TESTING AND VERIFICATION OF GAS PROTECTION SYSTEMS [CIRIA C735]

Similar documents
Ground Gas Developments. Emerging Guidance. SILC Annual Forum, April 30, 2013

Guidance on Ground gases, VOC s & Radon. Validation &Verification. By: Peter Atchison

Engineered Solutions for Ground Gas and Vapour Protection Measures

Understanding Gas Protection Measure Selection within Waterproofing Systems. John Naylor Technical Director

The importance of the design, installation and verification of gas protection measures

NHBC Requirements for Soil Capping Systems

VAPOR INTRUSION MITIGATION SOLUTIONS FOR BROWNFIELD REDEVELOPMENT. Jordan Kleine, MPA Southeast US District Manager

Part 5 Substructure and ground floors. Chapter 5.2. Suspended ground floors

CIRIA VOC remediation guidance

Visqueen Gas Barrier STRUCTURAL WATERPROOFING AND GAS PROTECTION SYSTEMS. CE Mark to EN 13967

High Performance DPM. Installation. Technical Support: LAST UPDATED: Page 1 CE Mark to EN 13967

HIGH PERFORMANCE BARRIER MEMBRANES Effective protection against CO 2, Radon, Methane, Hydrocarbons & VOCs

Modular approach to VOC assessment

BS8102 v BS8576 Top Trumps. John Naylor Technical Director

Visqueen Ultimate HC BLOK

Managing Risks on Brownfield Sites

Vapor Intrusion Mitigation: Answering the Common Questions Plaguing Brownfield Developers West Virginia Brownfields Conference

GP TITAN Waterproofing, Ground Gas, VOC and Hydrocarbon Proof Membrane THE ONLY FUTURE PROOFED QUAD ACTION MEMBRANE AVAILABLE.

PREMCRETE GAS RESISTANT DAMP-PROOF MEMBRANES HYDROPRUFE 7000

LAND AFFECTED BY CONTAMINATION Technical Guidance for Applicants & Developers Third Edition

City Policy & Procedure

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

VISQUEEN'S GAS SYSTEM THE COMPLETE SOLUTION PROTECTION GAS. CI/SfB (21.9) (L34) April 2018 v. 2 VISQUEEN'S GAS PROTECTION SYSTEM THE COMPLETE SOLUTION

Level 6 NVQ Diploma in Construction Site Management (Construction)

SOLCO MEMBRANES SOLSHIELD GAS MEMBRANE

Copyright 2007 Essex Contaminated Land Consortium All rights reserved. December 2007 v2

Level 6 NVQ Diploma in Construction Site Management (Construction)

WATERPROOFING SYSTEM

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Construction Operations (Construction)

Structural Eurocodes an overview

Via to:

Loss Prevention Standards

PHYSICAL FACILITIES Consultant s Handbook Specifications Division 07 Thermal and Moisture Protection 8400 Firestopping

A Guide to Structural Waterproofing

26 Visqueen 100% Recycled Ecomembrane 28 Visqueen DPM To Pifa Standard PROOF. membranes

Land Contamination Reports

Soil Treatment Facility Design and Operation for Bioremediation of Hydrocarbon Contaminated Soil. Version 1.0

Thermoplastic Waterproofing Membrane with APC Technology

Development of Land Affected by Contamination: A Guide for Developers

CAPITAL VALLEY PLASTICS MEMBRANES RADBAR GAS MEMBRANE

Briefing Document, Application and Selection Process. Assistant Health and Safety Officer

Gas barrier and damp proofing accessories

Foundations. Issue. Slab-On-Grade Liquid Water Control (See Figure 2-2) Goals. Guidance

Level 2 NVQ Diploma in Specialist Concrete Operations (Construction)

LAYING IBSTOCK CLAY PAVERS FOR PERMEABLE PAVEMENTS

PROTECH GAS RESISTANT MEMBRANES PROTECH GM+

Level 2 NVQ Diploma in Thermal Insulation (Construction) Qualification Specification

Environment Agency Guidance on Requirements for Land Contamination Reports. July 2005

Chemical & Hydrocarbon Resistant Membrane 0.00E E E E E E E E+03

Building materials group. Custom Fit Solutions to Meet Your Needs

The Design, Installation, and Use of Vapor Intrusion Barrier Systems October 1, 2014

