Breaking the Diamond: DDIs, CFIs, and SPUIs

Similar documents
The Folded Interchange: An Unconventional Design for the Reconstruction of Cloverleaf Interchanges

DDI s Can Move More Than Cars. Alex Ariniello. Presentation for the ITE Western District Annual Meeting. July, 2016 in Albuquerque, New Mexico

NCHRP 3-88 Guidelines for Ramp and Interchange Spacing

NCHRP Report 687 Guidelines for Ramp and Interchange Spacing

I 75 PD&E STUDIES TABLE OF CONTENTS DTTM, TECHNICAL REPORT No. 2 TABLE OF CONTENTS

Conclusions & Lessons Learned

CHAPTER 5 PARALLEL PARKWAY CORRIDOR IMPROVEMENTS

INTERCHANGE MODIFICATION REPORT

Diverging Diamond Interchanges and their Relation to Sustainable Design

DRAFT. SR-60 7 th Avenue Intersection Control Evaluation (ICE) I-605 Corridor Improvement Project (CIP) I-605/SR-60 EA# 3101U0

Interchange Design. Nick Hoernke, Bill Roth and Eric Sorensen

Diverging Diamond Interchanges in Michigan

CHAPTER 2: MODELING METHODOLOGY

APPENDIX B. Excerpts from the October 2002 Conceptual Alternatives Report

Environmental Consequences and Mitigation

COMPARISON OF SPUI & TUDI INTERCHANGE ALTERNATIVES WITH COMPUTER SIMULATION MODELING

Readily Implementable Signal Phasing Schemes for Diverging Diamond Interchanges

MEMORANDUM: INITIAL CONCEPTS SUMMARY

I-35/80 Operations Study: Douglas Avenue to NW 86 th Street FOR

I-17 and Happy Valley Road Diverging Diamond Interchange (DDI)

Michigan Department of Transportation Diverging Diamond Interchange (DDI) Informational Guide. April 2015

Impacts of Replacing a Tight Diamond Interchange with a SPUI A Wilsonville Interchange Study

DEVELOPMENT, ANALYSIS, AND DESIGN OF A NEW PARKWAY AT GRADE INTERSECTION (PAGI)

PROJECT STUDY REPORT. Cal Poly Pomona Senior Project

The New Highway Capacity Manual 6 th Edition It s Not Your Father s HCM

INSIGHTS INTO THE FIRST THREE DIVERGING DIAMOND INTERCHANGES IN MISSOURI. A Thesis presented to. the Faculty of the Graduate School

Maintenance of Traffic for Innovative Geometric Designs Work Zones

WELCOME IL 47. Community Advisory Group Meeting #5 Waubonsee Community College Wednesday, May 31, 2017

500 Interchange Design

A three-stage process was implemented in order to develop and evaluate the project concepts and provide recommendations for the project.

CHAPTER 4 GRADE SEPARATIONS AND INTERCHANGES

Woodburn Interchange Project Transportation Technical Report

500 Interchange Design

Informational Brochure. Proposed Interchange. Interstate Route 295 (I-295) AT Greenville Avenue (State Route 5) Town of Johnston, Rhode Island

Interchange Improvements at the Queen Elizabeth Way and Glendale Avenue

APPENDIX B. Public Works and Development Engineering Services Division Guidelines for Traffic Impact Studies

8.0 Chapter 8 Alternatives Analysis

Interstate-290 Carbon Monoxide Build vs No-build Analysis For Individual Intersection Locations in Oak Park

A Unique Application of Railroad Preemption with Queue Mitigation at a Roundabout Interchange

FINAL REPORT GUIDELINES FOR PRELIMINARY SELECTION OF THE OPTIMUM INTERCHANGE TYPE FOR A SPECIFIC LOCATION

Conceptual Design Report

9.0 I-26 & I-526 Interchange Improvements

MINNESOTA DEPARTMENT OF TRANSPORTATION Engineering Services Division Technical Memorandum No TS-03 December 5, 2016

Consideration of a Diverging Diamond Interchange in Saskatchewan. Paul H. A. Steel, Project Manager, M. Eng., P.Eng., Tetra Tech EBA Inc.

