. The project proponent shall provide helipad facility as required under NBC norms and shall seek permission of helipad from AAI accordingly. 38. The project proponent shall develop complete civic infrastructure of the Group Housing colony including internal roads, green belt development, sewerage line, Rain Water recharge arrangements, Storm water drainage system, Solid waste management site and provision for composting of bio-degradable waste, STP, water supply line, dual plumbing line, electric supply lines etc. and shall offer possession of the units/flats thereafter. 39. All system of water supply, sewerage system, STP etc. shall be provided based on revised requirement of @135 lpcd. 40. The site for solid waste management plant be earmarked on the layout plan and the detailed project for setting up the solid waste management plant shall be submitted to the Authority within one month. Helipad facility shall be provided as per the requirement. Complete civic infrastructure of the Group Housing colony shall be provided. Water requirement plan has been submitted as per 135LPCD consumption Detailed layout plan has been submitted and solid waste management is being done as per plan submitted. S.N Part B. General Conditions o 1 The project proponent shall ensure the commitments made in Form-I, form- 1A, EIA/EMP and other documents submitted to the SEIAA for the protection of environment and proposed environmental safeguards are We ensure to comply with the commitments made in Form 1, Form 1A, EIA/EMP and other documents submitted for the protection of environment.

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 complied with in letter and spirit. In case of contradiction between two or more documents on any point the most environmentally friendly commitment on the point shall be taken as commitment by project proponent. 2 Six monthly monitoring reports should be submitted to the HSPCB and Regional Office, MOEF, GOI, Northern Region, Chandigarh and a copy to the SEIAA Haryana 3. Noise, STP outlet and stack emissions shall be monitored daily. Other environmental parameters shall be monitored on monthly basis. After every 3 months the project proponent shall conduct environmental audit and shall take corrective measures, if required, without delay. 4. The SEIAA, Haryana reserves the right to add additional safeguard measures subsequently, if found necessary, Environmental clearance granted will be revoked if it is found that false information has been given for getting approval of this project. SEIAA reserves the right to revoke the clearance if conditions stipulated are not implemented to the satisfaction of SEIAA/MOEF. 5. The project proponent shall not violate any judicial orders/pronouncements issued by any Court/Tribunal. 6. All other statutory clearances such as the approvals for storage of diesel from Chief Controller of Explosives, Fire Department, Civil Aviation Department, Forest Conservation We are regularly submitting the compliance reports to the concerned department. Necessary monitoring is being done and accorded result reports are enclosed as Annexure III. Noted. Noted. Necessary clearances applicable to our project have been obtained.

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 Act,1980 and Wildlife (Protection) Act 1972, PLPA 1900, Forest Act,1927 etc. shall be obtained, as applicable by project proponents from the respective authorities prior to construction of the project. The project proponent should inform the public 7. that the project has been accorded Environment Clearance by the SEIAA and copies of the clearance letter are available with the State Pollution Control Board & SEIAA. This should be advertised within 7 days from the date of issue of the clearance letter at least in two local newspapers that are widely circulated in the region and the copy of the same should be forwarded to SEIAA Haryana. A copy of environmental Clearance conditions shall also be put on project proponent s website for public awareness. 8. Under the provisions of Environment (Protection) Act, 1986, legal action shall be initiated against the Project Proponent if it was found that construction of the project has been started before obtaining environmental clearance. 9. Any appeal against the Environmental Clearance shall lie with the National Green Tribunal, if preferred, within a period of 30 days as prescribed under section 16 of the National Green Tribunal Act, 2010. 10 The project proponent shall put in place Corporate Environment Policy as mentioned in MOEF, GOI OM No. J-11013/41/2006-IAII (I) We have complied with the requirement. Copy of Newspaper advertisement already been submitted. Noted. Noted. Corporate Environment Policy is enclosed as Annexure XI.