Agrément Certificate 17/5422 website: Product Sheet 1

Permavoid Geo-Cellular Modules. Performance Specification

16.3 An Agricultural Land Classification Report is included in ES Volume 2.

Glidevale offers a complete range

Design of Below Sub-slab Vapour Management System for a Commercial Building

Ground gas and VOCs Exploring continuous online ground-gas monitoring for accelerated risk assessment

SECTION (07100) - DAMPPROOFING AND WATERPROOFING

Understanding the practices and procedures for overseeing and organising the work environment (Electrical Installation) (ELTK03)

Level 2 NVQ Diploma in Specialist Concrete Operations (Construction)

Typical waterproofing using Shelterseal 3000X

Welcome to this continuing education seminar. This is the first of two parts of the High- Performance Building series.

NORTH CAROLINA ENERGY STAR CONFERENCE

Agrément Certificate 17/5387 website: Product Sheet 1

Agrément Certificate 96/3267 website: Product Sheet 2

BULLETIN 34: BUILDING ENVELOPE SERVICES APPROPRIATE PROFESSIONAL PRACTICE

Jabfloor 70, 100, 150, 200, 250

Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Highways Maintenance (Construction)

Ground Gas/Vapour Mitigation System

Learner Guide. Issue 1. 12/12

Brownfield Vapor Barriers: Chemical Compatibility, Testing and Advancements in Material Science

Level 5 NVQ Diploma in Occupational Health and Safety Practice

STATEMENT OF QUALIFICATIONS

Is licensing for me? A guide to becoming a licensed building practitioner (LBP)

Vapor Barriers Under Concrete Slabs Guidance for Selection and Location

Glidevale offers a complete range

Jabfloor High Performance (HP) 70 and 100

STRAIGHT TALK ABOUT WATER VAPOR RETARDERS/BARRIERS. STRAIGHT TALK ABOUT WATER VAPOR RETARDERS/BARRIERS BUCKLED FLOOR COVERING

What Is A GAS VAPOR BARRIER?

Agrément Certificate 16/5384 website: Product Sheet 1

Level 6 NVQ Diploma in Construction Contracting Operations Management

Control XT SECTION Resilient Athletic Flooring

GUIDE TO GOOD MANUFACTURING PRACTICE FOR MEDICINAL PRODUCTS

Level 6 NVQ Diploma in Occupational Health and Safety Practice

Visqueen High Performance Radon

Job Description. Gas and multi-trade workforce, apprentices and subcontractors as allocated to the post holder.

Pearson Edexcel Level 2 NVQ Diploma in Construction Operations and Civil Engineering Services Highways Maintenance (Construction) (QCF)

SECTION UTILITY BACKFILL MATERIALS

Specifications. Specifications (Architectual) Metallic System. Metallic System

Perm-A-Barrier VPS (Vapor Permeable Sheet)

UNIFIED FACILITIES GUIDE SPECIFICATIONS

SECTION FLUID-APPLIED MEMBRANE AIR BARRIERS, VAPOR PERMEABLE

Agrément Certificate 13/5069 website: Product Sheet 4

Layering Institutional Controls Region 9 Example. Alana Lee EPA Region 9

SECTION COPPER/ SOLDERED RF SYSTEM SPECIFICATIONS

BUILDING ENVELOPE PRODUCTS PROVIDING A FULL BUILDING ENVELOPE SYSTEM. Control Moisture Movement with Our Patented Technology

Michael Vernon, DELTA MEMBRANE SYSTEMS LIMITED INITIAL GROUND GAS ARTICLE FOR TBIC DISCUSSION on

Sheetseal GR RIW. Sheetseal GR

Master Specification WALLTITE ECO v.2 by BASF Canada Inc. Section SPRAY POLYURETHANE FOAM INSULATION Page 1

OLDROYD MEMBRANE SYSTEMS OLDROYD XS

Transcription:

TESTING AND VERIFICATION OF GAS PROTECTION SYSTEMS [CIRIA C735] July 2015

. OUTLINE OF PRESENTATION Guidance on membranes as VOC barriers [CIRIA C748] Testing and verification of gas protection systems [CIRIA C735] 1. The Project 2. Project Issues 3. Verification Procedure 4. Integrity testing 5. Reporting 6. Recommendations Case study Conclusions