The Secrets to HCM Consistency Using Simulation Models

I 95 EXPRESS LANES SOUTHERN TERMINUS EXTENSION TRAFFIC OPERATIONS AND SAFETY ANALYSIS REPORT

UNION CENTRE BLVD AND I-75 INTERCHANGE WEST CHESTER, OHIO

DIVERGING DIAMOND INTERCHANGE. Informational Guide

PROCEDURES FOR NEW OR REVISED FREEWAY ACCESS IN ARKANSAS

FOR INTERSTATE 81 AND ROUTE 37 INTERCHANGE FREDERICK COUNTY, VIRGINIA MILEPOST 310

Appendix C - Highway 400 Widening and Interchange Evaluation Summary Tables

I-95 Corridor Study Phase II Highway Element

Chapter GRADE SEPARATIONS & INTERCHANGES

EVALUATING THE APPLICATION OF DIVERGING DIAMOND INTERCHANGE IN ATHENS, ALABAMA

Operational and Safety Attributes of an Alternative Design, Space-Efficient One-Sided Interchange

Central Phoenix Transportation Framework Study

Stage One Reference Design Enhancements. Date: 2 October Cabinet-in-Confidence

4/26/2013. I-435 and Front Street Diverging Diamond Interchange Missouri Department of Transportation. KCITE 2012 Excellence in Transportation Award

ALBION FLATS DEVELOPMENT EXISTING TRAFFIC CONDITIONS AND POTENTIAL IMPACTS

I-35/I-80/Iowa 141 Interchange IJR and NEPA A Practical Approach to Resolving a Decades-Old Traffic Operations Challenge

GUIDE FOR THE PREPARATION OF TRAFFIC IMPACT STUDIES

C-TEP is pleased to present a short course; Innovative Intersections & Interchanges, March 14-16, 2016 in Calgary, Alberta.

TRANSPORTATION PROJECT REPORT DRAFT CONCEPTUAL ACCESS MODIFICATION PROPOSAL OCTOBER 2002

Ramp Reversal Research. Roy Parikh, P.E. TxDOT Fort Worth District

SIMULATION OF TRUCK SAFETY INSPECTION PROCEDURES AT THE TEXAS/MEXICO BORDER

ASSESSING THE IMPACT OF SECURITY MEASURES AT GATES OF SEAPORTS ON TRAFFIC OPERATION

BILLINGS BYPASS UPDATE

Evaluation of Alternative Intersections and Interchanges

Exit 73 I-29 Interchange Modification Justification Study

Traffic Analysis. Appendix I

Welcome and thank you for spending time with us today to talk about the 75 th Street Corridor Improvement Project.

Use of Microsimulation to Convey Access Management Techniques

COFFEE WITH THE MAYOR. September 10, 2010

Summary. Preliminary Alternative Development and Screening. DEIS July 23, 2018

Appendix D: Functional Classification Criteria and Characteristics, and MnDOT Access Guidance

On behalf of the Carolina Crossroads project team we thank you for taking the time to attend this meeting.

US 14 EIS (New Ulm to N. Mankato) Interchange and Intersection Type Comparison

RECOMMENDED RAMP DESIGN PROCEDURES FOR FACILITIES WITHOUT FRONTAGE ROADS

NW La Center Road/I-5 Interchange Improvement Project (MP 16.80)

Rapid City, SD HDR Project No RE: Replacement of Existing I-190 Twin Bridges at I-190/Silver Street Interchange, Rapid City, SD

1. Controlling the number of vehicles that are allowed to enter the freeway,

Project Prioritization for Urban and Rural Projects TEAM CONFERENCE March 7, 2018

Existing vs. Proposed Ramp Noise Sensitivity Analysis Austin Boulevard Interchange

The TIS is to be signed and sealed by a Florida Registered Professional Engineer.