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 dated 26.04.2012 within 3 months period. Latest Corporate Environment Policy should be submitted to SEIAA within 3 months of issuance of this letter. 11. The fund ear-marked for environment protection measures should be kept in separate account and should not be diverted for other purposes and year wise expenditure shall be reported to the SEIAA/RO MoEF GOI under rules prescribed for Environment Audit. 12 The project proponent shall ensure the compliance of Forest Department, Haryana Notification no. S.O.121/PA2/1900/S.4/97 dated 28.11.1997 13 The Project Proponent shall ensure that no vehicle during construction/operation phase enter the project premises without valid Pollution Unser Control certificate from competent authority. 14 The Project Proponent is responsible for compliance of all conditions in Environmental Clearance letter and project proponent can not absolve himself/herself of the responsibility by shifting it to any contractor engaged by project proponent. 15. The Project Proponent shall seek fresh Environmental Clearance if at any stage there is change in the planning of the proposed project. Noted and shall be complied. We ensure to comply with rules & regulations of Forest Department of Haryana. Vehicles operating during construction phase are having valid PUC certificates. PUC Certificates of few vehicles are enclosed as Annexure V. We understand that we are completely responsible for the compliance of all the safeguards stipulated in environmental clearance letter. Noted.

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 ANNEXURE I COPY OF GRANTED ENVIRONMENTAL CLEARANCE

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 ANNEXURE II COPY OF CONSENT TO ESTABLISH

To HARYANA STATE POLLUTION CONTROL BOARD C-11, SECTOR-6, PANCHKULA Website www.hspcb.gov.in E-Mail - hspcb.pkl@sifymail.com Telephone No. 0172-2577870-73 No. HSPCB/Consent/ : 2821213GUSOCTE290963 M/s : M/s Deepanshu Projects Pvt. Ltd. (Group Housing) at Sec-86, Gurgaon, Haryana GURGAON 110021 Sub. : Issue of Consent to Establish from pollution angle. Dated:31/10/2013 Please refer to your Consent to Establish application received in this office on the subject noted above.under the Authority of the Haryana State Pollution Control Board vide its agenda Item No. 47.8 dated 28.04.83 sanction to the issue of Consent to Establish with respect to pollution control of Water and Air is hereby accorded to the unit M/s Deepanshu Projects Pvt. Ltd. (Group Housing), for manufacturing of group housing colony with the following terms and conditions:- 1. The industry has declared that the quantity of effluent shall be 498 KL/Day i.e 0KL/Day for Trade Effluent, 0 KL/Day for Cooling, 498 KL/Day for Domestic and the same should not exceed. 2. The above Consent to Establish is valid for two years from the date of its issue to be extended for another one year at the discretion of the Board or till the time the unit starts its trial production whichever is earlier. The unit will have to set up the plant and obtain consent during this period. 3. The officer/official of the Board shall have the right to access and inspection of the industry in connection with the various processes and the treatment facilities being provided simultaneously with the construction of building/machinery. The effluent should conform the effluent standards as applicable 4. That necessary arrangement shall be made by the industry for the control of Air Pollution before commissioning the plant. The emitted pollutants will meet the emission and other standards as laid/will be prescribed by the Board from time to time. 5. The applicant will obtain consent under section 25/26 of the Water (Prevention & Control of Pollution) Act, 1974 and under section 21/22 of the Air (Prevention & Control of Pollution) Act,1981 as amended to-date-even before starting trial production 6. The above Consent to Establish is further subject to the conditions that the unit complies with all the laws/rules/decisions and competent directions of the Board/Government and its functionaries in all respects before commissioning of the operation and during its actual working strictly. 7. No in-process or post-process objectionable emission or the effluent will be allowed, if the scheme furnished by the unit turns out to be defective in any actual experience 8. The Electricity Department will give only temporary connection and permanent connection to the unit will be given after verifying the consent granted by the Board, both under Water Act and Air Act. 9. Unit will construct the proper septic tank as per Bureau of Indian Standards. 10. Unit will raise the stack height of DG Set/Boiler as per Board s norms.