GUIDANCE ON MEMBRANES AS VOC BARRIERS [CIRIA C748] Authors S Wilson (EPG) S Abbot (TCNF/ University of Leeds) S Mallett (Buro Happold) Background 1. Gas membrane break VOC migration pathways 2. VOCs migrate through polymeric materials 3. Guidance presents information on permeation 4. Risk based approach

GUIDANCE ON MEMBRANES AS VOC BARRIERS [CIRIA C748] Membrane function Hydrocarbon resistant HDPE not impermeable to VOCs Vapour transport mechanisms Permeation tests Membrane performance factors

GUIDANCE ON MEMBRANES AS VOC BARRIERS [CIRIA C748] Membrane durability 1. Potential chemical degradation 2. Chemical resistance tests

GUIDANCE ON MEMBRANES AS VOC BARRIERS [CIRIA C748] Membrane Selection Design Life Degradation Risk associated with VOC migration Potential for exposure Loading Installation Installation and verification

TESTING AND VERIFICATION OF GAS PROTECTION SYSTEMS [CIRIA C735] October 2014

C735 PRESENTATION STRUCTURE 1. The Project 2. Project Issues 3. Verification Procedure 4. Integrity testing 5. Reporting 6. Recommendations

C735 1. THE PROJECT Need Installed gas protection systems often inadequate Verification - fundamental to remediation Little current guidance for verification of gas protection systems Verification absent in design/ construction of buildings with gas protection systems Membrane resilience and integrity and well designed venting systems fundamental to performance of gas protection systems

1. THE PROJECT Need

1. THE PROJECT Need

1. THE PROJECT Need

1. THE PROJECT Team CIRIA PSG Chair Research Contractor PSG - J Kwan - G Card (GB Card) - L Cox neetaffel -Andureau (Buro Happold/Arup) - M Corban (MEC Environmental) - H Mallett (Buro Happold) - S Wilson (EPG) - 27 members from: NHBC LA & EA regulators contractors consultant suppliers

1. THE PROJECT Objectives 1. Determine and promote good practice 2. Define need and scope of verification 3. Describe integrity test methods and their selection 4. Identify practical constraints 5. Set out details of Verification Report [ CLR11 and SC030114]

1. THE PROJECT Regulatory framework Part 2A [Statutory guidance] Any remedial treatment action should include appropriate verification measures. In arranging for such measures, the enforcing authority should ensure that the person responsible for verification is a suitably qualified experienced practitioner. (Defra, 2012) NPPF Responsibility rests with developer Competent person CLG 2008 [Standard Conditions] Following completion of measures identified in the approved remediation scheme, a verification report (referred to in PPS23 as a validation report) that demonstrates the effectiveness of the remediation carried out must be produced, and is subject to the approval in writing of the Local Planning Authority.

1. THE PROJECT Regulatory framework NHBC [Chapter 4.1] Robust design and verification required [Cl D6 and D7] Specialist membrane installers [CSC National Occupational Standards VR612,613; NVQ level 2 Diploma Installation of gas membranes] Suitable person to prepare Verification Reports [Appendix 4.1D] Verification required on higher risk sites (Amber 2 and above) CIRIA [C735] The role and responsibilities of the local authority as primary regulator of land contamination, including land affected by ground gas emissions, is important for their assessment and approval of both the developers initial planning proposals (including remedial strategy) and the post development verification report

2. PROJECT ISSUES 1. Verification 2. Ventilation 3. Membrane integrity 4. Robustness and levels of redundancy 5. Conceptual Site Model

2. PROJECT ISSUES 1. Verification currently insufficient attention in design of gas protection systems A Verification Plan should be prepared as an integral part of the gas protection system at the design stage and submitted to the local authority regulator as an integral part of the remediation strategy. The verification plan should address i. Gas regime and gas protection system ii. Inspection regime iii. Integrity test programme (if any)

2. PROJECT ISSUES 2. High permeability layer and venting. 1990s reports - efficacy of venting Wilson & Card - proven screening method CIRIA C735 - high level of redundancy Ventilation is a very effective first line of defence in gas protection systems.

2. PROJECT ISSUES 3. Integrity of membranes BRE Minimum 1200g polyethylene Intact survival during construction. CIRIA C735 Critical property ability to survive construction intact. Key parameters material type; tensile strength, puncture resistance; permeability; need for protection; thickness (if welded).