Community Conversations for the I-35 Ramp Metering Project Begin This Month

SENSITIVITY ANALYSIS OF OPERATIONAL PERFORMANCE UNDER CONVENTIONAL DIAMOND INTERCHANGE AND DIVERGING DIAMOND INTERCHANGE

IH 30/IH 35E Reconstruction Project Pegasus Final Technical Memorandum - Evaluation of Conceptual Alternatives Task 7.5

Appendix B Highway 407 Interchange Review - Cochrane Street Area

5/11/2016 SR 15 SECTION 088 CSVT SOUTHERN SECTION SR 15 SECTION 088 CSVT SOUTHERN SECTION AGENDA

INTERACTIVE HIGHWAY SAFETY DESIGN MODEL (IHSDM)

State of the Practice, Case Studies and Analysis Tools on Unconventional Intersection & Interchange Designs in Maryland

Appendix D Functional Classification Criteria and Characteristics, and MnDOT Access Guidance

Automating Variable Speeds and Traveler Information with Real-Time Traffic and Weather

Overall project. The $288 million Phase 2 DesignBuild project starts construction. this spring, with completion by December 31, 2016

Military Highway Interchange

Community Advisory Committee Meeting No. 2. June 22, 2006

b. Include an evaluation of maintenance of traffic for ramps, local roads and cross streets.

WELCOME IL 47. Community Advisory Group Meeting #4 Waubonsee Community College Tuesday, November 15, 2016

Transcription:

Breaking the Diamond: DDIs, CFIs, and SPUIs Smith Siromaskul, P.E. Abstract With a recent push towards innovative solutions in interchange design, the diverging diamond interchange has been the next big thing. Two of its key weak points involve interchanges with heavy through movements along the crossroad and the split phasing of traffic along the crossroad creating issues with the coordination of traffic flow along the arterial corridor. This presentation examines a case study in which all conventional interchange concepts as well as the DDI were incapable of handling the travel demand. A number of atypical concepts were then considered including a marriage between the concept of a single point urban interchange and a continuous flow intersection to create an interchange with a single signal and crossroad left turns that do not conflict with the opposing through movement. Also considered were variations on the DDI. This presentation will outline the concepts and provide initial operational results from VISSIM analysis to determine if and when benefits can be found from the implementation of these interchange forms. Introduction Advances in roadway and interchange design often come in fits and spurts. A new concept creates interest, apparently works on paper, and seems like the next big thing. Everyone waits for the first guinea pig. The first one gets built and gets some attention. If it is done well, the idea gains ground. If it is done poorly, the idea loses ground regardless of whether it was the idea or the execution that is to blame. Roundabouts are a perfect example of this phenomenon. While the modern roundabout in the United States has gained widespread acceptance in many locations, in other regions it has not. In many of these cases, a local implementation is often to blame. In the case of roundabouts, many of these missteps have been nicknamed suicide circle or something to that effect. Single Point Urban Interchanges have been around since 1974 though their acceptance and implementation did not reach a broader scale until the 1990s. Diverging Diamond Interchanges have also been around since the mid-1970s i and are beginning their wide-scale deployment with 4 open as of the end of 2010. The Continuous Flow Intersection was developed and patented in 1987 ii and saw its first US implementation in 1996. This paper primarily covers the DDI and SPUI and attempts to find the breaking point of each. Concepts from the CFI were added to the SPUI to determine if the resulting hybrid interchange can handle more traffic than a conventional SPUI. The grade separation of the DDIs crossing intersections were also examined to see if braiding the DDIs crossroad movements would substantially increase its capacity as well.

The Diverging Diamond Interchange This paper was born out of research into the newest fad in interchange design, the diverging diamond interchange. The DDI has been rapidly gaining acceptance across the US with the number of sites under consideration growing exponentially since 2006. The selling point of the DDI is its reputation as an interchange that can provide high capacity with fewer lanes than traditional signalized interchanges (including the SPUI) while doing so with minimal right-of-way iii, particularly when compared to interchanges that include loop ramps. The DDI is an interchange that uses an intriguing twist in that crossroad traffic is shifted to the left side of oncoming traffic (assuming right-side driving) in the core of the interchange. The benefit to this twist is that the turning movements do not occur at the signalized intersections. Instead, the signals control the opposing through movements. Figure 1 - Rendering of the DDI at I-15 and Pioneer Crossing (opened in 2010) 1 This design excels where turning movement volumes to and from the ramps are high. Analysis has shown that high through volumes that conflict at the signals is its weak point. Depending on the traffic volumes and the spacing between the two ramp terminals, coordination with adjacent intersections and progression of both directions of travel are also potential hurdles. Progression in both directions is not always possible, but it can be done. No traffic analysis software currently on the market can optimize the signal timing of a DDI or of a corridor that has a DDI for progression in both directions. This must be done by hand using time/space diagrams. Both signals at a DDI are two-phase signals as no left turn phases are needed. 1 Source: HDR