11. Unit will maintain proper logbook of Water meter/sub meter before/after commissioning. 12. That in the case of an industry or any other process the activity is located in an area approved and that in case the activity is sited in an residential or institutional or commercial or agricultural area, the necessary permission for siting such industry and process in an residential or institutional or commercial or agricultural area or controlled area under Town and Country Planning laws CLU or Municipal laws has to be obtained from the competent Authority in law permitting this deviation and be submitted in original with the request for consent to operate. 13. That there is no discharge directly or indirectly from the unit or the process into any interstate river or Yamuna River or River Ghaggar. 14. That the industry or the unit concerned is not sited within any prohibited distances according to the Environmental Laws and Rules, Notification, Orders and Policies of Central Pollution control Board and Haryana State Pollution Control Board. 15. That of the unit is discharging its sewage or trade effluent into the public sewer meant to receive trade effluent from industries etc. then the permission of the Competent Authority owing and operating such public sewer giving permission letter to his unit shall be submitted at time of consent to operate. 16. That if at any time, there is adverse report from any adjoining neighbor or any other aggrieved party or Municipal Committee or Zila Parishad or any other public body against the unit s pollution; the Consent to Establish so granted shall be revoked. 17. That all the financial dues required under the rules and policies of the Board have been deposited in full by the unit for this Consent to Establish. 18. In case of change of name from previous Consent to Establish granted, fresh Consent to Establish fee shall be levied. 19. Green belt of adequate width shall be provided by the unit before commissioning. 20. In case of unit does not comply with the above conditions within the stipulated period, Consent to Establish will be revoked. 21. Industry should adopt water conservation measures to ensure minimum consumption of water in their Process. Ground water based proposals of new industries should get clearance from Central Ground Water Authority for scientific development of previous resource. 22. This Consent to Establish would be invalid if it is established in the non-conforming area. 23. That the unit will take all other clearances from concerned agencies, whenever required. 24. That the unit will obtain consent under Water & Air Acts & authorization under HWTM Rules from the Board before coming into production. 25. That the unit will not change its process without the prior permission of the Board. 26. That the Consent to Establish so granted will be invalid, if the unit falls in Aravali Area. 27. That the unit will comply with the Hazardous Waste Management Rules and will also make the non-leachate pit for storage of Hazardous waste and will undertake not to dispose off the same except for pit in their own premises or with the authorized disposal authority. 28. That the unit will submit an affidavit that it will comply with all the specific and general conditions as imposed in the above Consent to Establish within 30 days failing which Consent to Establish will be revoked. 29. That unit will obtain EIA from MoEF, if required at any stage. Specific Conditions Other Conditions :

1. The unit will take trial consent to operate before the occupation of the project. 2. The unit will install STP alongwith the main project. 3. The unit will install the project only on the land for which Town and Country Planning Department has given licenece. 4. The unit will comply all the terms and conditions of the Environmental Clearance granted by the SEIAA, Haryana. 5. Unit will obtain prior NOC/Permission from central Ground Water Authority in case under ground water resource is used. 6. The unit will achieve Zero effluent Discharge as proposed by unit. 7. The NOC is valid only for such land within this project which is under ownership of project proponent and for which report regarding Aravali area has been issued by DC, Gurgaon. 8. The unit will install adequate acoustic enclosures/chambers on their DG SETS with proper stack height as per prescribed norms to meet the prescribed standards under EP Rules, 1986. 9. The unit will install the adequate sewage treatment plant to meet the standards prescribed under EP Rules 1986. 10. The NOC will become invalid in case the project is found violating the provisions of notification no. S.O.191(E) dt. 27.01.2010 issued by MoEF Government of India regarding Ecosensitive Zone of Sultanpur National park. Senior Environmental Engineer II, HQ For and on be'half of chairman Haryana State Pollution Control Board

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 ANNEXURE III NABL ACCREDITATION CERTIFICATE & MONITORING REPORTS OF AIR, WATER, SOIL, NOISE & STACK

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 ANNEXURE IV HEALTH CERTIFICATES OF FEW WORKERS ENGAGED DURING CONSTRUCTION WORK

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 ANNEXURE V PUC CERTIFICATES OF FEW VEHICLES HIRED FOR CONSTRUCTION

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 ANNEXURE VI AUTHORIZATION LETTER FOR AUTHORIZED SIGNATORY

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 ANNEXURE VII AUTHORIZATION LETTER FOR NABET/QCI ACCREDITED CONSULTANCY ORGANIZATION FOR PREPARATION OF COMPLIANCE REPORT

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 ANNEXURE-VIII COPY OF WATER SUPPLY ASSURANCE FROM HSIIDC

M/s Deepanshu Projects Pvt. Ltd. Six Monthly Compliance June 2015 ANNEXURE-IX COPY OF AAI APPROVAL