2. PROJECT ISSUES 4. Robustness and levels of redundancy Increase with Characteristics Situation [Basis of approach in Wilson&Card 99, CIRIA C665, British Standard 8485, NHBC 2007]. 5. Conceptual site model An appropriate understanding of the conceptual site model is a critical element in the verification process

3. VERIFICATION PROCEDURES Need for appropriately qualified workforce Verification by competent experienced trained personnel. Third party verification Risk based approach to verification activities. Verifying that a gas protection system works is as important as design and installation. A Verification Plan should be prepared as an integral part of the gas protection system at the design stage and submitted to the local authority regulator as an integral part of the remediation strategy.

3. VERIFICATION PROCEDURES Risk based approach to verification and independence Requirement for 3rd party verification increases with risk. Environment Agency recommends avoidance of conflicts of interest in verification [independent verifier]

3. VERIFICATION PROCEDURES Inspection Verifier (independent or not) to be; Competent Experienced Suitably trained Pro Forma

3. VERIFICATION PROCEDURES Competence of installer Appropriately experienced & qualified workforce install gas protection system If not more intensive verification required Relevant qualification CSC level 2 NVQ Diploma in sub structure work occupations (Construction) installation of gas membranes. Qualification helps ensure work complies with National Occupational Standards V612, V613. A qualified workforce helps ensure adequate gas membrane installation and can make provision for less onerous verification plans.

4. INTEGRITY TESTING Combine with visual inspection Risk based Not Substitute for well designed/ installed gas protection systems Not to be used to obtain BS 8485 points

4. INTEGRITY TESTING a) Seams - Air channel - Mechanical - Air lance b) Areal - Tracer gas - Smoke - Dielectric porosity All have advantage and limitations. Risk based decision on need Planned Practical application/ limitation.

4. INTEGRITY TESTING - METHODS Standard specifications for 1. Tracer gas test 2. Smoke test 3. Dielectric porosity test

4. INTEGRITY TESTING - METHODS Integrity testing Issues to consider 1. Definition of test method 2. Issues specific to test type

4. INTEGRITY TESTING Selection of verification & integrity testing Annex 1 Risk based structure for verification and integrity testing Considers; Development type Gas regime Slab type Installer experience Provides Level of verification Type of integrity testing Read the explanatory Notes

5. REPORTING Accord with CLR11, SC030114/RI and NHBC Chapter 4.1, Tech Extra 07 Clear concise description of verification activities Phasing Verification report - Contents list Lines of evidence - Description of inspection regime - Description of elements of gas protection system - Presentation of material specifications etc. Meet regulatory requirements (inc planning conditions)

6. RECOMMENDATIONS 1. Recognition of CLO role and responsibility 2. Use of Conditions to require verification 3. Reject unsuitable reports 4. Upskill workforce [CSC - competent person] 5. Installers have / working towards NVQ 6. Verification plan integral element of strategy

6. RECOMMENDATIONS 7. Recognition of independent verification as important element 8. Risk based decision on verification (independence, gas regime, gas protection system, quality of product, installer competence) 9. Verifier independent, competent, experienced 10. Proprietary gas membrane should be specified [material type, tensile strength, puncture resistance, permeability, thickness (welded) & protected] 11. Research into integrity test methods 12. Use of standard inspection pro formas

CASE STUDY Question for you What is this a picture of?

CASE STUDY New building with passive gas protection measures Void former Membrane Venting via perimeter granular filled trench Verification

CASE STUDY Drawings prepared by Engineer Contractor installed gas protection system

CASE STUDY Drawings prepared by Engineer

CASE STUDY Contractor installed gas protection system

CASE STUDY 1. Membrane sealed over vent pipes 2. Concrete pavement laid 3. Debacle! But solved by good verification 1. Inspection 2. Identify issue 3. Devise solution [in conjunction with specialist & contractor] 4. Implement and 5. Verify and record

CONCLUSIONS 1. Installed gas protection systems often inadequate Solution: Adopt C735 2. Verification plan integral to Remedial Strategy 3. Ventilation VIP of system 4. Maintenance of membrane integrity 5. Integrity tests planned implemented by competent persons [as required] 6. Upskilling of workforce and verifier 7. Risk based approach to verification [activities, type, frequency, competence]