Single Point Urban Interchanges Single Point Urban Interchanges offer the ability to handle large amounts of through and turning traffic by shifting all of the conflicting movements to a single signalized intersection that is typically controlled by a three-phase signal. The SPUI is much easier to coordinate with adjacent signals along an arterial corridor but is extremely expensive to construct either over (Figure 2) or under (Figure 3) the freeway due primarily to structure costs related to its width and odd shape. Figure 2 SPUI: Crossroad over Freeway 2 Figure 3 SPUI: Crossroad under freeway 3 2 Source: HDR 3 Source: HDR

Breaking the Diamond For the analysis, a site was selected that was the first that HDR has analyzed where a DDI failed from a strictly operational aspect even without the influence of nearby intersections. The interchange in question is I-85 and Concord Mills/Burton Smith Boulevard, also known as Speedway Boulevard north of Charlotte, NC. To complicate matters, there is extensive existing development in all four quadrants. The Concord Mills Mall is located in the southwest quadrant and the Lowe s Motor Speedway is east of the interchange. In order to accommodate long term improvements in the area, the number of through lanes on the approaches to the interchange must not exceed three in each direction. The width of the bridge was assumed to be unconstrained for the comparative analysis. Figure 4 - Map of study location Figure 5 - Closer view of study corridor

Figure 4 - Turning movement percentages based on count data The volume scenarios used for this analysis ranged between the actual base volumes (2009 count data shown in Figure 5) to a maximum of 50% more traffic than the 2009 volumes (Figure 6). For simplicity, the increase in traffic volumes was applied universally to every movement. The base volume scenario for this analysis is based on the existing (2009) traffic data at this interchange. For each interchange alternative, the volumes were increased by 10% increments until the alternative fails. Failure, in the case of this analysis, involves the complete collapse of operations with more than 3% of traffic demand unserved (queuing off of the network). As the models are uncalibrated, they serve only as qualitative measures that can show the relative differences between models, but are not accurate for detailed level of service or delay estimates. Figure 5 - Baseline volumes by approach Breakpoints Table 1 shows the various volume scenarios in which the DDI and SPUI exceed their capacity. The problems that arise in the DDI pertain to the volumes that conflict at the two signals. Additional lanes would be needed at the crossing intersections which would require additional lanes on the approaches to the interchange, which, for the purposes of this comparison, were limited to three lanes in each direction. In the DDI alternatives, a fourth lane is added on the left (north side) approaching the interchange (from the west) which acts as a de facto left turn lane. A right turn lane is also provided on the crossroad approaches. Figure 6-150% volumes by approach Figure 7 shows the DDI alternative s lane configurations at the interchange. The queuing from the two signals extends beyond the edges of the network on the crossroad. The SPUI also uses three lanes in each direction and includes dual left turn lanes and dedicated right turn lanes on both approaches. (See Figure 8) The mode of failure for the SPUI was queue spillback from the left turns. Triple

lefts to and from the ramps would likely be required to make the SPUI function as the critical conflicts are the crossroad through movements and the crossroad lefts. The interchange is controlled by a threephase signal with all three phases serving significant demand. The only potential solution is to provide more capacity (more lanes) for each phase or to eliminate a phase. Table 1 Comparison of the DDI and SPUI Alternative Delay iv Demand v Total Demand Volume Scenario Delay Total Delay DDI Base + 30% 97 284 381 726 19515 3.7% SPUI Base + 20% 143 728 871 1708 18013 9.5% % Unserved vi Figure 7 VISSIM Screenshot of DDI alternative at 130% volume Figure 8 VISSIM Screenshot of SPUI alternative at 120% volume Displacing a Phase The SPUI s mode of failure resulted from a lack of capacity for each of the three phases at the signalized intersection. Under this particular scenario, adding more through lanes and turn lanes would lead to

unacceptably wide cross sections on the crossroad approaches. If adding capacity for each of the three signal phases is not an option, then removing a phase is the only remaining option. Figure 9 - Rendering of a Continuous Flow Intersection The Continuous Flow Intersection (Figure 9) is designed to handle significant amounts of left turning traffic while minimizing the effect left turning traffic would have on the opposing through movement. It does so by displacing the left turn movement. The left turns are moved to a signalized crossover prior to the cross-street. In this example, two of the four legs of the intersection have displaced left turns. In practice, one or all four legs could be designed with displaced left turns. Figure 10 - VISSIM Screenshot of a SPUI with Displaced Left Turns The signals at the two crossover intersections in this example are coordinated with the main signal at the intersection of the two arterials to ensure that through traffic flow is optimized. While the displaced left turn concept increases the number of stops required for left turning traffic, it eliminates the left turn phase from the main intersection. Eliminating one of the three phases from the main intersection allows more green time to be provided to the remaining phases and may shorten the cycle length of the signal, further reducing delay. Figure 10 shows what a SPUI would look like with the displaced left turn concept taken from the CFI and applied in a completely different concept which will be referred to in the rest of this paper as the CFSPUI.

While the CFSPUI fits the six-lane cross-section 750 feet from the centerline of the freeway, this design gets very wide at the interchange itself. The width of the crossroad is ten lanes plus a median wide enough to accommodate another two lanes for a total width of 12 lanes. That totals 144 feet without accounting for sidewalks, shy distances, drainage features, etc. shows the number of lanes needed at various cross-sections within the interchange. Displacing the left turns and removing a phase from the main signal does add two additional signals to this interchange. The analysis results for the CFSPUI show a significant improvement resulting from the displaced left turn. The SPUI failed spectacularly at the base plus 20% volume scenario. The CFSPUI does not reach the level of congestion experienced by the SPUI at base plus 20% even when the volume is increased to base plus 50%. Table 2 shows the results for various CFSPUI scenarios. The mode of breakdown for the CFSPUI was queuing Figure 11 - Cross-section widths for the CFSPUI from the main signal back along the arterial and the ramps. It should be noted that no alternative was analyzed for volumes greater than base plus 50% as volumes beyond that would require additional capacity leading into the model as well. Even at the base plus 50% volumes, it is unlikely that upstream signals on the arterials would be able to deliver these volumes to the interchange. Table 2 - Comparison of SPUI-based Alternatives Delay Demand Total Demand Alternative Volume Scenario Delay Total Delay SPUI Base + 20% 143 728 871 1708 18013 9.5% CFSPUI Base + 30% 50.8 151.3 202.1 370.1 19515 1.9% CFSPUI Base + 40% 63.2 269.2 332.4 628.6 21014 3.0% CFSPUI Base + 50% 89.6 519.4 609.1 1249.3 22517 5.6% % Unserved Diverging Diamonds and Braids The DDI failed at the base plus 30% scenario due to the capacity at the intersections that cross the two directions of through traffic on the crossroad. What if those crossings were grade separated? Geometric constraints, particularly those related to vertical geometry, are paramount to making a grade separation work at the crossing points of a DDI. Assuming a grade separation can be made to work, it is strongly recommended that the outbound crossroad go over the inbound crossroad as the inbound crossroad will likely need to be signalized to eliminate the weaving issue that would otherwise be created between the two ramp terminals.

Eliminating the need to signalize the crossing of the two directions of the crossroad does not result in a reduction in the number of signals needed. Instead, the signal removed by grade separation is instead used to control the crossroad through movement and its conflict with the exit ramp left turn. Grade separation can be done on one or both of the crossroad crossings. For this paper, the grade separation of only one crossing is referred to as the DDI PB (DDI partially braided, see Figure 12), and the grade separation of both crossings is referred to as the DDI FB (DDI fully braided, see Figure 13). In both figures, the darker color represents the bridge over the opposing roadway. Figure 12 - DDI - Partially Braided Figure 13 - DDI - Fully Braided While braiding (grade separating) the crossing intersection does not eliminate the need for a signal, as previously discussed, it does increase the green time that can be allocated to the through movement and has a measurable impact on operations. This will not always be the case because as with all DDI operations, the efficiency of a DDI is heavily dependent on the manner in which traffic volumes are distributed around the interchange. In other scenarios, it is expected that the ramp may need more green time than the crossroad. Table 3 shows the results for the three DDI alternatives: typical, partially braided, and fully braided.

Table 3 - Comparison of DDI-based Alternatives Delay Demand Total Demand Alternative Volume Scenario Delay Total Delay % Unserved DDI Base + 20% 78.9 48.3 127.2 130.7 18013 0.73% DDI Base + 30% 97.4 283.9 381.3 725.7 19515 3.72% DDI PB Base + 30% 76.1 126.5 202.6 411.8 19515 2.11% DDI PB Base + 40% 86.7 424.4 511.2 1083.9 21014 5.16% DDI FB Base + 30% 21.6 1.8 23.4 0.4 19515 0.00% DDI FB Base + 40% 26.6 13.4 40.0 11.2 21014 0.05% DDI FB Base + 50% 37.4 64.7 102.1 176.5 22517 0.78% In the case of the DDI-FB, additional benefit to the crossroad traffic results from the fact that through traffic only has a single signal to pass through. While the traditional DDI failed with the base plus 30% volume, the partially braided DDI performed slightly better and failed with base plus 40% volumes. The fully braided DDI did not fail even at base plus 50% volumes, though the ramp begins to queue significantly. In this volume scenario, the southbound exit ramp is carrying almost 2600 vehicles per hour and would likely need a third lane. The delay in the 50% model largely results from backups on the ramp that arise from a lack of distance from the network entrance to the point in which vehicles need to decide whether to turn right or left. Looking solely at the delay experienced within the network, the interchange is still performing efficiently, even under the heavy volume loads in this scenario. Summary The DDI and SPUI are widely considered to be the best available options for handling interchanges with large turning volumes without loops or directional ramps such as flyovers. In general, DDIs are much cheaper to construct than SPUIs, particularly when it comes to structure costs. Assuming a fixed width on the approaches, there are interesting twists that can be applied to modify both the DDI and the SPUI to get a bit more capacity from each of these concepts. Braiding the crossovers on a DDI can increase the capacity, but adds additional structures and may not be possible under some circumstances due to tricky vertical geometry required to provide adequate clearance at the crossovers. Displacing the left turns on a SPUI can increase the capacity of the interchange, though it results in a very large structure. However, the CFSPUI structure is more rectangular than a traditional SPUI structure. It is doubtful that a CFSPUI can be constructed where the freeway goes over the crossroad as the span length required to clear the entire interchange may lead to very large structure depths and costs.

Author Information Smith was involved in the selection of the DDI for Oregon s first deployment, the development of the Utah DOT s Diverging Diamond Interchange Guidelines, the Missouri DOT s post evaluation study for the MO 13 DDI, and the analysis and/or design of DDIs in North Carolina, South Dakota, Illinois, Wyoming, Colorado, Minnesota, Nevada, and Oregon. Smith has also been involved in the evaluation of CFIs in Oregon and Colorado. He has a background in both roadway design and traffic analysis and microsimulation. Smith Siromaskul, P.E. Professional Associate HDR Engineering 1001 SW 5 th Avenue, Suite 1800 Portland, OR 97204 503-449-1524 smith.siromaskul@hdrinc.com i The construction data of the first DDI in France is unknown, but thought to be in the mid-1970s. The first DDI in the United States opened to traffic in 2009 in Springfield, Missouri. ii U.S. Patent # 5049000, expired in 2003 (U.S. Patent and Trademark Office) iii The fact is that while the number of lanes required to meet a certain capacity is typically less than other interchanges, this does not always translate into reduced right-of-way. However, the right-of-way footprint is substantially different than other interchanges in terms of where right-of-way is required. iv delay refers to the delay encountered by vehicles waiting to enter the network v demand refers to the number of vehicles that could not enter the network vi Percent unserved refers to the percentage of vehicles that were unable to enter the network due to queue spillback. Ideally, the network would be coded, particularly on the ramps, for a longer distance upstream to allow for vehicles to make the lane changes required.